W912QR20R0065Plans-0001.pdf
PDF 9 MB Posted
- Solicitation number
- W912QR20R0065
About this file
This federal contract opportunity announcement seeks proposals for chiller system repairs at Wright-Patterson Air Force Base in Ohio. The scope of work includes replacing three 1100-ton chillers, chilled water pumps, condenser water pumps, and related electrical equipment. Additional requirements are installing new refrigerant monitoring, control systems, water treatment equipment, cooling towers, and structural repairs.
The contract will be awarded as a firm-fixed-price contract following a best value evaluation of technical factors and price. The estimated value is between $5-10 million. The solicitation number is W912QR20R0065 and proposals are due within 420 calendar days of notice to proceed. The North American Industry Classification System code is 238220. The opportunity is unrestricted with a 10% price evaluation preference for HUBZone small businesses. The point of contact is Josh Westgate at the Army Corps of Engineers Louisville District.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT GENERAL NOTES:
1. COORDINATE ALL WORK THROUGH THE GOVERNMENT CONTRACTING OFFICER.
2. ANY NEW TYPES OF HAZARDOUS MATERIALS TO BE USED, AND THE WASTES THAT MAY BE
GENERATED AS A RESULT OF THAT USE NEED TO BE CONSIDERED IN THE DESIGN. IF
APPROPRIATE, DEDICATED SPACE FOR STORAGE OF HAZARDOUS MATERIALS AND WASTE
NEED TO BE PROVIDED. IN ADDITION PROPER COORDINATION IS NEEDED WITH 88 CEG/CEIEC.
QUESTIONS CONCERNING THE REQUIREMENTS FOR STORAGE AND DISPOSAL OF ANY
HAZARDOUS MATERIALS CAN BE ADDRESSED BY THE 88 CEG/CEIEC HAZARDOUS MATERIALS
PM, MIKE VAUGHN, (937-257-8028 OR MICHAEL.VAUGHN.3@US.AF.MIL) OR 88 CEG/CEIEC
HAZARDOUS WASTE PM, GARY SELBY (937-257-3349 OR GARY.SELBY@US.AF.MIL).
3. BECAUSE IT IS NOT POSSIBLE TO DEFINITELY KNOW THE LOCATION OF ALL POTENTIAL
ASBESTOS CONTAINING MATERIALS (ACM) WITHIN A FACILITY, FOR INSTANCE ACM FIRE WALLS
OR ACM FLOOR TILE, THE CONTRACTOR PERFORMING THIS WORK SHALL COMPLY WITH ALL
RELEVANT PARTS OF 29 CFR 1910.1001 AND/OR 29 CFR 1926.1101 AS MAY BE APPLICABLE. A
LIMITED ASBESTOS AND LEAD-BASED PAINT SURVEY WAS PERFORMED ON 12 JUN 2017. THIS
REPORT CAN BE FOUND IN THE PROJECT SPECIFICATIONS. IDENTIFIED AREAS ARE NOTED ON
THE DRAWINGS. IF ADDITIONAL SUSPECT ASBESTOS-CONTAINING MATERIAL IS FOUND THE
CONTRACTOR SHALL STOP WORK IMMEDIATELY AND NOTIFY THE CONTRACTING OFFICER.
4. CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE HIS OWN TELEPHONE AND COMPUTER
CONNECTIONS FOR HIS CONSTRUCTION TRAILER ON SITE.
5. BUILDING WILL REMAIN OCCUPIED. CONTRACTOR SHALL COORDINATE ALL ACTIVITIES
REQUIRED IN BASE OCCUPIED AREAS WITH THE GOVERNMENT PROJECT MANAGER,
CONTRACTING OFFICER, AND BUILDING SECURITY OPERATIONS OFFICER.
6. CONTRACTOR SHALL REQUEST AND RECEIVE PERMISSION PRIOR TO ANY UTILITY OUTAGE A
MINIMUM OF 2 WEEKS PRIOR TO OUTAGE.
7. CONTRACTOR SHALL KEEP CONSTRUCTION SITE CLEAN AT ALL TIMES.
8. SOIL DISTURBANCE DURING THIS PROJECT, INCLUDING EQUIPMENT STAGING AREAS, WILL
REQUIRE EROSION CONTROL MEASURES. FOR PROJECTS THAT DISTURB LESS THAN AN ACRE
OF SOIL, AN EROSION CONTROL PLAN IS REQUIRED PRIOR TO DISTURBANCE. FOR PROJECTS
THAT DISTURB MORE THAN AN ACRE, A NOTICE OF INTENT (NOI) MUST BE APPROVED BY THE
OHIO EPA PRIOR TO ANY SOIL BEING DISTURBED AS WELL AS A STORM WATER POLLUTION
PREVENTION PLAN (SWPPP) APPROVED BY 88 CEG/CEIEA. THE CONSTRUCTION CONTRACTOR
SHALL PREPARE AND SUBMIT THE SWPPP AND DRAFT NOI TO THE CONTRACTING OFFICER'S
REPRESENTATIVE TO BE FORWARDED TO ENVIRONMENTAL MANAGEMENT, 88 CEG/CEIEA, FOR
REVIEW. ONCE THE SWPPP AND DRAFT NOI HAVE BEEN APPROVED BY THE COR AND
ENVIRONMENTAL MANAGEMENT, THE CONTRACTOR SHALL PREPARE AND FORWARD THE FINAL
NOI TO THE OHIO EPA. PLEASE CONTACT AND 88 CEG/CEIEA WATER PM, KAREN BEASON, BY
EMAIL AT KAREN.BEASON@US.AF.MIL OR BY PHONE AT (937) 257-5899 FOR ADDITIONAL
INFORMATION.
9. ANY FIRE SUPPRESSION EQUIPMENT CONTAINING IONIZING RADIOACTIVE MATERIAL (SMOKE
DETECTORS) AND ANY EMERGENCY EXIT SIGNS CONTAINING IONIZING RADIOACTIVE MATERIAL
SHALL BE TURNED INTO 88 CEG/CEIEC. COORDINATE THIS TURN-IN WITH WPAFB 88 CEG/CEIEC
RADIATION SAFETY BRANCH AT 937-257-7320.
10. THE WPAFB RECYCLING CENTER IS AVALLABLE FOR CONTRACTOR USE TO REDUCE WASTE
DISPOSAL. ALL RECYCLABLE METAL IS TO BE RECYCLED THROUGH THE BASE RECYCLING
CENTER. ALL RECYCLING MUST BE ACCOMPLISHED IN ACCORDANCE WITH THE WPAFB
SPECIFICATION SECTION 01 02 20. CONTACT WPAFB RECYCLING PROGRAM MANAGER AT
937-257-5060 TO CONFIRM WHAT MATERIALS ARE RECYCLABLE AND TO COORDINATE TURN-IN.
THE CONTRACTOR SHALL SUBMIT A QUARTERLY SUMMARY REPORT TO THE GOVERNMENT
CONTRACT REPRESENTATIVE IAW WPAFB SPECIFICATION SECTION 01 02 20 STATING (1) THE
COST TO RECYCLE AND THE TONNAGE OF CONSTRUCTION AND DEMOLITION MATERIALS
RECYCLED, (2) THE COST TO DIVERT/REUSE THE TONNAGE OF CONSTRUCTION AND
DEMOLITION MATERIALS DIVERTED/REUSED, (3) THE COST TO MULCH AND THE TONNAGE AND
COST OF CONSTRUCTION AND DEMOLITION MATERIALS MULCHED, (4) THE COST FOR
WASTE-TO-ENERGY AND THE TONNAGE OF CONSTRUCTION AND DEMOLITION MATERIALS
CONVERTED FROM WASTE-TO-ENERGY, (5) THE COST TO LANDFILL AND THE TONNAGE OF
CONSTRUCTION AND DEMOLITION MATERIALS LAND-FILLED, (6) THE COST TO INCINERATE AND
THE TONNAGE OF CONSTRUCTION AND DEMOLITION MATERIALS INCINERATED, AND (7)
EXPLANATION OF THE DIVERSION RATE APRIL 7, JULY 7, OCTOBER 7, JANUARY 7 COVERING THE
THREE MONTHS PRIOR. THE QUARTERLY SUMMARY REPORTS SHALL BE ON THE WPAFB
DIVERSION FORM. FOR ADDITIONAL INFORMATION CONTACT THE RECYCLING PM, DAVE
DALTON, AT (937) 257-5060 OR DAVID.DALTON.2@US.AF.MIL.
11. TURN-IN ALL MERCURY CONTAINING DEVICES, SWITCHES AND THERMOSTATS TO 88 CEG/CEIE
IN ACCORDANCE WITH WPAFB SPECIFICATION SECTION 01 02 20 FOR RECYCLING.
12. TURN-IN ALL MERCURY CONTAINING LAMPS TO 88 CEG/CEIE IN ACCORDANCE WITH WPAFB
SPECIFICATION SECTION 02 08 34.
13. TURN-IN ALL PCB CONTAINING LIGHT BALLAST TO 88 CEG/CEIE IN ACCORDANCE WITH WPAFB
SPECIFICATION SECTION 02 08 33.
14. REMOVE AND DISPOSE OF ANY ASBESTOS CONTAINING MATERIAL IN ACCORDANCE WITH
WPAFB SPECIFICATION SECTION 02 08 10.
15. ANY LEAD CONTAINING PAINT CONTROL MEASURES SHALL BE PERFORMED IN ACCORDANCE
WITH WPAFB SPECIFICATION 01 02 20.
16. RECOVER AND RECLAIM ANY REFRIGERANT IN ACCORDANCE WITH WPAFB SPECIFICATION
SECTION 02 09 10.
17. NO ASBESTOS-CONTAINING MATERIAL SHALL BE INSTALLED DURING THIS PROJECT.
18. ALL WINDOW AND DOOR FRAME CAULKING AND GLAZING WILL BE TREATED AS CONTAINING
ASBESTOS UNLESS TESTING PROVES IT TO BE ASBESTOS FREE.
19. THE GENERATION OF FUGITIVE EMISSIONS MUST BE KEPT TO A MINIMUM USING APPROVED
DUST SUPPRESSION METHODS SUCH AS WATER SPRAYS ON AREAS OF HIGH DUST
GENERATION. FOR ADDITIONAL INFORMATION PLEASE CONTACT 88 CEG/CEIE AIR PM CHRIS
TUMBUSCH (937-257-2455 OR CHRISTOPHER.TUMBUSCH@US.AF.MIL).
20. 30 DAYS PRIOR TO THE START OF WORK, THE CONTRACTOR SHALL TAKE A REPRESENTATIVE
SAMPLE OF THE HVAC SYSTEM WATER TO DETERMINE WHETHER IT CAN BE DRAINED DIRECTLY
INTO THE SANITARY SEWER. ANALYZE THE WATER TO DETERMINE THE TOTAL LEVEL OF EACH
OF THE FOLLOWING: CADMIUM, CHROMIUM, COPPER, CYANIDE, LEAD, MERCURY,
MOLYBDENUM, NICKEL, SILVER, ZINC AND SULFIDE. THE LAB PERFORMING THE ANALYSIS
MUST BE CERTIFIED BY OHIO EPA TO ANALYZE FOR THESE PARAMETERS. PROVIDE A COPY OF
THE LAB'S REPORT TO THE CONTRACTING OFFICER, WHO WILL IN TURN FORWARD IT TO 88
CEG/CEIEA FOR A DETERMINATION ON THE WASTEWATER DISPOSAL METHOD.
21. ALL CONTRACT WORK SHALL BE COMPLETED UNDER SUPERVISION OF A FACILITY ESCORT.
22. THERE WILL BE NO WORK ACCOMPLISHED ON ALL FEDERAL HOLIDAYS. (NEW YEAR'S DAY, MLK
DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY,
VETERANS DAY, THANKSGIVING, AND CHRISTMAS DAY).
23. DEMOLITION OF LOAD-BEARING WALLS OR STRUCTURAL COMPONENTS REQUIRE NOTIFICATION
OF DEMOLITION AND RENOVATION TO THE REGIONAL AIR POLLUTION AND CONTROL AGENCY
(RAPCA) A MINIMUM OF 10 WORK DAYS PRIOR TO BEGINNING CONSTRUCTION.
24. ALL METAL AND WIRING NEEDS TO BE RECYCLED AT THE WPAFB BASE RECYCLING CENTER.
CONTACT DAVE DALTON AT 937-257-5060 OR DAVID.DALTON.2@WPAFB.AF.MIL FOR ADDITIONAL
INFORMATION.
25. IF ANY DRINKING WATER MAINS ARE BEING EXTENDED, UPSIZED, OR NEW MAINS ARE BEING
INSTALLED, A PLANS APPROVAL MAY BE REQUIRED FROM THE OHIO EPA PRIOR TO BEGINNING
MAIN INSTALLATION. THE CONSTRUCTION CONTRACTOR SHALL PREPARE AND SUBMIT A
DRAFT PLANS APPROVAL PACKAGE TO THE CONTRACTING OFFICER'S REPRESENTATIVE,
INCLUDING A CHECK FOR ANY APPLICABLE OHIO EPA FEES, FOR REVIEW AND PROCESSING BY
ENVIRONMENTAL MANAGEMENT, 88 CEG/CEIEA. ENVIRONMENTAL MANAGEMENT SHALL
ENDORSE THE PACKAGE AS THE UTILITY OWNER AND SHALL SUBMIT IT TO OHIO EPA. PLEASE
CONTACT THE 88 CEG/CEIEA WATER PM, KAREN BEASON, BY EMAIL AT
KAREN.BEASON@US.AF.MIL OR BY PHONE AT 937-257-5899 FOR ADDITIONAL INFORMATION.
26. IF ANY SANITARY SEWER MAINS ARE BEING EXTENDED, UPSIZED OR NEW MAINS ARE BEING
INSTALLED A PERMIT TO INSTALL (PTI) MAY BE REQUIRED FROM THE OHIO EPA PRIOR TO
BEGINNING MAIN INSTALLATION. THE CONSTRUCTION CONTRACTOR SHALL PREPARE AND
SUBMIT A DRAFT PTI PACKAGE TO THE CONTRACTING OFFICER'S REPRESENTATIVE, INCLUDING
A CHECK FOR ANY APPLICABLE OHIO EPA FEES, FOR REVIEW AND PROCESSING BY
ENVIRONMENTAL MANAGEMENT, 88 CEG/CEIEA. ENVIRONMENTAL MANAGEMENT SHALL
ENDORSE THE PACKAGE AS THE UTILITY OWNER AND SHALL SUBMIT IT TO OHIO EPA. PLEASE
CONTACT THE 88 CEG/CEIEA WATER PM, KAREN BEASON, BY EMAIL AT
KAREN.BEASON@US.AF.MIL OR BY PHONE AT 937-257-5899 FOR ADDITIONAL INFORMATION.
27. IF ANY REFRIGERANT-CONTAINING EQUIPMENT SCHEDULED FOR NEW INSTALLATION,
INCLUDING WATER COOLERS, THEY MUST UTILIZE AN HFC REFRIGERANT. CFC AND HCFC
REFRIGERANTS ARE NOT AUTHORIZED FOR NEW EQUIPMENT INSTALLATIONS. FOR
ADDITIONAL INFORMATION PLEASE CONTACT THE 88 CEG/CEIEA AIR PM CHRIS TUMBUSCH.
CHRIS CAN BE REACHED AT 937-257-2455 OR BY EMAIL AT
CHRISTOPHER.TUMBUSCH@US.AF.MIL.
28. IF AN EMERGENCY GENERATOR OR BOILER WILL BE INSTALLED, AN AIR SOURCE PERMIT MAY
BE REQUIRED FOR THE GENERATOR AND POSSIBLY THE FUEL TANK. FOR ADDITIONAL
INFORMATION PLEASE CONTACT THE 88 CEG/CEIEA AIR PM CHRIS TUMBUSCH. CHRIS CAN BE
REACHED AT 937-257-2455 OR BY EMAIL AT CHRISTOPHER.TUMBUSCH@US.AF.MIL.
29. ANY TRANSFORMERS, SWITCH GEAR, OR ELECTRICAL PANELS CONTAINING OIL SCHEDULED
FOR REMOVAL MUST HAVE THE EQUIPMENT OIL VERIFIED TO BE NON PCB-CONTAINING PRIOR
TO TURN-IN. 88 CEG/CEIE MAINTAINS A BASE-WIDE PCB DATA-BASE FOR OIL CONTAINING
EQUIPMENT. IF THE EQUIPMENT CANNOT BE LOCATED IN THE DATA-BASE THE OIL FROM EACH
INDIVIDUAL PIECE OF EQUIPMENT MUST BE SAMPLED FOR PCB. PLEASE CONTACT THE 88
CEG/CEIEC USED OIL TECHNICIAN BOB JARUSIEWIC BY EMAIL AT
ROBERT.JARUSIEWIC@US.AF.MIL OR BY PHONE AT 937-257-2889 FOR ADDITIONAL
INFORMATION.
30. STORM WATER INNOVATIVE DESIGN MEASURES MUST BE INCORPORATED INTO THE DESIGN
IAW SECTION 438 OF THE ENERGY INDEPENDENCE AND SECURITY ACT (EISA) IF THE PROJECT HAS A FOOTPRINT THAT EXCEEDS 5000 SQ FT. PLEASE CONTACT THE 88 CEG/CEIEA WATER PM
KAREN BEASON BY EMAIL AT KAREN.BEASON@US.AF.MIL OR BY PHONE AT 937-257-5899 FOR
ADDITIONAL INFORMATION.
31. ALL FACILITY PROJECTS REGARDLESS OF FUNDING SOURCE THAT RESULT IN DOD REAL
PROPERTY ASSETS MUST COMPLY WITH UFC 1-200-02, HIGH PERFORMANCE AND SUSTAINABLE
BUILDING REQUIREMENTS. PLEASE ENSURE THESE REQUIREMENTS ARE INCORPORATED INTO
THE DESIGN AS APPROPRIATE.
32. COORDINATION OF THIS PROJECT WITH SHPO MAY BE REQUIRED IF WORK IS DONE TO A
BUILDING OR AREA LISTED AS HISTORIC. PLEASE CONTACT THE 88 CEG/CEIE CULTURAL
RESOURCES PM PAUL WOODRUFF. CONTACT PAUL BY EMAIL AT PAUL.WOODRUFF@US.AF.MIL
OR BY PHONE AT 937-257- 1374 FOR ADDITIONAL INFORMATION.
33. A CRANE PLAN SUBMITTAL IS REQUIRED FOR GOVERNMENT APPROVAL. THE CRANE PLAN
SHALL INCLUDE THE CRANE LOCATION, HEIGHT, DATES OF USE AND POINT OF CONTACT.
PLEASE NOTE THAT AN FAA FORM 7460-1 WILL BE REQUIRED IF CRANE IS OVER 200FT AND
THESE DOCUMENTS MAY TAKE 60 DAYS OR MORE TO PROCESS.
34. CONTRACTORS ARE FREE TO USE ANY PRODUCT WHICH MEETS THE GOVERNMENT'S MINIMUM
REQUIREMENTS AND NOT IN CONFLICT WITH OTHER CONTRACT PROVISIONS. UNLESS
INDICATED OTHERWISE ON THE PLANS OR SPECIFICATIONS (E.G. SOLE-SOURCE), ALL LISTED
MANUFACTURERS ARE THE BASIS OF DESIGN. FOR THESE BASIS OF DESIGN PRODUCTS,
OTHER MANUFACTURERS MAY BE SUBSTITUTED AS LONG AS THE STANDARD OF QUALITY AND
CHARACTERISTICS OF THE SUBSTITUTED MANUFACTURER MEET OR EXCEED THE STANDARD
OF QUALITY AND CHARACTERISTICS OF THE BASIS OF DESIGN.
S O
LI
C
IT
A
TI
O
N N
O
O P
TI
O
N A
L
FI
E
LD
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
P
N O
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
A
M E
N D
M E
N T
/1 8/
CERTIFIED FINAL
D S
N Z
H
TV
R
E P
A
IR
C H
IL
LE
D W
A
TE
R S
Y S
TE
M
, F A
C
IL
IT
Y
W
R
IG
H T
P A
TT
E
R S
O N
A
FB
B
D
E
F
G
2 4 6 8 10
W
2Q R
-1 8-
D -0
JU
LY
TH
C
IV
IL
E
N G
IN
E
E R
IN
G
G R
O U
P
W
R
IG
H T
A V
E . W
P A
FB
O
H
W
PA
FB
W
R
IG
H T-
P A
TT
E
R S
O N
A
IR
F O
R C
E B
A S
E W
2Q
R
R
A N
S I D
A E
C
US Army Corps of Engineers
7/17/2020
G-002
G E
N E
R A
L P
R O
JE
C
T N
O
TE
S
E .L
A R
U E
K .F
IE
LD
S
G .L
E
IT
C H G
-0
.D W
G
W
2Q R
R
-0
SHEET KEYNOTES:
1. EXISTING FURNITURE SHALL BE REMOVED AND DISPOSED OR SALVAGED BY CONTRACTOR.
COORDINATE WITH GOVERNMENT FOR ITEMS TO BE SALVAGED.
2. LAB DESK COUNTER TOP HAS BEEN IDENTIFIED AS ASBESTOS-CONTAINING MATERIAL.
ASBESTOS-CONTAINING FURNITURE SHALL BE REMOVED IN ACCORDANCE WITH WPAFB
SPECIFICATION SECTION 02 08 10.
3. NEW CONCRETE PAD. REFER TO ARCHITECTURAL SHEETS.
GENERAL SHEET NOTES:
1. REFER TO OTHER PLAN SHEETS FOR DETAILED EQUIPMENT INFORMATION.
2. THE FOLLOWING SURFACES IN THE CHEMICAL TREATMENT BUILDING TESTED POSITIVE FOR
LEAD CONTENT IN EXCESS OF THE EPA REGULATORY THRESHOLD OF 1.0 MG/CM2: YELLOW
CONCRETE CURBS. CONTRACTOR SHALL PERFORM LEAD CONTAINING PAINT CONTROL
MEASURES IN ACCORDANCE WITH WPAFB SPECIFICATION 01 02 20.
WH-1
ES-1
SUMP PUMP
SK-1
FC-1
PALLET
BRINE TANK
RESIN TANK
RESIN TANK
SPILL CONTAINMENT KIT
NON-OXIDIZING CHEMICAL
STORAGE TANK
OXYDIZING BIOCIDE CHEMICAL
STORAGE TANK
CHEMICAL STORAGE TANK AND
CONTAINMENT BASIN
ACC-1
PALLET
PIPE STAND (TYP)
FLOOR DRAIN (TYP)
CONCRETE BOLLARD (TYP.4)
01/2"=1'-0" 1' 2' 4'A2 CHEMICAL TREATMENT BUILDING LAYOUT
S O
LI
C
IT
A
TI
O
N N
O
O P
TI
O
N A
L
FI
E
LD
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
P
N O
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
A
M E
N D
M E
N T
8/
CERTIFIED FINAL
D S
N Z
H
TV
R
E P
A
IR
C H
IL
LE
D W
A
TE
R S
Y S
TE
M
, F A
C
IL
IT
Y
W
R
IG
H T
P A
TT
E
R S
O N
A
FB
B
D
E
F
G
2 4 6 8 10
W
2Q R
-1 8-
D -0
JU
LY
TH
C
IV
IL
E
N G
IN
E
E R
IN
G
G R
O U
P
W
R
IG
H T
A V
E . W
P A
FB
O
H
W
PA
FB
W
R
IG
H T-
P A
TT
E
R S
O N
A
IR
F O
R C
E B
A S
E W
2Q
R
R
A N
S I D
A E
C
NORTH
US Army Corps of Engineers
7/17/2020
G-111
C H
E M
IC
A
L
TR
E A
TM
E
N T
B U
IL
D
IN
G
G E
N E
R A
L
LA
Y O
U T
E .L
A R
U E
K .F
IE
LD
S
G .L
E
IT
C H G
-1
.D W
G
W
2Q R
R
-0
G
F
E
D
C
B
A
1 2 3
NEW PIPING RUN,
(18"0 & 20"0).
SEE NOTE 1
NEW W12x22 (@
UNDERSIDE OF
ELEVATED FLOOR
SLAB). SEE DETAIL
C8/S-101 FOR CONN.
INTO EXIST CONG.
NEW PIPE SUPPORT -�-----m======�-,nrwl�:r::
=--nr r
--=1 @ EXIST. CONG. COL.
SEE D5/S-101 FOR DETAIL
EXIST. CONG. COL.
(14"x14" ALONG LINE
CG1). CONTRACTOR
SHALL FIELD VERIFY
DIMS. --------------�w
NEW PIPE SUPPORT
@ EXIST. CONG. COL
SEE D5/S-101 FOR DETAIL
EXIST. CONG. COL.
(16"x16" ALONG LINE 26 AND 18"x18"
ALONG LINE 27).
CONTRACTOR SHALL
FIELD VERIFY DIMS.
<.1
.I
EXIST. CONG.
BEAM (1YP)
EXIST. CONG.
BEAM (TYP)
�---------H------------==it,.._ EXIST. CEILING
HUNG PIPING.
SEE NOTE 1
AREA WELL
OPENING
EXTENTS ------
) STEEL
T THIS
EXIST. CONG.
BEAMS -------.
12'--0"± (V.1.F.)
NEW W8x13
BEAM, (2)
SIDES OF NEW ----��r=�:;,<;;:::;:,,;;::::1,::;:t1 ��
PENETRATION ·· ·
0 0 1 · I
NEW 18" DIA. PIPE - �_,·
' lo 1/00 0 0
PENETRATION THRU
EXIST. CONG. ROOF.
SEE DETAIL B5/S-101
FOR FRAMING AROUND
PENETRATION & LOCATION
EXIST. PIPE
PENETRATIONS
L I I
(TO REMAIN) 17'-11"± (V.I.F.) 22'-5"± (V.I.F.) 22'-6"± (V.I.F.)
2::.
A1
26 27
PARTIAL BASEMENT PLAN - STRUCTURAL
SCALE: 1/8" = 1' - 0"
NOTES:
1. REFER TO MECHANICAL DRAWINGS FOR SIZE AND LOCATION OF NEW PIPING
AND FOR PENETRATION THRU EXISTING CONCRETE AT AREA WELL.
2. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS P RIOR TO
FABRICATION OF ANY NEW SUPPORT STEEL.
8'
4' 0 8'
�c.
i ti f"B.
u;
i +I
CG1)
u;
i +I
'.I'CX)-
CG
CF-
FACE OF
EXIST. COL.
NEW PIPING. SEE
MECH DWGS FOR
SIZE & ELEVATIONS.
PIPE ROLLER
(BELOW EA. PIPE)
SEE MECH. DWGS.
DIMS. TAKEN TO
CL OF ANCHORS
:t' T/MC8x BEAMS
" EL. 108'-9" +/-
(COORD w/ PIPE EL)
5'-6" a-
7 8
TOP EDGE
OF WT7
-8" (END OF MCB
TO PL3/8" CL) 9
a-
EXIST. CONG. COL
ALONG LINE 26 a- PL3/8" TO
MC8's. CONT
WELD 1 1/2"
ALONG VERT.
OF PL
a-
MC8 TO
WT7 1/4
C9 a-
"--��--< KICKER
NEW (2) MC8x8.5
HORIZ. SUPPORT,
EA. SIDE OF WT
WEB, w/ PL3/8" @
END OF SUPPORT
TO PL3/8"
..._____ NEW WT7x24x7'-6" LG
ALONG FACE OF EXIST.
COL CENTER ON WIDTH
BOT. OF DIAG.
KICKER
---- NEW 2L4x4x3/8 DIAG.
FASTEN NEW WT7 TO EXIST.
COLS. w/ 5/8"0 EPOXY ANCHORS, EMBED 5 5/8" INTO EXIST. COL.
(5 ANCHORS EA. SIDE OF WT
WEB - 5" GAGE FOR ANCHORS).
CARE SHOULD BE TAKEN TO LOCATE
ALL REINF. IN COLS. & WT SHALL
BE LOCATED TO AVOID ANCHOR/
REINF. INTERFERENCE. ----�
D5
PIPE HANGAR SUPPORT DETAIL - TYP
SCALE: 3/4" = 1' - 0"
EQ. EQ.
CL OF NEW PIPE ------
EXIST. 10" ELEVATED
CONG. SLAB (TO REMAIN) ---
EXIST. 12" CONG.
KICKER BETWEEN
WT7x & END PL3/8"
•. 3/16
KICKER TO
WT WEB
TOP OF MECH. ROOM
SLAB ON GRADE.
EL = 100'-0"
1' 6" 0 1'
NEW 18"0 PIPE
PENETRATION THRU
ELEVATED CONG.
SLAB
2-12
HSS TO
TOP
FLANGE
WALL (TO REMAIN) ----------- -T"---J- -+- -+-- - - -+-7"-
J
EXIST. CHANNEL. .... -. - ...._________,
l
TO BE REMOVED.
NEW HSS4x3x3/16 ALONG TOP SEE ARCH DWG.
OF NEW W8 BEAM. CONTRACTOR A-301 FOR ITEMS
SHALL FIELD VERIFY HEIGHT TO BE REMOVED
(BASED ON DISTANCE BETWEEN
TOP OF BEAM & BOT. OF CONG.) .1'--- EXIST. BENT PL
AND LENGTH (BETWEEN INSIDE
@CONG. SHELF
FACE OF WALL AND SLOPED (TO REMAIN)
PORTION OF CONG.) OF TUBE o
PRIOR TO FABRICATION ___ _,,
NEW W8 BEAM w/ L3x3x3/8x6"
LG. CLIP ANGLE EA. END. SEE
PLAN FOR SIZE & SPA OF BEAM.
AT CONN. TO CONG. WALL,
PROVIDE (2) 5/8"0 EPOXY
ANCHORS INTO EXIST. CONG.
WALL EMBED. 4" (MIN.). AT
CONN. TO W12, PROVIDE (2) 3/4"
DIA. A325 BOLT IN EA. ANGLE LEG.
B5
FRAMING AROUND PIPE PENETRATION
SCALE: 3/4" = 1' - 0"
� NEW W12 BEAM,
CENTER ON HORIZ.
SECTION OF EXIST.
CONG. HAUNCH. SEE
PLAN FOR SIZE & BEAM
SPAN. REFER TO DETAIL
C8/S-101 FOR CONN.
1'
@ EA. END INTO EXIST.
CONG.
6" 0 1'
W12 BEAM w/ L3x3x3/8x6"
LG. CONN., EA. SIDE OF
WEB. PROVIDE (2) 5/8"0
EPOXY ANCHORS IN L3x3
LEG BETWEEN EXIST. CONC.
EMBED ANCHOR 5 5/8" INTO
EXIST. CONG. (1YP.) -----
BOT. OF EXIST.
ELEV. SLAB
----i===---=::::::::::
==-===s-d�=-----_j
L3x3 TO
WEB 3/16
EXIST. CONG.
BEAM (TO REMAIN) ---
CB
W12x22 CONN. TO EXIST. CONG.
SCALE: 3/4" = 1' - 0"
SOUTHWEST
1' 5n 0
NORTHEAST """
I
INDOOR AANGE
KEY PLAN
SCALE: NTS
NORTH
1'
VEHICLE
SHELTER
US Army Corps of Engineers ®
SHEET ID
S-101 lJJ - !;;:
□CX)
t-z z 0 lJJ f'= :;; a.
□ 0::
z () w rn
CERTIFIED FINAL
W
2Q R
R
-0
H2EDMADJ
Cross-Out
E
D
C
B
A
0.
::::, Cl) >-' Cl)
0.
Cl)
A1
1 2 3
-� L__J
EXIST. CONG. WALLS / @ PERIMETER OF
� COOLING TOWER
SUMPS. -� I r7 u -� i
- L_J '
' I n I r tJ c:::::J OUTLINE OF NEW -� - ------ --
MECH. EQUIP. SEE
NOTE S
I I I tJ . c:::::J -� - ; ', I
' I
/ I I I
./ I,, .
t::::::J OUTLINE OF NEW
-� -D -- ·- --.-
MECH. EQUIP. SEE
NOTE S
EXIST. ACCESS
HATCH ENTRANCE
TO SUMP (TYP. EA. -� -
n c:::::J --tJ c:::::J . -� -
. ; ' . I ' I
D c:::::J -� -b c:::::J OUTLINE OF NEW
MECH. EQUIP. SEE -. _ __ _ --_ ..
NOTE 6
I I I
26' -8 1/2"± (INSIDE FACE TO INSIDE FACE OF SUMP)
COOLING TOWER PLAN - STRUCTURAL
SCALE: 3/16" = 1' - 0"
I
5'
EXIST. CHEMICAL
TREATMENT BLDG.,
SEE E5/S-111 FOR
NEW TANK LOCATION
& NEW FRAMING
MEMBERS
AL
4" THICKNESS OF SHOTCRETE
ONG INSIDE FACE OF EXIST.
NC. WALL. (TYP. ALONG EAST
LL, BETWEEN CONG. PIERS)
co
WA
NE
co
W CONG. PIER @
OLING TOWER SUMP
#3, (1) LOCATION IN
MP PIT #3. SEE NOTE 1
R NEW PIER AND NOTE
OR DEMO. OF EXIST.
PIT
SU
FO
2 F
EXI
@C
ST. CONG. PIERS
DOLING TOWER
P PIT (TYP. EA.
P PIT BAY- TO
AIN, U.N.O.)
SUM
AS
"iiiiiij S-501
SUM
REM
EXI ST. W12x BEAMS
FO R EQUIP. SUPPORT
P. EA. SUMP PIT (TY
BA Y - TO REMAIN)
EXI ST. CONG. WALL
TWEEN COOLING
WER SUMP PITS
P., TO REMAIN)
BE
TO
(TY
�q_-
NE
co
W CONG. PIERS @
OLING TOWER SUMP
#2, (2) LOCATIONS IN
MP PIT #2. SEE NOTE 1
R NEW PIER AND NOTE
OR DEMO. OF EXIST.
PIT
SU
FO
2 F
EXI ST. STEEL BEAM
JACENT TO EXIST.
NC. WALL (TYP.
LL LENGTH ALONG
ST EL. OF SUMP
AD
co
FU
EA
PIT S - TO REMAIN).
SE E NOTE 3 FOR
RROSION REPAIR. co
NE W CONG. PIER@
OLING TOWER SUMP
#1, (1) LOCATION IN
MP PIT #1. SEE NOTE 1
R NEW PIER AND NOTE
OR DEMO. OF EXIST.
co
PIT
SU
FO
2 F
EXI ST. CONG. WALLS
PERIMETER OF
OLING TOWER
MP PITS.
co
SU
5'
EXIST. CONG. SLAB
ON GRADE. T/SLAB
EL.= 100' -0" (TO REMAIN).
NEW MECH. TANK.
SEE NOTE 2 ---
7 8
10' -0" (V.I.F., INSIDE FACE TO
INSIDE FACE OF CONG.
WALL AROUND OPNG.)
EXTENTS OF EXIST. FLR.
GRATING (SEE NOTE 4)
3'-3" 4'-6"
EXIST. L4x4x1/4xCONT.
AROUND PERIMETER
OF OPNG. T/ANGLE
EL.= 99'-11" (TYP, TO
REMAIN)
INSIDE FACE
OF EXIST.
CONG. WALL
"==t== ===1= = ==t= ===1=77
NOTES:
PERIMETER STRUC.
OF EXIST. CHEM.
BLDG. (TO REMAIN)
ES
CL OF NEW
MECH. TANKS
EXIST. STEEL
MEMBERS.
SEE NOTE 1
CHEMICAL TREATMENT BLDG. PLAN - STRUCTURAL
SCALE: 1/4" = 1' - O"
NOTES:
1. EXISTING CS STEEL CHANNELS BELOW EXISTING FLOOR GRATING, SPANNING BETWEEN L4x4 ANGLES AT
PERIMETER OF BASIN OPENING. (TYP. U.N.O.). CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS OF
GRATING/STEEL SUPPORT SYSTEM PRIOR TO ANY NEW WORK.
2. NEW BRINE TANK (ASSUMED MAX. WEIGHT OF 4950 LBS) TO BE PLACED ATOP EXISTING CONCRETE SLAB ON
GRADE. REFER TO MECHANICAL DRAWINGS FOR TANK INFORMATION AND PLACEMENT LOCATION.
3. NEW RESIN TANKS (QUANTITY 2, EACH WITH MAX. WEIGHT OF 3850 LBS) TO BE PLACED ATOP THE EXISTING FLOOR GRATING/NEW STEEL BEAM SYSTEM. REFER TO MECHANICAL DRAWINGS FOR TANK INFORMATION.
NOTIFY CONTRACTING AUTHORITY IF PLACEMENT CHANGES FROM WHAT IS SHOWN ON PLAN.
4. EXISTING STEEL GRATING SHALL REMAIN AT EXTENTS OF OPENING. REINSTALL GRATING AFTER NEW STEEL
HAS BEEN INSTALLED (BELOW).
4'
NEW MC6x12 BEAMS
BELOW NEW MECH.
TANKS.
NEW MECH. TANKS.
SEE NOTE 3
1H-+-- EXIST. 1" METAL
FLOOR GRATING
(TO REMAIN)
2' o 4'
1. NEW 2'-0"x8"x7'-6"+/- CONCRETE PIERS AT EXISTING PIER LOCATIONS, ( 4 LOCATIONS TOTAL SHALL BE VERIFIED IN FIELD. 2 LOCATIONS
FIELD VERIFIED IN SUMP PIT tr2 AND 1 LOCATION IN EACH OF SUMP
PIT #1 AND #3). SEE PHOTOS C7/S-111 AND A7/S-111 FOR CONCRETE
DETERIORATION IN SUMPS #1 AND #3. CONTRACTOR SHALL FIELD
VERIFY ALL EXISTING CONCRETE CONDITIONS IN SUMPS AND
NOTIFY COR IF ANY FURTHER CONCRETE DETERIORATION IS
OCCURRING.
C7
TOWER 1 SUMP - DETERIORATED CONCRETE PIER
2. CONTRACTOR SHALL DEMOLISH EXISTING PIERS PRIOR TO
CONSTRUCTION OF NEW PIERS ( NEW PIERS TO BE PLACED AT SAME
LOCATION AS THE EXISTING PIERS BEING REMOVED). CONTRACTOR
SHALL FIELD VERIFY ANY DOWEL CONNECTION BETWEE N
PIERS/PERIMETER WALL AND NOTIFY COR OF THE EXISTING
CONNECTION CONDITIONS. SEE DETAIL A6/S-501 FOR EXISTING
3. EXISTING STEEL BEAMS WITH CORROSION AND RUST PRESENT.
CONTRACTOR SHALL CLEAN AND REMOVE ALL EXISTING
CORROSION/RUST FROM STEEL BEAMS AND FASTENERS AT THIS
LOCATION AND APPLY A COLD GALVANIZING REPAIR PAINT .
CONTRACTOR SHALL FIELD VERIFY EXISTING STEEL IN ALL SUMPS
A Tl Y O IF O S F TE L C 10 IS O U RI G.
0 CT R H L R VI E O I IS IN S M Pl AND
SCALE: N.T.S.
a:: - ..J.., LL UJ t- tC/J 0 -z
X UJ UJ UJ LL C/J
o�C/J (.') t- z z-
UJ
8(.')
SOUTHWEST SOUTHEAST
STEEL STRUCTURE PRIOR TO/DURING DEMOLITION OF CONCRETE
PIERS.
5. PROVIDE INTEGRAL WATERPROOFING ADMIXTURE TO CONCRETE
MIX DESIGN FOR ALL NEW CONCRETE APPLICATIONS
NORTHEAST """
ROOM WING
6. -·-·--- INDICATES EXTENTS OF NEW MECHANICAL EQUIPMENT. REFER
TO MECHANICAL DRAWINGS FOR LOCATION OF NEW EQUIPMENT,
INCLUDING PENETRATIONS THROUGH SUMP WALLS & FLOOR
PLATES. NEW EQUIPMENT PLACEMENT AND RAIL SYSTEM SHALL
KEY PLAN
BE SIMILAR TO EXISTING AND BE CENTERED ON STEEL BEAMS
{BELOW).
7. PROVIDE CRYSTALLINE WATERPROOFING APPLICATION TO ALL
EXISTING CONCRETE SURFACES INTERNAL TO SUMP. SEE
SPECIFICATION SECTION 07 16 16 FOR INFORMATION ON
APPLICATION PROCESS FOR WATERPROOFING.
8. SEE SPEC SECTION 03 37 13 FOR SHOTCRETE APPLICATION AND
9. SEE DETAIL A1/S-501 FOR EXISTING CONCRETE REPAIR
PROCEDURES AND QUANTITIES AT REMAINING LOCATIONS
THROUGHOUT SUMP EXTENTS (DOES NOT INCLUDE REPAIRS AT
PIERS TO BE REPLACED AND WALL TO RECEIVE SHOTCRETE
APPLICATION).
A?
TOWER 3 SUMP - DETERIORATED CONCRETE
SCALE: N.T.S.
SCALE: NTS
NORTH
PIER
I
INDOOR AANGE
ICLE
LTER
US Army Corps of Engineers ®
UJ - !;;: - □
t- z z 0 UJ fiC ::;; 0.
□ 0::
z () w Cl)::; UJ ci"' co"'··OZco ci 9 zO
0 z□
- 0:: t- a, !;,;o �� u-
□� t- 0:: � a: . : (0 UJ "' -o ... a g"' 00'>
::::,� _,_ z� ZN Cl) ::::, @3: 8 3: "' :g
'!,.., 0..., □ ..J
..J (.') < :a:
zoo·
0:: □ 0. "7 w QC/)
£1 � "'() >- o. □ zg
ID
< :E u..i -C/J 0:: :a: 0:: OCI) "'() N
C/J UJ �- ::::, UJ _z
□ Cl) □ Cl) () Cl) Cl)< Cl)< t: � 0. "' c:owo� 0� � 0:: I ·- C
� C!>Q "' .
LL��� a::> � --,:"' 0:: 0. LU � '< tfj
:a:
::e � a.:;�� Q)-� wz-,:
$��� 88 ,-(.') ��-"uo::
a, I :S: "t--
SHEET ID
S-111
CERTIFIED FINAL
W
2Q R
R
-0
E
D
C
B
A
1 2
CRACKING (WET/DRY)
ALONG FACE OF
CONC. SURFACES ------r
EXIST. REINF. BARS
WITHIN CONC. WALL
(V.1.F.)
EXTERIOR FACE
OF EXIST. CONC.
(WALL)
SPALL SURFACE
w/ CORRODED REINF.
BARS EXPOSED
• \• (REDUCTION IN
EXIST. REINF.
AREA<25%)
• • INTERIOR FACE
OF EXIST. CONC.
(WALL)
REPAIR PROCEDURE:
1. CONTRACTOR SHALL DETERMINE EXTENTS OF
SOUND CONCRETE AROUND SPALL SURFACE.
2. PROVIDE 3/4" (MAX.) DEEP SAWCUT (SAWCUT
SHALL NOT CUT THROUGH ANY EXISTING
REINFORCING BARS). EXTENTS OF SAWCUT
SHALL BE 2" BEYOND EXTENTS OF SPALL AREA.
(SAWCUT SHALL BE AT 20" ANGLE ALONG DEPTH)
3. REMOVE ALL LOOSE CONCRETE FROM AREA BY
METHODS NOT DAMAGING EXIST. REINF. BARS.
4. CHIP AWAY ANY CONCRETE FROM ALL SIDES OF
EXIST. REINF. & CLEAN ALL CORROSION FROM
REINF.
5. APPLY A CORROSION RESISTANT COATING TO
REINF (COATING SHALL ACT AS AN ANTI
CORROSION PRIMER AND BONDING AGENT).
6. APPLY BONDING MATERIAL TO EXPOSED
CONCRETE SURFACE & PATCH w/ POLYMER
MORTAR
7. SEE SPEC SECTION 03 01 00.
SPALLING SHALL BE ASSUMED
TO OCCUR OVER A TOT AL
AREA OF 750 SQ FT FOR ALL
CONCRETE SURFACES WITHIN
THE SUMPS
MISCELLANEOUS CONCRETE REPAIRS
SCALE: 1" = 1' - O"
�- PORTION OF EXIST.
CONG. SURFACE w/
REPAIR REQUIREMENTS
(FOR ILLUSTRATION
PURPOSES ONLY)
CRACK (INJECTION)
REPAIR PROCEDURE
(ASSUMED FOR A TOTAL OF
100 LF OF WALL SURFACE):
U T XI . CRACK
(TO SIZE) TO ALLOW FOR INJECTION
OF CRACK REPAIR MATERIAL (PER
MANUF. INSTRUCTIONS).
2. CLEAN CRACK OF ANY LOOSE OR
FOREIGN MATTER BY BRUSHING OR
CHIPPING METHODS..--- CONC. SURFACE SPALL
ALONG FACE OF CONC.
3. PROVIDE APPROPRIATE INJECTION
COMPOUND:
A. EPOXY INJECTION FOR CRACKING
w/ NO MOISTURE EVIDENT AT CRACK.
B. CEMENTITIOUS (POLYMERIZED)
MORTAR INJECTION FOR CRACKING
w/ MOISTURE EVIDENT AT CRACK
C. SEE SPEC SECTION 03 01 00 FOR ADD'L
PRODUCT INFORMATION
4. CLEAN SURFACE OF EXCESS COMPOUND
& SEAL CRACK AS NECESSARY.
REPAIR PROCEDURE:
UJ UJ
UJ >
(/) 0
EXIST. REINF. BARS
WITHIN CONC. WALL
(V.I.F.)
NEW REINF. BAR
& MECH. COUPLER.
SEE NOTE 6
SPALL SURFACE
w/ CORRODED REINF.
BARS EXPOSED
(REDUCTION IN
EXIST. REINF.
AREA>25%)
EXIST. REINF. BARS
w/ NO CORROSION
EVIDENT
__..- INTERIOR FACE
OF EXIST. CONC.
(WALL)
1. CONTRACTOR SHALL DETERMINE LOCATION
OF EXIST. REINF. BARS WHERE LOSS OF SECTION
IS NO LONGER EVIDENT.
2. REMOVE EXIST. CONC. 3" (MIN.) BEYOND THIS
LOCATION.
3. PROVIDE 3/4" (MAX.) DEEP SAWCUT (SAWCUT
SHALL NOT CUT THROUGH ANY EXISTING
REINFORCING BARS). THE SAWCUT SHALL BE
BEYOND EXTENTS OF NON-CORRODED REINF.
BARS.
4. REMOVE ALL LOOSE CONCRETE FROM AREA BY
METHODS NOT DAMAGING ANY EXIST. REINF. BARS.
5. APPLY A CORROSION RESISTANT COATING TO
REINF EXPOSED & REMAINING REINF. BARS (COATING
SHALL ACT AS AN ANTI CORROSION PRIMER AND
BONDING AGENT).
6. INSTALL MECHANICAL COUPLERS TO EXIST. REINF.
BARS & PROVIDE NEW REINF. BARS OF SAME SIZE
& SPA. TO COUPLERS. COAT NEW REINF. BARS w/
CORROSION RESISTANT COATING.
7. APPLY BONDING MATERIAL TO EXPOSED CONCRETE
SURFACE & PATCH w/ POLYMER MORTAR
8. SEE SPEC SECTION 03 01 00
0 1' 2'
EXIST. 1" METAL
GRATING TO BE
RE-INSTALLED AFTER
NEW STEEL BEAMS
INSTALLED.-----.__
EXIST. SLAB ON
GRADE. SEE PLAN
FOR EL. ------...
EXIST. CONC. WALL
@ BASIN (TYP AROUND
PERIMETER) ----�
INSIDE FACE OF
EXIST. CONC.
SUMP WALL ----.__
EXIST. W12 BEAM
TO REMAIN. SEE
NOTE 4 ON S-111 FOR
SHORING DURING
EXIST. PIER REMOVAL
F6
LOCATION TO MATCH EXIST.
L4x4 TO )-
.-,-...,t:'
MC6 3/16
� NEW MC6 CHANNEL
BELOW EXIST. GRATING.
SEE PLAN FOR SIZE &
LOCATION.
NEW L4x4x1/4 BETWEEN
NEW MC6 & EXIST. STEEL
BEAMS (TO REMAIN).
LOCATION SHALL BE
SIMILAR TO MEMBER
BEING REMOVED.
CHEMICAL BLDG. FRAMING DETAIL
SCALE: 3/4" = 1' - O"
4" (THICKNESS OF NEW
SHOTCRETE LAYER
BETWEEN CONC.
PIERS , SHOWN BEYOND)
1'-0"+/- (THICKNESS
OF EXIST PERIMETER
SUMP WALL)
1' 6" 0 1'
NOTE: I
ALL STRUCTURAL WORK SHALL BE SEQUENCED WITH
> MECHANICAL EQUIPMENT INSTALLATION. REFER TO
SHEET G-003 FOR PHASING/SEQUENCING COORDINATION. 1
EXIST. EXT.
BLDG WALL
EXIST. L4x4 (w/ ANCHORS
INTO WALL)@ TOP OF
CONC. WALL (TO REMAIN -
TYP. AROUND PERIMETER)
EXIST. CONC. WALL
@BASIN (TYP
AROUND PERIMETER)
.....__ L6x6x3/4x6" LG., w/ (2)
5/8" DIA. EPOXY ANCHORS.
EMBED. 4" INTO CONC.
WALL. CENTER L6x6 ON
NEW MC6 BEAM (TYP. EA.
END OF NEW MC6)
& NOTE 3 FOR CLEANING =
OF ANY CORROSION
± T/NEW CONC. PIER
( EL. 107'-6"+/- (V.I.F.
MATCH EXIST.)
PROVIDE (3) #4
STIRRUPS@
TOP OF PIER ---
NEW CONC. PIER. SEE
A1/S-111 FOR LOCATION
OF NEW PIERS & NOTE
1 FOR DIMS. ----�
#5 x 18" LG. DOWEL
@ NEW STIRRUP
LOCATIONS. EMBED.
& EPOXY 6" INTO
EXIST. CONC. WALL ----
PROVIDE #3 BARS
@ 12"oc, EA. WAY, CENTER IN NEW
SHOTCRETE LAYER
(BEYOND). EXTEND
HORIZ. THRU NEW
PIER. ----------
PROVIDE #4
STIRRUPS@
12"oc (MAX) ALONG
HEIGHT OF PIER _ ___,
EXIST. 10" CONC.
BASE SLAB (REINF.
NOT SHOWN FOR
CLARITY) ---�
r __ ...r:::�::1:,d r---tr--- NEW GROUT PAD
BELOW EXIST.
BEAM
EXIST. SUMP WALL
@ PERIMETER w/
EXIST. REINF
(PER AS-BUIL TS)
,......-- EXIST. DOWELS BETWEEN
SLAB & PIER (QUANTITY 6).
DOWELS TO REMAIN PER
EXIST. CONDITION.
CONTRACTOR SHALL
VERIFY QUANTITY &
CONDITION. NOTIFY
COR IF DOWEL REQUIRES
REPAIR
A6
PIER REPLACEMENT DETAIL
SCALE: 3/4" = 1' - O" 1' 6" 0 1'
INSIDE FACE OF
EXIST. CONC.
SUMP WALL -�
PROVIDE #3 BARS
@ 12"oc, EA. WAY, CENTER IN NEW
SHOTCRETE LAYER
(BEYOND). EXTEND
HORIZ. THRU NEW
PIER.
#4 STIRRUPS@
12"ocALONG
HEIGHT OF PIER
NEW CONC. PIER.
NEW (6) #6 VERT.
BARS IN NEW
CONC. PIER -�
4" (THICKNESS OF NEW
SHOTCRETE LAYER
BETWEEN CONC. PIERS)
1'-0"± (THICKNESS
OF EXIST PERIMETER
SUMP WALL
EXIST. SUMP WALL
@ PERIMETER (EXIST
REINF. NOT SHOWN
FOR CLARITY)
#5 x 18" LG. DOWEL
@ NEW STIRRUP
LOCATIONS. EMBED.
& EPOXY 6" INTO
EXIST. CONC. WALL
@1--�-=-�-: �-,4--�-�1-· - -o-,, --------,.,1,-s=·-o=----1·
US Army Corps of Engineers ® ci"' co "'··O Zco ci 9 zO
0 z□
- 0:: >- a, !;,;o �� u- □� >- 0:: � a:UJ "' -o >- 0 g"' =i � ...J- z� (/) =i @3: 8 3: '!, -, 0::
£1 � "'() >- a.
zg
"'<C (/) 0:: :a: 0:: OCI)
UJ �-□ (/) □ (/) () (/)
"' a. "'
=i" c:owo�
� 0:: I � C!>Q
LL��� � -<C"' 0:: a.
� '< tfj :a:
a.:;�� WZ<(
,-(.') ��-"uo::
a, I :S:
UJ
>- z z 0 UJ f'= :;; a.
□ 0::
z () UJ (/)
:;; UJ
. : (0 Om zN "' :g a..., □
...J
...J (.') <( :a: zo o ·"' i=O
□ a."?
UJ OC/l
□ :E u..i -"'() N C/l =i UJ _z t: � 0�
·- C a::>
LU
::e � Q)·-
C/)�
- 1-�u w ::::> Oil'. I
C/)
SHEET ID
S-501
CERTIFIED FINAL
W
2Q R
R
-0
E
D
C
B
A
9 " i µ L i-- 10"
T i
NEW SLAB/FLOOR MOUNTING
DETAILS FOR REMOVABLE
RAILINGS. SEE SHEET A301
WHERE LOCATED AND ALSO
PLAN VIEW#2
5" j
�1/2�
1'-0 1/2"
5" J
_j
;,. t .------+---IIll
11 II
NEW WALL MOUNTING DETAILS
FOR REMOVABLE RAILINGS.
SEE SHEET A301 WHERE
LOCATED AND ALSO PLAN
VIEW#2
NOTE:
1. PLATE AND MOUNTING TUBES
TO BE DESIGN BY RAILING
MANUFACTURER.0
E1
LJ
10"
RAILING BRACKETS
SCALE: 3" = 1' - o• 0 2" 4" a· - -
2. RAILING SYSTEM TO BE
FASTENED TO EXISTING
CONCRETE w/ 1/2"0 EPOXY
ANCHORS. EMBED 4 1/2"
INTO EXIST. CONCRETE
1' - -
NEW GALVANIZED PIPE ---
RAILING, SLAB
MOUNTED AND EACH
SECTION REMOVABLE
1 3/4"
INDICATES DIMENSION
TO CENTERLINE OF .
RAILING POST. - -
TYPICAL "'
N
I
NEW INSULATED METAL
PANELS ON NEW
CONCRETE CURB
N
3 1/2" 7'-10"
B"CONC CURB
ID
er:
u u z
2 1/2"
2 1/2" 7'-9 3/4"
N
I w
NEW GALVANIZED PIPE
RAILING, TOP OF WALL
MOUNTED AND EACH
SECTION REMOVABLE
�- EXISTING CONCRETE
FILLED PANELS TO BE
REMOVED
---- EXISTING LEDGE FOR
PANEL TO SEAT
SHALL REMAIN AT
PERIMETER
I E1 N
NEW GALVANIZED PIPE
RAILING, WALL ½ MOUNTED AND EACH in
SECTION REMOVABLE �-
N
I
I
I
I
I
I
I
I
I
'--,I_ I
N
I
I
I
I
I
I
I
I
I
I
I
..._�, EXISTING PIPE ------If--.
PENETRATIONS THROUGH
CONCRETE SLAB TO REMAIN
NEW DUCT PENETRATION. --'-_,;_ _____ .__
SEAL WATER TIGHT TO ro I
I
'----..ck- J
CONCRETE SLAB
NEW GALVANIZED PIPE
RAILING, WALL
MOUNTED AND EACH
SECTION REMOVABLE
6'-4"
5" 5• u u z
II
en
I
I I I I I I
I
__ J_J
I
I
I
_____________ _J
EXISTING AREA WELL - NEW WORK
SCALE: 1/4" = 1' - O" 4'
r-- EXISTING f
STOREFRONT
VESTIBULE TO
REMAIN
)-H!---- EXTENT OF AREA
WELL BELOW
L
2' 0
(2) #5 , HORIZ., CONT.
ALONG LENGTH OF
PERIMETER CURB
NEW CONG. CURB --�
AROUND PERIMETER
OF AREA WELL
OPENING. SEE PLAN
FOR LOCATION ON
(4) SIDES
TOP OF EXIST. ---.._
CONG. AROUND
AREA WELL
OPENING
SEE PLAN #2 BELOW ,
I I I
8"
1 1/2"
CLR.
;r
�1 w
:-1 w
� .l
8 9
GENERAL NOTES (DRAWINGS SHOW DESIGN INTENT):
A. EXISTING AREA WELL DEMOLITION:
B.
REMOVE ALL SEALANTS AND PREP SURFACES FOR NEW WORK
REMOVE EXISTING CONCRETE FILLED PANS CURRENTLY USED AS REMOVABLE
PANELS
REMOVE SEALANTS AND PREP FOR NEW WORK ALONG NORTH EDGE OF AREA WELL
REMOVE ALL LOOSE CONCRETE AND APPLY PROPER CONCRETE PATCHWORK TO
RESTORE TO ORIGINAL CONDITION AS MUCH AS PRACTICABLE
EXISTING AREA WELL NEW WORK
EXISTING POCKET THAT CONTAIN EXISTING PANELS AND LEDGE ANGLES ARE TO
REMAIN. PAINT ANCHORS TO REDUCE CORROSION AND SEAL ALL JOINTS
P ROVIDE A NEW CONCRETE CURB (8" WIDE) AT PERIMETER AS SHOWN ON SECTIONS
ON SHEET A-301. PROVIDE A SLOPE FOR PANELS THAT AS A MINIMUM OF 1/2" PER
F T.
,.--.,,...RO E A (A OLA N M ERi.A; ON
MATERIALS AND PREVENT CORROSION
P ROVIDE REINFORCED INSULATED METAL PANELS THAT SEAL TO EACH OTHER
WATERTIGHT AND OVERLAP CONCRETE CURB. METAL PANEL SHALL BE CAPABLE OF
SUPPORTING 300 LBS CONCENTRATED LOAD ASSOCIATED WITH MAINTENANCE
WORKERS.
PANELS SHALL HAVE A DRAINAGE SYSTEM THAT LEADS TO DRAINAGE BEYOND CURB.
PANELS SHALL BE SIZED TO BE MANUALLY REMOVED AND REPLACED INTO POSITIONS
SHOWN. PROVIDE HANDLES THAT ARE ACCESSIBLE. SIZE OF PANELS SHALL BE
#4 LI-BAR @ 48"oc ALONG -+--
LENGTH. EMBED & EPOXY
I
BASED ON ABILITY TO PHY SICALLY REMOVE THEM MANUALLY BY A MINIMUM OF 2
PEOPLE. (SUGGEST THAT 4 HANDLES BE PROVIDED, 2 ON EACH END, INSTALL
'--_.l,f.lliN.!;��!JI J,IA-M.!:::FAc::i{LJI D N P S �E !,IE'J\rtJ:..J.��Eif"__,, VERT. LEGS 6" INTO EXIST.
CONG. (TYP. ALONG EAST,
WEST, & SOUTH ELS.).
PROVIDE SINGLE LEG
DOWEL @ 48"oc ALONG
NORTH EL., CENTER IN
CURB
E5
CONCRETE CURB DETAIL
SCALE: 3" = 1' - O" 0 2" 4• 6" - --
ft
F
I
1'
E1
OF THEIR INTEGRITY)
PANELS SHALL BE LOCKED INTO POSITION FROM INSIDE OF AREA WELL FOR
SECURITY. SEE DETAIL ON SHEET A301 SHOWING SPRING LOADED LATCH. PANELS
ARE DESIGNED TO BE REMOVED AND REPLACED IN SEQUENCE WITH THE NORTH
PANEL TO BE THE FIRST REMOVED AND LAST TO BE REPLACED.
C. ADDITIONAL NEW WORK:
PROVIDE GALVANIZED RAILINGS SIMILAR TO THOSE SHOWN ON SHEET A-301.
RAILINGS SHALL BE MOUNTED ON THE FACE OF EXISTING CONCRETE ON THE WEST
AND SOUTH SIDE.
RAILINGS SHALL BE MOUNTED ON THE TOP OF CONCRETE WALL ON THE EAST SIDE
RAILINGS SHALL BE MOUNTED ON THE EXISTING CONCRETE SLAB ON THE NORTH
SIDE
.,,-- EXISTING CONCRETE
FILLED PANELS TO BE
REMOVED
EXISTING LEDGE FOR
PANEL TO SEAT
SHALL REMAIN AT
PERIMETER
r-- EXISTING f
STOREFRONT
VESTIBULE TO
REMAIN
I I ________________ : ---1 '>--Ill--- EXTENT OF AREA
I WELL BELOW
! EXISTING PIPE -------...
PENETRATIONS THROUGH
CONCRETE SLAB TO REMAIN
NEW DUCT PENETRATION. --�-----.,
SEAL WATER TIGHT TO
CONCRETE SLAB
II
II
u
I I I I I I
I
==:J_J
I
I
I
_____________ _J
I '
SOUTHWEST
SOUTHEAST
NORTHEAST
ROOM WING
KEY PLAN
A5
DN-
EXISTING AREA WELL - DEMOLITION
SCALE: 1/4" = 1' - O" 4'
SCALE: NTS
2' 0 4'
I
INDOOR AANGE
VEHICLE
SHELTER
US Army Corps of Engineers ®
SHEET ID
A-101
� LJ.J
lg t- z z 0 w f'= :;; D..
□ 0::
z uw en :;; w
CERTIFIED FINAL
W
2Q R
R
-0
D1
D3
F1
3 4
SK-1
WH-1
ES-12" SAN 11 EWH-1
CO
SP-1
3"13
RPZ-2
3"12
S O
LI
C
IT
A
TI
O
N N
O
O P
TI
O
N A
L
FI
E
LD
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
P
N O
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
A
M E
N D
M E
N T
8/
CERTIFIED FINAL
D S
N Z
H
TV
R
E P
A
IR
C H
IL
LE
D W
A
TE
R S
Y S
TE
M
, F A
C
IL
IT
Y
W
R
IG
H T
P A
TT
E
R S
O N
A
FB
B
D
E
F
G
2 4 6 8 10
W
2Q R
-1 8-
D -0
JU
LY
TH
C
IV
IL
E
N G
IN
E
E R
IN
G
G R
O U
P
W
R
IG
H T
A V
E . W
P A
FB
O
H
W
PA
FB
W
R
IG
H T-
P A
TT
E
R S
O N
A
IR
F O
R C
E B
A S
E W
2Q
R
R
A N
S I D
A E
C
NORTH
US Army Corps of Engineers
SCALE:
KEY PLAN
NTS
PHASE II
OFFICE
COMPLEX
PHASE I PHASE III
NORTHEAST
LAB
TOWER WING
SOUTHWEST
LAB
SOUTHEAST
LAB
SUPPORT
WING
CLEAN
ROOM WING
VEHICLE
SHELTER
7/17/2020
SHEET KEYNOTES:
1. DEMOLISH ONE COMPARTMENT SINK AND ALL ASSOCIATED WATER AND SANITARY
PIPING. REFER TO PHOTO B. SINK UNDERCOATING CONTAINS ASBESTOS-CONTAINING
MATERIAL. ASBESTOS-CONTAINING FURNITURE SHALL BE REMOVED IN ACCORDANCE
WITH WPAFB SPECIFICATION SECTION 02 08 10.
2. DEMOLISH EMERGENCY SHOWER/EYE-WASH COMBINATION. REFER TO DETAIL D3 ON
THIS SHEET.
3. PROVIDE FREESTANDING SINK. ROUTE SANITARY PIPING ABOVE SLAB AND CONNECT
TO NEW SUMP PUMP. PROVIDE NEW COLD AND HOT WATER PIPING AS DESCRIBED
ON SHEET P-501.
4. PROVIDE EMERGENCY SHOWER/EYE-WASH COMBINATION. REFER TO DETAIL A2 ON
THIS SHEET. CONNECT TO SANITARY PIPING ABOVE SLAB.
5. PROVIDE "TEPID-WATER" ELECTRIC WATER HEATER FOR EMERGENCY FIXTURES.
PROVIDE NEW COLD AND HOT WATER PIPING AS DESCRIBED ON SHEET P-501.
6. PATCH EXISTING FLOOR AROUND FLOOR DRAINS TO ALLOW FOR PROPER DRAINAGE.
SEE DETAIL F1 ON THIS SHEET.
7. PROVIDE DUPLEX SUMP PUMP (SP-1) WITH MANUFACTURER'S CONTROL PANEL.
RECONNECT EXISTING DRAIN LINES TO NEW SUMP PUMP BASIN. REFER TO DETAIL
A5/P-501. INTERFACE PUMP CONTROL PANEL TO THE BMS. REFER TO M-705 FOR
INTEGRATION POINTS.
8. SANITARY OUTLET FROM SUMP PUMP TO REMAIN.
9. DEMOLISH SUMP PUMP.
10. RECONNECT SUMP PUMP DISCHARGE TO THIS EXISTING CONNECTION.
11. PROVIDE POINT OF USE WATER HEATER AND POINT OF USE THERMOSTATIC MIXING
VALVE SIMILAR TO BRADLEY MODEL S59-4016. REFER TO PLUMBING SCHEDULE ON
THIS SHEET FOR ADDITIONAL INFORMATION. INSTALL PER MANUFACTURER'S
RECOMMENDATIONS.
12. RESIN TANK REGENERATION DISCHARGE LINE. PROVIDE 3" SANITARY LINE BELOW
EXISTING SLAB AND DISCHARGE INTO NEW SUMP PUMP. SLOPE PIPE AT 1/8" PER FT.
TOWARDS SUMP. REFER TO M-111 FOR CONTINUATION.
13. ROUTE PIPING OVERHEAD NO LOWER THAN 80" ABOVE FINISHED FLOOR. PROVIDE
ENOUGH CLEARANCE THAT A PALLET JACK AND FULL PALLET OF SALT CAN PASS
UNDERNEATH PIPING WITH A 6" CLEARANCE. PROVIDE ADJUSTABLE PIPE SADDLE
FLOOR SUPPORTS WITH BASE PLATE AND STANCHION ROD IN THE LOCATION
SUGGESTED ON THE PLAN. EPOXY PIPE SUPPORT BASE PLATES TO EXISTING SLAB ON
GRADE. PIPE SUPPORTS SHALL BE SIMILAR TO ANVIL INTERNATIONAL PRODUCTS. 3"
PIPING SHALL NOT BE SUPPORTED FROM THE CEILING. REFER TO M-111 FOR
CONTINUATION.
GENERAL SHEET NOTES:
1. NOT ALL VALVES AND EQUIPMENT ARE SHOWN FOR CLARITY.
2. THE FOLLOWING SURFACES IN THE CHEMICAL TREATMENT BUILDING TESTED
POSITIVE FOR LEAD CONTENT IN EXCESS OF THE EPA REGULATORY THRESHOLD OF
1.0 MG/CM2: YELLOW CONCRETE CURBS. CONTRACTOR SHALL PERFORM LEAD
CONTAINING PAINT CONTROL MEASURES IN ACCORDANCE WITH WPAFB
SPECIFICATION 01 02 20.
3. AS-BUILT DOCUMENTATION OF BUILDING 618 DOES NOT EXIST. EXISTING SANITARY
PIPING OUTLET METHODS AND ORIENTATION ASSUMED.
32"
11-1/2"
83-1/2"
42"
10"
52-1/2"
7"
9"
8" DIA. BOLT CENTERS
18"
3/8" DIA
(3 HOLES)
SIGN
WALL
STAINLESS STEEL
EYEWASH
WASTE 1-1/4" NATIONAL PIPE
THREAD TO NEW SUMP PUMP
PUSH PLATE
FOOT PEDAL
BRACE
SUPPLY 1-1/4"
NATIONAL PIPE THREAD
STAINLESS STEEL
SHOWER HEAD
EMERGENCY PULL HANDLE
BASE MOUNTING DETAIL
SUPPLY 1-1/4"
NATIONAL PIPE THREAD
BRACE
PLUMBING FIXTURE SCHEDULE
TAG FIXTURE DESCRIPTION BASIS OF DESIGN
MANUFACTURER
BASIS OF DESIGN
MODEL #
SK-1 FIXTURE: 16 GA, STAINLESS STEEL, SINGLE BOWL, WELDED CONSTRUCTION FOR CONSISTENT METAL GAUGE THICKNESS, 14" DEEP
BOWL WITH 3/4" COVED RADIUS, 8" BACKSPLASH, 1-1/2" EDGE RIM DESIGN, 3-1/2" DRAIN WITH BASKET STRAINERS INCLUDED, 1-5/8"
GALVANIZED LEGS WITH 1" ADJUSTABLE FEET, LEFT SIDE DRAIN BORAD.
ELKAY WNSF8124L2
FAUCET: 3 3/8" BODY, ADJUSTABLE ARMS, SHORT SPOUT WITH PAIL HOOK AND 3/4" MALE HOSE THREAD OUTLET, VANDAL PROOF LEVER HANDLE, OFFSET INLET SUPPLY ARM WITH 1/2" NPT FEMALE THREAD INLET, CHROME PLATE FINISH.
CHICAGO 445-HCABCP
DRAIN WITH NICKEL PLATED BRASS BODY WITH GRID STRAINER, POLISHED FINISH. MCGUIRE 165LK, 8902
ES-1 SHOWER AND EYE/FACE WASH: 8" STAINLESS STEEL SHOWER HEAD WITH SPEAKMAN IMPELLER FACEPLATE.
VALVE: 1" NPFT 316 STAINLESS STEEL, STAY-OPEN BALL VALVE. ACTIVATED BY RIGID STAINLESS STEEL PULL ROD WITH TRIANGULAR HANDLE. 304 STAINLESS STEEL TUBE. 1-1/4" NPTF INLET AND DRAIN. 8" STAINLESS STEEL FLOOR FLANGE. UNIT HAS NATURAL BRUSHED STAINLESS STEEL FINISH. EYE/FACE WASH: VALVE: 1/2" NPFT 316 STAINLESS STEEL, STAY-OPEN BALL VALVE. ACTIVATED BY STAINLESS STEEL PUSH HANDLE. SPRAY HEADS:
AERATED OUTLETS IN BRASS SPRAY HEADS SUPPLY CONVERGING STREAMS TO PRODUCE A CURTAIN OF AERATED WATER. VOLUME CONTROLS IN EACH SPRAY HEAD ENSURE PROPER SPRAY PATTERN. BRASS WATERWAYS ARE SHIELDED BY "SAFETY" YELLOW POLYPROPYLENE COVERS. RECEPTOR: STAINLESS STEEL.
SPEAKMAN SE-623
RPZ-1 3" REDUCED PRESSURE ZONE ASSEMBLY WITH TWO CHECK VALVES, PRESSURE RELIEF VALVE, AND TWO BALL OR GATE VALVES. STANDARD ORIENTATION. PROVIDE INDIRECT DRAIN WITH AIR GAP FITTING. REFER TO SHEET M-111.
FEBCO MASTERSERIES
880V
RPZ-2 3" REDUCED PRESSURE ZONE ASSEMBLY WITH TWO CHECK VALVES, PRESSURE RELIEF VALVE, AND TWO BALL OR GATE VALVES. STANDARD ORIENTATION. PROVIDE INDIRECT DRAIN WITH AIR GAP FITTING. REFER TO SHEET M-111.
WATTS 957
WH-1 ELECTRIC, TEPID WATER DELIVERY SYSTEM FOR EMERGENCY FIXTURES, 3" THICK POLYURETHANE FOAM INSULATED TANK WITH FACTORY PACKAGED AND PIPED MIXING VALVE. 119 US GALLONS STORAGE CAPACITY, TEPID WATER TEMPERATURE = 85 DEG. F, SOLID STAINLESS STEEL CONSTRUCTION. PROVIDE 3 kW ELEMENT at 208V-1-60 - 14 amp.
HUBBELL EMV
EWH-1 ELECTRIC, POINT-OF-USE FOR SERVICE TO SK-1. 1/2" NPT CONNECTIONS. MOUNT UNDER SINK. FIELD REPLACEABLE HEATING ELEMENT. 4 US GALLONS STORAGE CAPACITY, HOT WATER TEMPERATURE RANGE = 50 - 140 DEG. F, ELECTRICAL: 110/120 VOLTS, 12 AMPS, 1440 WATTS, POWER PLUG OUTLET READY.
CHRONOMITE CMT-4.0
SP-1 316 STAINLESS STEEL SUBMERSIBLE DUPLEX PUMP. PUMP SHALL BE CAPABLE OF DISCHARGING INFLUENT OF 35 GPM AT 20' HD RESISTANCE. PROVIDE PUMP CONTROL PANEL TO DUTY CYCLE PUMPS. PUMP MOTOR CASING.
PUMP VOLUTE, IMPELLER, SHAFT AND EXTERNAL HARDWARE SHALL BE 316 SS. EACH PUMP MOTOR:
208V-3PH-60HZ, 3.5 FLA, 18.15 LRA. ONE CIRCUIT SIZED FOR BOTH PUMPS SHALL BE PROVIDED TO THE PUMP
CONTROL PANEL.
BJM Pumps JX08SS
P-111
C H
E M
IC
A
L
TR
E A
TM
E
N T
B U
IL
D
IN
G
P
LU
M B
IN
G
M .M
U
IR
K .F
IE
LD
S
C .D
A
LT
O N P
-1
.D W
G
01/4"=1'-0" 2' 4' 8'A5 ENLARGED PLAN - CHEMICAL TREATMENT BUILDING - PLUMBING - DEMOLITION
01/4"=1'-0" 2' 4' 8'C5 ENLARGED PLAN - CHEMICAL TREATMENT BUILDING - PLUMBING
NTSA2 DETAIL - EMERGENCY EYE WASH
NONED1
PHOTO - ONE
COMPARTMENT SINK
NONED3
PHOTO - EMERGENCY
EYE WASH/SHOWER
NONEF1 PHOTO - DAMAGED FLOOR
W
2Q R
R
-0
(E)8" (E)2"
(E)12"
(E)8" (D)P-6
(E)ET-1
(E)AHU-31
(E)1.5"
(E)4"
(E)AS-1
(E)AHU-5
GENERAL SHEET NOTES:
1. NOT ALL VALVES AND EQUIPMENT ARE SHOWN FOR CLARITY. REFER TO MD801 AND M-801.
2. ALL WORK ON THIS SHEET SHALL BE SEQUENCED. THE CHILLED WATER PLANT SHALL NEVER
HAVE LESS THAN TWO CHILLER SYSTEMS (CHILLER, PUMPS, TOWER) READY FOR OPERATION.
REFER TO SUGGESTED SEQUENCE OF CONSTRUCTION ON THE G-003 SHEET.
3. THE FOLLOWING SURFACES IN THE CHILLER ROOM TESTED POSITIVE FOR LEAD CONTENT IN
EXCESS OF THE EPA REGULATORY THRESHOLD OF 1.0 MG/CM2: YELLOW CONCRETE CURBS,
LIGHT BLUE CHILLER COMPONENTS, RED CONCRETE FLOOR, GRAY ELECTRICAL BOXES, BLUE
PUMPS, ORANGE PIPES, GRAY PIPES. CONTRACTOR SHALL PERFORM LEAD CONTAINING PAINT
CONTROL MEASURES IN ACCORDANCE WITH WPAFB SPECIFICATION 01 02 20.
(D)P-1
(E )1
2"
(E)VFD
(D)P-2
(D)P-5
MATCH LINE THIS SHEET
(D)CH-3
(D)12"
(D)P-4
(D)12"
(E)CWP-7
(D)12"
(D)12"
M
(E)P-9
(E)P-8
(E)P-7
(E)FD
(E)FD
(E )4
M
M
(D)P-37
(E)12"
(E)12"
(D)12"
(D)12"
(E)FM
SHEET KEYNOTES:
1. DEMOLISH CHILLER SYSTEM COMPLETE.
2. DEMOLISH CHILLER ACCESS STAIRS. REPAIR DAMAGE TO THE CONCRETE PAD BECAUSE OF THIS
WORK.
3. EVACUATE REFRIGERANT R-123 FROM DEMOLISHED CHILLERS. DISPOSE OF PER SPECIFICATION
SECTION 02 09 10.
4. DEMOLISH AUTOMATIC BACKWASH VALVE AND STRUCTURAL SUPPORT COMPLETE.
5. REMOVE CONDENSER WATER PIPING AS INDICATED ON PLAN. UTILIZE UPSTREAM 3-WAY VALVE AND
SUPPLY LINE BUTTERFLY VALVE TO ISOLATE THE CONDENSER WATER SYSTEM.
6. DEMOLISH LAKOS FILTER. CONCRETE PAD TO REMAIN. REPAIR DAMAGE TO THE CONCRETE PAD
BECAUSE OF THIS WORK.
7. DEMOLISH CONDENSER WATER PUMP AND CONCRETE PAD.
8. DEMOLISH CHILLED WATER PUMP AND CONCRETE PAD.
9. DEMOLISH CHILLED WATER PUMP DISCHARGE PIPING BETWEEN PUMP AND CHILLER.
10. DEMOLISH CHILLED WATER PUMP SUCTION PIPING BETWEEN RETURN HEADER TEE AND PUMP. PROVIDE
BLIND FLANGE CONNECTIONS AT TEE BRANCH. ISOLATE AND DRAIN THE MAIN CHILLED WATER
PLANT BY CLOSING THE SEVEN(7) PAIRS OF ISOLATION VALES INDICATED ON THE NEW WORK
PLAN. THIS WORK WILL REQUIRE AN OUTAGE OF THE CHILLED WATER SYSTEM PLANT. SCHEDULE
CONSTRUCTION WITH BASE CE AND AFRL WITH AT LEAST TWO WEEKS NOTICE OF WORK.
11. DEMOLISH CHILLED WATER SUPPLY PIPING AND APPURTENANCES FROM CHILLER TO NEAREST
ISOLATION VALVE AS SHOWN ON PLAN.
12. DEMOLISH BUILDING REHEAT RETURN PIPING AND APPURTENANCES FROM NEAREST ISOLATION VALVES TO CHILLER'S HEAT RECOVERY BUNDLE. THE REHEAT RETURN PIPING TO EACH CHILLER IS PARALLELED IN SERIES WITH THE SUCTION LINE TO THE REHEAT PUMPS. DO NOT REMOVE ALL THE HEAT RECOVERY PIPING AT ONCE, PUMPS WILL DEADHEAD. PROVIDE FULL SIZE BRIDGE PIPING
ACROSS THE LINES AS DESCRIBED ON THE M-101.
13. DEMOLISH REFRIGERANT MONITORING SYSTEM AND APPURTENANCES.
14. POWER OFF BOOSTER PUMP (CWP-7) AND CLOSE THE ISOLATION VALVES AS INDICATED.
15. CLOSE BYPASS BALANCE VALVE TO PROHIBIT FLOW THROUGH THE BYPASS LINE. PLACE A
PERMANENT TAG ATTACHED TO THE VALVE INDICATED THAT THE "VALVE MUST REMAIN CLOSED TO
PROHIBIT FLOW THROUGH BYPASS LINE".
16. DEMOLISH BUILDING REHEAT RETURN MAIN PIPING AS INDICATED ON PLANS. UTILIZE INDICATED ISOLATION VALVES ON MAIN RETURN LINE AND BRANCH ISOLATION VALVES. THIS WILL REQUIRE A
BUILDING HEAT PLANT ISOLATION AND SHUT DOWN TO REMOVE AND INSTALL BRIDGE PIPING.
COORDINATE THIS WORK DURING ANNUAL STEAM PLANT SHUTDOWN, TYPICALLY IN JUNE.
17. TEMPORARY REMOVE REFRIGERANT EXHAUST FAN, DUCTWORK AND GRILLES TO MAKE ROOM FOR NEW CHILLER INGRESS. RECONNECT FAN, DUCTWORK AND GRILLES ONCE NEW CHILLERS ARE RIGGED INTO PLACE. CLEAN DUCTWORK GRILLES AND EXHAUST FAN PER SPECIFICATION SECTION 23 01 30.41.
18. EXISTING CHILLER STARTER PAD LOCATION. REFER TO ELECTRICAL PLANS FOR MORE INFORMATION.
19. DEMOLISH ABANDONED GENERATOR ROOM VENTILATION FAN, VENTILATION FAN DUCTWORK AND
APPURTENANCES. REMOVE OUTSIDE GOOSENECK CONNECTION.
20. EXISTING 6" PVC REFRIGERANT VENT PIPING TO REMAIN. TEMPORARILY REMOVE AS NECESSARY TO
ALLOW FOR CHILLER INGRESS. REINSTALL ONCE CHILLER INSTALLATION IS COMPLETE. PVC
PRIMER/CLEANER AND ADHESIVES SHALL BE COMPATIBLE WITH THE CHILLER'S REFRIGERANT. REFER
TO THE CHILLER MANUFACTURER'S IOM FOR COMPATIBILITY INFORMATION.
21. TEMPORARILY REMOVE STEEL IN AREA WELL TO ALLOW FOR CHILLER INGRESS. REINSTALL STEEL
ONCE CHILLERS ARE RIGGED INTO PLACE.
22. DEMOLISH ABANDONED HVAC UNIT.
23. EXISTING ELECTRICAL CONDUIT TO REMAIN.
24. DEMOLISH FENCE, SUPPORT POSTS AND CONTAINMENT CURB.
25. DEMOLISH REFRIGERANT EVACUATION MACHINE.
26. DEMOLISH GANTRY CRANE.
27. EXISTING TALON CONTROL PANEL TO REMAIN. TC-24 PANEL HAS 6 SPARE INPUTS AND 1 ANALOG
OUTPUT AND 4 DIGITAL OUPUTS.
(E)12/16
(D )2
0" Ø
(D)12"
(E)PTAC
(E)20"Ø
(E)BTU-5
(E)BTU-4
(E)8" RISER TO SECOND
FLOOR (BTU-5 370 GPM*)
(E)1 1/4" RISER
TO FIRST FLOOR
(E)2-W
(D)CH-1
(E)3"
(E)8"
(D)CH-2 3
A
(E)16"
(D)12"10
(D)12"10
(E)8"
(E)8"
(E)12" CWS
(E)12" CWS
(E)REHEAT
WATER EXP
TANK
REFER TO MD111
(D )1
8" Ø
(E )1
2"
(BTU-7 3,374 GPM*
BTU-9 2,105 GPM)
TOTAL 5,479 GPM)
(BTU-6 48 GPM
BTU-8 180 GPM)
TOTAL 228 GPM)
(E)12"
(E)14"
(E)12/30
(E)4" RISER TO
FIST FLOOR
(BTU-4 129 GPM*)
(E)14" RHS
AND RHR
(E)FM
(E)12"
(E)12"
(E)SUMP
PUMP
(E)AHU-25
(E)8" RISER TO
FIRST FLOOR
(BTU-3 1,098 GPM)
(E)4" LASER LOOP
WATER IN PME
(E)3" RISER TO FIRST FLOOR
(BTU-2 51 GPM)
(E)3" (E)4"
(E)3"
(E)18" CWR HEADER
(E)18" CWS HEADER
(E)12" CWS
(E)FD
(E)FM
(D)14" RHR
(D)14" RHR
(D)12" RHR
(E)12"
RHR
(E)18" HPS HEADER
(E)CH WATER EXP TANK
(E)BTU-3
(E)14" RHS
(E)CPF-1
(E)4" RISER TO
FIRST FLOOR
(BTU-1 180GPM)
01/8"=1'-0" 4' 8' 16'A5 PARTIAL BASEMENT PLAN - ELECTRICAL - DEMOLITION
01/8"=1'-0" 4' 8' 16'A2 PARTIAL BASEMENT PLAN - ELECTRICAL - DEMOLITION
MATCH LINE THIS SHEET
NTSD2 PHOTO - EXISTING CONDITIONS
(E)4"
(E )3
(E)4"
(E )4
(E)3"
(E)3" (E)4"
MATCH LINE THIS SHEET
(E )3
(E)3"
(E)BTU-1
(E)4"
(E)BTU-2
(E)4" RISER TO
FIRST FLOOR
(E)3" RISER TO
FIRST FLOOR
(E)CWP-3
(E)2" BYPASS
(E)2"
(E)CWP-4
(E)CWP-1A
(E)4"
MATCH LINE THIS SHEET
S O
LI
C
IT
A
TI
O
N N
O
O P
TI
O
N A
L
FI
E
LD
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
P
N O
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
A
M E
N D
M E
N T
8/
CERTIFIED FINAL
D S
N Z
H
TV
R
E P
A
IR
C H
IL
LE
D W
A
TE
R S
Y S
TE
M
, F A
C
IL
IT
Y
W
R
IG
H T
P A
TT
E
R S
O N
A
FB
B
D
E
F
G
2 4 6 8 10
W
2Q R
-1 8-
D -0
JU
LY
TH
C
IV
IL
E
N G
IN
E
E R
IN
G
G R
O U
P
W
R
IG
H T
A V
E . W
P A
FB
O
H
W
PA
FB
W
R
IG
H T-
P A
TT
E
R S
O N
A
IR
F O
R C
E B
A S
E W
2Q
R
R
A N
S I D
A E
C
NORTH
US Army Corps of Engineers
SCALE:
KEY PLAN
NTS
7/17/2020
MD101
P A
R
TI
A L
B A
S E
M E
N T
P
LA
N M
E C
H A
N
IC
A L
- D E
M O
LI
TI
O N
E .L
A R
U E
K .F
IE
LD
S
G .L
E
IT
C H M
D
1.
D
W G
W
2Q R
R
-0
1. REFER TO SHEET MD101 FOR CONTINUATION.
2. DEMOLISH COOLING TOWER AND ALL ASSOCIATED CONTROLS AND APPURTENANCES.
3. DEMOLISH ABOVE GROUND CONDENSER WATER SUPPLY (TO THE COOLING TOWER)
PIPING AS INDICATED.
4. REMOVE BOLTED PLATE WHICH COVERS OPENING BETWEEN SUMPS. REFER TO NEW
WORK PLAN M-111. THIS WORK SHALL BE SEQUENCED PER INSTRUCTION ON SHEET G-003.
5. CONCRETE PIERS TO BE REPAIRED. REFER TO STRUCTURAL PLAN FOR MORE
INFORMATION.
6. DEMOLISH SULFURIC ACID TANK. SAFELY DISPOSE OF SULFURIC ACID PER
SPECIFICATIONS AND PROVIDE DOCUMENTATION OF SAFE DISPOSAL.
7. DEMOLISH SULFURIC ACID TRANSFER PUMPS AND ALL ASSOCIATED TUBING.
8. DEMOLISH EXHAUST FAN. BACKDRAFT DAMPER AND OPENING TO REMAIN.
9. DISCONNECT EXISTING SCALE AND CORROSION INHIBITOR CHEMICAL STORAGE TANK AND
PREPARE FOR RELOCATION.
10. DISCONNECT EXISTING OXIDIZING BIOCIDE (BLEACH - NAOCL) CHEMICAL STORAGE TANK.
11. DISCONNECT NON-OXYDIZING (ISOTHIAZOLINE) CHEMICAL STORAGE TANK.
12. DEMOLISH SULFURIC ACID CHEMICAL INJECTION TUBING BACK TO INJECTION NOZZLES
AND CAP AND SEAL WATERTIGHT (TYP OF 6).
13. EXISTING CONDUCTIVITY AND CHEMICAL FEED CONTROLLERS (QTY 3).
14. EXISTING MAKE-UP WATER REMOTE READOUT (QTY 3).
15. EXISTING BYPASS RETICULATION PUMPS FOR COOLING TOWER BASINS.
16. EXISTING PIPING FROM CONDENSING WATER PIPING TUNNEL.
17. DEMOLISH WINDOW AIR CONDITIONER. PROVIDE 16GA ALUMINUM PANELS ON THE
INTERIOR AND EXTERIOR SIDE OF THE OPENING WITH R-13 FIBERGLASS BATT INSULATION
IN BETWEEN THE PLATES. FASTEN ALUMINUM PANEL TO THE EXISTING FRAMED OPENING.
FLASH AND SILICONE CAULK AROUND THE ENTIRE EXTERIOR PERIMETER AND FASTENERS
OF THE PANEL AND ENSURE A WATERTIGHT SEAL. PAINT THE EXTERIOR PANEL WITH A
MINIMUM TWO COATS OF EXTERIOR GRADE PAINT, COLOR TO MATCH ADJACENT
SURFACES.
18. EXISTING INTAKE AIR LOUVER. DEMOLISH SHUT OFF DAMPER IN OUTDOOR AIR
DUCTWORK.
19. DEMOLISH HEATING UNIT. DISCONNECT HOT WATER PIPING AND DEMOLISH BACK TO SLAB
AND TEMPORARILY CAP. REFER TO NEW WORK PLAN FOR MORE INFORMATION.
20. EXISTING TREATED WATER TO COOLING TOWER BASINS. EXISTING PIPE IS HEAT TRACED.
21. EXISTING PIPE TUNNEL BELOW GRADE. PORTIONS OF THE CHEMICAL TREATMENT
BUILDING OVERLAP THE TUNNEL BELOW.
22. DEMOLISH ABANDONED PNEUMATICS CONTROL PANEL AND ALL ASSOCIATED TUBING.
23. DEMOLISH TOWER BYPASS VALVE, ACTUATOR AND BYPASS PIPING COMPLETELY.
24. DEMOLISH MAKEUP WATER PIPING. EXISTING UTILITIES MAY BE PRESENT IN AREAS OF
EXCAVATION. CONTRACTOR SHALL HAND DIG AROUND UTILITIES TO PREVENT DAMAGE.
25. DEMOLISH CONDENSER WATER SUPPLY AND RETURN PIPING. THIS TASK SHALL BE
SEQUENCED TO MAINTAIN OPERATION OF TWO COOLING TOWERS AT ALL TIMES. REFER
TO SHEET G-003 FOR SUGGESTED SEQUENCE OF CONSTRUCTION. EXISTING UTILITIES
MAY BE PRESENT IN AREAS OF EXCAVATION. CONTRACTOR SHALL HAND DIG AROUND
UTILITIES TO PREVENT DAMAGE.
26. EXISTING STRUCTURAL STEEL SUPPORTING STEEL GRATING. REFER TO STRUCTURAL
PLANS FOR MORE INFORMATION.
27. OFFICE FURNITURE (DESK, CABINET, CHAIR, ETC.) IN CHEMICAL TREATMENT BUILDING TO
BE RELOCATED FROM THIS BUILDING. COORDINATE WITH COR FOR LOCATION OF
DISPLACED FURNITURE.
28. EXISTING PURGE AND BLOWDOWN PIPING OFF COOLING TOWER RETURN PIPING FOR
COOLING TOWERS. SEE DETAIL D2 ON SHEET M-111 FOR MORE INFORMATION.
29. EXISTING SPILL CONTAINMENT KIT TO REMAIN.
30. DEMOLISH SPILL CONTAINMENT BASIN.
31. ACID STORAGE CABINET TO BE RELOCATED. COORDINATE FINAL LOCATION WITH
CHEMICAL TREATMENT PROVIDER AND PROPERTY…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .