DEPARTMENT OF THE ARMY
LOUISVILLE DISTRICT, CORPS OF ENGINEERS
P.O. BOX 59
LOUISVILLE,KENTUCKY 40201-0059
REPLY T O
ATTENTION OF
Contracting Division 24 September 2020
INTEC Group Dawn, Inc.
RJ Runge GM Hill
Dear MATOC Contractors:
Reference is made to your Indefinite Delivery Indefinite Quantity Contracts, Numbers W912QR20D0021 through W912QR20D0024, Multiple Award Task Order Contracts for Construction Services for the Great Lakes and Ohio River Division Mission Boundaries.
As a result of Amendment 0002, we request you submit a price proposal for the Control Tower MCC replacement at Caesar Creek Lake, Waynesville, OH as detailed in the revised scope of work and specifications, this amendment will be posted on the Beta.SAM website at www.beta.sam.gov. is hereby amended as follows:
As a result of Amendment 0002, the Request for Proposal for the above project is hereby amended as follows:
******AMENDMENT 0002*******
01 20 00.00 06 Appendix I has been revised and revisions are marked in red.
Section 00 10 00 Price Breakout Schedule has been revised and replaced in its entirety.
The proposal submission date has been changed from 10:00 AM ET on 25 September 2020 to 16:00 PM ET 25 September 2020.
******AMENDMENT 0002*******
Proposals are due no later than 16:00 PM Eastern on 25 September 2020. Submit your proposal by email to John C. Butts at john.c.butts@usace.army.mil. Proposals not received by the stated date/time will not be considered.
Sincerely, Aaron L. Sanford Contracting Officer
(Signature) (Date)
(Printed Name)
(Firm Name)
MOTOR CONTROL CENTER REPLACEMENT W912QR-472590
Caesar Creek Lake September 2020
SECTION 00 10 00
00 10 00
PRICE BREAKOUT SCHEDULE
02/24
CONTRACT LINE ITEM SCHEDULE
Line Item No. Description Unit Amount
BASE PROPOSAL
0001. Construction: All work, materials, and labor required to remove and replace existing motor control center in Caesar Creek Control Tower. Job $______________________
0002. Design: All work and labor required to design replacement motor control center for the Caesar Creek Control Tower Job $ ______________________
Total Base Proposal $
OPTIONS
0003. Construction: All work, materials, and labor required to install fused disconnect switch downstream of Caesar Creek Control Tower service transformer. This includes replacement of service conductors. Job $
0004. Design: All work and labor required to design fused disconnect switch for Caesar Creek Control Tower service.
This includes replacement of the service Conductors. Job $
Total All Options $
TOTAL PROPOSAL $
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
MOTOR CONTROL CENTER REPLACEMENT W912QR-472590
Caesar Creek Lake September 2020
SECTION 00 10 00
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items, including options, of the CLIN Schedule.
Failure to do so may result in the offer being unacceptable.
NOTE NO. 3. The Offeror’s Base Bid and all Options will be evaluated on price only.
NOTE NO. 4.
The target ceiling for task order award is $110,000.00. The government cannot guarantee that funds exceeding this target ceiling can be made available for award. Offerors are under no obligation to approach this ceiling.
--END OF CLIN SCHEDULE—
01 20 00.00 06 – Task Order - Scope of Work – Appendix I
Summary of Electrical Work
All information below and in subsequent pages of this appendix shall be confirmed by the contractor during the site visit. The contractor shall be responsible for the design and installation of the motor control center;
included in the design shall be the connection of the functional controls to tower components. Existing conditions are as described below.
All work shall be in accordance with the following:
- NFPA 70 – National Electrical Code (2020)
- NFPA 70E – Electrical Safety in the Workplace (2018)
- UFC 3-501-01 - Electrical Engineering (10-06-2015)
- UFC 3-560-01 - Electrical Safety, O&M, with Change 5 (12-06-2006)
- EM385-1-1 – Safety and Health Requirements (2014)
Short circuit calculations shall be provided during the design and upon completion of installation. Calculations shall include all components of the tower electrical system, including existing utility transformers, motor control center, and existing loads. Power study reports, as well as electrical component detail information, such as circuit breaker types and sizes, shall be turned over to the government to allow for updates to arc flash study/stickers due to future system changes.
All electrical equipment shall have a minimum ampere interrupting capacity (AIC) equal to or greater than the short circuit capacity calculated. No series rated equipment shall be accepted.
Utility Service:
Incoming power to the control tower is provided by a utility owned (DP&L – Dayton Power & Lights), 120/208Y volt, 3-phase, pad mounted transformer. The secondary service conductors are (3)-#300kcmil copper with (1)-#2/0 neutral.
Base Proposal Items 0001/0002 - Motor Control Center Replacement Design/Installation:
The existing tower motor control center is a GE 7700 Line Control Center. The center section holds the generator main circuit breaker rated 200 amps and the right hand section holds the utility main circuit breaker rated 300 amps.
Currently, there is a keyed interlocking mechanism to prevent both breakers from being in the closed position at the same time. System voltage for the tower is 208/120 VAC.
The replacement motor control center shall be provided as a bottom fed, 3 section unit. It shall fit on the existing MCC concrete base and re-use existing conduits. The main and generator circuit breakers shall be rated the same as existing, as well as all circuit breakers currently feeding equipment in the tower. All internal wiring shall be sized in accordance with NFPA 70 – National Electrical Code (2020) and NEMA ICS – Industrial Control and Systems General Requirements (2020).
An operating mechanism shall be mounted on the primary disconnect of each starter unit. All new exterior bucket handle operators shall be of standard size, and shall be heavy duty type. It shall be mechanically interlocked with the unit door to prevent access, unless the disconnect is in the “OFF” position. A defeater shall be provided to bypass this interlock. With the door open, an interlock shall be provided to prevent inadvertent closing of the disconnect. A second interlock shall be provided to prevent removal or reinsertion of the unit while in the “ON” position. Padlocking facilities shall be provided to positively lock the disconnect in the “OFF” position with up to three (3) padlocks with the door open or closed. In addition, means shall be provided to padlock the unit in a partially withdrawn position with the stabs free of the vertical bus. See attachment 3 to this appendix for the existing power one line diagram.
All circuit breakers shall be molded case type circuit breakers. The main and generator circuit breakers shall be provide with a keyed interlocking mechanism to prevent accidental closing of both breakers simultaneously.
The main circuit breaker shall be provided with maintenance mode functionality that allows the operator to place the breaker into a maintenance mode. Maintenance mode shall reduce the short time trip current to its lowest setting when activated thus reducing the amount of available arc flash incident energy downstream of the circuit breaker. The main and generator circuit breakers shall be adjustable trip type, and final settings shall be determined by USACE after the project has been turned over to the government. Surge protection shall be provided directly downstream of the main circuit breaker and shall integrated to the MCC to reduce unnecessary use of wall space
In addition to providing power distribution, the new motor control center shall provide the identical functional control to tower components. See below for specific controls required by the MCC. The contractor shall disconnect existing equipment from existing MCC. New MCC components shall have same rating and functionality as existing controls. Existing power and control wiring external to MCC shall be utilized. Contractor shall verify existing conditions below and adjust final design to match if different from described.
The Hydraulic Power Unit’s (HPU) pump motors are each powered via a 70 amp circuit breaker and a NEMA size 2 starter. Start/stop functionality is provided via pushbuttons located at the HPU. These pushbuttons shall be rewired back into the MCC to provide start/stop control.
The MCC currently feeds the fuel transfer pump which fills tower fuel day tank from the above ground storage tank. The day tank is wired with its own controls, which provides automatic functionality for the filling of the tank. Currently the bucket only has the circuit breaker operator, a NEMA size 1 starter and a HOA switch present. The same functionality shall be provided with the new equipment. Ratings of the existing fuel pump are: 480 volts, ½ horsepower, and 2.3 FLA.
The vent fan is currently powered via a 480 volt, 15 amp, 1.5 H.P.
circuit breaker and a NEMA size 1 starter. The fan controls consist of start/stop buttons, and an overload reset button. The same functionality shall be provided in the new equipment.
The bridge crane is currently powered via a 480 volt, 90 amp circuit breaker with a 15 H.P. motor. The same functionality shall be provided in the new equipment.
The elevator is currently powered via a 35 amp circuit breaker with a 5 H.P. motor. The same functionality shall be provided in the new equipment.
The integral lighting panel is currently powered via a 480 volt, 100 amp circuit breaker. The same functionality shall be provided in the new equipment.
The jib crane is currently powered via a 480 volt, 15 amp, 2 H.P.
circuit breaker. The same functionality shall be provided in the new equipment.
Security cages shall be provided on the HPU pump motor buckets, and shall be similar to cages currently in use. See Attachment 1 for elevation of existing MCC showing security caging.
The existing MCC also has an integral lighting panel to provide circuits to power lighting, receptacles, and other 120 volt equipment. The panel and breakers will be replaced in kind and existing circuits shall be reconnected to the panel. All branch and feeder circuit breakers shall be replaced in kind with respect to type (GFI if applicable) and capacity. Replacement lighting panel shall be 30 space type.
The MCC shall also be equipped with digital power metering. A power meter shall be installed for both the main and generator circuit breakers, located within the respective MCC cabinet. Metering for main and generator shall be provided with the following features: 3 phase voltage, 3 phase current, 3 phase power in kVA/KW/KVAR, and power factor.
Additional equipment power meters are to be installed for each HPU pump motor, the bridge crane, the jib crane, and the elevator. Equipment metering shall be capable of 3 phase voltage and 3 phase current.
Option Items 0003/0004 – Disconnect Switch Design/Installation:
1. Fused service disconnect
AMENDMENT 0002**************************************************************
The existing Motor Control Center does not have an upstream overcurrent protective device. As currently installed, the MCC is fed from the commercial utility pad-mounted transformer at the end of the service bridge, directly into the main circuit breaker. A fused disconnect shall be provided directly downstream of the service transformer. The disconnect shall be 400 A, 600 VAC, heavy duty type, with a NEMA 3R type enclosure. Fuses shall be sized in accordance with NFPA 70, taking into consideration the sizing of the replacement MCC. The disconnect shall be installed on a slotted channel mounting frame adjacent to the transformer. Frame shall be supported with concrete footers. Final location shall be coordinated with the COR and Park Manager. Additionally, the existing service conductors currently routed from the service transformer to the existing motor control center shall be replaced. Existing conductors/conduits are sized as follows: 3-300 kcmil + 1- #2/0 awg neutral, run in 3" conduit. All grounding and bonding shall be in accordance with NFPA 70, Article 250, as well as any grounding direction from the utility. Coordinate installation of the disconnect with COR, Park Manager, and local utility. POC for local utility is:
Dayton Power and Light 1900 Dryden Road Dayton, OH 45439 http://www.dpandl.com
Lyle Garrison Program Manager Energy Efficiency
DP&L
Office: 937.331.4028
***************************************************************AMENDMENT 0002
List of Attachments
1 – Existing Site Photos
2 – Existing Motor Control Center Elevation
3 – Existing Power One Line Diagram
4 – OCPD Data
| Amendment 0002 |
| 00 10 00 Price Breakout Schedule Amendment 0002 |
| Summary of Electrical work Caesar Creek Amendment 0002 |
| 2020-09-24T09:32:06-0400 | |
| SANFORD.AARON.L.1512306574 |