DEPARTMENT OF THE ARMY

LOUISVILLE DISTRICT, CORPS OF ENGINEERS

P.O. BOX 59

LOUISVILLE,KENTUCKY 40201-0059

REPLY T O

ATTENTION OF

Contracting Division 22 September 2020

INTEC Group Dawn, Inc.

RJ Runge GM Hill

Dear MATOC Contractors:

Reference is made to your Indefinite Delivery Indefinite Quantity Contracts, Numbers W912QR20D0021 through W912QR20D0024, Multiple Award Task Order Contracts for Construction Services for the Great Lakes and Ohio River Division Mission Boundaries.

As a result of Amendment 0001, we request you submit a price proposal for the Control Tower MCC replacement at Caesar Creek Lake, Waynesville, OH as detailed in the revised scope of work and specifications, this amendment will be posted on the Beta.SAM website at www.beta.sam.gov. is hereby amended as follows:

As a result of Amendment 0001, the Request for Proposal for the above project is hereby amended as follows:

******AMENDMENT 0001*******

SECTION 3.2 General Information has been revised and replaced in its entirety.

Incorporate Appendix I, the Summary of Electrical Work, in its entirety.

The proposal submission date has been changed from 10:00 AM ET on 24 September 2020 to 10:00 AM ET 25 September 2020.

******AMENDMENT 0001*******

Proposals are due no later than 10:00 AM Eastern on 25 Spetember 2020. Submit your proposal by email to John C. Butts at john.c.butts@usace.army.mil. Proposals not received by the stated date/time will not be considered.

Sincerely, Aaron L. Sanford Contracting Officer

(Signature) (Date)

(Printed Name)

(Firm Name)

OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.

To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.

The Solicitation Number is: W912QR-02472590

The Bidder Inquiry Key is: A5D5TP-NX5FS3.

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret

Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Select Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

From this page you may view all bidder inquiries or add an inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

NOTES:

1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.

2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.

3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled five (5) calendar days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within two (2) calendar days prior to the closing date stated in the solicitation.

MOTOR CONTROL CENTER REPLACEMENT W91QR-472590

Caesar Creek Lake September 2020

Section 01 11 50 Page 1

SECTION 01 11 50

SUMMARY OF WORK

Amendment 0001 (22 September 2020)

PART 1 GENERAL

This section supplements section 01 11 00 in the base contract. Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order.

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. See the Submittal Register following Section 00 80 50.00 06.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes removal of the existing motor control center (MCC) in the Caesar Creek Lake Control Tower and subsequent replacement of said MCC, and incidental related work.

1.2.2 Location

The work is located at the Caesar Creek Lake Control Towe, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) will not be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, Section 01 11 50 Page 2 existing work must be in a condition equal to or better than that which existed before new work started.

1.5 UTILITY OUTAGE REQUESTS AND UTILITY CONNECTION REQUESTS

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 14 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved. See section

3.5.1.3 for more information.

1.6 ATTACHMENTS

Design/Build: Information provided in Appendix I of this specification is intended to guide the completion of the design by establishing existing conditions, and the desired character, appearance, and function of the new construction. The following Attachments are included and shall be used and strictly adhered-to in completing the design and construction of the project.

a. APPENDIX I Includes narrative of electrical scope of work, project site photos of affected equipment, one line diagram of existing motor control center, and an elevation of existing MCC.

1.7 PERMITS

The Contractor shall investigate and submit any permits necessary for the construction of this project. All permit applications shall be completed by the Contractor and provided to the Contracting Officer for submittal to the appropriate agency. Contractor shall pay all permit fees. Copies of all permits shall be provided to the USACE.

1.8 NOT USED

1.9 NOT USED

1.10 PERSONNEL REQUIREMENTS AND QUALIFICATIONS

1.10.1 Personnel Requirements

In addition to the superintendent, CQC staff and safety staff required by this section, Section 01 45 04.10 06 and 01 35 26.00 06, the contractor shall provide a full time Construction Project Manager for the entire life of this contract construction phase. The Construction Project Manager shall have a degree in Construction Management or Engineering and shall have 10 years of relative experience in construction management.

Section 01 11 50 Page 3

1.10.2 Site Safety and Health Officer (SSHO)

a. The SSHO shall be assigned as SSHO, but may have duties as the CQC System Manager and the Superintendent.

b. The SSHO and alternate(s) shall have an experience Level as follows and the Contractor must show evidence that the SSHO and alternate(s) have met these requirements. When an alternate is required for the project, the alternate shall have the same experience level and other qualifications as the SSHO. In addition, the SSHO and alternate(s) are also required to have:

(1) Completed, as a minimum, the 30-Hour OSHA Construction Industry safety class with current First Aid and CPR Training /AED , per EM- 385-1-1 Section 3.

(2) Either a person with 10 years of demonstratable SSHO experience on similar projects or a College graduate with Five (5) years of Construction Industry safety experience on similar projects in supervising or managing general or industry construction (managing safety programs or processes or conducting hazard analyses and developing controls).

(3) Maintained experience through having taken 24 hours of documented formal or on-line safety and health related coursework in the past three years. The training must be applicable to the work being performed on the contract. Teaching is not considered the equivalent of attending training.

(4) SSHO shall be able to demonstrate training in the following areas:

personal protective equipment and clothing to include selection, use and maintenance; hazard communication; scaffolding; fall protection; hazardous energy; confined space; and health hazard recognition, evaluation and control of chemical, physical and biological agents.

(5) SSHO shall be {Certified Safety Professional (CSP.

c.) The Contractor shall identify the SSHO and alternate(s) for this project and shall submit qualifications to the Government in resume form for acceptance. A copy of the letter to the SSHO and alternate(s) signed by an authorized official of the firm describing responsibilities and delegating authority to stop work when safety or occupational health of workers is compromised must be provided to the Government.

1.10.3 CQC System Manager Qualifications and Duties

The appropriate CQC personnel shall be present at the construction site as needed during work related to their areas of responsibility. In addition to the requirements of Section 01 45 04.10 06, Volume 1, CQC personnel resumes and site visit frequency shall be identified in the Design Quality Control Plan (DQCP) and accepted by the government.

The CQC System Manager shall be assigned as CQC System Manager but may have duties as superintendent in addition to quality control if a different

Section 01 11 50 Page 4 individual is used as the SSHO. In addition, installation QC shall be accomplished by a State of Ohio Certified Electrician with 5 years of experience, minimum. Design QC shall be accomplished by an Electrical Engineer, P.E.

1.11 BORROW, EXCAVATION AND WELDING PERMITS

1.11.1 BORROW

NOT USED

1.11.2 EXCAVATION

1.11.2.1 WELDING PERMITS

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL CONSTRUCTION REQUIREMENTS

The requirements include:

a. Construction considerations and use of the premises.

b. Protection of personnel and Government property.

c. Construction facilities and job site standards.

d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.

3.2 GENERAL INFORMATION

Contractor shall have shared use of all spaces for execution of the construction work as defined in the requirements of this RFP; all areas are currently occupied. Entrance into and interface with the surrounding facilities shall be coordinated in advance with the Contracting Officer.

Amend 0001***************************************************************** Because of the limited scope and complexity of the work, this project only requires one superintendent per FAR FAR 52.236-6. The superintendent in charge of this work shall personally contact the Contracting Officer's Representative a minimum of 72 hours before starting work on the contract, before restarting work after a lengthy delay, and prior to moving workers and equipment from one site of work to another.

Amend 0001***************************************************************** Coordinate all construction activities with:

a. Contracting Officer's Representative

Section 01 11 50 Page 5

b. Project Personnel/Park Manager

Prior to the start of any construction operations whatsoever, a schedule of work or operations in proper sequence shall be submitted by the contractor for approval by the Contracting Officer's Representative so as to cause a minimum amount of disruption to the normal flow of traffic on streets, pedestrian travel, installation security, and facility operations.

Coordinate all Construction and Use of Premises Activities with the Contracting Officer's Representative.

Coordinate with Contracting Officer's Representative the scheduling and routing of work, personnel access and material deliveries for the work.

The Contractor shall coordinate with Installation security regulations and personnel regarding worker and vehicle identification, badging, and permits.

See paragraph entitled IDENTIFICATION OF EMPLOYEES in Section 00 80 00.00 06 SPECIAL CLAUSES in Volume 1.

3.2.8 High-ranking officers, foreign dignitaries, or DOD employees may approach you. Only the Contracting Officer can make changes to the contract.

Bulletin Board. See 01 50 00.

Project and Safety Signs. See 01 50 00.

3.3 DOCUMENTATION

3.3.1 Construction Plan

Prior to the start of any onsite construction activities, the Contractor shall submit a detailed construction plan. The plan shall include a detailed schedule of the major construction activities. Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation.

Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

Once the schedule is approved, do not deviate from the sequence, without prior written approval.

3.3.2 Waste Disposal

Prior to the start of any onsite construction activities, the Contractor shall submit a written plan for disposing of waste materials resulting from work under this contract as described in this specification section and Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS, Volume 1.

3.4 DESIGN CONSIDERATIONS

Section 01 11 50 Page 6

The contractor shall use the information provided in this task order in conjunction with the base MATOC contract.

This project is design build and design is a part of this construction contract. The contractor shall follow requirement in Sections 01 03 00.00 06 and 01 33 16.00 10.

3.4.1 DESIGN REQUIREMENTS

Design submittals will be required at the following design phases:

Interim 65% design Final 100% Design Corrected Final Design

3.4.2 DESIGN SUBMITTAL DISTRIBUTION LIST

Each submittal reviewer copy shall include all items for any one design submittal, ie. hardcopy drawings of size indicated below (11x17 if not indicated), specifications, and design analysis. Provide CDs w/ drawings, specifications, and design analysis files.

SID and FF&E binders will be returned to the DB Contractor after each review for revisions. Reviewers will not insert/exchange pages/boards for revisions.

The 100% completed design binders, and any changes to the binders during construction, will be mailed to those listed below for record and reference.

The DB Contractor shall retain one copy for field use.

Note: 100% for SID and FF&E represents the corrected final, completing shortly after the Released For Construction Design submittal.

Submittal Reviewers & Mailing Addresses Copies Required

U.S. Army Corps of Engineers 2 CELRL-ED-D-E Jeff Timbas/Casey Thompson 600 Dr. Martin Luther King Jr. Place, Rm 972 Louisville, KY 40202

USACE Louisville District 1 PO Box 59 CELRL-OP-TM (Crutchfield) Louisville, KY 40201-0059

U.S. Army Corps of Engineers 1 Jim O’Boyle – Park Manager 4020 North Clarksville Road Waynesville, OH 45068

3.5 CONSTRUCTION CONSIDERATIONS

3.5.1 Use of Premises

The Contractor's use of the site, utility availability, and temporary facilities are described below.

Section 01 11 50 Page 7

3.5.1.1 Work Schedule

The Contractor shall schedule the work between the hours of 7:00 a.m. and 4:30 p.m. Monday through Friday except Federal Holidays.

a. Permission to perform any work outside of these hours must be in writing and submitted five (5) calendar days in advance for approval by the Contracting Officer.

b. The Government may or may not grant such permission at its discretion.

Work may be required to be performed on weekends if it is determined by the Contracting Officer that work will be disruptive to any installation operations. The Government will occupy areas adjacent to the work site during construction. Contractor shall schedule and perform the work so as not to interfere with the Government's operations. The Contractor shall cooperate fully with the Government during construction operations to minimize conflicts and to facilitate Government usage.

3.5.1.2 Parking and Facilities

Contractor Personal Vehicle Parking: The contractor may park vehicles on the access road and pull off adjacent to the control tower service bridge abutment. The Contractor shall coordinate with the Government on the exact number of available spaces, and shall make provisions to transport employees to the site should inadequate parking spaces be available on site.

The Contractor will not be permitted to use existing toilet and wash facilities. The contractor shall provide his own toilet and wash facilities if desired.

3.5.1.3 Utility Outages

Once an outage is approved, and prior to beginning of work on the utility system requiring shutdown, the contractor shall attend a pre-outage meeting with the Contracting officer and the Installation representative.

a. Any utility outages (gas, steam, electricity, and water) requested by the Contractor shall be submitted in writing no less than fourteen

(14) calendar days prior to proposed outage.

b. The Government reserves the right to reschedule the Contractor's proposed outage if deemed necessary.

c. In the event utility outages cannot be performed on any facility due to critical operation impact, the utility outages and any related work shall be performed on non-duty hours.

d. Contractor shall notify the Installation Park Manager prior to emergency utilities shutdown of the facilities.

Caesar Creel Lake requires installation to take place during predicted low water flow discharge. The installation shall be approved by the Park Manager as predicted by USACE Hydraulics (https://www.lrl-

Section 01 11 50 Page 8 wc.usace.army.mil/plots/cck.html). A downtime of 5 days shall be permitted, and shall be coordinated and approved by the project. Project may approve or reject contractor’s installation plan if inclement weather is forecasted for the near future at that time.

3.5.2 Project Site

Contractor shall maintain a neat and orderly workplace with clear paths of emergency egress within the construction area.

3.5.2.1 Protection and Maintenance of Traffic

Prior to commencement of demolition and construction, the Contractor shall coordinate daily access and egress from the area of construction with the Contracting Officer, both vehicle and pedestrian. The Contractor shall confine construction personnel and equipment travel and operations to the area of work. The Contractor shall request approval for the limits of construction from the Government and show on the construction plans. The contractor shall coordinate access ways for personnel and equipment with the contracting officer.

a. The Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. The Contractor shall prepare a traffic plan (vehicle and pedestrian) for the project area and submit it to the Contracting Officer for review and approval.

b. The Contractor shall maintain and protect pedestrian traffic inside and outside of project area. The Contractor shall not cause traffic interference on any interior corridors without approval from the Contracting Officer.

c. The traveling public shall be protected from damage to person and property.

3.5.2.2 Dust control

For interior work, the Contractor shall construct a dust partition wall around the interior perimeter of the space as necessary to prevent dust from travelling into the corridor space. For exterior work the contractor shall control all fugitive dust.

3.5.3 Storage of Materials

The Contractor shall be responsible for the storage and safekeeping of all material to be incorporated into the work. The Contractor shall be responsible for all aspects of safety and security within the storage area.

Outside space is extremely limited on the installation for the storage of materials, the Contractor shall limit storage of materials to areas within project area. The Contractor shall indicate if the use of a supplemental or other staging area is desired.

a. Upon the Contractor's request, the Contracting Officer will consider another or supplemental area for the Contractor's use and storage of equipment, trailers, and materials; however, this will be solely at the

Section 01 11 50 Page 9 discretion of the Park Manager and may not be approved. This area may not be in close proximity of the construction site but will be within the installation boundaries.

b. Fencing of materials or equipment will be required at storage locations; plastic strip inserts, colored installation selected color, must be used on the fence to screen the storage compound from the installation; fence posts must be embedded into grade as recommended by the manufacturer. The Contractor shall be responsible for cleanliness and orderliness of the area used and shall restore the area to its original condition upon completion of the project.

c. The Government will not provide utilities to the storage area.

Provide adequate storage facilitates for protection of materials and equipment. Materials and equipment shall be stored so as to ensure preservation of their quality of fitness for Work. Perishable items and items adversely affected by weather, rain, wind, dust, heat, or cold shall be stored within the designated area of construction, temporary waterproof sheds, or mobile facilities with raised floors, and heated if necessary.

Other materials and equipment shall be stored on wooden platforms and not on the ground.

Storage facilities shall be clean, in good condition, undamaged and free of rust or surface deterioration. Rental trailers shall be of a neutral color.

Unsightly material storage or office trailers will not be permitted.

The Contractor shall be responsible to maintain the condition of storage facilities, as defined above, and the entire construction site in a neat, orderly, professional and uncluttered manner at all times throughout the length of the contract.

3.5.4 Security

Security requirements shall be observed at all times. The Contractor shall be responsible for maintaining satisfactory standards of employee competency, conduct, appearance, and integrity. Personnel working on or involved with security alarms, secure areas or security infrastructure shall be US Citizens.

Construction operations shall be strictly confined to the designated area of Work.

The Contractor shall be responsible for the security of his own equipment.

3.5.5 Protection of Personnel and Government Property

Contractor shall comply with all applicable Federal, State, and Local safety codes, regulations, and requirements.

The Installation Safety Officer or his representative will attend preconstruction conferences to brief contractors on pertinent safety regulations and to provide guidance for safe operations during contract performance. Local safety guidance will be furnished to the Contractor for briefing his personnel.

Section 01 11 50 Page 10

The Contractor shall provide, no later than ten days after receiving Notice of Award, four (4) copies of their written safety program to the Contracting Officer for review. No construction shall commence until the Contractor's Safety Program has been reviewed and accepted by the Contracting Officer.

It is the Contractor's responsibility to maintain a secure construction site to prevent access to the work area by unauthorized personnel.

Safety posters, "hard hat area" posters, "authorized personnel only" posters, and any other notifications required by law shall be posted and maintained in sufficient quantity to be conspicuous on the job site.

The contractor shall protect all government property in adjacent areas from damages during the construction project; especially furniture and finishes.

In the event of damages of any nature caused by this work due to improper protection, precaution, or safety measures, such damages shall be repaired by the Contractor at no cost to the Government. In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of this contract, the Government will make the necessary corrections and the Contractor shall reimburse the Government for inconveniences, labor, and materials, involved.

The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas.

a. Such barricades shall be required whenever safe public access is prevented by construction activities or as otherwise necessary to ensure safety of both pedestrian and vehicular traffic.

b. Barricades shall be securely placed, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

3.5.6 Site Fire Protection

Site fire protection shall conform to NFPA 241 and EM 385-1-1.

Fire extinguisher equipment shall be provided in storage areas according to the hazard present.

Fire extinguishers listed or approved by a nationally recognized testing laboratory shall be used.

Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.

3.5.7 Waste Disposal

The Contractor is required to maintain a clean project site free of accumulating debris. Demolition debris and other construction waste shall be promptly disposed of at the end of each workday in proper waste containers maintained on the project site by the Contractor. Waste Disposal procedures shall be in compliance with the waste disposal plan submitted under the requirements of SECTION 01 574 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT, Volume 1.

Section 01 11 50 Page 11

Environmentally hazardous or other construction debris with special disposal requirements shall be stored on the site and disposed of offsite in a proper lawful manner.

All debris shall be removed from the site on a regular basis. Waste shall not be allowed to accumulate.

Construction waste and debris maintained on-site prior to off-site disposal shall be controlled in a manner to eliminate any potential health or safety hazards.

Burning of waste or any other material on-site is strictly prohibited.

The project job site shall be ["broom cleaned"] at the end of each work day.

The Contractor shall remove debris from the job site as it is generated and dispose of it in proper containers as outlined herein.

The Contractor shall coordinate dumpster location with the contracting officer.

3.6 CONTRACTOR DAMAGED FINISHES

Damage to any existing finishes or equipment, such as floors, ceilings, HVAC equipment, doors, paint, by the contractor shall be repaired or replaced by the contractor at the contractor expense to the satisfaction of the government.

3.7 DEMOLITION

3.7.1 General

The Contractor shall remove all demolition debris associated with the MCC replacemnt off of the confines of project and dispose of all demolition debris in a legal and regulated manner at the Contractor's expense with the exception of recyclable materials, which shall be handled in accordance with Paragraph 1.9 of this specification.

3.7.2 Contractor Submittals

Prior to commencing demolition, the Contractor shall submit a Demolition Plan to the Contracting Officer's Representative for review and acceptance.

The plan shall demonstrate the procedure for demolition, dust control, debris removal and safety that are to be followed during the work.

The Contractor shall submit a Schedule of Demolition Activities, indicating the following:

1. Detailed sequence of demolition work, with starting and ending dates for each activity.

2. Detailed schedule for interruption of utility services.

3. Coordination of shutoff, capping and continuation of utility services.

Section 01 11 50 Page 12

4. Location of temporary protection and means of egress.

3.7.3 Execution

The Contractor shall maintain all existing utility services and protect them against damage.

The Contractor shall not interrupt existing utilities serving adjacent facilities unless authorized in writing by the Contracting Officer.

The Contractor shall provide temporary barricades and other protection required to prevent injury to lay people.

The Contractor shall not remove any conduit feeding other areas not part of the project areas without coordination with the base CE. Do not demolish any conduit or cabling to HVAC system which originates outside the project area unless the equipment is to be replaced. All removed communications conduit must be removed and not abandoned in place.

The Contractor shall coordinate all roof penetrations with the roof warranty provided in Attachment 12**.

-- End of Section --

01 20 00.00 06 – Task Order - Scope of Work – Appendix I

Summary of Electrical Work

All information below and in subsequent pages of this appendix shall be confirmed by the contractor during the site visit. The contractor shall be responsible for the design and installation of the motor control center;

included in the design shall be the connection of the functional controls to tower components. Existing conditions are as described below.

All work shall be in accordance with the following:

- NFPA 70 – National Electrical Code (2020)

- NFPA 70E – Electrical Safety in the Workplace (2018)

- UFC 3-501-01 - Electrical Engineering (10-06-2015)

- UFC 3-560-01 - Electrical Safety, O&M, with Change 5 (12-06-2006)

- EM385-1-1 – Safety and Health Requirements (2014)

Short circuit calculations shall be provided during the design and upon completion of installation. Calculations shall include all components of the tower electrical system, including existing utility transformers, motor control center, and existing loads. Power study reports, as well as electrical component detail information, such as circuit breaker types and sizes, shall be turned over to the government to allow for updates to arc flash study/stickers due to future system changes.

All electrical equipment shall have a minimum ampere interrupting capacity (AIC) equal to or greater than the short circuit capacity calculated. No series rated equipment shall be accepted.

Utility Service:

Incoming power to the control tower is provided by a utility owned (DP&L – Dayton Power & Lights), 120/208Y volt, 3-phase, pad mounted transformer. The secondary service conductors are (3)-#300kcmil copper with (1)-#2/0 neutral.

Base Proposal Items 0001/0002 - Motor Control Center Replacement Design/Installation:

The existing tower motor control center is a GE 7700 Line Control Center. The center section holds the generator main circuit breaker rated 200 amps and the right hand section holds the utility main circuit breaker rated 300 amps.

Currently, there is a keyed interlocking mechanism to prevent both breakers from being in the closed position at the same time. System voltage for the tower is 208/120 VAC.

The replacement motor control center shall be provided as a bottom fed, 3 section unit. It shall fit on the existing MCC concrete base and re-use existing conduits. The main and generator circuit breakers shall be rated the same as existing, as well as all circuit breakers currently feeding equipment in the tower. All internal wiring shall be sized in accordance with NFPA 70 – National Electrical Code (2020) and NEMA ICS – Industrial Control and Systems General Requirements (2020).

An operating mechanism shall be mounted on the primary disconnect of each starter unit. All new exterior bucket handle operators shall be of standard size, and shall be heavy duty type. It shall be mechanically interlocked with the unit door to prevent access, unless the disconnect is in the “OFF” position. A defeater shall be provided to bypass this interlock. With the door open, an interlock shall be provided to prevent inadvertent closing of the disconnect. A second interlock shall be provided to prevent removal or reinsertion of the unit while in the “ON” position. Padlocking facilities shall be provided to positively lock the disconnect in the “OFF” position with up to three (3) padlocks with the door open or closed. In addition, means shall be provided to padlock the unit in a partially withdrawn position with the stabs free of the vertical bus. See attachment 3 to this appendix for the existing power one line diagram.

All circuit breakers shall be molded case type circuit breakers. The main and generator circuit breakers shall be provide with a keyed interlocking mechanism to prevent accidental closing of both breakers simultaneously.

The main circuit breaker shall be provided with maintenance mode functionality that allows the operator to place the breaker into a maintenance mode. Maintenance mode shall reduce the short time trip current to its lowest setting when activated thus reducing the amount of available arc flash incident energy downstream of the circuit breaker. The main and generator circuit breakers shall be adjustable trip type, and final settings shall be determined by USACE after the project has been turned over to the government. Surge protection shall be provided directly downstream of the main circuit breaker and shall integrated to the MCC to reduce unnecessary use of wall space

In addition to providing power distribution, the new motor control center shall provide the identical functional control to tower components. See below for specific controls required by the MCC. The contractor shall disconnect existing equipment from existing MCC. New MCC components shall have same rating and functionality as existing controls. Existing power and control wiring external to MCC shall be utilized. Contractor shall verify existing conditions below and adjust final design to match if different from described.

The Hydraulic Power Unit’s (HPU) pump motors are each powered via a 70 amp circuit breaker and a NEMA size 2 starter. Start/stop functionality is provided via pushbuttons located at the HPU. These pushbuttons shall be rewired back into the MCC to provide start/stop control.

The MCC currently feeds the fuel transfer pump which fills tower fuel day tank from the above ground storage tank. The day tank is wired with its own controls, which provides automatic functionality for the filling of the tank. Currently the bucket only has the circuit breaker operator, a NEMA size 1 starter and a HOA switch present. The same functionality shall be provided with the new equipment. Ratings of the existing fuel pump are: 480 volts, ½ horsepower, and 2.3 FLA.

The vent fan is currently powered via a 480 volt, 15 amp, 1.5 H.P.

circuit breaker and a NEMA size 1 starter. The fan controls consist of start/stop buttons, and an overload reset button. The same functionality shall be provided in the new equipment.

The bridge crane is currently powered via a 480 volt, 90 amp circuit breaker with a 15 H.P. motor. The same functionality shall be provided in the new equipment.

The elevator is currently powered via a 35 amp circuit breaker with a 5 H.P. motor. The same functionality shall be provided in the new equipment.

The integral lighting panel is currently powered via a 480 volt, 100 amp circuit breaker. The same functionality shall be provided in the new equipment.

The jib crane is currently powered via a 480 volt, 15 amp, 2 H.P.

circuit breaker. The same functionality shall be provided in the new equipment.

Security cages shall be provided on the HPU pump motor buckets, and shall be similar to cages currently in use. See Attachment 1 for elevation of existing MCC showing security caging.

The existing MCC also has an integral lighting panel to provide circuits to power lighting, receptacles, and other 120 volt equipment. The panel and breakers will be replaced in kind and existing circuits shall be reconnected to the panel. All branch and feeder circuit breakers shall be replaced in kind with respect to type (GFI if applicable) and capacity. Replacement lighting panel shall be 30 space type.

The MCC shall also be equipped with digital power metering. A power meter shall be installed for both the main and generator circuit breakers, located within the respective MCC cabinet. Metering for main and generator shall be provided with the following features: 3 phase voltage, 3 phase current, 3 phase power in kVA/KW/KVAR, and power factor.

Additional equipment power meters are to be installed for each HPU pump motor, the bridge crane, the jib crane, and the elevator. Equipment metering shall be capable of 3 phase voltage and 3 phase current.

Option Items 0003/0004 – Disconnect Switch Design/Installation:

1. Fused service disconnect

The existing Motor Control Center does not have an upstream overcurrent protective device. As currently installed, the MCC is fed from the commercial utility pad-mounted transformer at the end of the service bridge, directly into the main circuit breaker. A fused disconnect shall be provided directly downstream of the service transformer. The disconnect shall be 400 A, 600 VAC, heavy duty type, with a NEMA 3R type enclosure. Fuses shall be sized in accordance with NFPA 70, taking into consideration the sizing of the replacement MCC. The disconnect shall be installed on a slotted channel mounting frame adjacent to the transformer. Frame shall be supported with concrete footers. Final location shall be coordinated with the COR and Park Manager. All grounding and bonding shall be in accordance with NFPA 70, Article 250, as well as any grounding direction from the utility. Coordinate installation of the disconnect with COR, Park Manager, and local utility. POC for local utility is:

Dayton Power and Light 1900 Dryden Road

Dayton, OH 45439 http://www.dpandl.com

Lyle Garrison Program Manager Energy Efficiency

DP&L

Office: 937.331.4028 List of Attachments

1 – Existing Site Photos

2 – Existing Motor Control Center Elevation

3 – Existing Power One Line Diagram

4 – OCPD Data

Amendment 0001
01 11 50 Summary of Work Amend0001
Appendix I Summary of Electrical work Caesar Creek
2020-09-22T13:48:52-0400