INSTALL SMART METERS (BASE WIDE)

ENERGY PROJECT

PROJECT NUMBER WHAY092001

OVERVIEW:

The main objective of this project is to install “Smart Meters” base wide on Water, Gas and Electric systems. These meters will be tied into the existing Tracer Summit software located in CE.

ALL BUILDINGS LISTED REQUIRE ENVIRONMENTAL LAN PORTS AT EACH ELECTRICAL, GAS AND WATER METER LOCATION. SANG TO PROVIDE ENVIRONMENTAL LAN CONNECTIONS AT EACH ELECTRICAL, GAS AND WATER METER LOCATION.

REQUIREMENTS:

ELECTRICAL METERS

· Provide Labor to create (1) Custom Trend to monitor each Electrical Meter at the Tracer Summit Workstation (Includes Building #102, #107, #203, #213, #415)

· Provide Labor to create (1) Custom Invoice for each Electrical Meter displaying Monthly Electrical Usage for each Electrical Meter (Includes Building #102, #107, #203, #213, #415)

· Provide Technical Labor to Commission each provided Electrical Meter

· Electrical Meters do not have to provide Local Displays

· Provide and Install an Electrical Meter in the following Buildings:

Building #100
Building #101
Building #104
Building #105
Building #106
Building #108
Building #200
Building #202
Building #207
Building #208
Building #214
Building #300
Building #301
Building #302
Building #303
Building #303
Building #402
Building #403
Building #500

NATURAL GAS METERS

· Provide Labor to create (1) Custom Trend to monitor each Gas Meter at the Tracer Summit Workstation

· Provide Labor to create (1) Custom Invoice for each Gas Meter displaying Monthly Gas Usage for each Gas Meter

· Provide Technical Labor to Commission each provided Gas Meter

· Gas Meters will be provided with Local Display indicating Flow Rate

· Provide and Install a Gas Meter in the following Buildings:

Building #100
Building #101
Building #105
Building #106
Building #107
Building #108
Building #200
Building #202
Building #203
Building #207
Building #208
Building #213
Building #214
Building #300
Building #301
Building #302
Building #415

WATER METERS

· Provide Labor to create (1) Custom Trend to monitor each Water Meter at the Tracer Summit Workstation

· Provide Labor to create (1) Custom Invoice for each Water Meter displaying Monthly Water Usage for each Water Meter

· Provide Technical Labor to Commission each provided Water Meter

· Water Meters will be provided with Local Display indicating Flow Rate

· Provide and Install a Water Meter in the following Buildings:

Building #100
Building #102
Building #105
Building #106
Building #107
Building #200
Building #202
Building #203
Building #207
Building #208
Building #213
Building #214
Building #300
Building #301
Building #302
Building #403
Building #415

TRACER SUMMIT SERVER AND ENERGY SERVICES SOFTWARE

· Provide (1) Licensed Copy of Trane Energy Services Software to be installed on Tracer Summit Workstation in CE Building

· Provide Material and Labor to Install Existing Tracer Summit Database onto a Server located in CE Building. Trane will provide software and hardware for server application.

· Provide Customer Training on Tracer Summit Energy Services

· One Year Parts Warranty on Supplied Material

General Items

· All work will be performed during normal business hours.

· This proposal is only valid for the Buildings Listed in the Scope Section.

· SANG must have a configured and working Ethernet Port used for the Environmental System LAN in each Building

· SANG to provide recent utility invoices in order to configure utility rates for Monthly Electrical, Gas and Water Invoice Generation.

· SANG to de-energize and reenergize each Building Electrical Switch Gear during Normal Working Hours in order to install Electrical Meter in Building.

· SANG to shutoff and turn on each Building Gas and Water service during Normal Working Hours in order for Trane to install Gas and Water Meters in each Building.