W912PP25BA001 N80 Earth Covered Magazine - Amendment 003.pdf
PDF 4 MB Posted
- Solicitation number
- W912PP25BA001
About this file
This document is an Amendment (No. 0003) to Solicitation No. W912PP25BA001 for a Design Bid Build N80 Earth Covered Magazine project at White Sands Missile Range in Doña Ana County, New Mexico. The amendment updates several specification sections, including Contracting Forms and Supplements, Special Project Procedures, and Managing Demolition Waste. Key project requirements include strict access controls for the missile range, mandatory unexploded ordnance (UXO) training for all contractor personnel, environmental compliance for waste management, and navigation of complex site-specific procedures such as digging permits, utility locates, and roadblock considerations.
The amendment includes detailed wage determination information for various construction trades, with wage rates ranging from $13.61 for common laborers to $43.07 for pipefitters and HVAC installers. Contractors must comply with Executive Order minimum wage requirements, which mandate $17.75 per hour for covered workers in 2025. The project emphasizes environmental stewardship, requiring contractors to recycle construction and demolition debris, manage waste responsibly, and obtain necessary permits for activities like concrete crushing. The solicitation also highlights the restricted nature of White Sands Missile Range, with stringent access controls and background check requirements for all personnel.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE
PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
W912PP
Design Bid Build N80 EARTH COVERED MAGAZINE, WHITE SANDS MISSILE RANGE, DOÑA ANA COUNTY, NEW
MEXICO
1.This is Amendment No. 0003 to Solicitation No. W912PP25BA001. The following revisions shall be incorporated into the specifications. All other provisions shall remain unchanged.
U.S. ARMY ENGINEER DISTRICT, ALBUQUERQUE
CORPS OF ENGINEERS
4101 JEFFERSON PLAZA, N.E.
ALBUQUERQUE, NEW MEXICO 87109-3435
See Item 6
J
W912PP25BA001
1 2
08/28/2025
08/28/2025
W912PP25BA001
AMENDMENT No. 0003
2. SPECIFICATIONS: Delete the following listed pages and substitute the pages attached hereto. On the revised pages, for convenience, changes are emphasized by STRIKETHROUGH for deletions and UNDERLINE for additions from the previous issue. All portions of the revised (or new) pages shall apply whether or not changes have been indicated.
Delete Page Insert Page
00 50 00 – CONTRACTING FORMS AND
SUPPLEMENTS, Entirety
00 50 00 – CONTRACTING FORMS AND
SUPPLEMENTS, Entirety
01 35 20.00 44 - SPECIAL PROJECT
PROCEDURES FOR WHITE SANDS MISSILE
RANGE, Entirety
01 35 20.00 44 - SPECIAL PROJECT
PROCEDURES FOR WHITE SANDS MISSILE
RANGE, Entirety
01 74 19 SUPPLEMENTAL - MANAGING
DEMOLITION WASTE, Entirety
01 74 19 SUPPLEMENTAL - MANAGING
DEMOLITION WASTE, Entirety
APPENDIX A – BORROW PITS, Entirety APPENDIX A – BORROW PITS, Entirety
3. DRAWING CHANGES: The following drawings have been revised and the sequence number changed to indicate such revision:
Delete Page Insert Page
N.A. N.A.
////////LAST ITEM////////
Section 00 50 00 – Contracting Forms and Supplements
"General Decision Number: NM20250025 03/07/2025
Superseded General Decision Number: NM20240025
State: New Mexico
Construction Type: Building
County: Otero County in New Mexico.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025
1 02/14/2025 2 03/07/2025
CARP1245-004 06/01/2018
Rates Fringes
Carpenter Metal Stud Installation Only........................$ 24.08 10.79
ELEC0583-009 01/01/2025
Rates Fringes
ELECTRICIAN
Excluding Low Voltage Wiring for Alarms...........$ 38.00 5%+7.92
ENGI0953-012 01/01/2024
Rates Fringes
Power Equipment Operator
(2) Roller(Dirt and Grade Compaction).................$ 26.75 4.65
(4) Bobcat/Skid Loader......$ 27.70 4.65
(8) Crane...................$ 31.43 4.65
IRON0495-009 01/01/2023
Rates Fringes
IRONWORKER, ORNAMENTAL...........$ 28.05 18.11
IRONWORKER, STRUCTURAL (Metal Building Erection Only)..........$ 28.05 18.11
* PLUM0412-007 01/02/2025
Rates Fringes
PIPEFITTER (Including HVAC Pipe Installation)...............$ 43.07 16.60 PLUMBER (Excluding HVAC Pipe Installation)....................$ 43.07 16.60
SHEE0049-012 01/01/2024
Rates Fringes
Sheet Metal Worker (HVAC Duct and System Installation Only)....$ 37.50 18.51
* SUNM2010-013 11/09/2010
Rates Fringes
BOILERMAKER......................$ 21.77 3.98
BRICKLAYER.......................$ 20.36 5.74
CARPENTER (Acoustical Ceiling Installation Only)...............$ 20.79 0.00
CARPENTER (Drywall Finishing/Taping Only)...........$ 20.18 4.54
CARPENTER (Drywall Hanging Only)............................$ 21.39 2.85
CARPENTER (Form Work Only).......$ 20.46 5.61
CARPENTER, Excludes Acoustical Ceiling Installation, Batt Insulation, Drywall Finishing/Taping, Drywall Hanging, Form Work, and Metal Stud Installation................$ 20.86 6.25
CEMENT MASON/CONCRETE FINISHER...$ 17.72 ** 5.43
ELECTRICIAN (Low Voltage Wiring for Alarms)...............$ 28.25 6.62
FLOOR LAYER: Carpet.............$ 22.31 0.30
GLAZIER..........................$ 20.15 3.95
INSULATOR - BATT.................$ 24.44 8.43
IRONWORKER, REINFORCING..........$ 19.75 8.45
IRONWORKER, STRUCTURAL,
Excludes Metal Building Erection.........................$ 22.00 9.03
LABORER: Common or General......$ 13.61 ** 3.89
LABORER: Landscape & Irrigation.......................$ 10.60 ** 0.24
LABORER: Mason Tender - Brick...$ 13.77 ** 4.35
LABORER: Mason Tender - Cement/Concrete..................$ 11.51 ** 0.85
LABORER: Pipelayer..............$ 13.78 ** 2.20
OPERATOR: Backhoe...............$ 20.95 4.73
OPERATOR: Forklift..............$ 21.13 4.83
OPERATOR: Grader/Blade..........$ 21.40 4.95
OPERATOR: Loader (Front End)....$ 21.55 4.97
PAINTER: Brush, Roller and Spray, Excludes Drywall Finishing/Taping.................$ 16.10 ** 1.79
PLASTERER........................$ 12.00 ** 0.00
ROOFER...........................$ 13.24 ** 0.50
SHEET METAL WORKER, Excludes
HVAC Duct and Unit Installation.....................$ 22.01 9.65
TILE FINISHER....................$ 14.02 ** 0.00
TILE SETTER......................$ 19.00 0.00
TRUCK DRIVER: Dump Truck........$ 15.25 ** 3.89
TRUCK DRIVER: Pickup Truck......$ 15.91 ** 3.13
TRUCK DRIVER: Water Truck.......$ 16.26 ** 4.93
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
N80 EARTH COVERED MAGAZINE SOLICITATION No. W912PP25BA001 White Sands Missile Range, NM Solicitation Specifications
SECTION 01 35 20.00 44
SPECIAL PROJECT PROCEDURES FOR WHITE SANDS MISSILE RANGE
PART 1 GENERAL
1.1 NOTICE OF RESTRICTED ACCESS TO WHITE SANDS MISSILE RANGE
White Sands Missile Range is a restricted area in its entirety. Access to the Range by foreign nationals is not authorized unless approved on a case-by-case basis by the commander. The Contractors shall present to the Contracting Officer or his representative acceptable evidence of United States citizenship or bona fide immigrant alien status for each Contractor or sub-contractor employee who will perform work at this installation.
Requests for foreign national access shall be presented to the Contracting Officer at least 14 days prior to the desired access date. The following information must be included in each visit request: Name in full, security clearance, official title or position, nationality, visa, passport, order number, or serial number, date(s) desired and purpose of visit.
1.2 CONTRACTOR ACCESS PROGRAM
Contractors must complete and submit the attached Form 5000 for employee access. The current Access Control requirements published on the WSMR Directorate of Emergency Services website are as follows:
1.2.1 ACCESS CONTROL
All visitors to White Sands Missile Range (WSMR) must have a valid need for access and a White Sands Missile Range Point of Contact (POC) or sponsor for that visitor. The exception for this is to visit the Missile Park and Museum (in this case access will be restricted to the area of the museum).
When visitors arrive, they must have a valid state or federal ID, a WSMR sponsor or POC and provide that information to the access clerks or guards at the gate.
Entry Requirements for person without a Valid DOD ID Card requesting unescorted access:
1. A valid purpose for entering the installation; (Attend Meeting, visit Museum, Job interview, etc.)
2. Valid driver's license
3. Current vehicle registration (If operating a vehicle)
4. Proof of current insurance (If operating a vehicle)
5. License plate number
6. Provide the destination, name of facility, building number, street address, or unit name/designation
The visitor's POC/sponsor will be contacted and the visitor will be run through the NCIC-III database and a determination will be made for acceptability. Once acceptability has been determined a Temporary Gate Pass will be issued for short visits not to exceed 14 days. For visits
SECTION 01 35 20 Page 1 that exceed this time frame the visitors MUST have a SPONSOR and complete the Form 5000. The Form 5000 contains personal information and it must be protected. DO NOT transmit over open e-mail. Protect the document with a password and send the two forms over separate e-mails or provide information to the POC/Sponsor who will submit with an encrypted email and 102 for Main Post and/or Up Range. A pass completed by this method can be up to 365 days from the completed NCIC-III Check. (Done with the Form 5000 or a Temporary Gate Pass). The request forms must be submitted by the POC/Sponsor and not the requestor. Once acceptability has been determined, the Form 102 will be returned to the POC/Sponsor and the visitor will be granted a temporary pass to go to the WSMR access badge processing center.
For more information, please contact the Installation Physical Security Section at: 575-678-7626/5414/7905
For this Contract, the USACE Contracting Officer's Representative (COR) shall serve as the Government POC/Sponsor.
1.2.2 Background Checks
The Contractor may be requested to furnish information to conduct background checks for each employee to the Security Directorate and/or Pass & Badge Office prior to access to the installation.
1.2.3 Identification of Employees
The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the Contracting Officer. Prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. Contractor and subcontractor personnel shall wear identifying markings on hard hats clearly identifying the company for whom the employee works. Contractor personnel shall wear visible Contractor-furnished employee identification badges while physically on the Installation. Each badge shall include, as a minimum, the company name, employee name, photograph, Contract Title, Contract Number, and the expiration date of the badge.
1.2.4 Utility Outages
Although no outages are anticipated, the following guidelines are provided: Utility outage permits are required. The contractor is responsible for the coordination and submitting all forms and sketches required for any outage. Utility, road and railroad closures require a minimum ten(10) working days advance written notice and will be subject to WSRO approval. In the case of a road closure a sketch shall be in accordance with the Manual on Uniform Traffic Control Devices and shall be provided at no additional cost to the government.
1.2.5 General Requirements
The Contractor is responsible for daily clean-up and completes restoration of the area once the contract is complete. Work shall be accomplished in accordance with all applicable contract documents.
1.2.6 Environmental Concerns
The Contractor is responsible for getting all Environmental approvals
SECTION 01 35 20 Page 2
(SWPPP's, etc…). The Contractor shall prepare a SWPPP for review by the Government and shall be a co-permittee on the NPDES permit. Once the Government has reviewed and accepted the Contractor's submitted SWPPP, the Contractor shall submit a Notice Of Intent (NOI) and provide a copy to the Government no later than 5 days prior to earth disturbance. See Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS WHITE SANDS MISSILE RANGE for more detail.
SWPPP: All work shall be in accordance with the National Pollutant Discharge Elimination System Manual (NPDSM) December 2003. The Contractor is responsible for installing and maintaining all erosion and sediment control devices until permanent stabilization of the disturbed site has occurred. All erosion and sediment control devices shall be inspected weekly and after every storm and repairs made if necessary. At the completion of construction and after the vegetation has been established, the Contractor shall remove all temporary erosion and sediment control devices. The Contractor shall construct or install temporary and permanent erosion and sediment control best management practices (BMPs) in accordance with UFSWF Guide Specification Section 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS WHITE SANDS MISSILE RANGE.
Unexploded Ordinance (UXO): WSMR is an active range and all Contractor employees must have WSMR provided UXO training. Mandatory UXO training is required for all Contractor personnel prior to start of onsite activities. UXO Training is available online at:
https://www.wsmr.army.mil/ux/Pages/default.aspx . No one is allowed on WSMR range areas without the training. No one shall disturb any suspicious object or item that could be a UXO and it should be immediately reported to 678-7588 or 678-3411.
Information on projected roadblocks, lockouts, and lock-ins can be obtained by calling (575) 678-1178 (recording) and/or (575) 678-2222 (office).
1.3 Demolition Waste
All non-hazardous solid waste resulting from demolition operations (construction and demolition, C&D, debris) on WSMR shall be recycled and/or disposed of at an approved off-site solid waste or recycling facility. The contractor shall segregate and recycle, at a minimum, all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes. The contractor shall report to the WSMR Garrison Environmental Division Solid Waste Program Manager, the tons and type of material recycled and disposed, identify the recycling and disposal facility and provide the information to the government. The contractor shall be responsible for proper collection and disposal of all other non-hazardous solid waste (trash) generated at the job site. Cardboard, paper, aluminum cans, soda and water bottles should be recycled in any available blue recycling trailer conveniently located on main post.
As an alternative to off-site disposal and recycling of C&D debris, the contractor is authorized to recycle scrap metal, asphalt, concrete and clean fill on-site. The contractor must coordinate with the WSMR Garrison Environmental Division Solid Waste Manager (678-2415) and complete and submit the WSMR Diverted/Stockpiled Materials Monthly Report Form. The contractor is authorized to dispose of other acceptable C&D debris at the on-site C&D landfill. The attached WSMR C&D Waste Turn-In Inspection Sheet identifies C&D debris accepted at the on-site C&D landfill. The contractor shall report the tons and type of material recycled and
SECTION 01 35 20 Page 3 disposed to the government. The contractor is authorized to recycle all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes at the on-site scrap metal yard, Monday through Thursday, 7:30am to 11:30am and 12:30pm to 2:30pm.
Concrete shall be crushed in accordance with WSMR and New Mexico Air Quality regulations and government specifications. The contractor shall apply for a General Construction Permit (GCP) through New Mexico Environment Department. The contractor shall comply with the provisions (one of them is the use of water spray). Out of state contractors will need to provide a relocation notice from wherever they came from to New Mexico Environment Department as part of the GCP application. The contractor will coordinate with WSMR Garrison Environmental Division Air Quality Program Manager (678-2225) at the planning stage before crushing operation begins.
A satellite accumulation point (SAP) must be established by the contractor for accumulation of lead-based paint and asbestos waste generated during removal and abatement on WSMR. Contact the Hazardous Waste Management Center (HWMC), 678-4641, for further guidance. An SAP may also be required for proper management and disposal of paint related waste when other than latex or acrylic paint is used. An inventory of products to be used on WSMR, along with the manufacturer's SDS/MSDS, shall be provided to the HWMC prior to start of work. A satellite accumulation point (SAP) must be established by the contractor for accumulation of lead-based paint and asbestos waste generated during removal and abatement on WSMR. Contact the Hazardous Waste Management Center (HWMC), Raymond Duran, Hazardous Waste Program Manager, at 575-678-4641 or raymond.b.duran.civ@army.mil, for further guidance. Any asbestos related disposal/work, manifest, permits, etc. must go through Jon Harrison, jon.e.harrison2.civ@army.mil. An SAP may also be required for proper management and disposal of paint related waste when other than latex or acrylic paint is used. An inventory of products to be used on WSMR, along with the manufacturer's SDS, shall be provided to the HWMC prior to start of work.
1.4 DIGGING PERMIT AND UTILITY LOCATES
For all project activities requiring excavation, soil borings, or other subsurface work, the Contractor shall complete the attached WSMR Digging Permits in accordance with the Digging Permit Processes contain therein.
The Contractor is responsible for completing BOTH Digging Permits and obtain all required signatures/approvals to ensure all potential underground utilities and communication lines are identified. The Contractor shall allow a minimum of 45 calendar days for the WSMR Digging Permit Process from submission to Government Approval.
For the INFORMATION MANAGEMENT DIRECTORATE TRANSMISSION SECTION (WG-G6-DTE) EXCAVATION PERMIT, the form is to be filled out and e-mailed to Mr. Adam Carruth (adam.m.carruth.civ@mail.mil) and Mr. Danny Apodaca (daniel.d.apodaca2.civ@mail.mil). The WSMR Commo Group will mark/flag the commo lines in the area per the information provided, and when completed, e-mail the signed document back to the POC that submitted the locate request. The Commo group also signs the WSMR Digging Permit once the Commo Locate form and process has been completed.
For locates of utilities that do not belong to White Sands Missile Range, the Contractor shall submit a request through the website https://geocall.nm811.org/geocall/portal .
SECTION 01 35 20 Page 4
Contact: WSMR BOID Office at 575-678-1116 to request forms.
Email to: usarmy.wsmr.sec.list.zo-dpw-service-desk@army.mil.
1.5 Anticipated Roadblocks
Test missions at White Sands Missile Range involve required road closures to meet safety protocols. Accordingly, the Contractor shall anticipate eight (8) roadblock delays per month that may interrupt transportation into and from White Sands Missile Range, as well as travel within the White Sands Missile Range installation. Each roadblock has a duration up to two
(2) hours.
For locations of roadblocks on public roads, information is available at https://www.wsmr.army.mil/Pages/WhiteSandsRoadBlockSchedule.aspx .
To access information for the latest roadblock information, contact (575) 675-1178. The information is updated each weekday in the afternoon for the following day.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
SECTION 01 35 20 Page 5
WSMR Proposed Language—USACE and Other Solicitations and Contracts:
Managing Demolition Waste
1.) All non-hazardous solid waste resulting from demolition operations (construction and demolition, C&D, debris) on WSMR shall be recycled and/or disposed of at an approved off-site solid waste or recycling facility. The contractor shall segregate and recycle, at a minimum, all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes. The contractor shall report to the WSMR Garrison Environmental Division Solid Waste Compliance Manager, the tons and type of material recycled and disposed, identify the recycling and disposal facility and provide the information to the government. The contractor shall be responsible for proper collection and disposal of all other non-hazardous solid waste (trash) generated at the job site. Cardboard, paper, aluminum cans, soda and water bottles should be recycled in any available blue recycling bin conveniently located on Main Post.
2.) As an alternative to off-site disposal and recycling of C&D debris, the contractor is authorized to recycle scrap metal, asphalt, concrete and clean fill on-site. The contractor must coordinate with WSMR Garrison Environmental Division Solid Waste Compliance Manager (678-2415) and complete and submit the WSMR Diverted/ Stockpiled Materials Monthly Report Form, D-2. The contractor is authorized to dispose of other acceptable C&D debris at the on-site C&D landfill. The WSMR C&D Waste Turn-In Inspection Sheet, D-3, identifies C&D debris accepted at the on-site C&D landfill. The contractor shall report the tons and type of material recycled and disposed to the government. The contractor is authorized to recycle all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes at the on-site scrap metal yard, Monday through Thursday, 7:30am to 11:30am and 12:30pm to 2:30pm.
3.) Concrete shall be crushed in accordance with WSMR and New Mexico Air Quality regulations and government specifications. The contractor shall apply for a General Construction Permit (GCP) through New Mexico Environment Department. The contractor shall comply with the provisions (one of them is the use of water spray). Out of state contractors will need to provide a relocation notice from wherever they came from to New Mexico Environment Department as part of the GCP application. The contractor will coordinate with WSMR Garrison Environmental Division Air Quality Program Manager (678-2225) at the planning stage before the crushing operation begins.
l4ecejas Cross-Out
WSMR Diverted/Stockpiled Materials Monthly Report Form
Contract number:
Contractor:
Contractor C&D diversion/disposal POC:
Signature:
Date:
Refer all questions concerning diversion/disposal and return this form to WSMR Environmental Division Solid Waste Compliance Manager (678-2415) javier.mendoza.civ@mail.mil or 678-2225. NOTE: Form must be submitted monthly to report tons stockpiled.
Material Diverted CY Conversion Tons Asphalt/Concrete Asphalt (broken) x 0.70 =
Concrete (broken) x 1.20 =
Concrete (solid slab) x 1.30 =
Brick/Masonry/Tile Brick (broken) x 0.70 =
Rocks x 1.51 =
Land Clearing Soil x 0.60 =
Appendix A: Borrow Pits Main Post 85x11 Feb2022
HE
AD
QU
AR
TE
RS
HU
GH
ES
OW
EN
NIKE
WSMR
Museum
HUGHES ROAD
DIVERSION AREA
OWEN ROAD
BORROW PIT
S. HEADQUARTERS
BORROW PIT
Las Cruces Gate
WE
ST
ER
N
CA
LL
-U P A
RE
AS
NORTHERN CALL-UP AREA
HAFB
FORT BLISS
£¤380
£¤54
£¤54
£¤70
§̈¦10
§̈¦25
§̈¦25
")7
")7
Location on WSMR
AREA
MAPPED
Produced by the GIS Team for the Directorate of Public Works, WSMR.
WHITE SANDS MISSILE RANGE
0 1,000 2,000500 Feet
2/7/2022
File Location:Projects\Borrow_Pits\Borrow_Pits_MainPost_85x11_Feb2022.mxd
Borrow Pit Areas - Main Post Borrow Pit Areas
No warranty is made by the White Sands Missile Range as to the accuracy, reliability, or completeness of these data for individual use or aggregate use with other data, or for purposes not intended by WSMR.
Spatial information may not meet National Map
Accuracy Standards. This information may be updated without notice.
AREA CLOSED
PIT CLOSED
l4ecejas Cross-Out l4ecejas Cross-Out
| SF 30 |
| 00 50 00 – CONTRACTING FORMS AND |
SUPPLEMENTS
| 01 35 20.00 44 -SPECIAL PROJECT PROCEDURES FOR WHITE SANDS MISSILE RANGE |
| 01 74 19 SUPPLEMENTAL -MANAGING DEMOLITION WASTE |
| APPENDIX A: BORROW PITS |
File details come from the government source that posted it. Updated .