This solicitation requests proposals for the design and construction of an Integration Lab (REVIL) at Kirtland Air Force Base in New Mexico. The Army Corps of Engineers Engineering District Albuquerque seeks to award a firm fixed-price contract for design and construction services including site preparation, utilities, and a new lab facility. The period of performance is 730 calendar days from Notice to Proceed with construction to begin no earlier than October 2023. Proposals are due by August 2022 and award is expected in September 2022.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912PP24B0007

Date: January 2024

U.S. ARMY CORPS OF ENGINEERS

Construct Integration Lab

(REVIL)

Kirtland Air Force Base, New Mexico

RTA

Not For Construction Volume 1 of 2: Specifications

THIS PAGE INTENTIONALLY LEFT BLANK

Construct Integration Lab (REVIL)

Project Number: MHMV193108 Solicitation Number: W912PP24B0007

Kirtland Air Force Base, NM

100% Corrected Final (RTA) Specification

September 2023

CUI

This page was intentionally left blank for duplex printing.

Construct Integration Lab

(REVIL)

Kirtland Air Force Base, NM

MHMV193108

September 2023

Burns & McDonnell 9400 Ward Parkway

Kansas City, MO 64114

CERTIFICATION PAGE

CIVIL STRUCTURAL ARCHITECTURAL

FIRE PROTECTION MECHANICAL ELECTRICAL

09/01/2023

18634 r/ 'v/ifnw , 09/01/2023

9/6/20239/6/2023

09/01/2023

This page was intentionally left blank for duplex printing.

CONSTRUCT INTEGRATION LAB (REVIL)

KIRTLAND AFB, NM

W912PP24B0007

PROJECT TABLE OF CONTENTS - VOLUME 1 of 2

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00 SOLICITATION, OFFER, AND AWARD, SF1442;

PROPOSAL SCHEDULE, CORPORATE,

PARTNERSHIP, JOINT VENTURE CERTIFICATES

00 20 00 INSTRUCTIONS FOR PROCUREMENT

00 21 00 03/17 INSTRUCTIONS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 50 00 03/17 CONTRACTING FORMS AND SUPPLEMENTS -

Wage Determination

00 70 00 CONDITIONS OF THE CONTRACT

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/11, CHG 13: 08/21 WORK RESTRICTIONS

01 30 00 11/20, CHG 1: 08/21 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 3: 11/21 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/18, CHG 1: 11/21 FACILITY DATA REQUIREMENTS

01 91 00.15 10 05/19, CHG 2: 08/20 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10, CHG 2: 02/19 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

05 51 33 02/16, CHG 2: 02/18 METAL LADDERS

PROJECT TABLE OF CONTENTS

VOLUME 1 - SPECIFICATIONS

01 54 00 06/04 SECURITY

01 72 80 06/18 TRANSFER AND ACCEPTANCE OF MILITARY

REAL PROPERTY

W912PP24B0007

05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM

FOR AIR TIGHTNESS

07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING

07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION

07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION

07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION

07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS

07 54 19 02/13, CHG 3: 02/21 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES

08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE

DIVISION 09 - FINISHES

09 06 00 05/09, CHG 1: 11/13 SCHEDULES FOR FINISHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.20 08/20 INTERIOR SIGNAGE

10 22 19 08/17, CHG 1: 08/18 DEMOUNTABLE AND MOVABLE PARTITIONS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

DIVISION 12 - FURNISHINGS

12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 73 05/20, CHG 1: 08/20 SEISMIC CONTROL FOR MECHANICAL

EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

PROJECT TABLE OF CONTENTS

W912PP24B0007

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 30 00 05/20 HVAC AIR DISTRIBUTION

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS

23 82 46.00 40 05/17 ELECTRIC UNIT HEATERS

23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

25 05 11.03 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

DIVISION 26 - ELECTRICAL

26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 08 00 11/21 APPARATUS INSPECTION AND TESTING

26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED

TRANSFORMERS

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 08/08, CHG 2: 02/21 EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

PROJECT TABLE OF CONTENTS

W912PP24B0007

32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 23 08/17 AGGREGATE BASE COURSES

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR

ROADS AND SITE FACILITIES

32 15 00 05/17 AGGREGATE SURFACING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 92 19 08/17, CHG 1: 08/21 SEEDING

DIVISION 33 - UTILITIES

33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP

RUNNING

PROJECT TABLE OF CONTENTS

-- End of Project Table of Contents --

VOLUME 2 - DRAWINGS

W912PP24B0007 DESIGN BID BUILD FY 23 CONSTRUCT INTEGRATION LAB (REVIL), KIRTLAND AIR FORCE BASE, BERNALILLO COUNTY, NEW MEXICO

This acquisition is a Total Small Business Set-Aside.

Magnitude of Construction is betw een $5,000,000.00 - $10,000,000.00.

Bids must be delivered NO LATER THAN the time/date set for opening in Block 13A. Bids received after the time specif ied in block 13A w ill not be accepted. Please see instructions to Offerors for more information.

X

DIANA M KEERAN 505-342-3263

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

23-Jan-2024

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________475 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00 70 00

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 Feb 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY ENGINEER DISTRICT, ALBUQUERQUE

4101 JEFFERSON PLAZA NE

ALBUQUERQUE NM 87109-3435

W912PP

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

505-342-3496FAX:TEL: TEL: FAX:

W912PP24B0007 1 OF 84

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

PROPOSAL SCHEDULE

(To be attached to SF 1442)

Item Unit No. Description Quantity Unit Price Amount

BASE BID

0001 Total cost of Construction for Integration Lab (REVIL) Primary Facility, Complete

1 JOB *** $

0002 Total cost of Construction for Integration Lab (REVIL) Supporting Facilities, Complete

TOTAL AMOUNT BASE BID $

BID OPTION NO. 1

0003 Bid Option No. 1, Additional Light Lab, Complete (Add a second Light Lab)

TOTAL AMOUNT – BID OPTION NO. 1 $

BID OPTION NO. 2

0004 Bid Option No. 2, Additional High Bay, Complete (Add a third High Bay)

TOTAL AMOUNT – BID OPTION NO. 2 $

Page 3a of 84

BID OPTION NO. 3

0005 Bid Option No. 3, Asphalt Parking Lot, TOTAL AMOUNT – BID OPTION NO. 3 $

BID OPTION NO. 4

0006 Bid Option No. 4, Furniture and equipment, TOTAL AMOUNT – BID OPTION NO. 4 $

0007 Bid Option No. 5, Overhead Cranes, Complete (Two cranes, one in each High Bay)

TOTAL AMOUNT – BID OPTION NO. 5 $

Page 3b of 84

0008 Bid Option No. 6, Internal Communication Lines, Complete (Fiber and Copper runs from switch in comm room throughout facility)

TOTAL AMOUNT – BID OPTION NO. 6 $

RECAPITULATION

1. TOTAL AMOUNT - BASE BID $

2. TOTAL AMOUNT - BID OPTION NO. 1 $

3. TOTAL AMOUNT - BID OPTION NO. 2 $

4. TOTAL AMOUNT - BID OPTION NO. 3 $

5. TOTAL AMOUNT - BID OPTION NO. 4 $

6. TOTAL AMOUNT - BID OPTION NO. 5 $

7. TOTAL AMOUNT - BID OPTION NO. 6 $

8. TOTAL AMOUNT - BASE BID, BID OPTION NO. 1, BID OPTION $

NO. 2, BID OPTION NO. 3, BID OPTION NO. 4., BID OPTION

NO. 5, AND BID OPTION NO. 6.

Page 3c of 84

NOTES:

1. AWARD OF PROPOSAL ITEMS:

Award of all proposal items will be made to one bidder. Bidders must bid on all items.

2. EXERCISE OF OPTIONS:

The Government reserves the right to exercise the option(s) by written notice to the Contractor either singularly or in any combination for up to 90 calendar days after award of the Base Bid without an increase in the Offeror's bid price.

Completion of added options shall continue at the same schedule as the Base Bid unless otherwise noted in Section 00 73 00, SUPPLEMENTARY CONDITIONS, COMMENCEMENT; PROSECUTION AND COMPLETION OF WORK

3. EVALUATION OF OPTIONS:

(FAR 52.217-5) (JUL 1990) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirements. Evaluation of options will not obligate the Government to exercise the options.

4. ARITHMETIC DISCREPANCIES:

(a) For the purpose of initial evaluation of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purposes of bid evaluation, the government will proceed on the assumption that the bidder intends the bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

Page 3d of 84

NOTES: (Cont’d)

5. MODIFICATIONS TO BID BASED ON UNIT PRICE:

If a modification to a bid based on unit price is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

6. PROGRESS PAYMENT REQUESTS:

Progress payment Requests made by the Contractor pursuant to the provisions of Contract Clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, shall be submitted on ENG FORM 93 to the administration office as designated in Block 26, Standard Form 1442 Back, Solicitation, Offer and Award. ENG FORM 93 shall be submitted to that office on the 1st of each month in appropriate form and certified. Photocopies of the form shall be furnished on that same date to the Corps of Engineers offices designated at the Pre-Construction Conference.

7. ACCRUALS:

In accordance with USACE Engineer Financial Regulation (ER) 37-1-30, and other applicable Federal and DOD financial accounting standards, the

Contractor must assist government personnel with providing reasonably accurate estimates of the value of goods and/or services rendered to the Government pursuant to this contract for each calendar month during which goods and services are delivered. Standard forms and instructions will be provided by the Government to assist with meeting this requirement. These monthly estimates, which facilitate timely entry of accruals, must be received by the Government on or before four (4) business days prior to each calendar month-end.

8. ALL OTHER WORK NOT SEPARATELY LISTED:

All other work not separately listed shall not include Mobilization, Demobilization and Distributed Cost (for example Insurance, Quality Control, and/or Home Office Overhead, Field Overhead) related to other Bid Items.

9. UNIT ABBREVIATIONS:

EA. = EACH M. = METER

L.S. = LUMP SUM S.M. = SQUARE METER

L.F. = LINEAR FEET C.M. = CUBIC METER

S.F. = SQUARE FEET S.Y. = SQUARE YARD

C.F. = CUBIC FEET C.Y. = CUBIC YARD

- END OF PROPOSAL SCHEDULE -

W912PP24B0007

Section 00 10 00 - Solicitation

CORPORATE, PARTNERSHIP, JOINT VENTURE CERTIFICATES

If the offer is submitted by a corporation, partnership or a Joint Venture, the applicable form listed below must be completed and submitted with the Standard Form 1442. In the alternative, other evidence must be submitted to substantiate the authority of the person signing the offer. If a corporation, the same officer shall not execute both the offer and the certificate.

CORPORATE CERTIFICATE

I, _______________________________________________, certify that I am the Secretary of the corporation named as Offeror/Contractor herein; that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then __________________________ of said corporation; that said offer/contract was duly signed for and on behalf of said corporation by authority of its governing body, and is within the scope of its corporate powers.

______________________________ (CORPORATE SEAL)

(Secretary)

AUTHORITY TO BIND PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the offer had authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments, on behalf of said partnership, with the United States of America, except as follows: (State “none” or describe limitations, if any.)

This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to, and acknowledged by, the Contracting Officer.

(Type or Print Name) (Signature)

JOINT VENTURE

Provide a copy of the Joint-Venture (JV) agreement. The SF 1442, Solicitation, Offer and Award form must be signed by the party with the authority to bind the JV as indicated in the agreement. Each party to the JV agreement shall complete one of the following entries:

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation A)

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation B)

Section 00 20 00 - Instructions for Procurement

BIDDER’S CHECKLIST

All information required by the terms of the solicitation must be furnished. MISTAKES OR OMISSIONS CAN BE COSTLY. Failure to properly perform any one of these actions may cause your bid to be rejected. Important items for you to check, include but are not limited to, those listed below. This checklist is furnished only to assist you in submitting a proper bid.

[ ] Have you acknowledged receipt of ALL solicitation amendments? If in doubt as to the number of amendments issued, please contact Diana Keeran, Contract Specialist, at (505) 342-3263.

[ ] Have you completed Section 00 45 00, Representations and Certifications?

[ ] Is your bid properly signed?

[ ] Is your bid guarantee, if in the form of a bid bond, properly signed by both the bidder and surety and are all required seals affixed?

[ ] Is your bid guarantee in the proper form and amount?

[ ] Is the name in which you submitted the bid the same on your bid guarantee?

[ ] If required, have you entered a unit price for each bid item?

[ ] Are decimals in unit prices in the proper places? Are your figures legible?

[ ] Are the extensions of your unit prices and your total bid price correct?

[ ] Are all erasures or corrections initialed by the person signing the bid?

[ ] Have you reviewed your bid for possible errors in calculations or work left out?

[ ] Have you erroneously restricted your bid by altering the provisions of the solicitation?

[ ] Is the envelope containing your bid properly identified that it is a sealed bid and does it contain the correct solicitation number and bid opening time and Bidder’s Name and Address?

[ ] If any of the solicitation amendments involved changes to the bid schedule, did you use the amended schedule for submitting your bid?

[ ] Will your bid arrive on time and in the correct format? Late hand-carried bids will not be considered. See

FAR 52.214-7, LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS for further information pertaining to late mailed bids.

THE FOLLOWING ARE INSTRUCTIONS TO OFFERORS TO SECTION 00 20 00:

SUBMITTAL INFORMATION FOR BIDDERS

The following documents must be returned with your bid:

A. Tab 1--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s CAGE is entered in the block 14 with its name and address.

B. Tab 2 – Your acknowledgement of all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment. Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your bid.

C. Tab 3 – The completed Contract Line Item Number (CLIN) Schedule on the SF1442, and the Bid

Schedule with your proposed CLIN prices inserted where indicated. Prices must be proposed for all CLINS. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e. to two decimal places). Do not round off extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

D. Tab 4 -- Your completed Reps and Certs and/or SAM registration information

E. Tab 5 – Your Bid Guarantee (eg., Standard Form 24, “Bid Bond”)

F. Tab 6 – Pre Award Survey

DIRECTIONS FOR SUBMITTING BIDS:

The Government will not accept telegraphic or facsimile bids.

Bids must be delivered to 4101 Jefferson Plaza NE, Albuquerque, NM 87109, NO LATER THAN the time/date set for opening in Block 13A of the SF1442. Due to the security requirements at the U.S. Army Corps of Engineers, Albuquerque District Building, it may take longer to check in on the day of bid opening. Therefore, please allow sufficient time for turning in your bid. Late proposals/bids will NOT be accepted for any reason.

PRE-AWARD INFORMATION AND DETERMINATION OF CONTRACTOR RESPONSIBILITY

PRE-AWARD SURVEY. In accordance with FAR Part 9.104, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and equipment to be used in performing the work. Using the attached pre award survey below (Attachment A) each bidder shall furnish documentation of whether he is now or ever has been engaged in any work similar to that covered by these specifications, the dollar value thereof, the year in which such work was performed, and the manner of its execution. Documentation to be provided should demonstrate the bidder’s ability to prosecute the required work. This documentation shall include but is not limited to the following:

(a) The name and address of the office or firm under which such similar work was performed and the bidder’s role in that work. Bidder shall be able to demonstrate at least three (3) years recent experience (within five (5) years of the IFB closing date) with work similar to the work outlined in this solicitation.

(b) Awardee will be required to provide at least three (3) references for similar work, to include Business Name, Point of Contact, and telephone number.

(c) A list of key personnel available for this project and their qualifications.

(d) A copy of bidder’s latest financial statement, including the names of banks or other financial institutions with which the bidder conducts business. If the financial statement is more than 60 days old, a certificate should be attached stating that the financial condition is substantially the same, or if not the same, the changes that have taken place. Such statement will be treated as confidential.

(e) A list of present commitments, including the dollar value thereof, and name of office under which the work is being performed.

(f) A list of total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts. Acceptable evidence of “the ability to obtain” the required, adequate resources normally consists of a commitment of explicit arrangement that will be in existence at the time of contract award to rent, purchase, or otherwise acquire the needed facilities, equipment, other resources, or personnel.

RESPONSIBILITY. Award will be made to the lowest, responsible bidder whose bid, conforming to the invitation for bids, will be the most advantageous to the Government. To be determined responsible, the apparent low bidder shall:

(1) Have adequate financial resources to perform the contract, or the ability to obtain them. The contractor will be required to provide the Name of the Financial Institution, POC, and phone number.

(2) Have a satisfactory performance record. The contractor shall have no performance annotated with an individual rating of less than SATISFACTORY on any Final Evaluation within the last six

(6) years from the bid opening date.

(3) Have a satisfactory record of integrity and business ethics. Awardee will be required to provide at least three (3) references for similar work, to include Business Name, Point of Contact, and telephone number.

(4) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors). Per FAR 9.104-3, acceptable evidence normally consists of a commitment or explicit arrangement that will be in existence at the time of the contract to acquire the needed facilities, equipment, other resources or personnel.

(5) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and

(6) Be otherwise qualified and eligible to receive an award under applicable laws and regulations

BASIS FOR AWARD:

The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of all CLINS listed in the SF 1442.

USE OF THE WORDS “PROPOSER” AND “OFFEROR”

Whenever the word “Proposer” appears in the RFP it shall be construed to have the same meaning as the word “Offeror.”

REQUIREMENTS FOR PROTECTING FEDERAL CONTRACT INFORMATION (FCI) AND

CONTROLLED UNCLASSIFED INFORMATION (CUI)

Perspective offerors are advised that per current DoD guidance, they are required to comply with FAR 52.204-21, DFARS 252.204-7012, and DFARS 252.204-7020 requirements for safeguarding FCI and CUI for ALL DoD contract awards. In order to be considered for award, contractors are required to complete a cybersecurity assessment in the Supplier Performance Risk System (SPRS), https://www.sprs.csd.disa.mil PRIOR to submitting a proposal. Offerors must be registered in the Procurement Integrated Enterprise Environment (PiEE) in order to access SPRS. Offerors can register for PIEE access at https://piee.eb.mil/piee-landing .

AVAILABILITY OF PLANS AND SPECIFICATIONS

This solicitation will be issued via Internet only. Notification of amendments shall be made via Internet only, as well. It is therefore the contractor’s responsibility to check the following address daily for any posted changes to this solicitation. For security reasons, all technical and engineering data related to this solicitation will be distributed using SAM.gov, formerly Federal Business Opportunities (fbo.gov).

SAM.gov is a consolidation of ten legacy sites into a single database. In order to save searches, follow contract opportunities, request secure documents or sign up for an Interested Vendor List, you will need a login.gov account in SAM.gov. To create a login.gov account or link an existing login.gov account with SAM.gov follow the instructions on the SAM.gov website. Contractors registered with SAM.gov may view and/or download this solicitation and all amendments from the Internet after solicitation issuance at this site.

BIDDER INQUIRY AND PROPOSAL INFORMATION

a. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org.

1. To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page, you may view all bidder inquiries or add inquiry.

2. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

3. The Solicitation Number is: W912PP24B0007

The Bidder Inquiry Key is: GJHPJU-IRXIPE

b. The Bidder Inquiry System will be unavailable for new inquires 7 calendar days prior to IFB closing date at 2:00PM Mountain time, in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.

c. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

d. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

CONTRACTING OFFICER AUTHORITY

The Contracting Officer who signs this contract will be the primary Contracting Officer for this contract.

However, any Contracting Officer assigned to the Albuquerque District, contracting within his or her authority, may take formal action on this contract when a contract action needs to be taken and the primary Contracting Officer is unavailable.

NAICS CODE AND SMALL BUSINESS SIZE STANDARD

The North American Industry Classification System (NAICS) code for this acquisition is 236220. The small business size standard is: the average annual receipts of the concern and its affiliates for the preceding three fiscal years must not exceed $45.0 million.

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

WHO MAY SUBMIT PROPOSALS

Any legally organized Offeror may submit a proposal.

Firms submitting a proposal as a joint venture (JV) must ensure the following requirements are met:

a. Obtain a Tax Identification Number (TIN) for the joint venture.

b. Prepare the Section 004500, Representations and Certifications as a joint venture (e.g., providing the TIN for the JV)

c. Register in the System for Award Management (SAM) formerly Central Contractor

Registration (CCR) as a joint venture in which a unique CAGE Code will be obtained.

See FAR Clause 52.204-7, System for Award Management for further information in Section 002100.

d. Provide a copy of the JV agreement in the proposal submission.

SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION

The Offeror must ensure that your company’s data at the System for Award Management (SAM) website, https://www.sam.gov/portal/public/SAM/, is current per FAR 52.204-13, System for Award Management Maintenance. (This clause is included in Section 00 70 00 of this RFP.)

BONDS (FAR 28.102-2)

a. Bid Bond. Each Offeror shall submit with his offer a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in FAR 52.228-1. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. The bid bond shall remain in effect until Performance and Payment Bonds are provided and accepted.

b. Performance and Payment Bonds. Within ten (10) calendar days after contract award, and prior to contract performance, the Contractor shall furnish two bonds, a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties acceptable to the Government. The penal sum of such bonds will be as indicated in FAR 52.228-15.

NEW MEXICO GROSS RECEIPTS TAX (NMGR)

The Offeror should be aware that NMGR tax is applicable to this contract and the rate may vary for each county and city. The Gross Receipts Tax Rate is available from the New Mexico Taxation and Revenue

Department, (505) 841-6200. The Gross Receipts Tax Rate is available at http://www.tax.newmexico.gov.

FEDERAL, STATE AND LOCAL TAXES

The Offeror shall include all applicable federal, state and local taxes in the contract price. See FAR 52.229-3, Federal, State, and Local Taxes in Section 007000 for additional information.

PERFORMANCE OF WORK BY CONTRACTOR (FAR 36.501)

Unless such description has been submitted with the offer, the successful Offeror must furnish the Contracting Officer within 20 days after award, a description of the work that he intends to perform with his own organization (e.g., earthwork, paving, brickwork, or roofing), the percentage of the total work this represents, and the estimated cost thereof.

U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1

AND OSHA REQUIREMENTS

The successful contractor to this Request for Proposals will be required to comply with all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil. by selecting “Safety and Occupational Health” followed by “EM 385-1-1”. The Contractor must also comply with Occupational Safety and Health Act (OSHA) standards. OSHA standards are subject to change. It is the Contractor's responsibility to maintain familiarity with current OSHA standards.

Zero Accident Goal: The Albuquerque District, in its continual pursuit of excellence in safety has established a goal of zero accidents. To attain this goal, it will be necessary for contractor management to set the expectation that worker injury is unacceptable and to create a culture where employees at all levels accept ownership of their safety performance.

AMENDMENTS TO REQUEST FOR PROPOSALS

The right is reserved, as the interest of the Government may require, to revise the specifications and drawings both before and after the date set for receipt of offers. Such revisions, if any, will be announced by amendment(s) to the Request for Proposal. If the revisions and amendments are of a nature which require material changes in quantities, or prices offered, or both, the date set for receipt of offers may be postponed by such number of days as in the opinion of the Contracting Officer will enable the Offeror to revise the offer. In such cases, the amendment will include an announcement of the new date for receipt of offer.

COSTS RELATED TO PROPOSAL PREPARATION

All costs related to proposal preparation, including travel, will be borne solely by the Offeror. The Government is not liable for any costs incurred by the Offeror submitting an offer in response to this solicitation.

CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor’s performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $750,000.00, the USACE will evaluate contractor’s performance and prepare a performance report using the Construction Contractor Appraisal Support System (CCASS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CCASS requires specific software, called PKI certification, which is installed on the user’s computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov/. If the Contractor wishes to participate in the performance evaluation process, access to PPIRS and PKI certification is the sole responsibility of the Contractor.

ATTACHMENT A – PRE AWARD SURVEY

CONSTRUCTION CONTRACTOR

DATA

DATE:

Firm Name and Telephone Number Main Office Address (Street, City, and State)

Branch Offices Services Rendered Construction Design Consultant

Organization Individual Joint Venture Partnership Corporation

Date Organized Date Incorporated:

State:

Names of Officers and Other Key Personnel

I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below)

Partners:

Officers: Other Key:

Remainder: Subtotal Permanent:

Maximum Personnel at Any Time: Date: Total:

II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF (DATE):

Present Value ($)

Current Assets:

Acquisition Cost ($) Current Liabilities:

Net Worth:

IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION

WORK IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE

(LIST MOST RECENT FIRST)

V—LARGEST JOB EVER CONTRACTED

(If Other Than in Past Six Years)

$ LARGEST JOB IN PAST 6 YRS Contract Amount: Date: Description:

Owner:

$ Contract Amount: Date: Description:

Owner:

Avg. Annual Income $

VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES

NAME AND POSITION/TITLE OF PERSON SIGNING SIGNATURE

See attachment for explanations or detailed description of item(s) reported above.

The completed Construction Contractor Data Form with Supplemental Schedules A-C (see format which follows). If the offeror is a large multi- segmented business concerns, the data provided on the supplemental schedules may be limited to information that directly pertains to the specific segment of the business concern (e.g., the division, group, unit, etc.) proposed to perform work under the prospective contract with its own work force. If the offer is being submitted by a Joint Venture, submit a separate form for each Joint Venture participant. The offeror may submit pre-award survey information in another format, provided that the information furnished is substantially the same as that which would be furnished on the Construction Contractor Data Form and its supplemental schedules.

Current financial statements. If the financial statement is more than 60 days old, submit a certificate stating that the firm's financial condition is substantially the same, or, if not the same, state the changes that have taken place. If a Joint Venture, provide this information for each participant in the Joint Venture.

CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS

List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.

CONTRACT

DESCRIPTION/

ORGANIZATION/

PERCENT

NUMBER AMOUNT LOCATION CONTACT COMPLETE

PERSON/

PHONE NUMBER

Banking information. Provide letters from banks or other financial institutions with which the contractor conducts business. The letters should contain information about your firm's accounts, loans, lines of credit, etc. The Government is interested in financial stability, timely payments, the length and nature of the relationship between the firm and the financial institution, and the firm's financial ability to perform the contract. The letters should also provide the name and telephone number of the bank representative the Government may contact. If a Joint Venture, provide this information for each Joint Venture participant.

The Government will treat the pre-award survey information submitted by the offeror as proprietary

CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS

List below the principal construction projects your firm has completed within the past five years, including all DoD contracts. Description provided should demonstrate experience with work similar to this project.

NUMBER

AMOUNT

DESCRIPTION/

LOCATION

ORGANIZATION/

CONTACT PERSON/

PHONE NUMBER

PERCENT

SUBLET

CONSTRUCTION CONTRACTOR DATA – SCHEDULE C – CONSTRUCTION AND/OR TECHNICAL

EQUIPMENT

List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.

QUANTITY

DESCRIPTION

CONDITION

YEARS OF SERVICE

PRESENT STATUS

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.211-6 Brand Name or Equal AUG 1999 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition NOV 2021 52.215-20 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

NOV 2021

52.217-5 Evaluation Of Options JUL 1990 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction

FEB 1999

52.228-2 Additional Bond Security OCT 1997 252.215-7013 Supplies and Services Provided by Nontraditional Defense

Contractors

JAN 2023

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm, fixed price contract resulting from this solicitation.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.228-17 INDIVIDUAL SURETY--PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee--

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. ARMY CORPS OF ENGINEERS

ATTN: CONTRACTING DIVISION (CONTRACTING OFFICER)

4101 JEFFERSON PLAZA NE

ALBUQUERQUE, NM 87109-3435

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for January 30, 2024 at 09:00am. EVERYONE is to submit their information to Filemon Gallegos at…