W912PP21R0022 Amendment 0002.pdf
PDF 26 MB Posted
- Attached to
- FY20 MILL AND OVERLAY RWY 13-31 ALL ASPHALT & REPAIR SHOULDERS, CANNON AIR FORCE BASE, CURRY COUNTY, NM
- Solicitation number
- W912PP21R0022
About this file
This solicitation seeks offers for a mill and overlay project for Runway 13-31 at Cannon Air Force Base in Curry County, New Mexico. The Department of the Army Corps of Engineers Engineering District Albuquerque is requesting bids to mill and overlay the entire asphalt runway with new asphalt and repair adjacent shoulders. Interested parties should submit offers in response to solicitation number W912PP21R0022 by the date specified in the attached request for proposal. The opportunity is set aside for small businesses. Award is expected within 90 days of the response deadline contingent upon funding availability and satisfactory offer evaluations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
W912PP
FY-20 MILL AND OVERLAY OF RUNWAY 13-31 SHOULDERS, Cannon Air Force Base, Curry County, New Mexico
1.This is Amendment No. 0002 to Solicitation No. W912PP21R0022. The following revisions shall be incorporated into the specifications. All other provisions shall remain unchanged.
U.S. ARMY ENGINEER DISTRICT, ALBUQUERQUE
CORPS OF ENGINEERS
4101 JEFFERSON PLAZA, N.E.
ALBUQUERQUE, NEW MEXICO 87109-3435
See Item 6
J
W912PP21R0022
1 2
07/07/2021
05/17/2021
W912PP21R0022
AMENDMENT No. 0002
2. SPECIFICATIONS: Delete the following listed pages and substitute the pages attached hereto. On the revised pages, for convenience, changes are emphasized by STRIKETHROUGH for deletions and UNDERLINE for additions from the previous issue. All portions of the revised (or new) pages shall apply whether or not changes have been indicated.
Delete Page Insert Page
TABLE OF CONTENTS, ENTIRETY TABLE OF CONTENTS, ENTIRETY
PROPOSAL SCHEDULE, ENTIRETY PROPOSAL SCHEDULE, ENTIRETY
00 22 16 - SUPPLEMENTARY INSTRUCTIONS
TO PROPOSERS, PAGE 22 (PAGE 31 OF
SPECIFICATIONS PACKAGE)
00 22 16 - SUPPLEMENTARY INSTRUCTIONS
TO PROPOSERS, PAGE 22
00 50 00 - CONTRACTING FORMS AND
SUPPLEMENTS - Wage Determination, PAGE 89-90 (PAGES 100-101 OF
SPECIFICATIONS PACKAGE)
00 50 00 - CONTRACTING FORMS AND
SUPPLEMENTS - Wage Determination, PAGE 89-90
01 01 50 - PHASING OF WORK, ENTIRE
SECTION
01 01 50 - PHASING OF WORK, ENTIRE
SECTION
01 11 00 - SUMMARY OF WORK, ENTIRE
SECTION
01 11 00 - SUMMARY OF WORK, ENTIRE
SECTION
01 14 00 - WORK RESTRICTIONS, ENTIRE
SECTION
01 14 00 - WORK RESTRICTIONS, ENTIRE
SECTION
01 43 00 - AIRFIELD SAFETY, ENTIRE
SECTION
01 43 00 - AIRFIELD SAFETY, ENTIRE
SECTION
NA 01 50 00 – TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS
32 13 14.13 - CONCRETE PAVING FOR
AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS, ENTIRE SECTION
32 13 14.13 - CONCRETE PAVING FOR
AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS, ENTIRE SECTION
33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION, ENTIRE SECTION
33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION, ENTIRE SECTION
3. DRAWING CHANGES: The following drawings have been revised and the sequence number changed to indicate such revision:
Delete Page Insert Page
G002 INDEX OF DRAWINGS G002 INDEX OF DRAWINGS
C-101 PROJECT LOCATION AND VICINITY
MAPS
C-101 PROJECT LOCATION AND VICINITY
MAPS
CD102 DEMOLITION PLAN B CD102 DEMOLITION PLAN B
CS101-CS107 SITE PLAN A-G CS101-CS107 SITE PLAN A-G
CS115 TEMPORARTY PAVEMENT MARKINGS-
DISPLACED THRESHOLD
CS115 TEMPORARTY PAVEMENT MARKINGS-
DISPLACED THRESHOLD
EA102 ELECTRICAL GENERAL NOTES EA102 ELECTRICAL GENERAL NOTES
ES108-ES114 ELECTRICAL SITE MANHOLE
PLAN- AREA A-G
ES108-ES114 ELECTRICAL SITE MANHOLE
PLAN- AREA A-G
ES511 ELECTRICAL SITE DETAILS
CONCRETE ENCASED DUCTS
ES511 ELECTRICAL SITE DETAILS
CONCRETE ENCASED DUCTS
ES513 ELECTRICAL SITE DETAILS
MANHOLE, HANDHOLE, AND PULL BOX
ES513 ELECTRICAL SITE DETAILS
MANHOLE, HANDHOLE, AND PULL BOX
////////LAST ITEM////////
W912PP21R0022
AMENDMENT No. 0002
Page 2a of 2
FY-20 RUNWAY 13-31: MILL-OVERLAY ASPHALT RUNWAY & REP SHOULDERS #W912PP21R0022
CURRY COUNTY, NEW MEXICO
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00 SOLICITATION, OFFER, AND AWARD, SF 1442; PROPOSAL
SCHEDULE, CORPORATE, PARTNERSHIP, JOINT VENTURE CERTIFICATES
00 20 00 INSTRUCTIONS FOR PROCUREMENT
00 21 00 INSTRUCTIONS
00 22 16 SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 50 00 CONTRACTING FORMS AND SUPPLEMENTS - Wage Determination
00 70 00 CONDITIONS OF THE CONTRACT
DIVISION 01 - GENERAL REQUIREMENTS
01 01 01 SPECIAL CONTRACT REQUIREMENTS
01 01 50 PHASING OF WORK
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00 INTERFACE WITH OTHER WORK
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 43 00 AIRFIELD SAFETY (SPECIAL CONSIDERATIONS)
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 54 00 SECURITY
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 26 - ELECTRICAL
26 56 20 AIRFIELD LIGHTING AND VISUAL NAVIGATION AIDS
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 01 16.71 COLD MILLING ASPHALT PAVING
32 01 18.71 GROOVING OF AIRFIELD PAVING
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 11 13.13 LIME TREATED SUBGRADE
PROJECT TABLE OF CONTENTS Page 1
CURRY COUNTY, NEW MEXICO
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 ASPHALT PAVING FOR AIRFIELDS
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
PROJECT TABLE OF CONTENTS Page 2
-- End of Project Table of Contents --
APPENDIX
APPENDIX A CAFB ENV GUIDE
APPENDIX B CPT LOGS
Solicitation No. W912PP21R0022
Solicitation No. W912PP2
PROPOSAL SCHEDULE
(To be attached to SF 1442)
Item Unit
No. Description Quantity Unit Price Amount
BASE BID
TOTAL AMOUNT BASE BID $
BID OPTION NO. 1
0003 Seeding 1 JOB *** $
BID OPTION NO. 2
0004 Shoulders at Intersection 1 JOB *** $
Of 04-22
BID OPTION NO. 3
0005 Additional 1” of Milling 1 JOB *** $
And Overlay of Runway
BID OPTION NO. 4
0006 Re-Use of Existing Lights 1 JOB *** $
And Light Transformers
0001 Airfield Lighting and Wiring, Complete
1 JOB *** $
0002 Mill and Overlay of
Runway 13-31, Complete
1 JOB *** $
Solicitation No. W912PP2PROPOSAL SCHEDULE (Cont.)
(To be attached to SF 1442)
RECAPITULATION
1. TOTAL AMOUNT - BASE BID $
2. TOTAL AMOUNT - BID OPTION NO. 1 $
3. TOTAL AMOUNT - BID OPTION NO. 2 $
4. TOTAL AMOUNT - BID OPTION NO. 3 $
5. TOTAL AMOUNT - BID OPTION NO. 4 $
6. TOTAL AMOUNT - BASE BID AND BID OPTION NO. 1 THRU 4 $
NOTES:
1. Award of all proposal items will be made to one bidder. Award of Base Bid and Bid Options (if awarded) will be made to one bidder. Bidders must bid on all items.
2. EXERCISE OF OPTIONS. The Government reserves the right to exercise the option(s) by written notice to the Contractor either singularly or in any combination for up to 60 calendar days after award of the Base Bid without an increase in the Offeror's bid price. Completion of added options shall continue at the same schedule as the Base Bid unless otherwise noted in Section 00 70
00, CONDITIONS OF THE CONTRACT.
3. EVALUATION OF OPTIONS: (FAR 52.217-5) (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the
Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirements. Evaluation of options will not obligate the Government to exercise the options(s).
4. ARITHMETIC DISCREPANCIES:
(a) For the purpose of initial evaluation of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:
(1) Obviously misplaced decimal points will be corrected;
(2) Discrepancy between unit price and extended price, the unit price will govern;
(3) Apparent errors in extension of unit prices will be corrected;
Page 3a of 125
Solicitation No. W912PP2PROPOSAL SCHEDULE (Cont.)
(To be attached to SF 1442)
NOTES: (Cont’d)
(4) Apparent errors in addition of lump-sum and extended prices will be corrected.
(b) For the purposes of bid evaluation, the government will proceed on the assumption that the bidder intends the bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.
(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.
5. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
6. PROGRESS PAYMENT REQUESTS made by the Contractor pursuant to the provisions of Contract Clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, shall be submitted on ENG FORM 93 to the administration office as designated in Block 26, Standard Form 1442 Back, Solicitation, Offer and Award. ENG FORM 93 shall be submitted to that office on the 1st of each month in appropriate form and certified. Photocopies of the form shall be furnished on that same date to the
Corps of Engineers offices designated at the Pre-Construction Conference.
7. ACCRUALS. In accordance with USACE Engineer Financial Regulation (ER) 37- 1-
30, and other applicable Federal and DOD financial accounting standards, the
Contractor must assist government personnel with providing reasonably accurate estimates of the value of goods and/or services rendered to the Government pursuant to this contract for each calendar month during which goods and services are delivered. Standard forms and instructions will be provided by the
Government to assist with meeting this requirement. These monthly estimates, which facilitate timely entry of accruals, must be received by the Government on or before four (4) business days prior to each calendar month-end.
8. UNIT ABBREVIATIONS
EA. = EACH M. = METER
L.S. = LUMP SUM S.M. = SQUARE METER
L.F. = LINEAR FEET C.M. = CUBIC METER
S.F. = SQUARE FEET S.Y. = SQUARE YARD
C.F. = CUBIC FEET C.Y. = CUBIC YARD
- END OF PROPOSAL SCHEDULE -
Page 3b of 125
(2)
-2
(3)
(4)
(5)
(6)
CURRY COUNTY, NEW MEXICO AMENDMENT No. 0002
SECTION 01 01 50
PHASING OF WORK
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
1.1.1 First Sequence of Work
Foreign Object Debris (FOD) control requirements will be enforced in all phases. See Section 01 43 00 AIRFIELD SAFETY (SPECIAL CONSIDERATIONS) for FOD control requirements. The Contractor may perform additional construction activities concurrently and/or sequentially if the activities do not interfere with the phasing requirements and if approval is obtained in writing from the Contracting Officer prior to beginning the additional work.
Airfield construction waiver(s) will have to be approved before the performance period begins.
Approval of long lead submittals will have to occur before the 90 day performance period of phase 1 begins.
The 90 day performance period will have to be during a time of year when concrete airfield paving can occur.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Phasing Of Construction Plan ; G
1.3 Phasing of Construction Plan
The Contractor shall submit for approval a plan of the proposed phasing of construction. The proposed plan shall be submitted within 15 calendar days after receipt of notice to proceed. The plan may be a part of the preliminary network analysis as specified in Section 01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES , or may be submitted separately. The plan shall show all of the constraints specified in the GENERAL REQUIREMENTS paragraphs above. Contractor shall ensure that the plan addresses coordination with all of the key players, including the USACE, Air Force, and other Contractors performing work in the same area.
01 01 50 - 1
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
01 01 50 - 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan ; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes demolition of 920 lineal feet of existing 25 foot shoulders at Sections S10 and S11; installing asphalt paved shoulders and unpaved shoulders on both sides the entire length of the runway;
installing runway lighting; installing threshold lighting in tailhook gap;
installing counterpoise system; improving site subbase; grading for proper drainage to include removal and replacement of any manhole covers, painting/repainting airfield markings, as required; and all necessary work to bring paved and unpaved areas up to acceptable DoD NFPA and Unified Facility Criteria and incidental related work.
1.2.2 Location
The work is located at Runway 13-31, where it intersects Runway 04/22, approximately as indicated. The exact location will be shown by the Contracting Officer is located at Runway 13-31, excluding the intersection with Runway 04-22. Location of work to be performed is shown on project drawings .
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
01 11 00 - 1
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.5 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the storage area.
Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
01 11 00 - 2
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel ; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Contractor must be ready for operation as approved by Contracting Officer before work is started.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
c. The Contractor must conduct his operations so as to cause the lease possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
01 14 00 - 1
1.3.1.2 Additional Personnel Requirements
1.3.1.2.1 General Construction
General construction of the controlled area must be performed by U.S.
firms using U.S. citizens. General construction includes construction activities such as building site work, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Utility work that penetrates the controlled area and installation of doors in these areas are not general construction
1.3.1.3 Identification Badges and Installation Access
One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge. Furnish a completed Employment Eligibility Verification (DHS Form I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/I-9 by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
1.3.1.3.1 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, between 7:30 a.m. and 4:00 p.m. 0700 and 1400 , Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or
01 14 00 - 2 on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 8 hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II, "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area."
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
01 14 00 - 3
SECTION 01 43 00
AIRFIELD SAFETY
(SPECIAL CONSIDERATIONS)
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittal
Traffic Control Plan for Airfield Safety ; G
1.2 Traffic Control Plan for Airfield Safety
The Plan shall include, as a minimum, flagmen, FOD control and cleanup.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
The Contractor shall keep all paved surfaces that are in use by aircraft during the life of this contract, such as runways, taxiways, and hardstands, clean at all times and, specifically, free from small stones and any accumulation of dirt and mud (loose or compacted) that could damage aircraft propellers or jet aircraft.
3.1.1 Barriers
The Contractor shall provide barriers as needed to prevent foreign object debris (FOD) from entering the flight line during the life of this contract.
3.1.1.1 FOD Fence
A FOD fence shall be erected by the Contractor completely enclosing the area of work. The fence shall extend one (1) meter above finish grade without gaps or openings. Fence material shall be a composite of slit fabric fence and wire mesh. The fence shall be secured with free standing posts coated with reflective paint and spaced at 3 meter intervals. The fence shall be placed on the construction-site side of the posts.
Contractor access to all work areas shall be coordinated with the Contracting Officer to maintain the effectiveness of the FOD fence.
3.1.2 FOD Checks
Thorough FOD checks will be required whenever the Contractor's vehicles enter the flightline from roadways and worksites. FOD checks shall
01 43 00 - 1 include removing gravel and rocks from tire treads and removing or securing loose parts and debris on the vehicle undercarriage.
3.1.3 FOD Inspections
The Contractor shall participate in Daily FOD Inspections of the runway, taxiway, and ramp areas. The Contractor shall remove and dispose of any and all FOD identified in the Daily FOD Inspection, regardless of origin.
3.1.4 Adjacent Areas
Areas impacted by construction where pavement has been removed within the ramp area, or areas adjacent to the ramp where vegetation has been removed due to construction activities, will require periodic watering, or other acceptable means, to limit excessive blowing or dirt/dust within the ramp area.
3.2 ACCESSIBILITY
The taxiway and the perimeter of the entire ramp shall be accessible to aircraft under power during the entire life of the contract. The Contractor shall provide a traffic control plan that shall include, as a minimum, flagmen, FOD control, and clean-up. The Contractor's traffic control plan shall not regulate aircraft traffic unless aircraft safety is jeopardized.
01 43 00 - 2
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C511 (2017) Reduced-Pressure Principle Backflow Prevention Assembly
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA
20-1; TIA 20-2; TIA 20-3; TIA 20-4)
National Electrical Code
NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan ; G
Traffic Control Plan ; G
Haul Road Plan ; G
Contractor Computer Cybersecurity Compliance Statements ; G
01 50 00 - 1
Contractor Temporary Network Cybersecurity Compliance Statements ; G
SD-06 Test Reports
Backflow Preventer Tests
SD-07 Certificates
Backflow Tester Certification
Backflow Preventers Certificate of Full Approval
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
1.5 DOD CONDITION OF READINESS (COR)
DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots ( 58 mph ) or greater. Contact the Contracting Officer for the current COR setting.
Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.
Unless otherwise directed by the Contracting Officer, comply with:
a. Condition FOUR (Sustained winds of 58 mph or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat
01 50 00 - 2 piles less than 3.3 feet high. Remove all debris, trash, or objects that could become missile hazards. Review requirements pertaining to "Condition THREE" and continue action as necessary to attain "Condition FOUR" readiness. Contact Contracting Officer for weather and COR updates and completion of required actions.
b. Condition THREE (Sustained winds of 58 mph or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Reinforce or remove formwork and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite.
Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and COR updates and completion of required actions. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.
c. Condition TWO (Sustained winds of 58 mph or greater expected within 24 hours): Secure the jobsite, and leave Government premises.
d. Condition ONE. (Sustained winds of 58 mph or greater expected within 12 hours): Contractor access to the jobsite and Government premises is prohibited.
1.6 CYBERSECURITY DURING CONSTRUCTION
{For Reference Only: This subpart (and its subparts) relates to AC-18, SA-3, CCI-00258.} Meet the following requirements throughout the construction process.
1.6.1 Contractor Computer Equipment
Contractor owned computers may be used for construction. When used, contractor computers must meet the following requirements:
1.6.1.1 Operating System
The operating system must be an operating system currently supported by the manufacturer of the operating system. The operating system must be current on security patches and operating system manufacturer required updates.
1.6.1.2 Anti-Malware Software
The computer must run anti-malware software from a reputable software manufacturer. Anti-malware software must be a version currently supported by the software manufacturer, must be current on all patches and updates, and must use the latest definitions file. All computers used on this project must be scanned using the installed software at least once per day.
1.6.1.3 Passwords and Passphrases
The passwords and passphrases for all computers must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one
01 50 00 - 3 special character.
1.6.1.4 Contractor Computer Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using contractor owned computers. Contractor Computer Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company.
1.6.2 Temporary IP Networks
Temporary contractor-installed IP networks may be used during construction. When used, temporary contractor-installed IP networks must meet the following requirements:
1.6.2.1 Network Boundaries and Connections
The network must not extend outside the project site and must not connect to any IP network other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all network access from outside the project site is prohibited.
1.6.3 Government Access to Network
Government personnel must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification.
1.6.4 Temporary Wireless IP Networks
In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.
1.6.5 Passwords and Passphrases
The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum 8 characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Temporary Network Cybersecurity Compliance Statements for each company implementing a temporary IP network. Contractor Temporary Network Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company. If no temporary IP networks will be used, provide a single copy of the Statement indicating this.
01 50 00 - 4
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, and in location as approved by the Contracting Officer.
2.1.2 Project Identification Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site.
Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1 Section 04.
Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of
01 50 00 - 5 the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.
All fencing must meet the requirements of EM 385-1-1 . Remove the fence upon completion and acceptance of the work.
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches . Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Chain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases to form long spans as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.
2.5 BACKFLOW PREVENTERS
Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval is not acceptable.
Reduced pressure principle type conforming to the applicable requirements
01 50 00 - 6
AWWA C511. Provide backflow preventers complete with 150 pound flanged , mounted gate valve and strainer, stainless steel or bronze, internal parts.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Construction Contract employees must park privately owned vehicles in an area designated by the Contracting Officer. Employee parking must not interfere with existing and established parking requirements of the Government installation.
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.2.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.2.2 Payment for Utility Services
a. The Government will make all reasonably required utilities available from existing outlets and supplies, as specified in the Contract.
Unless otherwise provided in the Contract, the amount of each utility service consumed will be charged to or paid at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. Carefully conserve utilities furnished without charge.
b. Reasonable amounts of the following utilities will be made available u at the prevailing rates.
Utility Services
Cost ($) per Unit
Electricity
Potable Water
Salt Water
Compressed Air
Steam
Natural Gas
Sanitary Sewer
c. The point at which the Government will deliver such utilities or services and the quantity available is must be coordinated with the Contracting Officer. Pay all costs incurred in connecting, converting, and transferring the utilities to the work. Make connections, including providing backflow-preventing devices on connections to domestic water lines; and providing transformers; and make disconnections.
01 50 00 - 7
3.2.3 Meters and Temporary Connections
Provide and maintain necessary temporary connections, distribution lines, and meter bases (Government will provide meters) required to measure the amount of each utility used for the purpose of determining charges.
Notify the Contracting Officer, in writing, 5 working days before final electrical connection is desired so that a utilities contract can be established. The Government will provide a meter and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. Do not make the final electrical connection.
3.2.4 Advance Deposit
An advance deposit for utilities consisting of an estimated month's usage or a minimum of $50.00 will be required. The last monthly bills for the fiscal year will normally be offset by the deposit and adjustments will be billed or returned as appropriate. Services to be rendered for the next fiscal year, beginning 1 October, will require a new deposit.
Notification of the due date for this deposit will be mailed prior to the end of the current fiscal year.
3.2.5 Final Meter Reading
Before completion of the work and final acceptance of the work by the Government, notify the Contracting Officer, in writing, 5 working days before termination is desired. The Government will take a final meter reading, disconnect service, and remove the meters. Then remove all the temporary distribution lines, meter bases, and associated appurtenances.
Pay all outstanding utility bills before final acceptance of the work by the Government.
3.2.6 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 Section 02. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times.
Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.2.7 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.2.8 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
01 50 00 - 8
3.3 STATION OPERATION AFFECT ON CONTRACTOR OPERATIONS
3.3.1 Restricted Access Areas
The Government will monitor work in areas indicated. Notify Contracting Officer at least 14 calendar days prior to starting work in these areas.
[ ]. 3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close a thoroughfare or interfere with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan for Government approval detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness.
Brightly-colored (orange) vests are required for all personnel working in roadways. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of damage to roads caused by construction operations.
3.4.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the…