Plans and Specs Folk Pit River, California - W912PP19R0022

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. W912PP19R0022

DATE: JUNE 2019

U.S. ARMY CORPS OF ENGINEERS

ALBUQUERQUE DISTRICT

FY19 LAUER DAM REHABILITATION PROJECT

Project 474016

MODOC COUNTY, NORTH FORK PIT RIVER,

NORTH OF ALTURAS, CALIFORNIA

Volume 1 - Specifications

NOT FOR CONSTRUCTION

CONSTRUCTION SOLICITATION AND SPECIFICATIONS

THIS PAGE INTENTIONALLY LEFT BLANK

TOC -1

TABLE OF CONTENTS

VOLUME 1

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00 Solicitation, Offer, and Award (SF1442); Proposal Schedule Corporate, Partnership, Joint Venture Certificates 00 20 00 Instructions for Procurement 00 21 00 Instructions 00 22 16 Supplementary Instructions to Proposers 00 45 00 Representations and Certifications 00 50 00 Contracting Forms and Supplements 00 70 00 Conditions of the Contract 00 73 00 Supplementary Conditions

DIVISION 01 - GENERAL REQUIREMENTS

01 01 00 Construction Clauses 01 01 01 Special Contract Requirements 01 02 00 Brand Name or Equal 01 11 00 Summary of Work 01 20 00 Price and Payment Procedures 01 30 00 Administrative Requirements 01 31 00 Project Management and Coordination 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 45 00.00 Quality Control 01 45 00.15 Resident Management System contractor Mode (RMS CM) 01 50 00 Temporary Facilities 01 51 00 Utilities 01 57 00 Project Permits and Environmental Controls 01 58 00 Project Identification 01 71 23 Construction Surveying 01 72 00 As-Built Drawings 01 77 00 Closeout Procedures

DIVISION 02 - DEMOLITION

02 41 00 Demolition

DIVISION 03 - CONCRETE

03 05 00 Basic Concrete Materials 03 10 00 Concrete Forms and Accessories 03 15 50 Concrete Joints and Waterstops

TOC -2

03 20 00 Concrete Reinforcement 03 30 00 Cast-In-Place Concrete 03 39 00 Concrete Curing 03 48 00 Pre-Concrete Specialties

DIVISION 05 - METALS

05 50 00 Metal Fabrications

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 13 26 Self-Adhering Sheet Waterproofing

DIVISION 10 – SPECIALTIES

10 74 00 Fiberglass Parshall Flume

DIVISION 27 – COMMUNICATIONS

27 20 00 Instrumentation and Controls

DIVISION 31 – EARTHWORK

31 02 10 Water for Dust Abatement 31 10 00 Clearing and Grubbing 31 23 13 Subgrade Preparation 31 23 16 Excavation 31 23 19 Dewatering 31 23 23 Fill and Backfill 31 25 00 Erosion and Sediment Controls 31 32 32 Geotextiles

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 30 00 Site Reclamation

DIVISION 33 – UTILITIES

33 11 00 Welded Steel Pipe and Fittings 33 12 00 Slide Gates

VOLUME 2 - DRAWINGS

End Table of Contents

Lauer Dam Rehabilitation Project, Modoc County, CA

This is a Small Business Set Aside, Low est Priced Technically Acceptable (LPTA) Best Value Acquisition.

Magnitude of construction is betw een $5,000,000-$10,000,000.

***WE HAVE MOVED*** Hand carried proposals must be delivered to 6200 Jefferson Street NE, Albuquerque, NM 87109. Sealed technical proposal (original +5 hard copies) and f ive electronic (CD) copies and sealed price proposal (original + 1 electronic copy) are due at the place and time specif ied in Block 13. See Section 00 21 00 for information pertaining to the pre-proposal conference and site visit. For technical questions, see Section 00 20 00 pertaining to ProjNet. As this is not a sealed bid, offers w ill not be opened publicly. Offerors are required to sign in upon entry to the building. Therefore, allow sufficient time for turning in your proposal. This requirement may be delayed, cancelled or revised at any time during the solicitation process and is subject to the availability of funds.

KAREN K IRVING 505-342-3356

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

21-Jun-2019

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________487 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________007300

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________24 Jul 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY ENGINEER DISTRICT, ALBUQUERQUE

6200 JEFFERSON STREET NE

ALBUQUERQUE NM 87109-3435

W912PP

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

505-342-3496FAX:TEL: TEL: FAX:

W912PP19R0022 1 OF 151

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Solicitation No. W912PP19R0022

PROPOSAL SCHEDULE

(To be attached to SF 1442)

Item Unit No. Description Quantity Unit Price Amount

BASE BID

0001 Mobilization and

Demobilization, to include:

Preparing site access, mobilizing equipment and personnel, setting up equipment and facilities for the Work, cleanup and disposal of waste materials, restoration of the site upon completing the Work, and demobilizing. Item also includes bonds, insurance, permitting, and project management.

1 JOB *** $

0002 Dust Abatement, to include:

Application of water from Lauer Reservoir to reduce dust during construction.

0003 Dewatering, to include:

Providing labor, materials, and equipment necessary to control surface water and seepage infiltration into required excavations. Includes associated diversion and protection works for control and management of storm inflows.

0004 Erosion Control, to include:

Construction of erosion control facilities within construction limits as required.

Page 3a of 151

PROPOSAL SCHEDULE (Cont’d)

0005 Clearing and Grubbing, to include: Removing trees, vegetation, rubbish, and other deleterious items within the required excavations and limits of rockfill borrow areas.

27.5 ACRE $_________ $

0006 Stripping, to include:

Excavating and stockpiling topsoil within the limits of site disturbance. Onsite disposal of excess or unsuitable material is considered incidental to the cost of the Work.

1,500 CY $_________ $

0007 Temporary Access Road

Construction, to include:

Furnishing, placing and compacting road base material for Contractors’ construction access roads and staging areas.

0008 Required Excavations, to include: Excavating, hauling and stockpiling materials within the required excavation limits to the lines and grades shown. Onsite disposal of excess or unsuitable material, is considered incidental to the cost of the Work.

10,300 CY $_________ $

Page 3b of 151

0009 Subgrade Preparation, to include: Dental concrete applied to the foundation at the concrete core wall, concrete retaining walls, concrete outlet structures, and slush grout of exposed fractures.

270 SY $_________ $

0010 Clay Blanket, to include:

Removal, hauling, processing, moisture conditioning, and compacting Clay Blanket Material to the lines and grades shown in the Drawings.

1,700 CY $_________ $

0011 Geotextile, to include:

Furnishing and installing geotextile as shown in the Drawings.

5,800 SY $_________ $

0012 Zone 1 and Zone 2 Rockfill, to include: Excavating, processing, hauling, placing, spreading, and compacting Zone 1 and Zone 2 rockfill materials obtained from the borrow area. For bidding purposes, the Contractor shall assume four (4) roller passes with the specified equipment is necessary to compact each rockfill lift.

Item also includes permanent dam access road construction and slope protection.

19,000 CY $_________ $

Page 3c of 151

0013 Random Fill, to include:

Furnishing, placing, spreading, and compacting Random Fill materials.

1,600 CY $_________ $

0014 Rip Rap, to include:

Furnishing and placing riprap in locations shown in the Drawings.

300 CY $_________ $

0015 Concrete Plinth, to include:

Furnishing and placing reinforced concrete core wall plinth.

700 CY $_________ $

0016 Concrete core wall, to include, Furnish and placing reinforced concrete for the construction of concrete core wall. Item includes furnishing and installing the waterproofing membrane.

500 CY $_________ $

0017 Dam Crest Gravel Surfacing, to include: Hauling, placing, spreading, and compacting road surface materials at embankment crest and parking area.

460 CY $_________ $

0018 Crest Survey Monuments, to include: Furnishing and installing survey monuments.

6 EA $_________ $

Page 3d of 151

0019 First Fill and Dam Breach

Implementation, to include:

Complete pumped filling of reservoir between new and existing dam, including required water level holds.

Excavate breach of existing dam. Excludes riprap and removal of existing outlet works.

0020 Removal and Disposal of

Existing Structures, to include: Demolition, removal, and hauling of materials and structures offsite for disposal. Includes existing metal conduits, fencing and gates, and miscellaneous structures.

0021 Leveling Slab and Mass

Concrete, to include:

Furnishing and placing mass concrete for leveling slab under outlet works conduit encasement.

100 CY $_________ $

Page 3e of 151

No. Description Quantity Unit Price Amount_______

0022 Outlet Works, to include:

Furnishing and placing reinforced concrete outlet works structures, including the intake, the concrete encased steel outlet works conduit, the outlet structure, and flume structures. Includes formwork, thimbles, gates, grating, stoplogs, trashracks, staff gauge, steel pipe and required forms, materials, and embedments.

0023 Access Road Construction-

Spillway, Includes construction of permanent access road leading to the spillway.

0024 Clearing and Grubbing, to include: Removal of trees, vegetation, rubbish, and other items as necessary to provide a suitable working surface at the spillway.

1 ACRE $_________ $

0025 Required Spillway Excavations, to include: Removal and stockpiling of materials to construct new spillway. Onsite disposal of excess or unsuitable material is considered incidental to the cost of the Work.

260 CY $_________ $

Page 3f of 151

0026 Reinforced Concrete Spillway, to include: Furnishing and placing reinforced concrete, forms, and materials for the construction of spillway.

90 CY $_________ $

0027 Spillway Backfill, to include:

Placing backfill at the spillway sill.

0028 Miscellaneous Metal

Fabrications, to include:

Furnishing and installing miscellaneous metal work, safety posts, pipe guardrails, air vent outlets, bollards, and other structures.

0029 EWS Building – Concrete, to include: Furnishing and constructing EWS cast-in-place concrete building.

0030 Placing Topsoil, to include:

Placement of topsoil cover over disturbed borrow area.

1,500 CY $_________ $

0031 Seeding, Soil Supplements, and

Topsoil Erosion Control Matting, to include:

Furnishing and placing seed to re-vegetate areas for reclamation, including borrow areas and other disturbed areas. Includes erosion control on topsoil.

20 ACRE $_________ $

Page 3g of 151

0032 TERO Fees See Section 01 20 00 paragraph 1.4.

0033 All Other Work Not Separately

Listed.

TOTAL AMOUNT BASE BID $

NOTES:

1. Award of all proposal items will be made to one bidder. Award of Base Bid and Bid Options (if awarded) will be made to one bidder. Bidders must bid on all items.

(a) Offers will be evaluated based on the Offerors’ qualifications and the total of the Bid Schedule. Award will be made to the responsive offer which brings the best value.

(b) The Contracting Officer (CO) or Contracting Officer’s Representative

(COR) may remove items from the schedule based on available funds.

2. ARITHMETIC DISCREPANCIES:

(a) For the purpose of initial evaluation of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

Page 3h of 151

NOTES: (Cont’d)

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purposes of bid evaluation, the government will proceed on the assumption that the bidder intends the bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

3. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

4. PROGRESS PAYMENT REQUESTS made by the Contractor pursuant to the provisions of Contract Clause, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, shall be submitted on ENG FORM 93 to the administration office as designated in Block 26, Standard Form 1442 Back, Solicitation, Offer and Award. ENG FORM 93 shall be submitted to that office on the 1st of each month in appropriate form and certified. Photocopies of the form shall be furnished on that same date to the Corps of Engineers offices designated at the Pre-Construction Conference.

5. ACCRUALS. In accordance with USACE Engineer Financial Regulation (ER) 37- 1-30, and other applicable Federal and DOD financial accounting standards, the Contractor must assist government personnel with providing reasonably accurate estimates of the value of goods and/or services rendered to the Government pursuant to this contract for each calendar month during which goods and services are delivered. Standard forms and instructions will be provided by the Government to assist with meeting this requirement. These monthly estimates, which facilitate timely entry of accruals, must be received by the Government on or before four (4) business days prior to each calendar month-end.

6. All offers are subject to the terms and conditions of this solicitation.

7. Quantities provided in the schedule for lump sum are estimated quantities for comparison of offers only and, no claim shall be made against the Government for overruns or underruns.

8. Offerors’ submitted bid schedule shall include all items necessary to complete all construction and CONTRACTOR requirements presented in the Drawings and

Page 3i of 151

NOTES: (Cont’d)

Specifications. Work items not specifically identified in the Bid Schedule shall be incorporated into the Offerors’ lump sum line item pricing for related work.

9. CONTRACTOR is responsible for paying fees related to the Pit River Tribe’s Tribal Employment Rights Ordinance.

8. UNIT ABBREVIATIONS

EA. = EACH M. = METER

JOB = L.S. = LUMP SUM S.M. = SQUARE METER

L.F. = LINEAR FEET C.M. = CUBIC METER

S.F. = SQUARE FEET S.Y. = SQUARE YARD

C.F. = CUBIC FEET C.Y. = CUBIC YARD

- END OF PROPOSAL SCHEDULE -

W912PP19R0022

CORPORATE, PARTNERSHIP, JOINT VENTURE CERTIFICATES

If the offer is submitted by a corporation, partnership or a Joint Venture, the applicable form listed below must be completed and submitted with the Standard Form 1442. In the alternative, other evidence must be submitted to substantiate the authority of the person signing the offer. If a corporation, the same officer shall not execute both the offer and the certificate.

CORPORATE CERTIFICATE

I, _______________________________________________, certify that I am the Secretary of the corporation named as Offeror/Contractor herein; that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then __________________________ of said corporation; that said offer/contract was duly signed for and on behalf of said corporation by authority of its governing body, and is within the scope of its corporate powers.

______________________________ (CORPORATE SEAL)

(Secretary)

AUTHORITY TO BIND PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the offer had authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments, on behalf of said partnership, with the United States of America, except as follows: (State “none” or describe limitations, if any.)

This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to, and acknowledged by, the Contracting Officer.

(Type or Print Name) (Signature)

JOINT VENTURE

Provide a copy of the Joint-Venture (JV) agreement. The SF 1442, Solicitation, Offer and Award form must be signed by the party with the authority to bind the JV as indicated in the agreement. Each party to the JV agreement shall complete one of the following entries:

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation A)

I, _______________________________________________, certify that I am the Secretary of the Corporation named as Offeror/Contractor herein, that __________________________________________________ who signed this offer/contract on behalf of the Offeror/Contractor was then _________________________ of said corporation by authority of its governing body and is within the scope of its corporate powers.

IN WITNESS WHEROF, I have hereunto affixed my hand and the seal of said corporation this ______________________ day of _____________________.

AFFIX CORPORATE SEAL ___________________________

(Secretary)

(Corporation B)

Section 00 20 00 - Instructions for Procurement

THE FOLLOWING ARE INSTRUCTIONS TO OFFERORS TO SECTION 00 20 00:

USE OF THE WORDS “PROPOSER” AND “OFFEROR”

Whenever the word “Proposer” appears in the RFP it shall be construed to have the same meaning as the word “Offeror.”

AVAILABILITY OF PLANS AND SPECIFICATIONS

This solicitation will be issued via Internet only. Notification of amendments shall be made via Internet only, as well. It is therefore the contractor’s responsibility to check the following address daily for any posted changes to this solicitation. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities (FedBizOpps) system. FedBizOpps is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders must register with FedBizOpps before accessing the system. Registration instructions can be found on the FedBizOpps website at www.fbo.gov by clicking on the “Register Now” hyperlink. Contractors registered with FedBizOpps may view and/or download this solicitation and all amendments from the Internet after solicitation issuance at this site.

BIDDER INQUIRY AND PROPOSAL INFORMATION

a. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org.

1. To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self-register, go to the aforementioned web page and click on the BID tab.

Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page, you may view all bidder inquiries or add inquiry.

3. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

4. The Solicitation Number is: W912PP19R0022 The Bidder Inquiry Key is: 7MVB55-WVCE29

b. The Bidder Inquiry System will be unavailable for new inquires 7 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.

c. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

d. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

e. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

CONTRACTING OFFICER AUTHORITY

The Contracting Officer who signs this contract will be the primary Contracting Officer for this contract. However, any Contracting Officer assigned to the Albuquerque District, contracting within his or her authority, may take formal action on this contract when a contract action needs to be taken and the primary Contracting Officer is unavailable.

NAICS CODE AND SMALL BUSINESS SIZE STANDARD

The North American Industry Classification System (NAICS) code for this acquisition is 237990. The small business size standard is: the average annual receipts of the concern and its affiliates for the preceding three fiscal years must not exceed $36.5 million.

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

ESTIMATED CONSTRUCTION COST (FAR 36.204)

The estimated magnitude of construction for this project is between $5,000,000.00 and $10,000,000.00.

INSTRUCTIONS FOR SUBMISSION OF THE PRICE PROPOSAL

The offeror shall submit to the Government a price proposal broken out by line item in the format indicated on the Proposal Schedule in Section 001000 of this solicitation. A cost-element breakdown, in sufficient detail for the Government to perform a cost analysis, shall be attached for each proposed line item and must reflect any specific requirements established by the Contracting Officer. Supporting breakdowns must be furnished for each cost element, consistent with the offeror's cost accounting system, and shall include basic elements of cost such as direct labor, materials, equipment, and subcontracted items. Indirect costs, including markups, for field overhead, general and administrative expenses, gross receipt taxes or other taxes, bond rate, profit, and any other applicable costs shall also be provided.

WHO MAY SUBMIT PROPOSALS

Any legally organized Offeror may submit a proposal.

Firms submitting a proposal as a joint venture (JV) must ensure the following requirements are met:

a. Obtain a Tax Identification Number (TIN) for the joint venture.

b. Prepare the Section 004500, Representations and Certifications as a joint venture (e.g., providing the TIN for the JV)

c. Register in the System for Award Management (SAM) formerly Central Contractor Registration

(CCR) as a joint venture in which a unique CAGE Code will be obtained. See FAR Clause 52.204-7, System for Award Management and DFARS Clause 252.204-7004; Alternate A, System for Award Management for further information in Section 007000.

d. Provide a copy of the JV agreement in the proposal submission.

SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION

The Offeror must ensure that your company’s data at the System for Award Management (SAM) website, https://www.sam.gov/portal/public/SAM/, is current per FAR 52.204-13, System for Award Management Registration (July 2013). (This clause is included in Section 007000 of this RFP.)

a. Performance and Payment Bonds. Within ten (10) calendar days after contract award, and prior to contract performance, the Contractor shall furnish two bonds, a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties acceptable to the Government. The penal sum of such bonds will be as indicated in FAR 52.228-15.

WHO WILL EVALUATE THE PROPOSALS

The Evaluation Committee will be composed of Corps of Engineers and Air Force personnel. A list of the members of the committee will not be released and contact with members of the committee is prohibited. Efforts to solicit support from the committee will be considered grounds for disqualification of an Offeror’s proposal.

BONDS (FAR 28.102-2)

a. Bid Bond. Each Offeror shall submit with his offer a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in FAR 52.228-1.

When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. The bid bond shall remain in effect until Performance and Payment Bonds are provided and accepted.

b. Performance and Payment Bonds. Within ten (10) calendar days after contract award, and prior to contract performance, the Contractor shall furnish two bonds, a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties acceptable to the Government. The penal sum of such bonds will be as indicated in FAR 52.228-15.

FEDERAL, STATE AND LOCAL TAXES

The Offeror shall include all applicable federal, state and local taxes in the contract price. See FAR 52.229-4, Federal, State, and Local Taxes in Section 007000 for additional information.

PRE-AWARD INFORMATION

Each Offeror shall provide, upon request of the Contracting Officer, a list of present commitments, including the dollar value thereof, and name of office under which the work is being performed.

PERFORMANCE OF WORK BY CONTRACTOR (FAR 36.501)

Unless such description has been submitted with the offer, the successful Offeror must furnish the Contracting Officer within 20 days after award, a description of the work that he intends to perform with his own organization (e.g., earthwork, paving, brickwork, or roofing), the percentage of the total work this represents, and the estimated cost thereof.

U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1

AND OSHA REQUIREMENTS

The successful contractor to this Request for Proposals will be required to comply with all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil. by selecting “Safety and Occupational Health” followed by “EM 385-1- 1”. The Contractor must also comply with Occupational Safety and Health Act (OSHA) standards. OSHA standards are subject to change. It is the Contractor's responsibility to maintain familiarity with current OSHA standards.

AMENDMENTS TO REQUEST FOR PROPOSALS

The right is reserved, as the interest of the Government may require, to revise the specifications and drawings both before and after the date set for receipt of offers. Such revisions, if any, will be announced by amendment(s) to the Request for Proposal. If the revisions and amendments are of a nature which require material changes in quantities, or prices offered, or both, the date set for receipt of offers may be postponed by such number of days as in the opinion of the Contracting Officer will enable the Offeror to revise the offer. In such cases, the amendment will include an announcement of the new date for receipt of offer.

COSTS RELATED TO PROPOSAL PREPARATION

All costs related to proposal preparation, including travel, will be borne solely by the Offeror. The Government is not liable for any costs incurred by the Offeror submitting an offer in response to this solicitation.

CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor’s performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $700,000.00, the USACE will evaluate contractor’s performance and prepare a performance report using the Construction Contractor Appraisal Support System (CCASS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CCASS requires specific software, called PKI certification, which is installed on the user’s computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov/. If the Contractor wishes to participate in the performance evaluation process, access to PPIRS and PKI certification is the sole responsibility of the Contractor.

OFFEROR’S CHECKLIST

Administrative Notice to Bidders. Before signing and submitting your bid, please take note of the following administrative details, as failure to properly perform any one of these actions may cause your bid to be rejected:

[ ] Have you acknowledged receipt of ALL solicitation amendments? If in doubt as to the number of amendments issued, please contact Karen Irving, Contract Specialist, at (505) 342-3356.

[ ] Have you completed Section 00 45 00, Representations and Certifications?

[ ] Is your offer in sealed envelopes, price and technical, marked to show the Offeror’s name and address, the solicitation number, and the date and time offers are due?

[ ] If any of the solicitation amendments involved changes to the proposal schedule, did you use the amended schedule for submitting your proposal?

[ ] Is your proposal guarantee in the proper form and amount?

[ ] Will your proposal arrive on time? In order for a late proposal to be considered, it must have been dispatched in accordance with the provisions of FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition.” Facsimile proposals will not be accepted.

[ ] Have you reviewed your proposal for possible errors in calculations or work left out?

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.211-2 Availability of Specifications, Standards, and Data Item

Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST)

APR 2014

52.211-6 Brand Name or Equal AUG 1999 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data or

Information Other Than Certified Cost or Pricing Data

OCT 2010

52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work

MAY 2014

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be [ ] DX rated order; [X] DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm, fixed price contract resulting from this solicitation.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

6.8% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Modoc County, California.

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. ARMY CORPS OF ENGINEERS

Attn: Contracting Division (Contracting Officer) 6200 Jefferson NE Albuquerque, NM 87109

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for July 11, 2019 at 8:30am. A high clearance vehicle is required.

(c) Lauer Dam is located about 15 miles Northeast of Alturas, California. We will be meeting at the tribal mobile office on XL-Ranch Reservation, which is approximately 5 miles from Alturas. To get there, take HW-395/299 East from Alturas. When you are approaching the Agriculture Inspection station, slow down and prepare to turn left on to the Reservation just after you pass the station. You will see a mobile office ahead on the left side. For directions, call Tom Dang (916) 425-4962 or Bruce Blair (541) 591-5307.

(d) Offerors are cautioned that nothing said or done at the pre-proposal conference or site visit will qualify or modify the terms of the solicitation document. The only instrument that shall qualify or modify the solicitation document is a formal amendment, in writing, per FAR 15.206.

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/vmfara.htm http://farsite.hill.af.mil/vmdfara.htm http://farsite.hill.af.mil/vmafara.htm

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of provision)

252.236-7008 CONTRACT PRICES - BIDDING SCHEDULES. (DEC 1991)

(a) The Government's payment for the items listed in the Bidding Schedule shall constitute full compensation to the Contractor for --

(1) Furnishing all plant, labor, equipment, appliances, and materials; and

(2) Performing all operations required to complete the work in conformity with the drawings and specifications.

(b) The Contractor shall include in the prices for the items listed in the Bidding Schedule all costs for work in the specifications, whether or not specifically listed in the Bidding Schedule.

Section 00 22 16 - Supplementary Instructions to Proposers

PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, AND BASIS FOR AWARD

1.0 GENERAL REQUIREMENTS

The intent of this Request for Proposal (RFP) is to solicit proposals for the Lauer Dam Rehabilitation Project Modoc County, North Fork Pit River, North of Alturas, California. The Government reserves the right to award a contract without discussions IAW FAR 52.215-1. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a technical and cost/price standpoint. Offerors shall organize their proposals as described herein. Proposals may be determined non-responsive for failure to follow this format.

The proposal shall describe the capability of the Offeror to perform the requirements of the Statement of Work (SOW). The proposal should be specific and complete in every detail; and should be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the requirements. The proposal should be practical, legible, clear, and coherent.

In order to effectively and equitably evaluate all proposals, the Contracting Officer must receive information containing sufficient detail to allow review and evaluation by the Government. Proposal clarity, organization, and cross-referencing are mandatory. Failure to submit and organize proposals as requested may adversely affects an Offeror's evaluation.

Proposals shall not exceed the page limits described. Provide all information in tabbed sections.

2.0 SUBMISSION FORMAT

a. COVER SHEET & TABLE OF CONTENTS. Proposals shall consist of two (2) volumes. A cover sheet identifying the Offeror (name, address, point of contact), project description, and solicitation number shall be provided. The second sheet shall be a table of contents. The proposals shall contain a detailed table of contents. If more than one binder is used, the complete table of contents shall be included in each. Offers that violate these rules unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation without receiving any further consideration. Neither the cover sheet nor the table of contents count toward the page limitations.

b. TABS. Written proposal materials shall be submitted in standard three ring loose-leaf binders. Proposals shall be tabbed and labeled as specified in a manner to afford easy identification from a Table of Contents.

c. FONT SIZE. Shall not be less than 10 point. Pages will be double-sided and each page shall be identified with the appropriate page number centered at the bottom of the page.

d. SHEET SIZE. Shall be 8-1/2 inches x 11 inches; however, if drawings, charts, or other graphics are submitted, sheets no larger than 11 inches x 17 inches and folded to 8-1/2 inches x 11 inches shall be used.

All sheets shall be dated and numbered.

e. PAGE LIMITS. The proposal shall not exceed the specified page limits.