A21 - Questions and Answers 1.pdf
PDF 60 KB Posted
- Attached to
- AIWW DA 64 Subsurface Investigation Federal contract opportunity
- Solicitation number
- W912PM25QA002
About this file
This is a Questions and Answers document for solicitation W912PM25QA002 regarding subsurface investigation at AIWW DA 64, providing clarifications about technical requirements and logistics for the project.
The document confirms that only CPT logs and raw CPT data are required deliverables, with no formal report needed. It clarifies that contractors must determine their own load/unload spot on the island, as none is designated, and notes that site conditions shown in February 2024 photos may have changed due to erosion. The quote submission deadline is March 13, 2025 at 3PM ET. USACE personnel will be onsite with the drilling crew, eliminating the need for additional contractor personnel. Hand auger work shown in project figures will be performed by USACE staff and is not part of the contractor's scope.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A21 - Solicitation Amendment 3_ W912PM25QA0020003 SF 30.pdf | ||
| A21 - Solicitation Amendment 3- W912PM25QA0020003.pdf | ||
| A21 - Site Visit Sign in Sheet.pdf | ||
| A2 - Statement of Work_AIWW DA64_REV 2-26-25.pdf | ||
| A21 - Solicitation Amendment W912PM25QA0020002 SF 30.pdf | ||
| A21 - Solicitation Amendment W912PM25QA0020001 SF 30.pdf | ||
| A21 - Solicitation Amendment - W912PM25QA0020001.pdf | ||
| A2 - Statement of Work_AIWW DA64_REV 2-19-25.pdf | ||
| A21 - Solicitation - W912PM25QA002.pdf | ||
| A21 - Attachment 2 - Scope of Work.pdf | ||
| A21 - Attachment 01 - Wage Determination.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 1
1. From reading the RFP, you just need the CPT data and logs? No report?
Answer: Yes, no report is needed. CPT logs and raw CPT data are the required submittals.
2. Is there an unload/load spot on the island? If so, how steep are the slopes?
Answer: There is not a designated load/unload spot. The load/unload spot will need to be determined by the contractor. Embankment slopes vary across the site. The SOW has been amended to show photos from an USACE site visit that was performed on February 12, 2024. Please note conditions of the site could have changed since the site visit was performed due to beach erosion and other factors.
3. When is the quote due?
Answer: Quotes are due 13 March 2025 at 3PM ET per the solicitation.
4. Do we need to have someone onsite during the field operations?
Answer: No, USACE personnel will be onsite with the drilling crew, additional personnel outside the drilling crew is not needed.
5. The Figure shows hand auger locations, but the scope doesn’t mention them. Will we need to perform those?
Answer: No, hand augers will be performed by USACE staff.