A22_-_Solicitation_W912PM19T0003_Questions_and_Answers_12-4-18.pdf
PDF 191 KB Posted
- Attached to
- Philpott Fire, Security & Camera System Upgrade
- Solicitation number
- W912PM19T0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A2_-_Statement_of_Work_.pdf | ||
| H1_-_Drawings_and_maps.pdf | ||
| A19-_Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Responses
Solicitation W912PM19T0003 - Philpott Fire, Security & Camera System Upgrade
1. Are Ceilings Suspended? Or Hard Lid?
Response: The ceilings in the control room and the office are suspended. The others are hard lid.
2. Are there existing Cable Trays for wiring above ceilings?
Response: Only in the control room.
3. Can Existing Wiring be utilized?
Response: No, the wiring needs to be replaced.
4. Is a “UPS” required? If so, What Time/Power Duration is required?
Response: No, it is not required.
5. Are “Or Equal” Equipment substitutions allowed?
Response: If it is stated in the contract.
6. Is “Plenum Wire” acceptable?
Response: If it is allowed by the applicable codes referenced in the specifications.
7. Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t?
8. Response: The contractor shall submit his work scheduled and a decision will be made at that time.
9. Please post any Q&A's.
Response: NA – See this document
10. Please provide a BILL OF MATERIALS?
Response: See the contract plans, specifications, and drawings.