A22_-_Solicitation_W912PM19T0003_Questions_and_Answers_12-4-18.pdf

PDF 191 KB Posted

Attached to
Philpott Fire, Security & Camera System Upgrade
Solicitation number
W912PM19T0003
Issued by

View the file

Other files

File Type Posted
A2_-_Statement_of_Work_.pdf PDF
H1_-_Drawings_and_maps.pdf PDF
A19-_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Responses

Solicitation W912PM19T0003 - Philpott Fire, Security & Camera System Upgrade

1. Are Ceilings Suspended? Or Hard Lid?

Response: The ceilings in the control room and the office are suspended. The others are hard lid.

2. Are there existing Cable Trays for wiring above ceilings?

Response: Only in the control room.

3. Can Existing Wiring be utilized?

Response: No, the wiring needs to be replaced.

4. Is a “UPS” required? If so, What Time/Power Duration is required?

Response: No, it is not required.

5. Are “Or Equal” Equipment substitutions allowed?

Response: If it is stated in the contract.

6. Is “Plenum Wire” acceptable?

Response: If it is allowed by the applicable codes referenced in the specifications.

7. Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t?

8. Response: The contractor shall submit his work scheduled and a decision will be made at that time.

9. Please post any Q&A's.

Response: NA – See this document

10. Please provide a BILL OF MATERIALS?

Response: See the contract plans, specifications, and drawings.