Statement of Work - Ground Penetrating Radar - Please field all questions to andrea.m.green@usace.army.mil

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

GROUND PENETRATING RADAR INVESTIGATION

FALLS LAKE DAM OOUTLET WORKS CONDUIT, RALEIGH, NC

February 15, 2018

I GENERAL REQUIREMENTS

1. General. The Contractor shall furnish all labor, equipment, supplies, tools and incidentals necessary to perform a ground penetrating radar investigation and other services as specified herein.

2. Employee Supervision and Non-Personal Services. The Contractor’s employees shall at all times conduct themselves in a manner compatible with the non-personal services nature of this contractual instrument. The Contractor workforce shall under no circumstances allow themselves to be under the supervision and control of a Government officer or employee.

3. Responsibility. The Contractor shall furnish qualified personnel to ensure the accomplishment of the work specified in this Scope of Work (SOW). Additionally, the Contractor shall furnish all services, investigations, and travel required in connection with this

SOW.

4. Direction. The Contractor shall accept directions only from the Wilmington District Contracting Officer, Mrs. Karri Mares, or the duly authorized Contracting Officer's Representative (COR), Mr. Carl Baynard (910-251-4089). Requests or desires of the Users, Using Agency, or any other party made directly to the Contractor shall be immediately brought to the attention of the COR for this contract. Any changes to this SOW must be authorized in writing by the Contracting Officer, Mrs. Karri Mares (910-251-4863).

5. Request for Payment.

The Contractor shall provide a copy of the invoice upon completion of agreed services. The invoice shall be provided through the USPS or email, to the COR named below. The contractor shall ensure that the following are included on the invoice:

• Contract #

• Invoice #

• Company Name

• Invoiced Line Item(s) must match the Contract Line Item(s)

• Small Business, Veteran Owned, or 8A – If applicable, indicate on invoice

U.S. Army Corps of Engineers or __________@usace.army.mil

Wilmington District Attn: _______________ 69 Darlington Avenue Wilmington, NC 28403-1343

6. Coordination. The principal Wilmington District technical point of contact for Falls Conduit GPR is, Mr. Tom Child (910-251-4103). In his absence, Mr. Christopher Norton (910) 251- 4102 can be contacted to discuss technical requirements of this scope of work. The Contractor shall designate a project manager who shall be the principal point of contact for the Wilmington District in administering this contract. The Contractor’s project manager shall be responsible for all coordination to ensure the work is accomplished in a professional manner. Any directions given that are viewed by the Contractor as a change to the SOW affecting contract fee and time shall be brought to the immediate attention of the Contracting Officer or the COR.

7. Points of Contact. USACE contacts for technical assistance.

US Army Corps of Engineers Wilmington District Personnel Title Phone Email

Tom Child Technical POC 910-251-4103 thomas.n.child@usace.army.mil

Christopher Norton Technical POC 910-251-4102 christopher.a.norton@usace.army.mil

William (Bill) Bond Project Coordinator 910-251-4826 william.j.bond@usace.army.mil

Carol Banaits Operations Project Manager 919-846-9332 carol.m.banaitis@usace.army.mil

Karri Mares Contracting Officer 910-251-4473 charlene.l.figgins@usace.army.mil

Carl Baynard COR 910-251-4089 carl.f.baynard@usace.army.mil

II. STATEMENT OF SERVICES

1. Purpose. The Wilmington District (USACOE) would like to perform a Ground Penetrating Radar (GPR) investigation inside the concrete outlet conduit at the Falls Dam Outlet works. The purpose is to detect any voids in the concrete, the rebar locations, if possible the location of a water stop, and if the GPR can penetrate the concrete, any voids in the soil on the outside of the conduit.

2. Description of Work. Falls Lake Dam is a Corps of Engineers (USACE) earthen dam on the north side of Raleigh, NC. A plan view of the dam is shown in Figure 1. During a routine conduit inspection of the concrete outlet works conduit, minor leaks were discovered at the construction joint of monoliths C-7 and C-8. See Figures 2, 3, and 4 for the joint location. The conduit is elliptical in shape as shown in Figure 2, about 19 feet high, 15 feet wide, and about 270 feet long. The leaks are on the right abutment side of the conduit above or in the curve of the elliptical conduit. The flow was measured as 0.28 gallons per minute (gpm). The thickness of the concrete varies at this joint with C-7 being 2.5 feet thick and C-8 being 2.0 feet thick.

Located at the joint is a nine (9) inch long water stop also shown in Figure 2. The exact depth of the water stop in the concrete is unknown. The walls of the conduit are lined with a fine-grained soil like material from the floor of the conduit to just above the discovered leaks, see Figure 5. The contractor shall remove this material prior to performing the GPR work where it may interfere with performing the GPR work. The GPR investigation shall be located along a line about two (2) feet above the leaks for the entire length (270 feet) on both sides of the conduit wall. No ladders should be necessary for this work. In order to perform the work being solicited, USACOE shall close the conduit reducing the outlet flow. However, a flow of two to six (2 – 6) inches of water will remain in the conduit after the conduit is shut down. The conduit can be shut down for a maximum of five (5) hours per day. The conduit is a confined space entry requiring lock-out tag-out, confined space training, and equipment such as gas meters.

The conduit shut down of five (5) hours per day includes about 45 minutes to one (1) hour for lock-out tag-out procedures to take place at the outlet works intake tower on the lake side of the dam. The contractor shall provide all equipment necessary to perform the work described and all accessories such as cables, radios, gas monitors, PPE, PFD’s, etc. It is required to have at least one person outside of the conduit to be in contact with the personnel inside the conduit a two way communication device, such as a walkie talkie, as a safety measure. Access to the conduit is only by boat launched into the water just downstream of the dam, see Figure 8.

3. Government Furnished Materials. Upon award of the contract, the Government will furnish the Contractor with the following:

Two small john boats, to carry personnel and necessary equipment to the conduit entrance, can be delivered to the parking area downstream of the fishing pier. One boat can carry 2 people and the other 4 people. The boats are to be paddled. No powered motors allowed. The Contractor shall be responsible for launching the boats. See Figures 6 and 7, to view the area around the fishing pier the work. Call Ms. Banaitis to arrange for the boat.

Confined space entry permit and performing the lock out tag out procedures.

The Raleigh fire Department shall be notified of the confined space entry and be on stand-by.

4. Submittals. The Contractor shall submit the following:

Accident Prevention Plan. Safety of all parties is a major concern. The Contractor shall comply with guidance established in the Corps of Engineers Safety Manual, EM 385-1-1, dated 30 NOV 2014 and any applicable State regulations. The Contractor shall deliver an Accident Prevention Plan to the Corps of Engineers for approval at least 10 working days prior to commencing work.

No work shall be performed until the plan is approved by the USACE. The plan shall follow the guidelines established in EM 385 to include, but not limited to: the location of the work site, verify emergency contact information and telephone numbers, evacuation plan to the nearest medical facility, required safety equipment, certified first aid personnel, spill prevention and HAZMAT information, and an Activity Hazard Analysis. The Contractor shall be responsible for conducting a daily Safety Brief and Risk Assessment prior to commencing work each day. All personnel shall be properly clothed and protected for working on the water. Wilmington District reserves the right to halt operations for any safety violations. The Wilmington Safety Officer is Mr. Bill Harris and he may be reached at 910-251-4698.

Work Plan. The Contractor shall submit a work plan and cost estimate to the USACE as part of this proposal. The work plan shall include the types of equipment to be used, a description of field procedures, and the number of personnel to be on site. The estimate shall reflect the time required to perform the work described.

Draft and Final Report. Reports shall include, at a minimum, a description of the work, a description of the procedures and equipment used, tasks completed, photographs, scans or maps, interpretations of the scans or maps, a condition assessment, and a conclusion from the investigation. The Contractor shall submit a draft report with items described in the previous sentence. The final report shall include a bound Ground Penetrating Radar report containing all the elements and meeting the requirements herein. In addition to the hard copy of the reports, the Contractor shall furnish computer files containing all the test data in Excel and PDF file formats.

Submittals shall be made to Mr. Carl Baynard, USACE – Geotechnical and Dam Safety Section, 69 Darlington Avenue, Wilmington, NC 28403-1343.

5. Completion of Work.

Following Contract Award:

• 5 calendar days: submit an Accident Prevention Plan and Sampling Plan.

• No later than 15 Calendar days: begin GPR investigation.

• No later than 18 Calendar days: complete GPR investigation.

Following Completion of GPR investigation:

• No later than15 calendar days following the completion of the investigation submit a draft report to Wilmington District for review.

Following Completion of Draft Report:

• No later than 3 business days from submittal of the Draft Report: comments will be provided by Wilmington District.

• No later than 3 calendar days from receiving Draft Report comments: submit Final Report to Wilmington District.

6. Antiterrorism/Operations Security Requirements (AT/OPSEC)

The Contractor will be required to adhere to the following conditions:

Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Pre‐screen candidates by using E‐Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award.

http://www.dhs.gov/E http://www.dhs.gov/E