SOW_Charleston_Harbor_PED.pdf

PDF 1 MB Posted

Attached to
Charleston Harbor Vibracore PED Sampling Federal contract opportunity
Solicitation number
W912PM-16-T-0008
Issued by
Department of the Army Corps of Engineers Engineering District Wilmington

View the file

Other files for this federal contract opportunity

Other files attached to Charleston Harbor Vibracore PED Sampling, newest first.
File Type Posted
SOW_Charleston_Harbor_PED_Revised_2-4-16.pdf PDF
Wage_Determinations_-_SC.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Subsurface Investigation and Geotechnical Laboratory Testing Results, Charleston Harbor, Post-45 Preconstruction Engineering and Design, Beneficial Use of Disposal Material

Charleston County, SC

I. GENERAL REQUIREMENTS

1. General. The Contractor shall furnish all labor, equipment, supplies, tools and incidentals necessary to perform the Vibracore Sampling, develop Drilling Logs, perform soils laboratory testing, and provide other services as specified herein. Vibracore Borings are located within the following reaches of Charleston Harbor; Wando, Bennis, Rebellion Reaches and within the

Charleston Harbor Entrance Channel. See Figures 1, 2 & 3 (Attached) for vibracore boring location, water depths (MLLW), and channel stationing. The results from the vibracore drilling effort will be evaluated by both Wilmington and Charleston Districts for developing the

Beneficial Use of Dredged (BUD) Material plan for Preliminary Engineering and Design (PED) of the Charleston Harbor Post-45 Deepening.

An additional option to this contact is conducting a washprobe sounding investigation. The washprobe soundings are located in the outer 7-miles of the Entrance Channel, which includes the proposed 3-mile extension (See Figure 4-Attached). These soundings will be utilized to verify refusal conditions in the Entrance Channel for the project PED phase.

2. Employee Supervision and Non-Personal Services. The Contractor’s employees shall at all times conduct themselves in a manner compatible with the non-personal services nature of this contractual instrument. The Contractor’s workforce shall under no circumstances allow themselves to be under the supervision and control of a U.S. Army Corps of Engineers (USACE) officer or employee.

3. Responsibility. The Contractor shall furnish qualified personnel to ensure the accomplishment of work specified in this Scope of Work (SOW). Additionally, the Contractor shall furnish all services, equipment, personnel, and travel required in connection with this SOW.

4. Direction. The Contractor shall accept directions only from the Wilmington District

Contracting Officer (KO), Ms. Charlenne Figgins (910-251-4473). Requests or desires of the

Users, Using Agency, or any other party made directly to the Contractor shall be immediately brought to the attention of the KO for this Contract. Any changes to this SOW must be authorized in writing by the KO.

5. Request for Payment. The Contractor shall prepare and submit the request for payment using

ENG Form 93. The ENG Form 93 shall be submitted for payment processing to: U.S. Army

Engineer District, Wilmington, ATTN: CESAW-TS-EE, 69 Darlington Avenue, Wilmington, NC 28403. When submitting for final payment, include a Release of Claims Statement on the

ENG 93. The following statement is acceptable:

“The undersigned Contractor, under Contract Number ________________ between the

United States of America and said Contractor for

___________________________________________, hereby releases the United States, its officers, agents, and employees from any and all claims, demands, or liabilities of any kind arising under, by virtue of, or in any matter related to, said contract or any modification or change thereof, including, but not limited to, any claims under the Contract Disputes Act or the

Equal Access to Justice Act, except for the following claim(s) in the stated amount(s):

(Contractor, please write “NONE”, or a description of the exception.)

Name: ___________________

Signature: ________________ Date: ______________

6. CONTRACTOR Responsibility Clause and Dispute Resolution. CONTRACTOR

Responsibility is covered under FAR clause 52.236-23. The USACE and the Contractor agree to cooperate with each other in the resolution of issues arising under this contract, to include use of non-binding alternative dispute event resolution techniques where appropriate and mutually acceptable. In the event of legal action brought by others against either or both parties, the

USACE and Contractor agree to cooperate with each other to the greatest extent practicable.

7. Coordination. The Wilmington District technical points of contact for this task order are Mr.

Kelley Kaltenbach (910-251-4879) and, in his absence, Mr. Carl Baynard (910-251-4089). The

Contracting Officer’s Representative (COR) is Mr. Mitchell Hall (910-251-4742). All submittals shall be made to Mr. Hall (ATTN: Hall, CESAW-ECP-EG). The Contractor shall designate a project manager who shall be the principal point of contact for the Wilmington District in administering this contract. The Contractor's project manager shall be responsible for all coordination to ensure the work is accomplished in a professional manner. Any directions given that are viewed by the Contractor as a change to the SOW affecting contract fee and time shall be brought to the immediate attention of the KO or the COR.

II. STATEMENT OF SERVICES

1. Description of Work.

Base Contract: The Contractor shall perform a total of 29 vibracore borings for this contract. The vibracores shall be advanced to a maximum depth of 20-feet or to refusal, whichever is encountered first. The locations of all borings have been established and are shown in Figures 1-3 (Attached). The borehole coordinates are given in Table 1 in SC

State Plane NAD 83 International Feet. All depths will be referenced to Mean Lower

Low Water (MLLW).

The Contractor shall perform sampling procedures on all borings in accordance with the paragraph “Vibracore Sampling”.

The Contractor shall complete Preliminary and Final Drilling Logs for all borings in accordance with the paragraph “Drilling Logs”.

The Contractor shall take detailed photographs of the cores that highlight the changes in stratigraphy with elevation referenced to MLLW. These will be submitted with the Final

Drilling Logs, as referred to above.

The Contractor shall perform grain size laboratory testing on the selected samples in accordance with the paragraph “Laboratory Testing Procedures”.

Additional Washprobe: The Contractor shall perform a total of 30 washprobe soundings.

The washprobe soundings are located in the Entrance Channel between 15 and 22 miles offshore from the mouth of the harbor, in waters that range in depth from 52 to 58 feet

(MLLW). The washprobe sounding coordinates are given in Table 2 in SC State Plane

NAD 83 International Feet. All elevations will be referenced to MLLW.

The Contractor shall perform washprobe soundings in accordance with the paragraph

“Washprobe Soundings”.

2. Purpose. Vibracoring, sampling and lab testing are necessary to determine material quality for the purpose of BUD material for the following; bird habitat, benthic fauna habitat and harbor construction fill. USACE personnel will make the BUD determination. Washprobe soundings are required in the outer portions of the Entrance Channel in order to verify that the materials within the dredging prism are unconsolidated, and that no hard/resistant material is present.

3. USACE Furnished Materials. Maps showing boring and washprobe locations are provided in

Figures 1-4 (attached). Coordinates are provided in Tables 1 and 2. A copy of the gINT version of ENG Form 1836 to be utilized for the vibracore drilling logs will be furnished after contract award. GIS shape and raster files of borings, washprobes, project bathymetry, and historical data will be provided upon request. Sample intervals for testing and archiving will be provided by

Wilmington USACE, based upon the Contractor’s Draft Boring Logs.

4. Vibracore Sampling. Borings shall be performed within 20 feet of the locations provided by

USACE, Wilmington District. Vibracoring shall be accomplished by vibrating a sampling tube to a depth of 20 feet below the ocean floor, unless refusal is encountered. Vibracore refusal is defined as a penetration rate of less than 0.1 feet in 10 seconds. At each boring location, real-time kinematic (RTK) Global Positioning System (GPS) surveying techniques shall be utilized to provide accuracies of 0.2 feet both vertically and horizontally. Boring identification will be designated according to the table provided. The recovered vibracore sampling tubes shall be carefully transported to the Contractor’s lab. Upon arrival, the tubes shall be cut open and a photographic mosaic log depicting the stratigraphic horizons relative to MLLW elevation shall be produced. Each core shall be field classified and logged in accordance with the Unified Soil

Classification System (USCS). Major changes in stratigraphy will be identified and referenced to

MLLW. Upon completion of sampling and field classification, Preliminary Drilling Logs and all field documentation shall be submitted to the Wilmington District for sample interval selection and follow-on laboratory testing. In order to expedite sample interval selection, and follow-on laboratory testing, Preliminary Drilling Logs and field documentation shall be submitted to the

Wilmington District after each harbor reach (Bennis, Rebellion, Wando and Entrance Channel) is completed.

5. Drilling Logs. Preliminary and Final Drilling Logs shall be developed using engineering form

ENG 1836. In order to expedite sample interval selection, and follow-on laboratory testing, Preliminary Drilling Logs and field documentation shall be submitted to the Wilmington District upon completion of each harbor reach. Preliminary Drilling Logs, at a minimum, shall include the date and time the boring was taken, the horizontal location of the boring (SC State Plane

FIPS 3900 NAD 83 International Feet), ocean bottom elevation (MLLW), a visual description and USCS classification of stratigraphy including depths for the entire length of recovered material, sample intervals, boring recovery, depth of refusal, and water depth with tidal corrections (MLLW). The USACE shall determine the sample intervals to be tested and

“archived” from each boring from the Preliminary Drilling Logs. Final Drilling Logs and gINT project database shall be submitted to the Wilmington District as part of the Final Report, and shall include laboratory testing results. Samples sent for lab testing shall be designated “S-1, S-

2, S-3, etc…” on the drilling logs under “column f” on ENG Form 1836, with top and bottom elevations listed. Evaluations and inference shall be the responsibility of the USACE. “Archived

Samples” shall refer to samples that will not be tested as part of this contract, and will be sent to the USACE for storage. USACE will keep the archive samples if their testing is required at a later date. For estimating purposes, assume there will be two (2) Archived Samples per boring

(total of 58 samples).

6. Washprobe Soundings. Thirty washprobes (aka “jet probes”) shall be performed using similar methods that have been previously employed by the Government. By definition, a washprobe sounding consists of lowering a 2-inch I.D. open-ended steel drill rod (or similar pipe) with a nozzle to the seafloor. Then, air or water is jetted to advance the pipe through the unconsolidated sediments on the seafloor to a refusal depth. Any variations to the pipe size shall be noted in the

Contractor’s bid documents. No soil or rock samples are collected during the wash probing effort. Particular attention is given to the water depth, channel bottom, penetration depth of washprobe sounding, time, and any tidal correction factors. The washprobe sounding indicates the elevation at which hard material (i.e. refusal to washprobe penetration) was encountered. A typical washprobe sounding on a Government Vessel (equipped with a crane and pumping system) takes less than 5 –minutes to complete. Information such as the x and y location of the sounding, z1 elevation of the seafloor (sounding or depth finder), and z2 refusal elevation is required in tabular format.

7. Laboratory Testing Procedures. Laboratory tests shall be conducted by a soils lab certified by the USACE or by the SC/NC Department of Transportation. Laboratory testing shall be the responsibility of the Contractor. On average, and for estimating purposes, three (3) samples will be collected from each boring for testing for a total of 87 gradation samples. In addition, two archive samples per boring (58 samples) will be collected-but will not be tested in this contract.

USACE will determine the depth interval and compositing details for each sample. This number is the maximum number of gradation samples that will be required. The Contractor shall be paid only for the number of completed lab tests. The final lab results shall be included in the Final

Report, and shall contain visual USCS/ASTM D2487 soil classifications, and grain size test results in both tabular and graphical formats. Lab results shall also be included in the Final

Drilling Logs.

Three (3) test procedures shall be performed on each sample: (1) American Society for Testing and Materials (ASTM) test procedure D422 entitled “Standard Test Method for Particle-Size

Analysis of Soils”; (2) D2487 “Classification of Soils for Engineering Purposes (Unified Soils

Classification System)”, and (3) visual % shell and limestone rock fragment determination. The following sieve sizes shall be used: ¾ in., ½ in., 3/8 in., No. 4, No. 10, No. 20, No. 40, No. 60, No. 100, and No. 200, for the test procedure ASTM D422. Fines passing the #200 sieve will be subject to hydrometer testing (as per ASTM D422) to determine percentage of silt and clay fines.

Visual percent shell content and visual percent limestone rock fragment content shall be estimated for the ¾ in., 3/8 in., and No.4 sieves.

8. Cost Proposal. The Contractor shall submit a sampling plan to the USACE as part of his proposal. The sampling plan shall include the type of vibracore machine, the size of the vibracore tube, the material from which the tubes are made, the size and description of the boat(s) to be used, the number of boat and drill crew members, the qualifications of the laboratory performing analyses, and a description of the survey equipment to be used to collect coordinate and elevation data. For the cost proposal, the Contractor shall assume 29 vibracore borings, 87 soil gradation and hydrometer tests, 87 visual determination of shell and rock fragment content for the no.4, 3/8 in., and ¾ in. sieves, 29 Preliminary Drilling Logs in gINT format, 29 photographic mosaic logs, 30 Washprobe soundings in an excel file, gINT database, a

Final Report including Final Drilling Logs, washprobe soundings table, laboratory analyses, and shipping of archive samples and sieved samples. The estimate shall include daily costs for vessel operation and number of days required for the washprobe and vibracoring effort.

9. Reports. The Contractor shall furnish Preliminary Drilling Logs, and a Final Report to the

USACE. Preliminary Drilling Logs and gINT project file update shall be submitted upon completion of each harbor reach as described in Section “Vibracore Sampling” above. The Final

Report shall include, at a minimum, a description of the work, a map with boring and sounding locations, Final Drilling Logs, core photographic mosaic logs, tabulated Washprobe Sounding data, and Lab Data with gradation tables and curves for each sample tested. The Final Report shall be in accordance with applicable report requirements for ASTM D2487/USCS and ASTM

D422, including both tabulation and graph format of the percentage passing each sieve, and visual estimations for limestone and shell content. The gradation curves shall include the project name, laboratory name, boring number, sample identification number and date the sample was tested. In addition to the hard copy of the reports, the Contractor shall furnish electronic/digital files containing all the lab test data in Excel and PDF formats. These files shall contain the project name at the top, boring number, sample identification number, depth of sample, visual classification, and percentage passing each sieve, and percentage clay and silt for the test procedure in ASTM D-422.

10. Submittals. The CONTRACTOR shall submit the following:

The Preliminary Drilling Logs, Draft Report and Final Report shall be submitted electronically to the COR for review at the following e-mail address:

mitch.h.hall@usace.army.mil

The Final Report shall be bound and titled; “Subsurface Investigation and Geotechnical

Laboratory Testing Results, Charleston Harbor, Post-45 Preconstruction Engineering and

Design, Beneficial Use of Disposal Material, Charleston County, SC”, containing all the elements and meeting the requirements herein. Three hard copies of the Final Report and 3 CD-

ROMs shall be submitted, and be deemed acceptable before final payment is made.

Final Submittals shall be made to the following recipients and mailing addresses:

(1) Mr. Mitchell Hall, P.G. (CESAW-TS-EG), Chief, Geotechnical and Environmental Remediation Section, 69 Darlington Avenue, Wilmington, NC 28403-1343.

(2) Mr. Alan Shirey, P.E. (CESAC-PM-PL)

Project Management & Planning Section

69A Hagood Avenue, Charleston, SC 29403-5107.

(3) Mr. Mark Messersmith

Project Management & Planning Section

69A Hagood Avenue, Charleston, SC 294-5107.

11. Safety. Safety of all parties is a major concern. The Charleston Harbor is a busy harbor with large container vessels and recreational craft. The Contractor shall coordinate the work effort with the U. S. Coast Guard and comply with all their requests. The Contractor shall ensure his operations have a minimal effect on navigation. The Contractor shall comply with guidance established in the Corps of Engineers Safety Manual, EM 385-1-1, dated 15 SEP 2008 and any applicable State and U. S. Coast Guard regulations. The Contractor shall deliver an Accident

Prevention Plan to the Corps of Engineers for approval 10-days prior to commencing drilling operations. No work shall be performed until the plan is approved by the USACE. The plan shall follow the guidelines established in EM 385 to include: the location of the work site, contact verified emergency contact information to the local Coast Guard station, evacuation plan to the nearest medical facility, emergency radio frequencies and telephone numbers, required safety equipment, certified first aid personnel, spill prevention and HAZMAT information, and an

Activity Hazard Analysis. The Contractor shall be responsible for conducting a daily Safety

Brief and Risk Assessment prior to commencing work each day. All personnel shall be properly clothed and protected for working on the water. Wilmington District reserves the right to halt drilling operations for any safety violations. The Wilmington Safety Officer is Mr. Bill Harris and he may be reached at 910-251-4698.

12. Completion of Work. The field work shall be completed within 45 days of contract award.

The Contractor shall complete the report writing within 60 days of contract award.

13. OPSEC Reference:

2b. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate

Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive

2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as

NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

15. The Contractor must pre-screen Candidates using the E-verify Program

(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

14. Tables and Figures. Attached.

Table 1: Vibracore Locations for Wando, Bennis and Rebellion Reaches, and the Entrance

Channel, subsections EC-1 and EC-2.

Boring_ID Northing Easting

BENR15-01 345777 2337834

BENR15-02 345522 2337692

BENR15-03 345404 2338578

BENR15-04 345178 2338434

BENR15-05 344972 2338319

BENR15-06 345326 2337584

BENR15-07 344605 2339669

BENR15-08 344367 2339475

BENR15-09 344454 2340471

BENR15-10 343934 2340666

BENR15-11 343795 2341556

CHEC15-01 329609 2358597

CHEC15-02 329206 2359334

CHEC15-03 328974 2360384

CHEC15-04 328473 2360674

CHEC15-05 327962 2361531

CHEC15-06 327345 2361997

CHEC15-07 327356 2362715

CHEC15-08 326847 2363645

REBR15-01 342937 2342572

REBR15-02 342673 2342512

REBR15-03 342322 2343698

REBR15-04 341840 2343776

REBR15-05 341550 2344739

REBR15-06 341221 2344784

REBR15-07 340881 2344856

WLRW15-01 361939 2337036

WLRW15-02 360650 2335853

WLRW15-03 359767 2334910

B e n n is

E n tr a n c e C h a n n e l

R e b e ll io n

W a n d o

Table 2: Washprobe Locations for the Entrance Channel, subsections EC-14 to EC-21.

Name Easting Northing

WP-15-01 2418572 296428

WP-15-02 2422229 294504

WP-15-03 2422848 294735

WP-15-04 2424872 293077

WP-15-05 2425210 293501

WP-15-06 2425852 292350

WP-15-07 2426502 292913

WP-15-08 2428902 291593

WP-15-09 2429010 290692

WP-15-10 2430057 290176

WP-15-11 2431064 290239

WP-15-12 2431727 289709

WP-15-13 2434329 288555

WP-15-14 2434964 287924

WP-15-15 2437206 286232

WP-15-16 2437581 286759

WP-15-17 2438149 286441

WP-15-18 2438614 286169

WP-15-19 2438418 285535

WP-15-20 2439736 285471

WP-15-21 2443671 282584

WP-15-22 2443946 282909

WP-15-23 2444240 283213

WP-15-24 2445951 281454

WP-15-25 2446314 281722

WP-15-26 2446590 281957

WP-15-27 2446702 281017

WP-15-28 2447050 281332

WP-15-29 2449462 279588

WP-15-30 2450012 279891

Figure 1: Location of beneficial use vibracores (x 3) in Wando Reach expansion. PDF map object click here → Post45_PED_BUD_Vi bracores_Wando09SEP15.pdf

Figure 2: Location of beneficial use vibracores (x 18) in Bennis & Rebellion Reach. PDF map object click here → bracores_27OCT15_Bennis&Rebellion.pdf

Figure 3: Location of beneficial use vibracores (x 8) in the Entrance Channel. PDF map object click here → bracores_EC09OCT15.pdf

Figure 4: Location of PED washprobes (x 30) in the Entrance Channel. PDF map object click here →

Post45_PED_Washpr obes_EC09OCT15.pdf

File details come from the government source that posted it. Updated .