AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912PM-16-B-0028 is hereby amended for the follow ing reasons:
a) To incorporate additional specification sections and revised plan sheets. See the Technical Summary of Changes, attached.
b) The date and time for receipt of bids is not changed by this modification .
c) All other terms, provisions, and conditions of the solicitation remain unchanged.
///////////////////////////////////////////////////////// LAST ITEM \\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM-16-B-0028
X 9B. DATED (SEE ITEM 11)
23-Aug-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Aug-2016
CODE
U S ARMY CORPS OF ENGINEERS
ATTN: JERE F. WEST, 69 DARLINGTON AVE
WILMINGTON NC 28403
W912PM 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PM-16-B-0028
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SUMMARY OF CHANGES
(End of Summary of Changes)
W912PM-16-B-0028
Amendment 0003
TECHNICAL SUMMARY OF CHANGES
SPECIFICATIONS:
The revised Sections and/or Attachments listed below (revised by Amendment No. 0003) is hereby added to and made a part of the solicitation.
Revised Section Revised Attachment Project Table of Contents 01 33 00 – Attachment 1 ENG Form 4288
Following sections were inadvertently omitted from 100% Advertise Specifications and have been added to and made a part of the solicitation.
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
07 21 19 RETROFIT BLANKET INSULATION SYSTEM
07 42 13 METAL WALL PANELS
08 11 13 STEEL DOORS AND FRAMES
08 71 00 DOOR HARDWARE
31 00 00 EARTHWORK
31 32 11 SOIL SURFACE EROSION CONTROL
32 92 19 SEEDING
33 11 00 WATER UTILITY DISTRIBUTION PIPING
The following section has been deleted:
07 21 29 SPRAY APPLIED FOAM INSULATION
DRAWINGS:
Delete existing Sheet Numbers E-602, E-701, ED101 and EP101 in their entirety and replace with revised enclosed Sheets.
Summary of Scope included in Drawing Revisions:
Remove the existing 200A service disconnect and feeder from SUS transformer to panel 'B'. Provide new 200A, 3-pole breaker in panel 'A' and install a new 200A feeder from panel 'A' to panel 'B'. Install new 600A service entrance rated fused disconnect on exterior wall of building near panel 'A'. New 600A secondary from SUS transformer will connect to new 600A disconnect and feed new panel 'A'. Panel 'A' will change from a service entrance rated MCB panel to a standard main lug only panel.
SF-00005-16 - Renovate Storage Bldg O-1908, SOTF W912PM-16-B-0028 Fort. Bragg, NC
PROJECT TABLE OF CONTENTS
****Amendment 0003****
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
STANDARD FORM 1442
00 10 00 SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
00 21 00 INSTRUCTIONS
00 21 13 INSTRUCTIONS TO BIDDERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 05 GENERAL AND SPECIAL PROVISIONS
01 00 60 SECURITY PROCEDURES GUIDE
01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 19 RETROFIT BLANKET INSULATION SYSTEM
07 42 13 METAL WALL PANELS
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 33 23 OVERHEAD COILING DOORS
08 71 00 DOOR HARDWARE
PROJECT TABLE OF CONTENTS Page 1 (Revised by Amendment 0003)
DIVISION 09 - FINISHES
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 21 - FIRE SUPPRESSION
21 13 00.00 40 FIRE-SUPPRESSION SPRINKLER SYSTEMS
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 23 00 REFRIGERANT PIPING
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 PANELBOARDS
26 53 00.00 40 EXIT SIGNS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 32 11 SOIL SURFACE EROSION CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
****Amendment 0003****
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2 (Revised by Amendment 0003)
SUBMITTAL REGISTER (ER 415-1-10) TITLE AND LOCATION DATE
CONTRACTOR CONTRACT NUMBER
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
SECTION - 01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
1 01 10 00.10 38 1.10 List of Subcontractors PRECON SUBMTL FIO
2 01 10 00.10 38 1.2 Progress Chart PRECON SUBMTL GA
3 01 10 00.10 38 1.10 Quality Control Plan PRECON SUBMTL GA
4 01 10 00.10 38 1.10 Certificate of Insurance PRECON SUBMTL FIO
5 01 10 00.10 38 1.5 PROGRESS SCHEDULE PRODUCT DATA FIO
6 01 10 00.10 38 1.10 Completion of Corps CQC Course CERTIFICATES FIO
7 01 10 00.10 38 1.10 Letter Appointing Superintendent CERTIFICATES FIO
8 01 10 00.10 38 1.9 Contractor testing laboratory CERTIFICATES GA
9 01 10 00.10 38 1.9 Commercial testing laboratory CERTIFICATES GA
SECTION - 01 14 00 WORK RESTRICTIONS
1 01 14 00 1.3.1.1 List of Contact Personnel PRECON SUBMTL FIO
SECTION - 01 32 01.00 10 PROJECT SCHEDULE
1 01 32 01.00 10 1.3 Project Scheduler Qualifications PRECON SUBMTL GA
2 01 32 01.00 10 3.4.1 Preliminary Project Schedule PRECON SUBMTL GA
3 01 32 01.00 10 3.4.2 Initial Project Schedule PRECON SUBMTL GA
4 01 32 01.00 10 3.6.2 Periodic Schedule Update PRECON SUBMTL GA
SECTION - 01 33 00 SUBMITTAL PROCEDURES
1 01 33 00 1.7 Submittal Register PRECON SUBMTL GA
SECTION - 01 33 29 LEED(TM) DOCUMENTATION
1 01 33 29 1.5.3.1 Preliminary Sustainability Notebook PRECON SUBMTL GA
2 01 33 29 1.5.3.1 Preliminary High Performance and Sustain PRECON SUBMTL FIO
3 01 33 29 1.5.3.1 Final Sustainability Notebook CLOSEOUT SUBMTL GA
4 01 33 29 1.5.3.1 Final High Performance and Sustainable B CLOSEOUT SUBMTL GA
SECTION - 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
1 01 35 26 1.7 Accident Prevention Plan (APP) PRECON SUBMTL GA
2 01 35 26 1.4 Monthly Exposure Reports TEST REPORTS FIO
3 01 35 26 1.12 Notifications and Reports TEST REPORTS FIO
4 01 35 26 1.12.2 Accident Reports TEST REPORTS GA
5 01 35 26 1.12.3 LHE Inspection Reports TEST REPORTS FIO
6 01 35 26 1.6.1.5 Crane Operators/Riggers CERTIFICATES FIO
7 01 35 26 1.7.2.2 Standard Lift Plan CERTIFICATES GA
8 01 35 26 1.7.2.3 Critical Lift Plan CERTIFICATES GA
9 01 35 26 1.8 Activity Hazard Analysis (AHA) CERTIFICATES FIO
10 01 35 26 1.9.1 Confined Space Entry Permit CERTIFICATES FIO
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
11 01 35 26 1.9.1 Hot Work Permit CERTIFICATES FIO
12 01 35 26 1.12.4 Certificate of Compliance CERTIFICATES FIO
SECTION - 01 45 00.00 10 QUALITY CONTROL
1 01 45 00.00 10 3.2 Contractor Quality Control (CQC) Plan PRECON SUBMTL GA
2 01 45 00.00 10 3.9 Verification Statement TEST REPORTS FIO
SECTION - 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROL
1 01 50 00 1.3 Construction Site Plan PRECON SUBMTL FIO
2 01 50 00 3.4.1 Traffic Control Plan PRECON SUBMTL FIO
SECTION - 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
1 01 57 19 1.5.1 Preconstruction Survey PRECON SUBMTL FIO
2 01 57 19 1.8 Solid Waste Management Permit PRECON SUBMTL GA
3 01 57 19 1.5.2 Regulatory Notifications PRECON SUBMTL GA
4 01 57 19 1.6 Environmental Protection Plan PRECON SUBMTL GA
5 01 57 19 1.6.9.1 Dirt and Dust Control Plan PRECON SUBMTL GA
6 01 57 19 1.5.4 Employee Training Records PRECON SUBMTL GA
7 01 57 19 1.5.4 Employee Training Records CERTIFICATES FIO
8 01 57 19 3.7.1 Waste Determination Documentation CLOSEOUT SUBMTL FIO
9 01 57 19 3.7.2.6 Disposal Documentation for Hazardous and CLOSEOUT SUBMTL FIO
10 01 57 19 1.5.4 Assembled Employee Training Records CLOSEOUT SUBMTL GA
11 01 57 19 1.8 Solid Waste Management Permit CLOSEOUT SUBMTL GA
12 01 57 19 3.7.2.1 Hazardous Waste/Debris Management CLOSEOUT SUBMTL GA
13 01 57 19 1.5.2 Regulatory Notifications CLOSEOUT SUBMTL GA
SECTION - 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
1 01 74 19 1.6 Waste Management Plan PRECON SUBMTL GA
2 01 74 19 1.7 Records CLOSEOUT SUBMTL FIO
SECTION - 01 78 00 CLOSEOUT SUBMITTALS
1 01 78 00 1.7.1 Warranty Management Plan PRODUCT DATA FIO
2 01 78 00 1.7.5 Warranty Tags PRODUCT DATA FIO
3 01 78 00 1.5 Spare Parts Data PRODUCT DATA FIO
4 01 78 00 1.7.1 Instructions MFRS INSTR FIO
5 01 78 00 3.6 Operation and Maintenance Manuals O&M DATA GA
6 01 78 00 3.3 Record Drawings CLOSEOUT SUBMTL GA
7 01 78 00 2.3 Certification of EPA Designated Items CLOSEOUT SUBMTL GA
8 01 78 00 3.8 Interim DD FORM 1354 CLOSEOUT SUBMTL GA
9 01 78 00 3.8 Checklist for DD FORM 1354 CLOSEOUT SUBMTL GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
SECTION - 02 41 00 DEMOLITION
1 02 41 00 1.2.1 Demolition Plan PRECON SUBMTL GA
2 02 41 00 1.8 Existing Conditions PRECON SUBMTL FIO
3 02 41 00 1.6 Notification CERTIFICATES GA
SECTION - 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
1 03 30 53 1.4 Installation Drawings SHOP DRAWINGS GA
2 03 30 53 2.2.3.1 Air-Entraining Admixture PRODUCT DATA FIO
3 03 30 53 2.2.3.2 Accelerating Admixture PRODUCT DATA FIO
4 03 30 53 2.2.3.3 Water-Reducing or Retarding Admixture PRODUCT DATA FIO
5 03 30 53 2.2.10 Curing Materials PRODUCT DATA FIO
6 03 30 53 2.2.6 Expansion Joint Filler Strips, Premolded PRODUCT DATA FIO
7 03 30 53 2.2.7 Joint Sealants - Field Molded Sealants PRODUCT DATA FIO
8 03 30 53 3.2 Conveying and Placing Concrete PRODUCT DATA FIO
9 03 30 53 2.2.8 Formwork PRODUCT DATA FIO
10 03 30 53 2.3 Mix Design Data PRODUCT DATA GA
11 03 30 53 2.3 Ready-Mix Concrete PRODUCT DATA GA
12 03 30 53 2.4.1 Curing Compound PRODUCT DATA GA
13 03 30 53 2.2.5 Mechanical Reinforcing Bar Connectors PRODUCT DATA FIO
14 03 30 53 2.2.2 Aggregates TEST REPORTS FIO
15 03 30 53 2.1.3 Concrete Mixture Proportions TEST REPORTS GA
16 03 30 53 3.3.3.2 Measurement of Floor Tolerances TEST REPORTS FIO
17 03 30 53 3.8.3 Compressive Strength Testing TEST REPORTS GA
18 03 30 53 3.8.3 Slump TEST REPORTS GA
19 03 30 53 3.8.3 Air Content TEST REPORTS FIO
20 03 30 53 2.2.4 Water TEST REPORTS FIO
21 03 30 53 2.2.1 Cementitious Materials CERTIFICATES FIO
22 03 30 53 2.2.2 Aggregates CERTIFICATES FIO
23 03 30 53 2.3 Delivery Tickets CERTIFICATES FIO
24 03 30 53 2.4.1 Curing Compound MFRS INSTR FIO
SECTION - 05 50 13 MISCELLANEOUS METAL FABRICATIONS
1 05 50 13 2.3 Guard posts SHOP DRAWINGS FIO
2 05 50 13 2.4 Angles and Plates SHOP DRAWINGS FIO
SECTION - 05 51 00 METAL STAIRS
1 05 51 00 2.13 Metal Stair System SHOP DRAWINGS GA
2 05 51 00 2.13 Stair framing calculations SHOP DRAWINGS GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
3 05 51 00 2.15 Steel Stairs PRODUCT DATA GA
4 05 51 00 1.3 Welder Qualification CERTIFICATES GA
5 05 51 00 2.15 Steel Stairs MFRS INSTR FIO
SECTION - 05 52 00 METAL RAILINGS
1 05 52 00 2.1 Fabrication Drawings SHOP DRAWINGS GA
2 05 52 00 1.3.1 Welder Qualification CERTIFICATES GA
3 05 52 00 3.2 Installation Instructions MFRS INSTR GA
SECTION - 07 21 19 Foamed-in-Place Insulation 1 07 21 19 2.5 Pressure Sensitive Tape PRODUCT DATA FIO
2 07 21 19 2.7 Accessories PRODUCT DATA FIO
3 07 21 19 2.4 Fabric Liner PRODUCT DATA GA
4 07 21 19 Insulation MFRS INSTR FIO
5 07 21 19 3.3.1 Manufacturers Written Directions MFRS INSTR FIO
6 07 21 19 2.1.1 Recycled Content for Insulation Material CLOSEOUT SUBMTL FIO
7 07 21 19 2.1.2 Reduce Volatile Organic Compounds (VOC) CLOSEOUT SUBMTL FIO
SECTION - 07 42 13 METAL WALL PANELS
1 07 42 13 1.5.3 Qualification of Manufacturer PRECON SUBMTL GA
2 07 42 13 1.5.4 Qualification of Installation Contractor PRECON SUBMTL GA
3 07 42 13 1.8 Warranty PRECON SUBMTL GA
4 07 42 13 1.5.1.1 Installation Drawings SHOP DRAWINGS GA
5 07 42 13 2.1 Recycled Content; PRODUCT DATA FIO
6 07 42 13 2.2.1 Exterior Wall Panel PRODUCT DATA GA
7 07 42 13 2.2.1 Wall Liner Panel PRODUCT DATA GA
8 07 42 13 2.2.2 Factory Color Finish PRODUCT DATA GA
9 07 42 13 1.5.5 Closure Materials PRODUCT DATA FIO
10 07 42 13 2.5.4.4 Pressure Sensitive Tape PRODUCT DATA FIO
11 07 42 13 2.5.4.1 Sealants and Caulking PRODUCT DATA FIO
12 07 42 13 1.5.3.1 Galvanizing Repair Paint PRODUCT DATA FIO
13 07 42 13 1.5.3.1 Enamel Repair Paint PRODUCT DATA FIO
14 07 42 13 2.5 Accessories PRODUCT DATA FIO
15 07 42 13 2.2.1 Exterior Wall Panel SAMPLES GA
16 07 42 13 2.2.1 Wall Liner Panel SAMPLES GA
17 07 42 13 2.2.2.5 Color chart SAMPLES GA
18 07 42 13 1.5.1.2 Wind load design analysis DESIGN DATA GA
19 07 42 13 3.7.2 Leakage Tests TEST REPORTS GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
20 07 42 13 1.3.2 Wind Load Tests TEST REPORTS GA
21 07 42 13 2.2.2.6 Coating TEST REPORTS GA
22 07 42 13 2.2.2.6 Chalking TEST REPORTS GA
23 07 42 13 1.3.2 Seismic Tests TEST REPORTS GA
24 07 42 13 1.5.3.1 Coil Stock CERTIFICATES GA
25 07 42 13 1.5.3.1 Fasteners CERTIFICATES GA
26 07 42 13 1.5.3.1 Galvanizing Repair Paint CERTIFICATES GA
27 07 42 13 1.5.3.1 Enamel Repair Paint CERTIFICATES GA
28 07 42 13 3.3 Installation MFRS INSTR GA
29 07 42 13 3.8.1 Manufacturer's Field Reports MFRS FLD REPT GA
30 07 42 13 1.8 Warranty CLOSEOUT SUBMTL GA
31 07 42 13 1.5.6 Maintenance Instructions CLOSEOUT SUBMTL GA
32 07 42 13 1.8.1 20 year 'No Dollar Limit' warranty for l CLOSEOUT SUBMTL FIO
SECTION - 07 92 00 JOINT SEALANTS
1 07 92 00 2.1 Sealants PRODUCT DATA GA
2 07 92 00 2.2 Primers PRODUCT DATA GA
3 07 92 00 2.3 Bond Breakers PRODUCT DATA GA
4 07 92 00 2.4 Backstops PRODUCT DATA GA
5 07 92 00 3.1 Field Adhesion PRODUCT DATA GA
6 07 92 00 3.4.7 Sealant CERTIFICATES FIO
7 07 92 00 2.2 Primers CERTIFICATES FIO
8 07 92 00 2.3 Bond Breakers CERTIFICATES FIO
9 07 92 00 1.4 Volatile Organic Compounds (VOC) Content CERTIFICATES FIO
10 07 92 00 2.1.1 Volatile Organic Compounds (VOC) Content CERTIFICATES FIO
11 07 92 00 1.4 Volatile Organic Compounds (VOC) Content CLOSEOUT SUBMTL FIO
12 07 92 00 2.1.1 Volatile Organic Compounds (VOC) Content CLOSEOUT SUBMTL FIO
SECTION - 08 11 13 STEEL DOORS AND FRAMES
1 08 11 13 2.1 Doors SHOP DRAWINGS GA
2 08 11 13 2.3 Frames SHOP DRAWINGS GA
3 08 11 13 2.1 Doors PRODUCT DATA GA
4 08 11 13 2.3 Frames PRODUCT DATA GA
SECTION - 08 33 23 OVERHEAD COILING DOORS
1 08 33 23 2.2.1 Overhead Coiling Doors SHOP DRAWINGS GA
2 08 33 23 2.2.3 Counterbalancing Mechanism SHOP DRAWINGS GA
3 08 33 23 2.2.4 Electric Door Operators SHOP DRAWINGS GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
4 08 33 23 2.2.1.3 Bottom Bars SHOP DRAWINGS GA
5 08 33 23 2.1.1.1 Guides SHOP DRAWINGS GA
6 08 33 23 2.2.3.1 Mounting Brackets SHOP DRAWINGS GA
7 08 33 23 2.2.1.8 Overhead Drum SHOP DRAWINGS GA
8 08 33 23 3.3.2 Hood SHOP DRAWINGS GA
9 08 33 23 2.1.1.1 Installation Drawings SHOP DRAWINGS GA
10 08 33 23 2.2.1 Overhead Coiling Doors PRODUCT DATA GA
11 08 33 23 2.2.2 Hardware PRODUCT DATA GA
12 08 33 23 2.2.3 Counterbalancing Mechanism PRODUCT DATA GA
13 08 33 23 2.2.4 Electric Door Operators PRODUCT DATA GA
14 08 33 23 2.2.1 Overhead Coiling Doors DESIGN DATA GA
15 08 33 23 2.2.2 Hardware DESIGN DATA GA
16 08 33 23 2.2.3 Counterbalancing Mechanism DESIGN DATA GA
17 08 33 23 2.2.4 Electric Door Operators DESIGN DATA GA
18 08 33 23 1.3.1 Powder Coatings Certificate DESIGN DATA GA
19 08 33 23 3.3.2 Operation and Maintenance Manuals O&M DATA GA
20 08 33 23 3.3.2 Materials O&M DATA GA
21 08 33 23 3.3.2 Devices O&M DATA GA
22 08 33 23 3.3.2 Procedures O&M DATA GA
23 08 33 23 3.3.2 Manufacture's Brochures O&M DATA GA
24 08 33 23 3.3.2 Parts Lists O&M DATA GA
25 08 33 23 3.3.1 Warranty CLOSEOUT SUBMTL GA
SECTION - 08 71 00 DOOR HARDWARE
1 08 71 00 1.3 Manufacturer's Detail Drawings SHOP DRAWINGS GA
2 08 71 00 1.3 Verification of Existing Conditions SHOP DRAWINGS GA
3 08 71 00 1.5 Hardware Schedule SHOP DRAWINGS GA
4 08 71 00 2.3.5 Keying System SHOP DRAWINGS GA
5 08 71 00 2.3 Hardware Items PRODUCT DATA GA
6 08 71 00 3.1 Installation MFRS INSTR FIO
7 08 71 00 1.5 Hardware Schedule O&M DATA GA
8 08 71 00 1.6.1 Key Bitting CLOSEOUT SUBMTL FIO
SECTION - 09 90 00 PAINTS AND COATINGS
1 09 90 00 1.4.2 Certification PRODUCT DATA FIO
2 09 90 00 2.1 Coating PRODUCT DATA GA
3 09 90 00 2.1 Manufacturer's Technical Data Sheets PRODUCT DATA FIO
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
4 09 90 00 1.10 Color SAMPLES GA
5 09 90 00 1.3 Applicator's qualifications CERTIFICATES FIO
6 09 90 00 1.4.1.2 Qualification Testing CERTIFICATES GA
7 09 90 00 3.2.1 Application instructions MFRS INSTR FIO
8 09 90 00 3.4.2 Mixing MFRS INSTR FIO
9 09 90 00 1.7.2 Manufacturer's Material Safety Data Shee MFRS INSTR FIO
10 09 90 00 2.1 Coatings O&M DATA FIO
11 09 90 00 1.9.1 Local/Regional Materials CLOSEOUT SUBMTL FIO
12 09 90 00 2.1 Materials CLOSEOUT SUBMTL FIO
SECTION - 10 44 16 FIRE EXTINGUISHERS
1 10 44 16 2.2.1 Cabinets SHOP DRAWINGS GA
2 10 44 16 2.1.2 Extinguishers PRODUCT DATA GA
3 10 44 16 2.1.3 Accessories PRODUCT DATA GA
4 10 44 16 2.2.1 Cabinets PRODUCT DATA GA
5 10 44 16 3.2.1 Replacement Parts List PRODUCT DATA GA
SECTION - 21 13 00.00 40 FIRE-SUPPRESSION SPRINKLER SYSTEMS
1 21 13 00.00 40 1.2 Record of Existing Conditions PRECON SUBMTL GA
2 21 13 00.00 40 2.2.2 Supporting Elements SHOP DRAWINGS GA
3 21 13 00.00 40 2.2.3 Fire-Department Connections SHOP DRAWINGS GA
4 21 13 00.00 40 2.2.5 Sprinkler Heads SHOP DRAWINGS GA
5 21 13 00.00 40 2.2.6 Valves SHOP DRAWINGS GA
6 21 13 00.00 40 2.2.1 Aboveground Piping Materials PRODUCT DATA GA
7 21 13 00.00 40 2.2.6 Valves PRODUCT DATA GA
8 21 13 00.00 40 2.2.4 Riser Alarm Equipment PRODUCT DATA GA
9 21 13 00.00 40 2.2.5 Sprinkler Heads PRODUCT DATA GA
10 21 13 00.00 40 2.3 Materials PRODUCT DATA GA
11 21 13 00.00 40 2.2.2 Supporting Elements PRODUCT DATA GA
12 21 13 00.00 40 2.1 Equipment and Performance Data PRODUCT DATA GA
13 21 13 00.00 40 Part 2 Design Analysis and Calculations DESIGN DATA GA
14 21 13 00.00 40 3.3.5 Pressure Tests TEST REPORTS GA
SECTION - 21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
1 21 13 13.00 10 1.4.3 Shop Drawings SHOP DRAWINGS GA
2 21 13 13.00 10 3.6 As-Built Drawings SHOP DRAWINGS GA
3 21 13 13.00 10 1.4.1 Fire Protection Related Submittals PRODUCT DATA FIO
4 21 13 13.00 10 2.3 Materials and Equipment PRODUCT DATA GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
5 21 13 13.00 10 1.6 Spare Parts PRODUCT DATA FIO
6 21 13 13.00 10 3.5 Preliminary Tests PRODUCT DATA GA
7 21 13 13.00 10 3.6 Final Acceptance Test PRODUCT DATA GA
8 21 13 13.00 10 1.4.1 Fire Protection Specialist PRODUCT DATA GA
9 21 13 13.00 10 1.4.2 Sprinkler System Installer PRODUCT DATA GA
10 21 13 13.00 10 1.4.3 Sway Bracing DESIGN DATA GA
11 21 13 13.00 10 1.2.1.3 Hydraulic Calculations DESIGN DATA GA
12 21 13 13.00 10 3.5 Preliminary Test Report TEST REPORTS GA
13 21 13 13.00 10 3.6 Final Acceptance Test Report TEST REPORTS GA
14 21 13 13.00 10 3.6 Operating and Maintenance Manuals O&M DATA GA
SECTION - 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
1 23 00 00 1.4.5 Detail Drawings SHOP DRAWINGS GA
2 23 00 00 2.9.1.1 Metallic Flexible Duct PRODUCT DATA FIO
3 23 00 00 2.9.1.2 Insulated Nonmetallic Flexible Duct Runo PRODUCT DATA FIO
4 23 00 00 2.9.1.2 Duct Connectors PRODUCT DATA FIO
5 23 00 00 2.9.2 Duct Access Doors PRODUCT DATA GA
6 23 00 00 2.9.3 Fire Dampers PRODUCT DATA FIO
7 23 00 00 2.9.4 Manual Balancing Dampers PRODUCT DATA GA
8 23 00 00 2.9.7 Sound Attenuation Equipment PRODUCT DATA FIO
9 23 00 00 2.9.7 Acoustical Duct Liner PRODUCT DATA FIO
10 23 00 00 2.9.8.1 Diffusers PRODUCT DATA FIO
11 23 00 00 2.9.8.2 Registers and Grilles PRODUCT DATA FIO
12 23 00 00 2.9.9 Louvers PRODUCT DATA FIO
13 23 00 00 2.10.1.1 Centrifugal Fans PRODUCT DATA FIO
14 23 00 00 2.11 Air Handling Units PRODUCT DATA GA
15 23 00 00 2.12 Energy Recovery Devices PRODUCT DATA GA
16 23 00 00 1.4.6 Test Procedures PRODUCT DATA FIO
17 23 00 00 1.2.1.2 Diagrams PRODUCT DATA GA
18 23 00 00 3.12 Performance Tests TEST REPORTS GA
19 23 00 00 3.10 Damper Acceptance Test TEST REPORTS GA
20 23 00 00 3.2 Manufacturer's Installation Instructions MFRS INSTR FIO
21 23 00 00 3.14.2 Operation and Maintenance Training MFRS INSTR FIO
22 23 00 00 3.14.1 Operation and Maintenance Manuals O&M DATA FIO
23 23 00 00 2.9.3 Fire Dampers O&M DATA GA
24 23 00 00 2.9.4 Manual Balancing Dampers O&M DATA GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
25 23 00 00 2.10.1.1 Centrifugal Fans O&M DATA GA
26 23 00 00 2.11 Air Handling Units O&M DATA GA
SECTION - 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
1 23 03 00.00 20 2.1.1 Energy Efficient Equipment for Motors CLOSEOUT SUBMTL FIO
2 23 03 00.00 20 2.1.2 Reduce Volatile Organic Compounds (VOC) CLOSEOUT SUBMTL FIO
SECTION - 23 05 48.00 40 VIBRATION AND SEISMIC CTRLS/HVAC PIPING
1 23 05 48.00 40 1.2 Installation Drawings SHOP DRAWINGS GA
2 23 05 48.00 40 1.2 Outline Drawings SHOP DRAWINGS GA
3 23 05 48.00 40 1.2 Equipment and Performance Data PRODUCT DATA GA
4 23 05 48.00 40 2.2.5 Isolators PRODUCT DATA GA
5 23 05 48.00 40 2.4 Type of Isolator TEST REPORTS GA
6 23 05 48.00 40 2.4 Type of Base TEST REPORTS GA
7 23 05 48.00 40 2.4 Allowable Deflection TEST REPORTS GA
8 23 05 48.00 40 2.4 Measured Deflection TEST REPORTS GA
SECTION - 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
1 23 05 93 1.3 Records of Existing Conditions PRECON SUBMTL GA
2 23 05 93 1.3.2 Records of Existing Conditions PRECON SUBMTL GA
3 23 05 93 1.5.3.1 TAB Firm PRECON SUBMTL GA
4 23 05 93 1.2 TAB team assistants PRECON SUBMTL GA
5 23 05 93 1.2 TAB team engineer PRECON SUBMTL GA
6 23 05 93 1.5.3.2 TAB Specialist PRECON SUBMTL GA
7 23 05 93 1.2 TAB team field leader PRECON SUBMTL GA
8 23 05 93 1.3.2 TAB Schematic Drawings and Report Forms SHOP DRAWINGS GA
9 23 05 93 1.3 Equipment and Performance Data PRODUCT DATA GA
10 23 05 93 1.5.3.4 TAB Related HVAC Submittals PRODUCT DATA GA
11 23 05 93 1.5.2 TAB Procedures PRODUCT DATA GA
12 23 05 93 1.5.2 Calibration PRODUCT DATA GA
13 23 05 93 1.3.2 Systems Readiness Check PRODUCT DATA GA
14 23 05 93 1.5.4 TAB Execution PRODUCT DATA GA
15 23 05 93 1.5.4.3 TAB Verification PRODUCT DATA GA
16 23 05 93 1.3.2 Design review report TEST REPORTS GA
17 23 05 93 1.3.2 Design review report TEST REPORTS GA
18 23 05 93 1.7.2.1 Design review report TEST REPORTS GA
19 23 05 93 1.7.2.1 Design review report TEST REPORTS GA
20 23 05 93 1.7.2 Pre-Final DALT report TEST REPORTS GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
21 23 05 93 3.3.5 Pre-Final DALT report TEST REPORTS GA
22 23 05 93 1.7.2 Final DALT report TEST REPORTS GA
23 23 05 93 3.3.8 Final DALT report TEST REPORTS GA
24 23 05 93 1.5.5.2 TAB report for Season 1 TEST REPORTS GA
25 23 05 93 1.5.5.2 TAB report for Season 2 TEST REPORTS GA
26 23 05 93 1.5.3.1 TAB Firm TEST REPORTS GA
27 23 05 93 1.5.1 Independent TAB Agency and Personnel QuaTEST REPORTS GA
28 23 05 93 1.7.2 DALT and TAB Submittal and Work ScheduleTEST REPORTS GA
29 23 05 93 1.7.2.2 Pre-field DALT preliminary notification TEST REPORTS GA
30 23 05 93 1.7.2.3 Pre-field TAB engineering report TEST REPORTS GA
31 23 05 93 1.7.2 Advanced notice for Season 1 TAB field TEST REPORTS GA
SECTION - 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
1 23 07 00 3.2 Duct Insulation Systems SHOP DRAWINGS FIO
2 23 07 00 1.4.2 Certification PRODUCT DATA FIO
3 23 07 00 3.2 Duct Insulation Systems PRODUCT DATA GA
4 23 07 00 2.2.1.3 Thermal Insulation SAMPLES GA
5 23 07 00 3.2 Duct Insulation Systems MFRS INSTR GA
SECTION - 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
1 23 09 00 3.2 DDC Contractor Design Drawings SHOP DRAWINGS GA
2 23 09 00 3.2 Final As-Built Drawings SHOP DRAWINGS GA
3 23 09 00 1.8.4 Certificate of Networthiness Documentati PRODUCT DATA GA
4 23 09 00 1.8.1 Programming Software PRODUCT DATA GA
5 23 09 00 1.8.2 Controller Application Programs PRODUCT DATA GA
6 23 09 00 2.2 Manufacturer's Product Data PRODUCT DATA GA
7 23 09 00 2.2.1 XIF files PRODUCT DATA GA
8 23 09 00 3.4.3 Draft LNS Database PRODUCT DATA GA
9 23 09 00 3.5.4 Final LNS Database PRODUCT DATA GA
10 23 09 00 1.8.3 LNS Plug-ins PRODUCT DATA GA
11 23 09 00 3.4.2 Start-Up Testing Report TEST REPORTS GA
12 23 09 00 3.5.1 PVT Procedures TEST REPORTS GA
13 23 09 00 3.5.3 PVT Report TEST REPORTS GA
14 23 09 00 1.9.1 Pre-Construction Quality Control (QC) Ch TEST REPORTS GA
15 23 09 00 1.9.2 Post-Construction Quality Control (QC) C TEST REPORTS GA
16 23 09 00 3.6 Operation and Maintenance (O&M) Instruct O&M DATA GA
17 23 09 00 3.8.1 Training Documentation O&M DATA GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
18 23 09 00 2.5 Enclosure Keys CLOSEOUT SUBMTL GA
19 23 09 00 3.1.6.1 Password Summary Report CLOSEOUT SUBMTL GA
20 23 09 00 1.9.3 Closeout Quality Control (QC) Checklist CLOSEOUT SUBMTL GA
SECTION - 23 23 00 REFRIGERANT PIPING
1 23 23 00 2.3 Refrigerant Piping System SHOP DRAWINGS GA
2 23 23 00 2.3 Refrigerant Piping System PRODUCT DATA FIO
3 23 23 00 1.5.2 Spare Parts PRODUCT DATA FIO
4 23 23 00 1.3.1 Qualifications PRODUCT DATA FIO
5 23 23 00 3.5 Refrigerant Piping Tests PRODUCT DATA FIO
6 23 23 00 3.1 Verification of Dimensions PRODUCT DATA FIO
7 23 23 00 3.5 Refrigerant Piping Tests TEST REPORTS FIO
8 23 23 00 2.1 Service Organization CERTIFICATES FIO
9 23 23 00 1.5 Maintenance O&M DATA GA
10 23 23 00 3.4 Operation and Maintenance Manuals O&M DATA GA
11 23 23 00 3.4 Demonstrations O&M DATA GA
SECTION - 26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
1 26 05 00.00 40 2.1 Material, Equipment, and Fixture Lists PRECON SUBMTL GA
2 26 05 00.00 40 2.1.1 Conduits and Raceways PRODUCT DATA GA
3 26 05 00.00 40 2.1.2 Wire and Cable PRODUCT DATA GA
4 26 05 00.00 40 3.2.1.8 Splices and Connectors PRODUCT DATA GA
5 26 05 00.00 40 2.1.3 Switches PRODUCT DATA GA
6 26 05 00.00 40 2.1.4 Receptacles PRODUCT DATA GA
7 26 05 00.00 40 2.1.5 Outlets, Outlet Boxes, and Pull Boxes PRODUCT DATA GA
8 26 05 00.00 40 2.1.7 Circuit Breakers PRODUCT DATA GA
9 26 05 00.00 40 2.1.6 Panelboards PRODUCT DATA GA
10 26 05 00.00 40 2.1.8 Lamps and Lighting Fixtures PRODUCT DATA GA
11 26 05 00.00 40 3.3 Continuity Test TEST REPORTS GA
12 26 05 00.00 40 3.3 Phase-Rotation Tests TEST REPORTS GA
13 26 05 00.00 40 3.3 Insulation Resistance Test TEST REPORTS GA
14 26 05 00.00 40 1.4 Certification CERTIFICATES GA
15 26 05 00.00 40 Part 2 Manufacturer's Instructions MFRS INSTR GA
SECTION - 26 20 00 INTERIOR DISTRIBUTION SYSTEM
1 26 20 00 2.12 Panelboards SHOP DRAWINGS GA
2 26 20 00 3.1.8.1 Marking strips SHOP DRAWINGS GA
3 26 20 00 2.11 Receptacles PRODUCT DATA GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
4 26 20 00 2.12.3 Circuit breakers PRODUCT DATA GA
5 26 20 00 2.9 Switches PRODUCT DATA GA
6 26 20 00 2.13 Enclosed circuit breakers PRODUCT DATA GA
7 26 20 00 2.14 Manual motor starters PRODUCT DATA GA
8 26 20 00 3.5.2 600-volt wiring test TEST REPORTS GA
9 26 20 00 3.5.4 Grounding system test TEST REPORTS GA
10 26 20 00 3.5.3 Ground-fault receptacle test TEST REPORTS GA
11 26 20 00 2.10 Fuses CERTIFICATES GA
12 26 20 00 1.5.1 Electrical Systems CERTIFICATES GA
SECTION - 26 24 16.00 40 PANELBOARDS
1 26 24 16.00 40 2.1.1 Detail Drawings SHOP DRAWINGS GA
2 26 24 16.00 40 2.1.1 Outline Drawings SHOP DRAWINGS GA
3 26 24 16.00 40 1.3 Panelboards PRODUCT DATA GA
4 26 24 16.00 40 2.1.1 Panelboards PRODUCT DATA GA
5 26 24 16.00 40 2.1.3 Directory Card and Holder PRODUCT DATA GA
6 26 24 16.00 40 3.2 Continuity Tests TEST REPORTS GA
7 26 24 16.00 40 3.2 Insulation Tests TEST REPORTS GA
8 26 24 16.00 40 1.4 Statements CERTIFICATES GA
9 26 24 16.00 40 1.3 Panelboards MFRS INSTR GA
10 26 24 16.00 40 2.1.1 Panelboards MFRS INSTR GA
SECTION - 26 53 00.00 40 EXIT SIGNS
1 26 53 00.00 40 1.2.1 Material, Equipment, and Fixture Lists PRECON SUBMTL GA
2 26 53 00.00 40 1.2.1 Exit Lighting Units SHOP DRAWINGS GA
3 26 53 00.00 40 1.2.1 Exit Lighting Units Outline Drawings SHOP DRAWINGS FIO
4 26 53 00.00 40 1.2.1 Exit Lighting Units PRODUCT DATA GA
5 26 53 00.00 40 1.2.1 Accessories PRODUCT DATA GA
6 26 53 00.00 40 3.2.1 Operational Tests TEST REPORTS GA
7 26 53 00.00 40 1.2.1 Energy Efficiencies CERTIFICATES GA
SECTION - 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
1 28 31 76 2.1.2 Nameplates SHOP DRAWINGS GA
2 28 31 76 2.13.10 Instructions SHOP DRAWINGS GA
3 28 31 76 3.2.1 Wiring Diagrams SHOP DRAWINGS GA
4 28 31 76 1.2.1 System Layout SHOP DRAWINGS GA
5 28 31 76 2.3 System Operation SHOP DRAWINGS GA
6 28 31 76 2.16 Notification Appliances SHOP DRAWINGS GA
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
7 28 31 76 2.14 Amplifiers SHOP DRAWINGS GA
8 28 31 76 1.6 Technical Data And Computer Software PRODUCT DATA GA
9 28 31 76 2.13 Fire Alarm Control Unit and Mass Notific PRODUCT DATA GA
10 28 31 76 3.2.2 Terminal cabinets PRODUCT DATA GA
11 28 31 76 2.15 Manual stations PRODUCT DATA GA
12 28 31 76 2.12.1 Batteries PRODUCT DATA GA
13 28 31 76 2.12.2 Battery chargers PRODUCT DATA GA
14 28 31 76 2.10 Smoke sensors PRODUCT DATA GA
15 28 31 76 2.16 Notification appliances PRODUCT DATA GA
16 28 31 76 2.7 Addressable interface devices PRODUCT DATA GA
17 28 31 76 2.14 Amplifiers PRODUCT DATA GA
18 28 31 76 2.14 Tone generators PRODUCT DATA GA
19 28 31 76 2.14 Digitalized voice generators PRODUCT DATA GA
20 28 31 76 1.4.4 Local Operating Console (LOC) PRODUCT DATA GA
21 28 31 76 2.12.1.2 Battery power DESIGN DATA GA
22 28 31 76 2.12.2 Battery chargers DESIGN DATA GA
23 28 31 76 3.7 Field Quality Control TEST REPORTS FIO
24 28 31 76 3.7.1 Testing Procedures TEST REPORTS GA
25 28 31 76 2.10.4 Smoke sensor testing TEST REPORTS GA
26 28 31 76 1.7.1.4 Installer CERTIFICATES FIO
27 28 31 76 3.7.2.2 Formal Inspection and Tests CERTIFICATES FIO
28 28 31 76 3.7.2.3 Final Testing CERTIFICATES FIO
29 28 31 76 2.3 System Operation MFRS FLD REPT GA
30 28 31 76 1.7.2.2 Fire Alarm/Mass Notification System MFRS FLD REPT FIO
31 28 31 76 3.10 Operation and Maintenance (O&M) Instruct O&M DATA GA
32 28 31 76 3.8 Instruction of Government Employees O&M DATA GA
33 28 31 76 3.7.2.4 As-Built Drawings CLOSEOUT SUBMTL FIO
SECTION - 31 00 00 EARTHWORK
1 31 00 00 3.8 Utilization of Excavated Materials PRODUCT DATA GA
2 31 00 00 3.15 Testing TEST REPORTS FIO
3 31 00 00 2.1 Borrow Site Testing TEST REPORTS FIO
4 31 00 00 3.15 Testing CERTIFICATES FIO
SECTION - 31 32 11 SOIL SURFACE EROSION CONTROL
1 31 32 11 2.1.3 Mulch Control Netting and Filter Fabric PRODUCT DATA FIO
2 31 32 11 2.3 Erosion Control Blankets PRODUCT DATA FIO
ACTIVITY
No.
TRANS-
MITTAL
No.
ITEM
No.
SPEC
PARAGRAPH
No.
DESCRIPTION OF
SUBMITTAL
TYPE OF SUBMITTAL
CLASSI-
FICATION
FIO
GA, DA,
CR, or S
REVIEWER
OFFICE / NAME
CONTRACTOR
SCHEDULE DATES
CONTRACTOR
ACTION
GOVERNMENT
ACTION
SUBMIT
NEEDED
BY
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
CODE
CORPS
RECEIVED
DATE
CODE
CORPS
RETURNED
DATE
SF-00005-16,RENOVATE STORAGE BLDG 0-1908
W912PM-16-B-0028 NA
30 Aug 2016
SORT : SECTION & ITEMRANGE : ALL
3 31 32 11 2.2 Geotextile Fabrics PRODUCT DATA FIO
4 31 32 11 1.2 Equipment PRODUCT DATA FIO
SECTION - 32 92 19 SEEDING
1 32 92 19 2.2.1 Topsoil composition tests TEST REPORTS FIO
2 32 92 19 2.1 seed CERTIFICATES FIO
SECTION - 33 11 00 WATER DISTRIBUTION
1 33 11 00 2.2 Pipe, Fittings, Joints and Couplings PRODUCT DATA GA
2 33 11 00 2.3 Valves PRODUCT DATA GA
3 33 11 00 2.3.3 Valve Boxes PRODUCT DATA FIO
4 33 11 00 2.4.1 Hydrants PRODUCT DATA GA
5 33 11 00 2.5.1 Tapping Sleeves PRODUCT DATA GA
6 33 11 00 3.2.7 Bacteriological Samples TEST REPORTS GA
7 33 11 00 2.2 Pipe, Fittings, Joints and Couplings CERTIFICATES FIO
8 33 11 00 2.2.1.1 Lining CERTIFICATES FIO
9 33 11 00 2.2.1.1 Lining CERTIFICATES FIO
10 33 11 00 2.2.2.1.1 Lining for Fittings CERTIFICATES FIO
11 33 11 00 2.3 Valves CERTIFICATES FIO
12 33 11 00 2.4.1 Hydrants CERTIFICATES FIO
13 33 11 00 1.3.2.1.2 Backflow Prevention Training Certificate CERTIFICATES FIO
14 33 11 00 1.3.2.1.1 Backflow Tester CERTIFICATES FIO
15 33 11 00 3.2.7 Disinfection Procedures CERTIFICATES FIO
16 33 11 00 3.2.1 Manufacturer's Instructions MFRS INSTR FIO
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 30 53
MISCELLANEOUS CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.4.1 Regulatory Requirements
1.4.2 Flatness and Levelness of Floor Slabs
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
2.1.1 Strength
2.1.2 Construction Tolerances
2.1.3 Concrete Mixture Proportions
2.2 MATERIALS
2.2.1 Cementitious Materials
2.2.1.1 Portland Cement
2.2.1.2 Pozzolan
2.2.2 Aggregates
2.2.3 Admixtures
2.2.3.1 Air-Entraining Admixture
2.2.3.2 Accelerating Admixture
2.2.3.3 Water-Reducing or Retarding Admixture
2.2.4 Water
2.2.5 Reinforcing Steel
2.2.6 Expansion Joint Filler Strips, Premolded
2.2.7 Joint Sealants - Field Molded Sealants
2.2.8 Formwork
2.2.9 Form Coatings
2.2.10 Curing Materials
2.3 READY-MIX CONCRETE
2.4 ACCESSORIES
2.4.1 Curing Compound
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Embedded Items
3.1.2 Formwork Installation
3.1.3 Production of Concrete
3.1.3.1 Ready-Mixed Concrete
3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing
3.2 CONVEYING AND PLACING CONCRETE
3.2.1 Cold-Weather Requirements
3.2.2 Hot-Weather Requirements
SECTION 03 30 53 Page 1 (ADDED: Amendment 0003)
3.3 FINISHING
3.3.1 Temperature Requirement
3.3.2 Finishing Formed Surfaces
3.3.3 Finishing Unformed Surfaces
3.3.3.1 Flat Floor Finishes
3.3.3.2 Measurement of Floor Tolerances
3.3.3.3 Expansion and Contraction Joints
3.4 CURING AND PROTECTION
3.5 FORM WORK
3.5.1 Removal of Forms
3.6 STEEL REINFORCING
3.6.1 Fabrication
3.6.2 Splicing
3.6.3 Supports
3.7 EMBEDDED ITEMS
3.8 TESTING AND INSPECTING
3.8.1 Field Testing Technicians
3.8.2 Preparations for Placing
3.8.3 Sampling and Testing
3.8.4 Action Required
3.8.4.1 Placing
3.8.4.2 Air Content
3.8.4.3 Slump
-- End of Section Table of Contents --
SECTION 03 30 53 Page 2
****Amendment 0003****
SECTION 03 30 53
MISCELLANEOUS CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 SUMMARY
Perform all work in accordance with ACI 318.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 301 (2010; ERTA 2015) Specifications for Structural Concrete
ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 306R (2010) Guide to Cold Weather Concreting
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016) Building Code Requirements for Structural Concrete and Commentary
ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM A1064/A1064M (2015) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A615/A615M (2015a; E 2015) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
SECTION 03 30 53 Page 3
ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete
ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2015) Standard Specification for Portland Cement
ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM C172/C172M (2014a) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C31/C31M (2015a; E 2016) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates
ASTM C39/C39M (2015a) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C494/C494M (2015a) Standard Specification for Chemical Admixtures for Concrete
ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
SECTION 03 30 53 Page 4
ASTM C685/C685M (2014) Concrete Made by Volumetric Batching and Continuous Mixing
ASTM C920 (2014a) Standard Specification for Elastomeric Joint Sealants
ASTM C94/C94M (2015) Standard Specification for Ready-Mixed Concrete
ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion
ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates
ASTM D98 (2015) Calcium Chloride
ASTM E1155 (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM E1155M (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers (Metric)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings; G
SD-03 Product Data
Air-Entraining Admixture Accelerating Admixture Water-Reducing or Retarding Admixture Curing Materials Expansion Joint Filler Strips, Premolded Joint Sealants - Field Molded Sealants Conveying and Placing Concrete Formwork Mix Design Data; G Ready-Mix Concrete; G Curing Compound; G Mechanical Reinforcing Bar Connectors
SECTION 03 30 53 Page 5
SD-06 Test Reports
Aggregates Concrete Mixture Proportions; G Measurement of Floor Tolerances Compressive Strength Testing; G Slump; G Air Content Water
SD-07 Certificates
Cementitious Materials Aggregates Delivery Tickets
SD-08 Manufacturer's Instructions
Curing Compound
1.4 QUALITY ASSURANCE
Indicate specific locations of Concrete Placement, Steel Reinforcement, Expansion Joints, and Control Joints on installation drawings and include, but not be limited to, square feet of concrete placements, thicknesses and widths, plan dimensions, and arrangement of cast-in-place concrete section.
1.4.1 Regulatory Requirements
The state statutory and regulatory requirements form a part of this specification to the extent required.
1.4.2 Flatness and Levelness of Floor Slabs
Conduct floor flatness and levelness test, (FF and FL respectively), on floor slabs in accordance with the provisions set forth in ASTM E1155M or ASTM E1155. Make floor tolerance measurements by the approved laboratory and inspection service within 24 hours after completion of final troweling operation and before forms and shores have been removed. Provide results of floor tolerance tests, including formal notice of acceptance or rejection of the work, to the Contracting Officer within 24 hours after data collection.
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
The Government retains the option to sample and test aggregates and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Obtain samples of aggregates at the point of batching in accordance with ASTM D75/D75M. Sample concrete in accordance with ASTM C172/C172M. Determine slump and air content in accordance with ASTM C143/C143M and ASTM C231/C231M, respectively, when cylinders are molded. Prepare, cure, and transport compression test specimens in accordance with ASTM C31/C31M. Test compression test specimens in accordance with ASTM C39/C39M. Take samples for strength tests not less than once each shift in which concrete is produced. Provide
SECTION 03 30 53 Page 6 a minimum of five specimens from each sample; two to be tested at 28 days (90 days if pozzolan is used) for acceptance, two will be tested at 7 days for information and one held in reserve.
2.1.1 Strength
Acceptance test results are the average strengths of two specimens tested at 28 days (90 days if pozzolan is used). The strength of the concrete is considered satisfactory so long as the average of three consecutive acceptance test results equal or exceed the specified compressive strength, f'c, but not more than 20 percent, and no individual acceptance test result falls below f'c by more than 500 psi.
2.1.2 Construction Tolerances
Apply a Class "C" finish to all surfaces except those specified to receive a Class "D" finish. Apply a Class "D" finish to all post-construction surfaces which will be permanently concealed. Surface requirements for the classes of finish required are as specified in ACI 117.
2.1.3 Concrete Mixture Proportions
Concrete mixture proportions are the responsibility of the Contractor.
Mixture proportions must include the dry weights of cementitious material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is 3,000 psi at 28 days (90 days if pozzolan is used). The maximum nominal size coarse aggregate is 3/4 inch, in accordance with ACI 304R.