AMENDMENT0002

View the file

Other files

File Type Posted
Bid_Abstract_Afetr_Bid_Opening.pdf PDF
W912PM-13-B-0006-0002_Conformed_Copy.pdf PDF
FY14_EII_Amd2_Plans.pdf PDF
Site_Visit_Sign-In.pdf PDF
EI_FY14_Amd1_Plans.pdf PDF
EII_FY14_Amendment0001.pdf PDF
FY14_EagleIsland_AdvPlans.pdf PDF
FY14_EI_ADV_SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation Number W912PM-13-B-0006, Wilmington Harbor Eagle Island DA Improvements 2014, New Hanover and Brunsw ick Counties, North Carolina, is amended as follow s:

See attached Summary of Changes.

The date and time for receipt of bids has NOT changed.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Sep-2013

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM-13-B-0006

X 9B. DATED (SEE ITEM 11)

19-Aug-2013

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Sep-2013

CODE

U S ARMY CORPS OF ENGINEERS

WILMINGTON DISTRICT

ATTN: CHARLENNE FIGGINS

69 DARLINGTON AVE

WILMINGTON NC 28403-1343

W912PM 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PM-13-B-0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 18-Sep-2013 12:00 AM to 18-Sep-2013 02:00 PM.

CLIN 0005

This CLIN has been renumbered to CLIN 0007.

CLIN 0005 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0005 1 Lump Sum Spillway 3

In accordance with plans and specifications.

FOB: Destination

NET AMT

CLIN 0006 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006 7 Each Spillway Riser Safety Modifications

Spillways 1, 4, 5, 6, 7, 8 and 9 in accordance with plans and specifications.

FOB: Destination

NET AMT

INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0005:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

The following Acceptance/Inspection Schedule was added for CLIN 0006:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

W912PM-13-B-0006

The following have been modified:

TOTAL AMOUNT OF LINE ITEMS 0001 - 0007

W912PM‐13‐B‐0006

SUMMARY OF CHANGES

PROJECT TABLE OF CONTENTS

Delete existing Project Table of Contents and replace with enclosed revised Project Table of Contents.

SECTION 00 01 15 – LIST OF DRAWINGS

Delete existing pages 2 and 3 and replace with enclosed revised pages 2 and 3.

SECTION 01 11 00 – SUMMARY OF WORK

Delete existing page 3 and replace with enclosed revised page 3.

SECTION 01 33 00 – SUBMITTAL PROCEDURES

Delete existing Attachment 1 submittal register ENG 4288 (pages 1 and 2) and replace with enclosed revised submittal register ENG 4288 (pages 1 and 2).

SECTION 31 05 21 – GEOGRID

Add section in its entirety.

SECTION 31 05 22 – GEOTEXTILE

Delete existing pages 4 and 5 and replace with enclosed revised pages 4 and 5.

SECTION 33 40 02 – SPILLWAY SYSTEM

Delete existing pages 7, 8, and 9 and replace with enclosed revised pages 7, 8, and 9.

W912PM‐13‐B‐0006

NOTE:

Text that is added or revised by this amendment is replaced in its entirety and underlined and/or printed in bold and/or stamped appropriately.

The text changes may have necessitated reformatting of subsequent text or pages. If this is the case, those pages have also been issued as amended pages but are not underlined or bold text.

DRAWINGS

(1) Delete plates G‐1, G‐2, S‐1, and S‐6 in their entirety and replace with enclosed revised plates G‐1, G‐

2, S‐1, and S‐6.

(2) Add plates C‐9, C‐10, and S‐9 in their entirety.

(3) PEN AND INK CHANGE – There are now 21 drawings in the set, so all drawing sheet numbers should read “of 21” AND sheets are now renumbered beginning at the new plate C‐9 through the new plate S‐9

– See the index sheet, plate G‐1, for the correct order of drawings.

(End of Summary of Changes)

Encls

(As stated)

FY 14 Eagle Island DA Improvements W912PM-13-B-0006 Brunswick Co, NC

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00010 SOLICITATION CONTRACT FORM

00100 BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

00600 REPRESENTATIONS & CERTIFICATIONS

00700 CONTRACT CLAUSES

00800 SPECIAL CONTRACT REQUIREMENTS

00 01 15 LIST OF DRAWINGS

00 73 00 SUPPLEMENTARY CONDITIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)

01 45 01 USACE QUALITY CONTROL

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 31 - EARTHWORK

31 01 00 DIKE EMBANKMENT

31 05 21 GEOGRID

31 05 22 GEOTEXTILE

31 11 00.10 CLEARING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWER

33 40 02 SPILLWAY SYSTEM

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1 Revised by Amendment 0002

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

PLATE

NO.

SHEET

NO.

TITLE

COVER

G-1 1 INDEX OF DRAWINGS

G-2 2 LOCATION MAP

C-1 3 SEDIMENT AND EROSION CONTROL PLAN - CELL 3 SPILLWAYS

C-2 4 SEDIMENT AND EROSION CONTROL - DETAILS

C-3 5 DEMOLITION PROFILE AND NEW PROFILE - SPILLWAY 7

C-4 6 SITE PLAN - SPILLWAY 7

C-5 7 PROFILE - SPILLWAY 8

C-6 8 SITE PLAN - SPILLWAY 8

C-7 9 PROFILE - SPILLWAY 9

C-8 10 SITE PLAN - SPILLWAY 9

C-9 11 SITE PLAN - SPILLWAY 3

C-10 12 DEMOLITION PROFILE AND NEW PROFILE SPILLWAY 3

S-1 13 SPILLWAY DETAILS, EXCAVATION

S-2 14 SPILLWAY DETAILS

S-3 15 4X8 SPILLWAY DETAILS - SHEET 1 OF 4

S-4 16 4X8 SPILLWAY DETAILS - SHEET 2 OF 4

DOCUMENT 00 01 15 Page 2

PLATE

NO.

SHEET

NO.

TITLE

S-5 17 4X8 SPILLWAY DETAILS - SHEET 3 OF 4

S-6 18 4X8 SPILLWAY DETAILS - SHEET 3 OF 4

S-7 19 STEEL WALKWAY DETAILS

S-8 20 STEEL WALKWAY SUPPORT DETAILS

S-9 21 SPILLWAY DETAILS EXCAVATION

1.3 SUPPLEMENTARY DRAWING

The supplementary drawings may not be a part of the contract but are included with the drawings for information.

1.3.1 Reference Drawings

The reference drawings (Plates R-1 through R-3) provided are intended only to show the original construction. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract.

REF PLATE

NO.

REFERENCE TITLE

R-1 PIPE SADDLE DETAILS

R-2 MISCELLANEOUS DETAILS

R-3 SADDLE SUPPORT DETAIL

-- End of Document --

DOCUMENT 00 01 15 Page 3

g. Demolition Spillway 3 - The Contractor shall remove and dispose the 30-inch OD steel spillway pipe, anti seep collar, concrete pipe saddle, and timber pipe support frames. The 30-inch HDPE pipe shall be removed and transported to a safe location on site for storage until it is to be reinstalled.

h. Modify Existing Spillway Risers for Spillways 1, 4, 5, and 6. The Contractor shall fabricate modifications to the steel spillway riser boxes as shown on the contract drawings. Modifications include installation of:

access hatch door, fixed vertical ladder, and confined space entry and rescue system equipment.

1.1.2 Location

The project is located within Brunswick County, North Carolina. U.S.

Highways 17, 74, 76 and 421 as well as North Carolina Highway 133 serve the general area where the work will be performed.

1.2 OCCUPANCY OF PREMISES

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.3 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, and Improvements" the Contractor shall:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause "FAR 52.245-2, Government Property (Fixed Price Contracts)" the Government will furnish materials for installation by the Contractor. Government furnished property is listed in spec section 01 10 00.10 38, paragraph IDENTIFICATION OF GOVERNMENT FURNISHED PROPERTY.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SUBMITTAL REGISTER (ER 415-1-10) TITLE AND LOCATION DATE

CONTRACTOR CONTRACT NUMBER

ACTIVITY

No.

TRANS-

MITTAL

No.

ITEM

No.

SPEC

PARAGRAPH

No.

DESCRIPTION OF

SUBMITTAL

TYPE OF SUBMITTAL

CLASSI-

FICATION

FIO

GA, DA

or CR

REVIEWER

OFFICE / NAME

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

GOVERNMENT

ACTION

SUBMIT

NEEDED

BY

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

CODE

CORPS

RECEIVED

DATE

CODE

CORPS

RETURNED

DATE

Eagle Island Improvements FY14

W912PM-13-B-0006 NA

09 Sep 2013

SORT : SECTION & ITEMRANGE : ALL

SECTION - 01 10 00.10 38 SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

1 01 10 00.10 38 1.16 List of Subcontractors PRECON SUBMTL FIO

2 01 10 00.10 38 1.3 Progress Chart PRECON SUBMTL GA

3 01 10 00.10 38 1.16 Quality Control Plan PRECON SUBMTL GA

4 01 10 00.10 38 1.16 Certificate of Insurance CERTIFICATES FIO

5 01 10 00.10 38 1.16 Completion of Corps CQC Course CERTIFICATES FIO

6 01 10 00.10 38 1.16 Letter Appointing Superintendent CERTIFICATES FIO

7 01 10 00.10 38 1.15 testing facilities CERTIFICATES GA

SECTION - 01 33 00 SUBMITTAL PROCEDURES

1 01 33 00 1.8 Submittal Register PRECON SUBMTL GA

2 01 33 00 1.4 Delegation of Authority PRECON SUBMTL GA

SECTION - 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

1 01 35 26 1.6 Accident Prevention Plan (APP) PRECON SUBMTL GA

2 01 35 26 1.5.1.2 Crane Operators PRECON SUBMTL GA

3 01 35 26 1.5.1.1 Site Safety and Health Officer PRECON SUBMTL GA

4 01 35 26 1.7 Activity Hazard Analysis (AHA) DESIGN DATA GA

5 01 35 26 1.6.1 Crane Critical Lift Plan DESIGN DATA GA

6 01 35 26 1.12 Notifications and Reports TEST REPORTS FIO

7 01 35 26 1.12.2 Accident Reports TEST REPORTS FIO

8 01 35 26 1.12.3 Crane Reports TEST REPORTS FIO

9 01 35 26 1.8 Confined Space Entry Permit CERTIFICATES FIO

10 01 35 26 1.8 Hot work permit CERTIFICATES FIO

11 01 35 26 3.5.1 License CERTIFICATES FIO

12 01 35 26 1.12.4 Certificate of Compliance CERTIFICATES FIO

SECTION - 01 57 20.00 10 ENVIRONMENTAL PROTECTION

1 01 57 20.00 10 1.8 Environmental Protection Plan PRECON SUBMTL GA

SECTION - 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

1 01 57 23 1.3 Erosion and Sediment Controls TEST REPORTS FIO

2 01 57 23 2.1.4 Mill Certificate or Affidavit CERTIFICATES FIO

SECTION - 02 41 00 DEMOLITION

1 02 41 00 1.6.1 Existing Conditions PRECON SUBMTL GA

2 02 41 00 1.8 Work Plan SHOP DRAWINGS GA

SECTION - 31 01 00 DIKE EMBANKMENT

1 31 01 00 1.5.2 Acceptance Section Work Plan PRECON SUBMTL GA

2 31 01 00 1.6 Heavy Equipment PRODUCT DATA FIO

K7IMIMSJ

Typewritten Text Revised by Amendment0002

K7IMIMSJ

Typewritten Text

SUBMITTAL REGISTER (ER 415-1-10) TITLE AND LOCATION DATE

CONTRACTOR CONTRACT NUMBER

ACTIVITY

No.

TRANS-

MITTAL

No.

ITEM

No.

SPEC

PARAGRAPH

No.

DESCRIPTION OF

SUBMITTAL

TYPE OF SUBMITTAL

CLASSI-

FICATION

FIO

GA, DA

or CR

REVIEWER

OFFICE / NAME

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

GOVERNMENT

ACTION

SUBMIT

NEEDED

BY

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

CODE

CORPS

RECEIVED

DATE

CODE

CORPS

RETURNED

DATE

Eagle Island Improvements FY14

W912PM-13-B-0006 NA

09 Sep 2013

SORT : SECTION & ITEMRANGE : ALL

3 31 01 00 3.8 Testing TEST REPORTS FIO

4 31 01 00 3.8 Testing Laboratory CERTIFICATES FIO

SECTION - 31 05 21 GEOGRID SOIL REINFORCEMENT

1 31 05 21 1.3 Geogrid PRODUCT DATA FIO

SECTION - 31 05 22 GEOTEXTILES

1 31 05 22 1.3 Certificate of Compliance CERTIFICATES GA

SECTION - 31 11 00.10 CLEARING

1 31 11 00.10 3.2.1 Burn Plan SHOP DRAWINGS GA

2 31 11 00.10 3.2.2 Burn Plan SHOP DRAWINGS GA

SECTION - 32 92 19 SEEDING

1 32 92 19 2.5.3 Wood cellulose fiber mulch PRODUCT DATA FIO

2 32 92 19 2.4 Fertilizer PRODUCT DATA FIO

3 32 92 19 3.6 Seed Establishment Period PRODUCT DATA FIO

4 32 92 19 2.1 seed CERTIFICATES FIO

SECTION - 33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWER

1 33 34 00 3.2 Hydrostatic Tests TEST REPORTS FIO

SECTION - 33 40 02 SPILLWAY SYSTEM

1 33 40 02 2.1.3.6 Thickness PRECON SUBMTL GA

2 33 40 02 2.1.3 Coating System PRECON SUBMTL GA

3 33 40 02 2.7 Concrete PRECON SUBMTL GA

4 33 40 02 2.8 Reinforcing Steel SHOP DRAWINGS FIO

5 33 40 02 2.1 Spillway SHOP DRAWINGS GA

6 33 40 02 2.2 Spillway Pipe SHOP DRAWINGS GA

7 33 40 02 2.1.4.1 Ladders SHOP DRAWINGS GA

8 33 40 02 2.1.4.2 Confined Space Entry and Rescue System E SHOP DRAWINGS GA

9 33 40 02 2.2.2 Screen PRODUCT DATA GA

10 33 40 02 2.2.1 High Density Polyethylene (HDPE) Pipe PRODUCT DATA GA

11 33 40 02 2.1.4.3 Access Hatch Door PRODUCT DATA GA

K7IMIMSJ

Typewritten Text Revised by Amendment0002

SECTION TABLE OF CONTENTS

DIVISION 31 - EARTHWORK

SECTION 31 05 21

GEOGRID

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 SUBMITTALS

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Geogrid

2.1.2 Mat Base

PART 3 EXECUTION

3.1 DELIVERY, STORAGE AND HANDLING

3.2 PLACEMENT

3.2.1 Clearing

3.2.2 Geogrid

3.2.3 Mat Base

3.2.4 Repairs to Geogrid

3.3 MEASUREMENT AND PAYMENT

-- End of Section Table of Contents --

SECTION 31 05 21 Page 1

SECTION 31 05 21

GEOGRID

PART 1 GENERAL

1.1 SCOPE

The work covered by this section of the specifications consists of furnishing all labor, equipment, supplies, materials, tools, and incidentals to furnish and install a geogrid-reinforced mat base as specified.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 4595 (1986; R 2001) Tensile Properties of Geotextiles by the Wide-Width Strip Method

ASTM D 4751 (2004) Determining Apparent Opening Size of a Geotextile

ASTM D 4759 (2002) Determining the Specification Conformance of Geosynthetics

GEOSYNTHETIC INSTITUTE (GSI)

GSI GRI GG1 (1987; R 1988) Geogrid Rib Tensile Strength

GSI GRI GC7 (1997) Determination of Adhesion and Bond Strength of Geocomposites

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Geogrid

Submit manufacturer's written descriptive literature, specifications, performance test data, instructions, installation recommendations and repair procedures for the geogrid.

SECTION 31 05 21 Page 2

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Geogrid

The material shall be a polymer grid structure specifically manufactured for use as soil reinforcement with high tensile strength in two perpendicular directions (biaxial). The geogrid must be evaluated based on testing of the total structure and not based on simply adding the values of the individual components. The geogrid shall meet the following minimum average roll value (MARV) criteria (ASTM D 4759):

PHYSICAL PROPERTY TEST METHOD MINIMUM AVG. ROLL VALUE

As Measured by Calibers

Aperture Size --- 0.5 to 2.0 in.

Min. Open Area ASTM D 4751 50 to 80 percent Min. Strength ASTM D 4595 @2% Strain 280 lb/ft @5% Strain 580 lb/ft Node Junction Strength GSI GRI GC7 500 lb/ft Tensile Modulus GSI GRI GG1 14,000 lb/ft

In machine and cross machine directions, no offset allowance nor preloading permitted.

2.1.2 Mat Base

Mat base material shall be as specified in Section 31 01 00: DIKE

EMBANKMENT.

PART 3 EXECUTION

3.1 DELIVERY, STORAGE AND HANDLING

The geogrid materials shall be packaged, shipped, stored and handled ensuring that no damage is incurred. Materials shall be delivered only after the required submittals have been received and approved by the Contracting Officer. The Contractor shall be responsible for keeping the geogrid free of dirt, dust, soil, or any other foreign materials. The geogrid shall be protected from ultraviolet exposure during manufacture, shipping and at all storage locations. The geogrid shall not be exposed to ultraviolet light for more than 14 days. All geogrid material found to be damaged shall be replaced with new material at the Contractor's expense.

Each roll shall be labeled with the Manufacturer's name, product identification, lot number, roll number, and roll dimensions.

3.2 PLACEMENT

The Contractor shall furnish to the Contracting Officer the manufacturer's written installation procedures for the geogrid upon delivery of this material to the site. Placement shall be in accordance with the manufacturer's installation procedures or modifications thereto as approved by the Contracting Officer, as required to ensure that the geogrid provides total coverage of the existing ground within the required placement limits.

SECTION 31 05 21 Page 3

3.2.1 Clearing

Clearing of the dike embankment footprint area to accept the geogrid shall be as specified in Section 31 11 00.10: CLEARING.

3.2.2 Geogrid

After the footprint area has been cleared as specified and approved by the Contracting Officer, the Contractor shall place the geogrid directly upon the cleared surface leaving it relatively smooth and free from excessive undulations. The geogrid shall be unrolled in a direction perpendicular to the centerline of the embankment and overlapped 3 feet along the sides and ends of adjacent geogrids. Due to the soft nature of the existing ground it may be necessary to physically tie adjacent geogrids to each other to ensure proper overlap after placement of the layer of coarse-grained material.

3.2.3 Mat Base

After the geogrid has been placed as specified, coarse-grained material shall be placed carefully upon it. Equipment used to place and distribute the coarse-grained material shall comply with the requirements specified in Section 31 01 00: DIKE EMBANKMENT, paragraph EQUIPMENT, subparagraphs "Dike Embankment" and "Mat Base". The total thickness of the cohesionless mat base layer shown in the plans shall be placed in a single lift to minimize disturbance of the underlying geogrid and foundation by the equipment.

Care shall be taken that the leading edge of the coarse-grained layer be at least 20 feet from a geogrid end-lap position at the end of the daily operations.

3.2.4 Repairs to Geogrid

Repairs to the geogrid shall be made in accordance with the manufacturer's repair procedures. The Contractor shall furnish the Contracting Officer the manufacturer's written repair procedure upon delivery of the geogrid to the site.

3.3 MEASUREMENT AND PAYMENT

Measurement for payment for work required by this section of the specifications shall be made of the actual total surface area in square yards covered by the geogrid as shown in the contract drawings. Final quantities of geogrid shall be based on as-built conditions. No allowance will be made for waste, overlap, or materials used for the convenience of the Contractor. Geogrid installed and accepted by the Contracting Officer will be paid for at the contract unit price for "INSTALL GEOGRID" as listed in the bidding schedule. Payment for the construction of the mat base shall be as specified in Section 31 01 00: DIKE EMBANKMENT.

-- End of Section --

SECTION 31 05 21 Page 4

2.1.2 Seam Strength Testing

The Contractor shall collect samples of field and factory sewn seams and arrange for laboratory strength testing in accordance with ASTM D4884. All samples shall be tested to verify that the geotextile meets the requirements specified.

PART 3 EXECUTION

3.1 SURFACE PREPARATION

The underlying surface to receive the geotextile shall be prepared to a relatively smooth condition free of tire ruts, erosion gullies, obstructions, depressions and debris.

3.2 PLACEMENT

The Contractor shall furnish to the Contracting Officer or his/her designated representative the manufacturer's written installation procedures for the geotextile upon delivery of this material to the site.

The Contractor shall visually inspect all rolls of geotextile for damage and imperfections prior to its placement. Damaged and defective rolls of geotextile shall be marked and repaired as required. The Contractor shall place the geotextile in accordance with the manufacturer's installation procedures and as specified herein. Panels of geotextile shall be cut using a hot knife. Each panel shall be oriented with the long dimension (machine direction) perpendicular to the centerline of the dike embankment within a tolerance of 5 degrees. The geotextile shall be laid flat and smooth to minimize tension, stress, folds, wrinkles, and creases. Sections displaced by wind or other occurrences shall be approved by the Contracting Officer or his/her designated representative prior to their use. New geotextile to new geotextile shall overlap 3-feet. New geotextile to existing geotextile shall overlap 10-feet. New to new and new to existing geotextile seams are not required to be sewn.

Geotextile shall be placed during reconstruction of the dike embankment at Spillway 7 as shown on the drawings. Placement of three layers of geotextile shall be required at each of the spillway replacement locations. Geotextile shall be placed above and below the new spillway pipe as shown on the drawings. The third or top layer of geotextile shall be placed to match the elevation of the existing geotextile at spillway 7.

The top layer of new geotextile shall overlap the existing geotextile a minimum of 10-feet. At spillway 7 the top layer of geotextile shall be placed at elevation 24' NAVD 88. Geotextile shall also be placed around the spillway pipes for the french drain and beneath the spillway riser concrete foundation pads as shown on the drawings.

3.3 PROTECTION

Delivery, storage, and handling of geotextile shall be in accordance with ASTM D4873. The geotextile shall be protected during installation from clogging, penetrations, tears, and other damage. Damaged geotextile shall be repaired or replaced. Adequate ballast, such as sand bags, shall be used to prevent uplift by wind. Vehicular traffic other than that required for placement will not be allowed directly on the geotextile until a layer of compacted cover soil, a minimum of 18 inches thick has been placed upon

it. The geotextile shall be protected from ultraviolet exposure during

SECTION 31 05 22 Page 4 manufacture, shipping and at all storage locations. The geotextile shall not be exposed to ultraviolet light for more than 14 days. Overlying materials shall be installed so that the geotextile is not shifted, damaged, or placed in tension. During placement, the height of drop of cover soil shall be no greater than 12 inches.

3.4 SEAMING

Seams shall be constructed in accordance with the manufacturer's requirements as necessary to ensure seam strength as specified in TABLE 1.

The Contractor shall furnish the Contracting Officer or his/her designated representative the manufacturer's written seam construction requirements upon delivery of the geotextile to the site. Seams shall be continuously sewn along the selvage of each panel and tested at a minimum frequency as specified in ASTM D4884. Seams running normal to the reinforcement direction are not allowed except as permitted for making patch repairs.

3.5 REPAIRS

Damaged or defective geotextile shall be replaced or repaired. Repair shall be made in accordance with the manufacturer's repair procedures. The Contractor shall furnish the Contracting Officer or his/her designated representative the manufacturer's written repair procedure upon delivery of the geotextile to the site. Geotextile which cannot be repaired shall be replaced.

3.6 MEASUREMENT AND PAYMENT

There will be no direct measurement of work performed in connection with the construction and installation of geotextile. The appropriate contract lump sum price for "SPILLWAY 7" in the BIDDING SCHEDULE shall constitute full compensation for furnishing all labor, materials, plant, equipment, tools, supplies, and incidentals necessary to complete the work included in this section and detailed on the plans.

-- End of Section --

SECTION 31 05 22 Page 5 because of shrinkage during the curing reaction. The total dry film thickness of the two coats of coal tar epoxy shall not exceed 60 mils. The dry film thickness of anyone coat shall not exceed 40 mils. Coats exceeding these thicknesses shall be stripped off and redone at the Contractor's expense.

2.1.3.7 Manufacturer's Recommendations

The Contractor shall follow all instructions and recommendations of the paint manufacturer regarding those items which are not spoken to by these specifications or by SSPC PS 11.01.

2.1.4 Spillway Riser Access

The Contractor shall modify existing spillway riser structures to include:

an access hatch door, a fixed vertical ladder, and confined space entry and rescue system equipment. The fixed vertical ladder shall be located on the interior of the backside (side with ½-inch plate steel) of the riser structure. The access hatch door, ladder and confined space entry equipment are to provide access to the interior of the spillway riser structure for purposes of maintenance and access to stoplogs. Spillway riser access modifications shall be made to spillway riser structures for Spillways 1, 4, 5, 6, 7, 8, and 9.

2.1.4.1 Ladders

The Contractor shall provide fixed vertical ladders for each spillway riser as indicated on the drawings. The fixed vertical ladders shall not be less than 16 inches wide, measured inside the rails, and shall have rungs not less than 7/8-inch in diameter, equally spaced on approximately 12-inch centers. The vertical ladders, including fastenings, shall be designed for a total load of 1,000 pounds. Ladders shall have an extension that extends a minimum of 3-feet above the grating of the top of the spillway riser.

Ladders shall be fabricated from steel conforming to ASTM A 36/A 36M and shall be hot dipped galvanized after fabrication to meet ASTM A 123/A 123M.

Ladders shall be fabricated to meet the requirements of ANSI A14.3.

2.1.4.2 Confined Space Entry and Rescue System Equipment

The Contractor shall provide confined space entry and rescue system equipment for each spillway riser as indicated on the drawings. The equipment shall consist of: 1) a base that is bolted to the top horizontal steel beam of the bridge support, 2) a mast that will provide an offset from the base to the center of the hatch opening, 3) the mast shall include a mast extension component , if necessary, to provide a 7-foot clearance between the end of the mast and the top surface of the spillway riser, and 4) self retracting winch with a minimum of 50 feet of 3/16-inch galvanized cable. The confined space entry and rescue system equipment shall be manufactured to comply with the requirements of USACE EM 385-1-1 and ASSE/SAFE A10.32.

2.1.4.3 Access Hatch Door

The Contractor shall provide stainless steel access hatch door for each spillway riser as indicated on the drawings. Include lifting mechanism, automatic hold open arm, slam lock with handle, and flush lift handle with red vinyl grip. Use automatic hold open arm that locks in the 90 degree position. Use door constructed with ¼ inch diamond plate cover capable of withstanding a live load of 300 pounds per square foot. Provide stainless

SECTION 33 40 02 Page 7 steel cylinder lock with two keys per lock. Key all the locks the same.

2.2 SPILLWAY PIPE

The new spillway discharge pipe placed through the embankment at Spillway 7 shall be SDR 11 HDPE pipe. The new spillway pump out pipe for Spillways 7, 8 and 9 shall be ductile iron pipe and shall comply with the requirements of Section 33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWERS.

The existing 30-inch HDPE pipe for Spillways 7 and 8 shall be removed during demolition of the existing timber support frames and reinstalled after new timber support frames have been constructed. If additional HDPE is needed it shall meet the requirements of subparagraph High Density Polyethylene (HDPE) Pipe.

2.2.1 High Density Polyethylene (HDPE) Pipe

The HDPE pipe shall be 12-inch SDR 11-IPS high density polyethylene (HDPE) plastic meeting, as a minimum, the requirements of ASTM F 714. The Contractor shall provide certification that the plastic pipe meets these requirements.

2.2.2 Screen for Pipe Opening

The pipe openings in the spillway boxes shall have a wire mesh attached to the flanges. The screen shall be constructed of stainless steel Type 304 material. Opening size shall be 1-inch square and wire diameter shall be 0.1200-inch. Wire mesh shall be attached to the openings of the pump-out pipes (Spillway 7, 8 and 9) and gate valve opening (Spillway 7 only).

2.3 HARDWARE

2.3.1 Spillway Riser Hardware

Hardware (nuts, bolts, and washers) for bolting spillway riser sections together, for spillway riser assembly, and attaching spillway riser to spillway foundation pad shall be suitable for its intended use and shall (as a minimum) conform strength wise to ASTM 307, and shall be stainless steel meeting ASTM F 593 for bolts and ASTM F594 for nuts.

2.3.2 Steel Walkway Hardware

Hardware (nuts, bolts, and washers) for bolting steel walkway shall be suitable for its intended use and shall (as a minimum) conform strength wise to ASTM A 325, and shall be stainless steel meeting ASTM F 593 for bolts and ASTM F594 for nuts.

2.3.3 Timber Pipe Support and Stoplog Hardware

Hardware (nuts, bolts, and washers) for bolting timber pipe support frames and lag screws for stoplogs shall be suitable for its intended use and shall (as a minimum) conform strength wise to ASTM A 307, and shall be galvanized. Galvanized hardware shall be galvanized in accordance with

ASTM A 153/A 153M.

2.4 PIPE SUPPORT FRAMES

All lumber shall be treated in accordance with AWPA U1 (.40 pcf retention, waterborne preservative, for ground contact) and shall be S4S. Wood shall be No.2 Southern Pine or approved equal. Area of treated wood exposed by

SECTION 33 40 02 Page 8 cutting or drilling shall receive field treatment of preservatives in accordance with AWPA M4.

2.5 WALKWAY

Structural steel members required for fabrication of the walkway and supporting columns shall conform to ASTM A 572/A 572M, Grade 50 and shall be the size and shape as shown on the drawings. The steel used shall be suitable for welded and bolted construction. All steel members of the walkway and supporting columns shall be hot dipped galvanized in accordance with ASTM A123/A123M.

2.6 STOPLOGS

Stoplogs shall be tongue and groove (T&G) lumber, Southern Pine No. 2 or approved equal, treated in accordance with AWPA U1 (2.5 pcf retention, waterborne preservative) after fabrication. Untreated No. 2 white oak may also be used.

2.7 CONCRETE

2.7.1 Spillway Riser Foundation and Walkway Support Pad

Concrete shall be NCDOT Class "AA" concrete with a minimum 28 day compressive strength of 4500 PSI. Concrete, materials, placement, admixture, testing and sampling shall be in accordance with the NCDOT specifications. A minimum of three strength test cylinders shall be made by the Contractor for concrete placement. One cylinder shall be strength tested at 7 days and one at 28 days by the Contractor with the third held in reserve. Minimum concrete strength for erection of the spillway is 3000

PSI.

2.8 REINFORCING STEEL FOR SPILLWAY FOUNDATION AND WALKWAY SUPPORT PAD

Reinforcing steel for the spillway foundation pad shall be #4 deformed bars, conforming to ASTM A 615/A 615M, Grade 60 and shall conform to the size and spacing as shown on the drawings.

2.9 GEOTEXTILE

See drawings for geotextile placement requirements for the spillway foundation pad and in the backfill for the spillway pipe.

2.10 SATISFACTORY MATERIAL

Satisfactory material shall conform to the requirements of Section 31 01 00:

DIKE EMBANKMENT.

22.11 SPILLWAY RISER/DISCHARGE PIPE CONNECTION

The connection between plastic pipe and spillway riser shall consist of a polyethylene flange connector or stub end connector (SDR 11 rating) with a metal slip-on back-up ring (or back-up flange) which shall be stainless steel or ductile iron which has been hot-dipped galvanized. Ductile iron material shall meet ASTM A 536. The back-up ring shall be convoluted, rated at 150 lb., and conform to ANSI/ASME B16.5 vital dimensions.

SECTION 33 40 02 Page 9

SF30
SUMMARY OF CHANGES
PROJECT TABLE OF CONTENTS - Revised
SECTION 00 01 15
Revised pages 2 and 3
SECTION 01 11 00
Revised page 3
SECTION 01 33 00
Revised attachment - Form ENG 4288
SECTION 31 05 21
Added section - all pages
SECTION 31 05 22
Revised pages 4 and 5
SECTION 33 40 02
Revised pages 7, 8 and 9

File details come from the government source that posted it. Updated .