This is a series of presentation slides from an Industry Day event for a Remedial Action Construction (RAC) IDIQ contract opportunity at the Iron King Mine - Humboldt Smelter Superfund Site in Dewey-Humboldt, AZ. The contract, with Notice ID W912PL25S0009, has a ceiling value of $249M with individual task orders ranging from $1M to $50M over a 60-month period of performance.

The project involves environmental cleanup of two contaminated areas separated by Highway 69: the former Iron King Mine (1910-1968) on the west side with a 120-foot high, 4 million cubic yard tailings pile, and the former Humboldt Smelter (late 1800s-1937) on the east side containing mine waste, dross, contaminated soils and slag. The work requires excavation, transport and consolidation of contaminated materials into two newly constructed repositories (one on each side of the highway), with no waste crossing the highway. The primary NAICS code is 237990 (Other Heavy and Civil Engineering Construction), with several secondary NAICS codes identified for subcontracting opportunities including site preparation, concrete work, freight trucking, masonry, utilities, and engineering services. Key dates include an Industry Day on January 28, 2025 and Sources Sought submissions due February 11, 2025. The project is a collaboration between the US Army Corps of Engineers Los Angeles District and the EPA.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Iron King Mine – Humboldt Smelter Remedial Action Construction (RAC)

Indefinite Delivery/Indefinite Quantity (IDIQ) Contract up to $249M

NOTICE ID W912PL25S0009

RAC 1

• This is a SOURCES SOUGHT announcement, Industry Day in accordance with an interagency agreement between the USACE Los Angeles District and the United States Environmental Protection Agency (EPA) for the Iron King Mine – Humboldt Smelter (IKM-HS) Superfund Site.

• This is This is SOURCES SOUGHT, NOTICE ID W912PL25S0009 for the Remedial Action Construction, Indefinite Delivery/Indefinite Quantity (IDIQ) Contract up to $249M.

• The Task Orders will be $1M to $50M in value.

• The Construction Contractor will be expected to perform construction activities as required by EPA’s Record of Decision (October 2023) for the Iron King Mine/Humbolt Smelter Superfund Site and specified by the remedial design.

• The Government is seeking to identify firms under the North American Industry Classification System (NAICS) 237990 (Other Heavy and Civil Engineering Construction).

• This notice is for market research purposes only and IS NOT A REQUEST FOR PROPOSAL (RFP) nor does it restrict the Government as to the ultimate acquisition approach.

• The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice.

RAC 2

IRON KING MINE - HUMBOLDT SMELTER

INDUSTRY DAY INTRODUCTION

• Decades ago, the former Iron King Mine (1910 – 1968) and former Humboldt Smelter (late 1800s to 1937) left behind millions of tons of mining wastes including mine tailings and other types of wastes in Dewey-Humboldt.

• At the former mine on the west side of AZ State Route, Highway 69 (highway), a 120-foot high 4 million-cubic yard tailings pile remains that is high in arsenic and lead.

• The former smelter on the east side of the highway contains mine waste, waste dross, extensive contaminated soils, and a wall of monolithic slag hanging over a river.

• The contaminated Chaparral Gulch drainage between the mine and the smelter contains a flood plain filled with tailings and held back by a dam, as well as buried alluvium mixed with tailings.

• At the former mine on the west side of the highway there is a 120-foot high 4 million-cubic yard tailings pile remains that is high in arsenic and lead. On the east side of the highway, 1.1 million-cubic yard tailings pile remains that is also high in arsenic and lead.

• The remedy will require widespread excavation, transport, disposal and consolidation of wastes into two newly constructed and permanently capped repositories, one on each side of the highway. No waste will cross the highway during remediation.

RAC 3

PROJECT OVERVIEW

HWY 69

RAC 4

RD IDIQ LOCATION

IRON KING MINE - HUMBOLDT SMELTER

SITE MAP

Consolidation/Containment at Two

Repositories: waste does not cross AZ State Route, Highway 69.

U.S. Environmental Protection Agency Region 9 Dewey-Humboldt, AZ Contamination Levels of Site Areas

RAC 6RAC 5

RAC IDIQ – BEFORE & AFTER

IRON KING MINE - HUMBOLDT SMELTER, LOCATION

RAC 6

East of HWY 69, Future Smelter Tailings Swale Repository Location

West of HWY 69, Future Main Tailings Pile Repository Location

0 10 20 30 40 50 60 70 80 90

RAC IDIQ <$249M

Sources Sought Submittals Due, Tuesday, 11FEB2025

Industry Day, Tuesday, 28JAN2025

Acquisition Planning Contract Award Duration Contract Period of Performance

IDIQ Anticipated Period of Performance is 60 Months

RFP Advertisement

Contract Award

MONTHS

Iron King Mine – Humboldt Smelter RAC IDIQ Proposed Schedule

NOTICE ID W912PL25S0009

This schedule is notional

RAC 7

NOTICE ID W912PL25S0009

PRIMARY NAICS & SECONDARY NAICS(SUBCONRACTING OPPORTUNITIES)

PRIMARY NAICS (Prime Contractor)

Other Heavy and Civil Engineering Construction: 237990 - The Construction Contractor will be expected to perform the work described in the ROD Alternative 3B, including the dam removal, retaining wall construction, creating a cap for the two repositories, and other construction activities as described and/or as needed for the site.

SECONDARY NAICS (Subcontracting Opportunities)

238910 - Site Preparation Contractors: Excavation, Grading, Foundation Excavation, Demo 238110 - Poured Concrete Foundation and Structure Contractors: Concrete Block or Cast-In-Place 484220 - Specialized Freight (Except Used Goods) Trucking, Local: Dirt, Soil 238140 - Masonry Contractors 237110 - Water and Sewer Line and Related Structures Construction: Drainage Systems, Minor Utilities 541330 - Engineering: Temporary Engineering or Services

RAC 8

Slide Number 1
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
RAC IDIQ – BEFORE & AFTER�IRON KING MINE - HUMBOLDT SMELTER, LOCATION
Slide Number 7
Slide Number 8