This document provides details for a federal construction contract opportunity for the High Water Crossing at Vamori Wash project. The U.S. Army Corps of Engineers Los Angeles District is seeking to award a firm fixed price construction contract to construct multiple high-water culvert crossings across the Vamori Wash in Pima County, Arizona near the U.S./Mexico border on the Tohono O'odham Nation. Work will include earthwork, culvert installation, fencing, erosion control elements, and other related construction tasks. The estimated value of the contract is between $10-20 million. The NAICS code is 237310 and it is reserved 100% for small businesses. The solicitation will be posted on BetaSAM and proposals are due by July 16, 2021, with award anticipated by August 2021.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912PL21R0015

High-water Crossing at Vamori Wash Trip Report (08-June-2021 Site Visit)

1 | P a g e

ATTENDEES

NAME ORG TITLE EMAIL

Brandon Colvin USACE Project Manager Brandon.l.colvin@usace.army.mil

Ralph Castillo CBP Tribal Liaison Rafael.m.castillo@cbp.dhs.gov

Aaron Salas CBP Tribal Liaison aaron.salas@cbp.dhs.gov

Adam Johnston USACE Project Engineer Adam.J.Johnston@usace.army.mil

Anthony Heim SWP Project Manager anthonyh@swpcontracting.com

Koury Catt SWP Project Manager kcatt@swpcontracting.com

Michael Kitchell Brad Cole

Const.

Superintendent mkitchell@bradcoleconstruction.com

Gary Denton Technology

Const.

Project Manger gary@tciaz.net

Shay More Meridian PM a.more@meridiancon.net

Jacob buckley Southwest siteworks president jakebuckley@southwestsiteworks.com

Patrick Spencer

Spencer

Construction

LLC

CEO

pspencer@spencerconstructionaz.com

Aaron De La O Whelcon

Contractors ILC, Project Engineer estimating@whelcon.com

Steve Melton International

Towers VP Construction smelton@itowersllc.com

Jeff Jones Meridian Controller J.jones@meridiancon.net

Sam Lucio Lucio Endeavors Co-owner lucioendeavors@gmail.com

Andy Smith Ashton

Companies

Estimate/Project

Manager asmith@ashtoncoinc.com

Troy Hile Dawson Project Manager thile@dawsonohana.com

Alex Birch Kiewit Superintendent Alex.birch@kiewit.com

Dave Breitkreitz International

Towers Construction Manager dbreitkreitz@itowersllc.com

Shaylen Putz

Picacho

Concrete

Structures

Estimator shaylen@picachoconcrete.com

2 | P a g e

OBJECTIVE

A project site visit for the W912PL21R0015 High-water Crossing at Vamori Wash project was held on Tuesday, 08-June-2021 at 10:00am (meeting location below). The objective of this site visit was to provide interested contractors access to the project site.

MEETING NOTES

The attendees were reminded that the site visit was to provide access to the project site, and that all questions or inquiries must be routed through the ProjNet Bidder Inquiries system.

USACE and CBP representatives discussed the general layout and site access for the project such as the main highway access to the project area (IR 19), lay down yard location (San Miguel gate) and the project specific location (Vamori Wash). Attendees were reminded of the importance of ensuring they follow all traffic and local laws while traveling to and from, and while working on the Tohono O’odham Nation.

CBP reminded the contractors that CBP will not be provide security for the project. Any required security would be provided by the contractor. Tohono O’odham Nation (TON) representatives reminded the contractors of the important of working on the Nation in a respectful way, and the importance of following all of the requirements outlined regarding working on the TON. The

TON timeframes required for review/approvals must be factor into the project schedule.

Contractors must not assume that durations can be shorted on these processes.

CBP reminded the contractors that the cultural and biological monitoring services will be procured by CBP via a separate contract. CBP also outlined that tribal members were sometimes cross the border via the gate adjacent to the lay down yard. This is not to be used for any reason.

The group then traveled via caravan to the project site/location. Additional tribal members arrived during the specific site visit portion. They reminded contractors again of the importance of following the tribal laws, and in being good stewards of the land during construction.

3 | P a g e

MAPS & SITE INFORMATION

Location Coordinates: 31.554928628930714, -111.76978744175901

SCHEDULE

08-June-2021

▪ 0945-1000: Met at Vamori Wash Lay Down Yard (map and coordinates above)

▪ 1000-1100: Orientation and site walk

PROJECT POINTS OF CONTACT

Brandon Colvin (Primary POC) Project Manager US Army Corps of Engineers Brandon.L.Colvin@usace.army.mil 602-518-5822

Adam Johnston (Backup POC) Project Engineer Tucson Resident Office Adam.J.Johnston@usace.army.mil 520-584-1678

Rafael M. Castillo (Backup POC) Tucson Sector Tribal Liaison Office: 520-519-2640 Cell: 520-403-6235 RAFAEL.M.CASTILLO@cbp.dhs.gov

Brandon Colvin, USACE Project Manager

2021-06-11T14:16:36-0700
COLVIN.BRANDON.LEE.1502221031

File details come from the government source that posted it. Updated .