This notice describes a federal construction contract opportunity for the F-35 Munitions Conveyor Facility at Nellis Air Force Base in Nevada. The project involves building a 60,546 square foot concrete pad and sunshade canopy to support munitions assembly operations for the F-35 aircraft. The project is set aside for 8(a) small businesses and has an estimated value between $5-10 million. The U.S. Army Corps of Engineers will issue the solicitation on or around June 15th, 2020 via the SAM.gov website, with bids due on or around July 17th. The solicitation will use the Invitation for Bid procurement method. Interested 8(a) contractors must register in SAM.gov to receive the solicitation and submit a bid and any other requested documents, which will be evaluated for responsiveness and responsibility. The lowest priced, responsive, and responsible bidder will be considered for award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912PL20B0006 Certified Bid Abstract.pdf | ||
| W912PL20B0006_Amendment0005.pdf | ||
| W912PL20B0006_Amendment0003.pdf | ||
| _site_visit sign in sheets. pdf.pdf | ||
| W912PL20B0006_Amendment0002.pdf | ||
| W912PL20B0006_Amendment0001.pdf | ||
| W912PL20B0006_Solicitation_Specifications.pdf | ||
| W912PL20B0006_Solicitation_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 104
0004 15Jul2020
USACE, Los Angeles District ATTN: Contracting Division East Region Branch 915 Wilshire Boulevard, Suite 930 Los Angeles, CA 90017
W912PL20B0006
15JUN2020
F-35 Munitions Conveyor Facility, Nellis AFB, NV
The purpose of this amendment is to make the following changes identified within the continuation sheet.
All other terms and conditions remain unchanged.
W912PL20B0006
AMEND 0004
Changes are:
1. Spec Table Of Contents (replace)
a. Delete specification section 09 65 00
2. 01 33 00 Submittal Register (replace)
3. 01 50 00 (delete paragraph 3.3.1)
4. 07 41 13 (add new spec section)
5. 09 29 00 (add new spec section)
6. Drawing sheet A-010 (replace)
7. Drawing sheet A-500 (replace)
8. Drawing sheet A-601 (replace)
F-35A Munitions Assembly Conveyor Facility 2266
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24 FACILITY DATA REQUIREMENTS
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
03 33 00 CAST-IN-PLACE ARCHITECTURAL CONCRETE
03 42 13 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 27 10 BUILDING AIR BARRIER SYSTEM
07 41 13 METAL ROOF PANELS
07 41 63 FABRICATED ROOF PANEL ASSEMBLIES
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 71 00 DOOR HARDWARE
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
PROJECT TABLE OF CONTENTS Page 1 Amendment 004
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 METAL BUILDING SYSTEMS
13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 48.19 SEISMIC BRACING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 23 00 REFRIGERANT PIPING
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 26 - ELECTRICAL
26 05 19.10 INSULATED WIRE AND CABLE
26 05 48 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 64 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE BASE COURSES
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS
32 17 23 PAVEMENT MARKINGS
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 48 PAGES
F-35A Munitions Assembly Conveyor Facility
01 32 01 SD-01 Preconstruction Submittals
1.3 GProject Scheduler Qualifications
3.5Bar Chart Schedule
3.1 GProject Schedule
3.5.1 GPreliminary Project Schedule
3.5.2 GInitial Project Schedule
3.6.1Data Optical Discs
3.5.3 GPeriodic Schedule Update
3.7.2 GPeriodic Schedule Update
3.9.1 GJustification of Delay
3.9.3 GTime Impact Analysis
3.9.4 GForensic Schedule Analysis
3.1.1 GSchedule Status Report
01 33 00 SD-01 Preconstruction Submittals
1.9 GSubmittal Register
01 33 29 SD-01 Preconstruction Submittals
1.5.3.1 GPreliminary High Performance
and Sustainable Building Checklist
1.4.1 GSustainability Action Plan
1.5.3.1 GPreliminary Sustainability
eNotebook SD-11 Closeout Submittals
1.5.3.1 GFinal High Performance and
Sustainable Building Checklist
1.5.3.1 GFinal Sustainability eNotebook
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 48 PAGES
01 33 29 1.5.3.1 GAmended Final Sustainability eNotebook
1.5.3.1 GAmended Final High
Performance and Sustainable Building Checklist
01 35 26 SD-01 Preconstruction Submittals
1.6 G DOAccident Prevention Plan (APP)
1.6.2.11 GHealth Hazard Control Plan
1.6.2.12 GEmergency Action Plan
1.6.2.2 GStandard Lift Plan
1.6.2.3 G DOCritical Lift Plan
1.7Activity Hazard Analysis (AHA)
1.6.2.13 GCovid-19 Monitoring Plan
SD-06 Test Reports 1.11.3Monthly Exposure Reports 1.11Notifications and Reports
1.11.2 G DOAccident Investigation Reports
1.11.4LHE Inspection Reports 1.11.6Regulatory Citations and
Violations SD-07 Certificates
1.5.1.4Crane Operators/Riggers 1.8.1Confined Space Entry Permit 1.8.1Hot Work Permit 1.11.5Certificate of Compliance 3.7Excavation Permit
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 48 PAGES
01 35 26 1.5.1.4Proof of Current Qualification 01 45 00 SD-01 Preconstruction Submittals
3.2 GContractor Quality Control Plan
3.7.2.1 GMTC validation
SD-06 Test Reports 3.9.2Verification Statement
01 45 35 SD-01 Preconstruction Submittals 3.1.2Written Practices 3.1.2NDT Procedures and Equipment
Calibration Records SD-06 Test Reports
3.1.2Daily Reports 3.1.1Biweekly Reports
SD-07 Certificates 2.1Fabrication Plant 2.1AC472 Accreditation 2.1Steel Joist Institute Membership
2.1 GCertificate of Compliance
1.5 GSpecial Inspector
3.1.2Qualification Records
SD-11 Closeout Submittals
3.1.2 GComprehensive Final Report
01 50 00 SD-01 Preconstruction Submittals
1.3 GConstruction Site Plan
3.1.7.1 GTraffic Control Plan
3.6 GSafety Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 48 PAGES
01 50 00 1.4 GTemporary Earthwork Plan
3.1.7.3 GDust Control Methods And
Procedures
2.2 GHaul Road Plan
SD-06 Test Reports 2.4Backflow Preventer Tests
SD-07 Certificates 1.7.1Backflow Tester 1.7Backflow Preventers 1.7.2Backflow Prevention Training
Certificate 01 57 19 SD-01 Preconstruction Submittals
1.6 GEnvironmental Protection Plan
1.6 GEnvironmental Protection Plan
1.6 GEnvironmental Protection Plan
1.6.3 GEnvironmental Protection Plan
1.11 GEnvironmental Protection Plan
3.8.3 GEnvironmental Protection Plan
3.4.1 GATC application
1.6.2 GDust Control Permit
1.6.3Environmental Permits
3.8.4.1 GApproval Letter
3.8.4.1Authorized Desert Tortoise
Biologist Qualifications Statement And Request
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 48 PAGES
01 57 19 3.8.4.2Preconstruction Desert Tortoise Survey Data
SD-03 Product Data 1.6.2Safety Data Sheets
SD-07 Certificates 1.6.3Certifications
01 57 23 SD-01 Preconstruction Submittals
1.5.1 G DOSWPPP
1.5.1 G DOSWPPP
SD-03 Product Data 1.5.1.2BMP Product Data 3.1.1BMP Product Data 3.1.1BMP Product Data 3.1.1BMP Product Data
SD-06 Test Reports 3.1.1SWPPP Amendments 3.2.1SWPPP Amendments 3.2.1SWPPP Amendments 3.2.1SWPPP Amendments 3.2.1SWPPP Amendments 3.2.1SWPPP Amendments
SD-10 Operation and Maintenance Data
3.1.2 G DOPost-Construction Storm Water
Management Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 48 PAGES
01 57 23 3.1.2 G DOPost-Construction Storm Water Management Plan
SD-11 Closeout Submittals
3.1.2 G DOFinal SWPPP
3.2.1 G DOFinal SWPPP
3.1.2 G DONOT Application
3.1.2 G DONOT Application
3.1.2 G DONOT Application
01 58 00 SD-02 Shop Drawings
1.4.1 GSign Legend Orders
01 74 19 SD-01 Preconstruction Submittals
1.5 GWaste Management Plan
SD-11 Closeout Submittals
1.6 SRecords
01 78 00 SD-03 Product Data 1.7.1Warranty Management Plan 1.7.5Warranty Tags 1.5Spare Parts Data
SD-06 Test Reports
3.1.4 Gworking as-built drawings
3.2 G DOfinal as-built record drawings
SD-08 Manufacturer’s Instructions 1.7.1Instructions
SD-10 Operation and Maintenance Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 48 PAGES
01 78 00 3.9Operation and Maintenance Manuals
SD-11 Closeout Submittals
1.3.4 G DORecord Drawings
2.3 GCertification of EPA Designated
Items
3.11 GInterim DD FORM 1354
3.11 GChecklist for DD FORM 1354
3.6 GFinal Approved Shop Drawings
3.7 GConstruction Contract
Specifications 3.8As-Built Record of Equipment and Materials
3.11 GHigh Performance And
Sustainable Building (Hpsb) Checklist
01 78 23 SD-10 Operation and Maintenance Data
1.4 GO&M Database
3.1.1 GTraining Plan
3.1.3 GTraining Outline
3.1.2 GTraining Content
SD-11 Closeout Submittals
3.1.4 GTraining Video Recording
3.1.6 GValidation of Training Completion
01 78 24 SD-01 Preconstruction Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 48 PAGES
01 78 24 1.4.1Facility Data Project Execution Plan
SD-10 Operation and Maintenance Data
3.1 GFacility Data Workbook, Construction Progress
3.1 GFacility Document Set, Construction Progress
SD-11 Closeout Submittals
3.2 GFacility Data Workbook, Construction Final
1.4.3 GFacility Document Set, Construction Final
3.2 GFacility Document Set, Construction Final 01 91 00.15 SD-01 Preconstruction Submittals
1.7 GCommissioning Firm
1.7.1 GLead Commissioning Specialist
1.7.2 GTechnical Commissioning
Specialists
1.7 GCommissioning Firm's Contract
SD-06 Test Reports
3.1.2.1 GInterim Construction Phase
Commissioning Plan
3.1.2.1 GInterim Construction Phase
Commissioning Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 48 PAGES
01 91 00.15 3.1.2.2 GFinal Construction Phase Commissioning Plan
3.1.2.1.2 GTemplate Building Envelope
Inspection Checklists
3.1.4.2 GBuilding Envelope Inspection
Checklists
3.1.4.3 GPre-Functional Checklists
1.8Issues Log
3.2 GCommissioning Report
SD-07 Certificates
1.9 GCertificate of Readiness
SD-10 Operation and Maintenance Data
3.1.5 GTraining Plan
3.1.5 GTraining Attendance Rosters
3.1.6 GSystems Manual and
Computerized Maintenance Management System Manual
SD-11 Closeout Submittals
3.2 SFinal Commissioning Report
03 30 53 SD-02 Shop Drawings
1.4 GInstallation Drawings
SD-03 Product Data 2.2.3.1Air-Entraining Admixture 2.2.3.2Accelerating Admixture
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 48 PAGES
03 30 53 2.2.3.3Water-Reducing or Retarding Admixture
2.2.11Curing Materials 2.2.6Expansion Joint Filler Strips, Premolded 2.2.7Joint Sealants - Field Molded
Sealants 3.2Conveying and Placing Concrete 2.2.8Formwork
2.3 GMix Design Data
2.3Ready-Mix Concrete 2.4.1Curing Compound 2.2.5Mechanical Reinforcing Bar
Connectors SD-06 Test Reports
2.2.2Aggregates
2.1.3 GConcrete Mixture Proportions
3.8.3 GCompressive Strength Testing
3.8.3 GSlump
3.8.3Air Content 2.2.4Water
SD-07 Certificates 2.2.1Cementitious Materials 2.2.2Aggregates 2.3Delivery Tickets
SD-08 Manufacturer’s Instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 48 PAGES
03 30 53 2.4.1Curing Compound 03 33 00 SD-02 Shop Drawings
1.4.1Detail Drawings SD-04 Samples
2.1Materials 1.4.2Panels
03 42 13 SD-01 Preconstruction Submittals 1.3.2.2Quality Control Procedures
SD-02 Shop Drawings
2.1.1 GStandard Precast Units
2.1.2 GCustom-Made Precast Units
3.2.4.3Special Finishes
SD-03 Product Data 2.1.1Standard Precast Units 2.1.3Proprietary Precast Units 3.1.3Embedded Items 2.2.5Accessories
SD-05 Design Data
2.1.2 GDesign Calculations
2.1.5.1 GConcrete Mix Proportions
SD-06 Test Reports 1.3.2.4Test Reports
SD-07 Certificates 1.3.2.2Quality Control Procedures
04 20 00 SD-02 Shop Drawings
3.3.2.1 G DO Cut CMU
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 48 PAGES
04 20 00 3.4.1.1 G DO Detail Drawings SD-03 Product Data
1.5.1 G ROHot Weather Procedures
1.5.2 G ROCold Weather Procedures
2.4.1.1 G ROCementitious Materials
SD-04 Samples
2.2.2.2 G ROConcrete Masonry Units (CMU)
2.4.1.4 G ROAdmixtures for Masonry Mortar
2.6.2 G ROAnchors, Ties, and Bar
Positioners
2.6.3 G ROJoint Reinforcement
SD-05 Design Data
2.1.2 G ROMasonry Compressive Strength
2.2.2.4Fire-Rated Concrete Masonry
Units
3.2.5 G ROBracing Calculations
SD-06 Test Reports 2.2.2.4Fire-Rated Concrete Masonry
Units SD-07 Certificates
1.3.1Special Masonry Inspector Qualifications
2.2.2.2Concrete Masonry Units (CMU) 2.4.1.1Cementitious Materials 2.4.1.4Admixtures for Masonry Mortar 2.4.2.2Admixtures for Grout
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 48 PAGES
04 20 00 2.6.2Anchors, Ties, and Bar Positioners
2.6.3Joint Reinforcement SD-08 Manufacturer’s Instructions
2.4.1.4Admixtures for Masonry Mortar 2.4.2.2Admixtures for Grout
SD-10 Operation and Maintenance Data
3.8Take-Back Program 06 10 00 SD-03 Product Data
1.8Fire-retardant Treatment 2.2.2Adhesives
SD-06 Test Reports 1.4.3Preservative-treated
SD-07 Certificates 1.9.1Certificates of Grade 1.7Preservative Treatment
06 20 00 SD-02 Shop Drawings
1.3 GDetail Drawings Indicating All
Wood Assemblies SD-03 Product Data
2.1 GWood Products
2.4 GCountertops
1.4 GTreated Wood Products
2.2 GSoffits
2.3 GFascias and Trim
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 48 PAGES
06 20 00 2.7 GHardware and Accessories
2.1.7 SRecycled Content For
Mdf/Particleboard
2.1.13 SVoc Content For Siding
2.8.1.2 SIndoor Air Quality For
Non-Aerosol Adhesives
2.8.1.2 SIndoor Air Quality For Aerosol
Adhesives SD-04 Samples
1.5 GSamples
SD-07 Certificates
1.7.1.1 GCertificates of Grade
2.1.7 SIndoor Air Quality For Mdf And
Particleboard
2.1.13 SCertified Sustainably Harvested
Siding 07 05 23 SD-01 Preconstruction Submittals
1.4 GWork Plan
SD-03 Product Data
2.2 GThermal Imaging Camera
SD-05 Design Data
3.2 GEnvelope Surface Area
Calculations
SD-07 Certificates 1.6.2.1Pressure Test Agency 1.6.2.2Thermographer Qualifications
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 48 PAGES
07 05 23 1.6.3Test Instruments 1.6.3Date Of Last Calibration
SD-06 Test Reports
3.5 GPressure Test Procedures
3.5.8 GAir Leakage Test Report
3.6.5 GDiagnostic Test Report
07 27 10 SD-04 Samples
3.1.2 GMock-Up
SD-06 Test Reports
1.8 GDesign Review Report
3.1.3 GTesting and Inspection
SD-07 Certificates
1.7 GAir Barrier Inspector
07 41 13 SD-02 Shop Drawings
1.4.5 GRoofing Panels
1.4.5 GFlashing and Accessories
1.4.5 GGutter/Downspout Assembly
SD-03 Product Data
2.1 GRoof Panels
SRecycled Content for Aluminum Roof Panels
2.1.1 SRecycled Content for Steel Roof
Panels
1.4.5 GFactory-Applied Color Finish
2.4 GAccessories
1.4.5 GFasteners
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 48 PAGES
07 41 13 1.4.5 GPressure Sensitive Tape
2.7 GUnderlayments
2.8 GGaskets and Sealing/Insulating
Compounds
1.4.5 GCoil Stock
1.4.5 GAluminized Steel Repair Paint
GEnamel Repair Paint GGalvanizing Repair Paint
SD-04 Samples
2.1 GRoof Panels
1.4.5 GFactory-applied Color Finish
2.4 GAccessories
1.4.5 GFasteners
1.4.5 GGaskets and Sealant/Insulating
Compounds SD-05 Design Data
1.2.1.2 GWind Uplift Resistance
SD-06 Test Reports
1.2.1.1 GLeakage Test Report
1.2.1.2 GWind Uplift Test Report
2.6.1 GFire Rating Test Report
2.2 GFactory Finish and Color
Performance Requirements SD-07 Certificates
2.1 GRoof Panels
1.4.5 GCoil Stock Compatibility
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 48 PAGES
07 41 13 2.7.1 GSelf-Adhering Modified Bitumen Underlayment
1.4.1 GQualification of Manufacturer
1.4.2 GQualification of Applicator
SD-08 Manufacturer’s Instructions
2.6 GInsulation
1.4.5 GInstallation Manual
SD-09 Manufacturer’s Field Reports
3.10.1 GManufacturer's Field Inspection
Reports
SD-11 Closeout Submittals
1.8 GWarranties
3.11 GInformation Card
07 41 63 SD-01 Preconstruction Submittals
1.4.1 GQualification of Manufacturer
1.4.1 GQualification of Installer
1.4.1 GQualifications for Welding
1.4.1 GWork Plan
1.4.1 GOn-Site Inspection and
Acceptance Procedure SD-02 Shop Drawings
1.4.1 GRoofing Panels
1.4.1 GFlashing and Accessories
1.4.1 GGutter/Downspout Assembly
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 48 PAGES
07 41 63 1.4.1 GSustainable Acquisition
1.4.1 GCoil Stock
1.4.1 GFactory Color Finish
1.4.1 GSub-girts and Formed Shapes
1.4.1 GClosure Materials
1.4.1 GInsulation
1.4.1 GPressure-Sensitive Tape
1.4.1 GSealants and Caulking
1.4.1 GRated Wall Assembly
1.4.1 GGalvanizing Repair Paint
1.4.1 GEnamel Repair Paint
1.4.1 GAluminized Steel Repair Paint
1.4.1 GAccessories
SD-04 Samples
1.4.1 GCoil Stock
1.4.1 GRoofing Panels
2.3.1.2 GFasteners
2.5.1 GMetal Closure Strips
1.4.1 GInsulation
1.4.1 GManufacturer's Color Charts and
Chips SD-05 Design Data
1.4.1Wind Design Analysis 1.4.1Seismic Design Analysis
SD-06 Test Reports
3.4.1.2 GLeakage Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 48 PAGES
07 41 63 1.4.1 GFire Rating Test Report
3.1 GCoatings and Base Metals of
Metal Roofing
1.4.1 GFactory Finish and Color
Performance Requirements
1.4.1 GWind Uplift Test Report
1.4.1 GSeismic Test Report
SD-07 Certificates 1.4.1Coil Stock 2.3.1.2Fasteners 1.4.1Galvanizing Repair Paint 1.4.1Enamel Repair Paint 1.4.1Safety Data Sheets 2.4.5Coating Physical Properties:
SD-08 Manufacturer’s Instructions 1.4.1Installation of Roof Panel
Assemblies SD-11 Closeout Submittals
1.7Warranty
3.3.5 GInformation Form and Placard
3.4.2Manufacturer's Field Inspection
Reports 1.4.1Application Instructions 1.7.120-Year 'No-Dollar-Limit'
Warranty For Labor And Materials 07 60 00 SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 48 PAGES
07 60 00 2.2.1 GExposed Sheet Metal
2.2.1 GGravel Stops and fascia
3.1.11 GBase Flashing
3.1.12 GCounterflashing
3.1.19 GFlashing at Roof Penetrations
and Equipment Supports
2.2.15 GReglets
3.1.22 GCopings
3.1.16 GDrip Edges
3.1.17 GEave Flashing
2.1 SRecycled Content
SD-03 Product Data
2.2.12 GCool Roof
SD-04 Samples
1.4.2 GFinish Samples
SD-08 Manufacturer’s Instructions
1.4.3 GInstructions for Installation
3.5 GQuality Control Plan
SD-10 Operation and Maintenance Data
1.4.3 GCleaning and Maintenance
07 84 00 SD-02 Shop Drawings
2.1 GFirestopping System
SD-03 Product Data
2.2 GFirestopping Materials
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 48 PAGES
07 84 00 3.3 GInspection SD-07 Certificates
1.5.2Inspector Qualifications 2.2Firestopping Materials
1.5.1 GInstaller Qualifications
07 92 00 SD-03 Product Data
2.2 GSealants
2.3 GPrimers
2.4 GBond Breakers
2.5 GBackstops
3.1 GField Adhesion
SD-07 Certificates
1.4.1 GIndoor Air Quality
SD-11 Closeout Submittals
2.2.1 SIndoor Air Quality For Interior
Sealants
2.2.3 SIndoor Air Quality For Interior
Floor Joint Sealants
2.2.4 SIndoor Air Quality For Interior
Acoustical Sealants
2.6 SIndoor Air Quality For Interior
Caulking 08 11 13 SD-02 Shop Drawings
2.1 GDoors
2.1 GDoors
2.4 GFrames
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 48 PAGES
08 11 13 2.4 GFrames 2.2Accessories 2.5Weatherstripping
SD-03 Product Data
2.1 GDoors
2.4 GFrames
2.2Accessories 2.5Weatherstripping
SD-04 Samples
2.7.3 GFactory-applied enamel finish
08 71 00 SD-02 Shop Drawings
1.3 GManufacturer's Detail Drawings
1.3 GVerification of Existing Conditions
1.5 GHardware Schedule
2.3.8 GKeying System
SD-03 Product Data
2.3 GHardware Items
SD-08 Manufacturer’s Instructions 3.1Installation
SD-10 Operation and Maintenance Data
1.5 GHardware Schedule
SD-11 Closeout Submittals
1.6.1Key Bitting 09 22 00 SD-02 Shop Drawings
2.1 GMetal support systems
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 48 PAGES
09 29 00 SD-03 Product Data Abuse Resistant Gypsum Board
2.1.5Accessories 2.1.1Gypsum Board
SD-06 Test Reports GASTM E90 Factory Test Report
SD-07 Certificates
2.1 GAsbestos Free Materials
09 51 00 SD-02 Shop Drawings
2.1 GApproved Detail Drawings
SD-03 Product Data
2.2.1.1 SRecycled Content For Type Iii
Ceiling Tiles
2.3 SRecycled Content For
Suspension Systems SD-04 Samples
2.2 GAcoustical Units
2.2.1.1 GAcoustical Ceiling Tiles
SD-06 Test Reports
2.1.1 GCeiling Attenuation Class and
Test SD-07 Certificates
2.2.1.1 SIndoor Air Quality For Type Iii
Ceiling Tiles
09 90 00 SD-02 Shop Drawings 3.9Piping Identification
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 48 PAGES
09 90 00 SD-03 Product Data
2.1 GCoating
SD-04 Samples
1.10 GColor
1.5.2 GTextured Wall Coating System
SD-07 Certificates 1.4Applicator's Qualifications
1.5.1.2 GQualification Testing
2.1Indoor Air Quality for Paints and
Primers SD-08 Manufacturer’s Instructions
3.5.2Mixing 1.8.2Manufacturer's Safety Data
Sheets SD-10 Operation and Maintenance Data
2.1 GCoatings
09 96 00 SD-01 Preconstruction Submittals
1.3Equipment List SD-03 Product Data
2.2.1Epoxy Coatings SD-04 Samples
1.3Color Chips SD-07 Certificates
2.2.1Epoxy Coatings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 48 PAGES
09 96 00 3.1.4Manufacturer's Printed Instructions
13 34 19 SD-01 Preconstruction Submittals
1.6.3 GManufacturer's Qualifications
SD-02 Shop Drawings
1.2.1.7 GDetail Drawings
1.6.1 GDetail Drawings
1.2.6 GErection Plan
SD-03 Product Data
1.6.1 G ROManufacturer's Catalog Data
SD-04 Samples
1.6.1 G ROCoil Stock
2.1.8 G ROCoil Stock
1.2.1.9 G RORoof Panels
1.2.1.9 G ROWall Panels
2.5.2 G ROFasteners
2.7.1 G ROMetal Closure Strips
2.4.2 G ROManufacturer's Color Charts and
Chips SD-05 Design Data
1.6.1 G ROManufacturer's Descriptive and
Technical Literature
1.6.1 G ROManufacturer's Building Design
Analysis
SD-06 Test Reports
1.6.1 G ROTest Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 48 PAGES
13 34 19 1.6.1 G ROCoatings and Base Metals
1.6.1 G ROFactory Color Finish Performance
Requirements SD-07 Certificates
1.6.1 G ROSystem Components
1.6.1 G ROCoil Stock
2.1.8 G ROCoil Stock
1.6.1 G ROAluminized Steel Repair Paint
1.6.1 G ROGalvanizing Repair Paint
1.6.1 G ROEnamel Repair Paint
1.6.1 G ROQualification of Manufacturer
1.6.1 G ROQualification of Erector
SD-08 Manufacturer’s Instructions
1.6.2 G ROInstallation of Roof and Wall
panels
1.7 G ROShipping, Handling, and Storage
SD-11 Closeout Submittals
3.11.1 G ROManufacturer's Warranty
3.11.2 G ROContractor's Warranty for
Installation 13 48 00 SD-02 Shop Drawings
3.1 GBracing
3.4 GResilient Vibration Isolation
Devices
2.1 GEquipment Requirements
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 48 PAGES
13 48 00 3.1 GBracing
2.1 GEquipment Requirements
3.3 GAnchor Bolts
2.1.2 GVibration Isolators
3.4.2 GSnubbers
SD-05 Design Data
1.2.3 GDesign Calculations
SD-06 Test Reports
3.3 GAnchor Bolts
SD-07 Certificates
3.6 GICC ES AC156 Shake Table Test
23 00 00 SD-02 Shop Drawings
1.4.4 GDetail Drawings
SD-03 Product Data 2.8.1.2Duct Connectors
2.8.2 GDuct Access Doors
2.8.7Louvers 1.4.5Test Procedures
1.2.1.2 GDiagrams
2.8.1 SIndoor Air Quality for Duct
Sealants 2.8.1.1Metallic Flexible Duct 2.8.1.2Insulated Nonmetallic Flexible
Duct Runouts 2.8.5Sound Attenuation Equipment 2.8.5.3Acoustical Duct Liner
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 48 PAGES
23 00 00 2.8.6.1Registers And Grilles 2.8.8Air Vents, Penthouses, And
Goosenecks
2.10 GAir Handling Units
SD-06 Test Reports
3.11 GPerformance Tests
SD-07 Certificates 1.4.3Ozone Depleting Substances
Technician Certification SD-08 Manufacturer’s Instructions
3.2Manufacturer's Installation Instructions
3.13.2Operation and Maintenance Training
SD-10 Operation and Maintenance Data
3.13.1 GOperation and Maintenance
Manuals
SD-11 Closeout Submittals
3.12 SIndoor Air Quality During
Construction 23 05 48.19 SD-02 Shop Drawings
3.1Coupling and Bracing 3.3Flexible Couplings or Joints 2.2Equipment Restraint
1.2.4 GContractor Designed Bracing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 48 PAGES
23 05 48.19 SD-03 Product Data
3.1 GCoupling and Bracing
3.3 GFlexible Couplings Or Joints
2.2 GEquipment Restraint
1.2.4 GContractor Designed Bracing
2.6Snubbers 3.9Anchor Bolts 2.2.2Vibration Isolators
SD-05 Design Data 1.2.4Design Calculations
SD-06 Test Reports
3.9 GAnchor Bolts
23 05 93 SD-01 Preconstruction Submittals
1.3.3 GRecords of Existing Conditions
1.5.3.1 GTAB Firm
1.2 GTAB Team Assistants
1.2 GTAB Team Engineer
1.5.3.2 GTAB Specialist
1.2 GTAB Team Field Leader
SD-02 Shop Drawings
1.3.3 GTAB Schematic Drawings and
Report Forms SD-03 Product Data
1.3 GEquipment and Performance
Data
1.5.3.4 GTAB Related HVAC Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 48 PAGES
23 05 93 1.5.2 GTAB Procedures
1.5.2 GCalibration
1.3.3 GSystems Readiness Check
1.5.4 GTAB Execution
1.5.4.3 GTAB Verification
SD-06 Test Reports
3.3.5 GCompleted Pre-Final DALT
Report
3.3.8 GCertified Final DALT Report
1.7.2.1 GTAB Design Review Report
1.5.5.2 GTAB Report for Season 1
1.5.5.2 GTAB Report for Season 2
SD-07 Certificates
1.5.1 GIndependent TAB Agency and
Personnel Qualifications
1.7.2 GDALT and TAB Submittal and
Work Schedule
1.7.2.3 GTAB Pre-Field Engineering
Report
1.5.3.1 GTAB Firm
1.3.3 GDesign Review Report
1.7.2.2 GPre-field DALT Preliminary
Notification
1.7.2 GAdvanced Notice for Season 1
TAB Field Work
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 48 PAGES
23 05 93 1.7.2 GPrerequisite HVAC Work Check Out List For Season 1
1.7.2 GAdvanced Notice for Season 2
TAB Field Work
1.7.2 GPrerequisite Hvac Work Check
Out List For Season 2
23 07 00 SD-02 Shop Drawings
3.2.2.4 GMICA Plates
2.3Pipe Insulation Systems 3.2Pipe Insulation Systems 3.3Duct Insulation Systems 3.4Equipment Insulation Systems
2.3.1 SRecycled content for insulation
materials SD-03 Product Data
2.3 GPipe Insulation Systems
3.2 GPipe Insulation Systems
3.3 GDuct Insulation Systems
3.4 GEquipment Insulation Systems
SD-04 Samples
2.2.1.3 GThermal Insulation
3.1.1 GDisplay Samples
SD-07 Certificates
2.2.1 SIndoor air quality for adhesives
SD-08 Manufacturer’s Instructions
2.3 GPipe Insulation Systems
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 48 PAGES
23 07 00 3.2 GPipe Insulation Systems
3.3 GDuct Insulation Systems
3.4 GEquipment Insulation Systems
23 23 00 SD-02 Shop Drawings
2.3 GRefrigerant Piping System
SD-03 Product Data 2.3Refrigerant Piping System 1.5.2Spare Parts 1.3.1Qualifications 3.5Refrigerant Piping Tests 3.1Verification of Dimensions
SD-06 Test Reports 3.5Refrigerant Piping Tests
SD-07 Certificates 2.1Service Organization
SD-10 Operation and Maintenance Data
1.5 GMaintenance
3.4 GOperation and Maintenance
Manuals
3.4 GDemonstrations
23 81 00 SD-03 Product Data 3.7.1Spare Parts 3.4Posted Instructions 2.5.1Coil Corrosion Protection 3.6System Performance Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 48 PAGES
23 81 00 3.4 GTraining 1.5Inventory 2.2.2.5Environmental Data 2.1Supplied Products 2.2Manufacturer's Standard Catalog
Data 2.4.1Humidifier
SD-06 Test Reports
3.5 GRefrigerant Tests, Charging, and
Start-Up
3.6 GSystem Performance Tests
SD-07 Certificates 3.7.2Service Organizations
SD-10 Operation and Maintenance Data
3.4 GOperation and Maintenance
Manuals
SD-11 Closeout Submittals
2.2.2.3 SOzone Depleting Substances
26 05 19.10 SD-03 Product Data
2.1.1 GWire and Cable
2.1.3.1 GConductors
3.1Cable Manufacturing Data
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 48 PAGES
26 05 19.10 3.2 GTest Report(s), Inspection Report(s), and Verification Report(s)
26 05 48 SD-02 Shop Drawings 3.2Lighting Fixtures in Buildings and under Exterior Canopy 1.3Equipment Requirements
SD-03 Product Data
3.2 GLighting Fixtures in Buildings and
under Exterior Canopy
1.3 GEquipment Requirements
1.2.4 GContractor Designed Bracing
26 12 19.10 SD-02 Shop Drawings
1.4.1 GPad-mounted Transformer
Drawings SD-03 Product Data
2.2 GPad-mounted Transformers
SD-06 Test Reports
3.6.1 GAcceptance Checks and Tests
SD-07 Certificates
2.2.2.1 GTransformer Efficiencies
SD-09 Manufacturer’s Field Reports
2.7.1 GTransformer Test Schedule
2.7.2 GDesign Tests
2.7.3 GRoutine and Other Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 48 PAGES
26 12 19.10 SD-10 Operation and Maintenance Data
1.5.1 GTransformer(s)
26 20 00 SD-02 Shop Drawings
2.12 GPanelboards
2.25 GWireways
3.1.8.1 GMarking strips
SD-03 Product Data
2.11 GReceptacles
2.12.3 GCircuit breakers
2.9 GSwitches
2.13 GEnclosed circuit breakers
2.17 GManual motor starters
2.26 GMetering
2.20.3 GGrounding Busbar
2.27 GSurge protective devices
2.16 GMotor Controllers
SD-06 Test Reports
3.5.2 G600-volt wiring test
3.5.4 GGrounding system test
3.5.3 GGround-fault receptacle test
SD-07 Certificates
2.10 GFuses
SD-10 Operation and Maintenance Data
1.5.1 GElectrical Systems
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 48 PAGES
26 20 00 2.26 GMetering 26 35 43 SD-02 Shop Drawings
1.3.1 GFrequency Converter Drawings
SD-03 Product Data
2.1 GFrequency Converter
SD-06 Test Reports
1.3.3 GWork Plan
1.3.4 GRoutine Factory Test Plan
1.3.5 GSpecial Factory Test Plan
1.3.6 GPerformance Test Plan
2.2.1 GTest Schedule
1.3.8 GRoutine Factory Tests
2.2.2 GRoutine Factory Tests
1.3.9 GSpecial Factory Tests
2.2.3 GSpecial Factory Tests
SD-07 Certificates
1.3.2 GQualifications of Manufacturer
1.3.7 GUL Listing
SD-09 Manufacturer’s Field Reports
3.2.3 GInitial Inspection and Tests
1.3.10 GPerformance Tests
3.2.4 GPerformance Tests
3.3.1 GTraining Syllabus
SD-10 Operation and Maintenance Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 48 PAGES
26 35 43 2.1 GFrequency Converter
1.4.1.2 GPreliminary Operation and
Maintenance Manuals 26 41 00 SD-02 Shop Drawings
1.4.1.1 GOverall lightning protection
system
1.4.1.2 GEach…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .