AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 15

0003 Sep 12, 2018

USACE-LOS ANGELES DISTRICT

CONTRACTING DIVISION, EAST REGION BRANCH

915 WILSHIRE BLVD, SUITE 1440

LOS ANGELES, CA 90017

W912PL-18-R-0087

Aug 28, 2018

Amendment 0003 under Solicitation No. W912PL-18-R-0087 for Retrofit Bldg 228, Nellis AFB, Clark County, Nevada

1. Please replace Section 00 22 00 Supplementary Instructions in its entirety.

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code) . Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date) .

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By) . Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor) . For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated ). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data) .

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B . The contracting officer's signature is not required on solicitation amendments. The contracting offier's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13 . Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification) .

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

Total contract price increased by $

Total contract price decreased by $

Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

A reference to the letter determination; and

A statement of the net amount determined to be due in settlement of the contract.

(g)

(h)

(i)

(ii)

(1)

(2)

(3)

(4)

(5)

(6)

(i)

(ii)

(iii)

STANDARD FORM 30 (REV. 10-83) BACK

(1) Accounting classification Net increase $

W912PL-18-R-0087

SECTION 00 22 00 - 1

Retrofit Bldg 228, Nellis AFB, Nevada

Amendment 0003

SECTION 00 22 00

SUPPLEMENTARY INSTRUCTIONS

I GENERAL SUBMISSION REQUIREMENT

II GENERAL INSTRUCTIONS

III SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL

IV SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL

V PROPOSAL COVER SHEET

VI PERFORMANCE ASSESSEMENT REPORT (PAR)

VII SAMPLE COVER LETTER

VIII NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (PPQ)

SECTION 00 22 00 - 2

SECTION 00 22 00

SUPPLEMENTARY INSTRUCTIONS

I. GENERAL SUBMISSION REQUIREMENTS:

In order to effectively and equitably evaluate all offers, the Contracting Officer must receive sufficiently detailed information that clearly responds to the technical evaluation factors listed in Section 00 22 16.

Offerors shall submit their proposal packages in accordance with the instructions outlined in Section 00 22 00, Instructions to Proposers.

Each Offeror must submit their responses to the technical evaluation factors in a Technical Proposal and Price Proposal. The Technical Proposal and Price Proposal must be submitted as separate distinct volumes. Both the Technical Proposal (Volume II) and a Price Proposal (Volume I) must be received by the closing date and time set for receipt of proposals.

No dollar amounts or pricing information from the Price Proposal are to be included in the responses to the technical evaluation factors.

All information intended by the Offeror to be evaluated must be submitted as part of the Technical Proposal.

II. GENERAL INSTRUCTIONS:

All written portions: Use only 8 ½ by 11 inch paper, unless another size is specifically authorized elsewhere in this section for a particular submission. Do not use 11” X 14” or 11” X 17” size sheets (e.g.

fold-outs) unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 12, an unusual font style such as script, or condensed print.

Three-ring binders are preferred. Do not use spring clamps or exceed the recommended capacity of the fastener or binder. Do not use plastic multi-hole/spiral binding systems, heat binding systems, or other systems which do not facilitate the ready insertion of additional pages.

“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the Offeror’s Technical Proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offeror— Competitive Acquisition”, paragraph (3), “Restriction on disclosure and use of data”.

The Corps of Engineers recognizes that submittals by the Offeror may contain confidential or proprietary information; however, the Government reserves the right to make inquiries into the information disclosed. The submission of false or misleading information may be grounds for disqualification of the proposal.

Offeror(s) shall submit their proposal packages to the Los Angeles District Corps of Engineers (COE) in accordance with Section 00 22 00.

III. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL (VOLUME I):

Number of Sets of the Price Proposal: Submit One (1) original hard copy and one electronic copy on

CD.

Format and Contents of the Price Proposal/List of Tabs:

SECTION 00 22 00 - 3

The Price Proposal shall be appropriately labeled as such and shall be organized as indicated in the following chart.

TAB CONTENTS OF THE PRICE PROPOSAL

TAB #1

Proposal Cover Sheet

SF1442 Solicitation, Offer, and Award

TAB #2 The Completed Pricing Schedule

TAB #3 A Bid Guarantee (e.g., Standard Form 24, “Bid Bond”)

TAB #4 Representations and Certifications

TAB # 5 Joint Venture/Teaming Agreement (If Applicable)

IV. SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL (VOLUME II):

Number of Sets and Pages of the Technical Proposal: Submit one original hardcopy of the written Technical Proposal. In addition, submit four complete copies of the technical proposal on Compact Disk (CD) using a searchable “.pdf” file format. The Technical Proposals shall be in 8-1/2" x 11" format, bound as a single document, with single-sided or double-sided pages being acceptable. Condensed print is not permitted. The Proposals shall be separated with section tabs, and the tabs shall clearly identify the contents of each section. The Maximum number of pages for the Technical Proposal is thirty (30) pages single sided or fifteen (15) pages double sided. Performance Assessment Report (PAR) are included within the page limitation. Resumes up to 5 pages single sided and the Past Performance Questionnaires (PPQ) will not be included in the above page count. Each page shall be sequentially numbered for that section.

Format and Contents of the Technical Proposal/List of Tabs: The original and all copies of the technical proposal will be appropriately labeled as such. Each set shall be organized using the tabs specified in the chart below. The tabs directly correlate to the evaluation factors identified in Section 00 22 16.

TAB CONTENTS OF THE TECHNICAL PROPOSAL

TAB #1 EXPERIENCE ON SIMILAR CONTRACTS

TAB #2 TECHNICAL APPROACH, METHODS AND PROCEDURES

TAB #3 PAST PERFORMANCE ON RECENT, RELEVANT CONTRACTS

TAB #4 CORPORATE/ MANAGEMENT STRUCTURE

TAB #5 SCHEDULE

Detailed Submission Requirements for the Technical Proposal: Submit detailed responses to the evaluation factors under each of the tabs as follows:

SECTION 00 22 00 - 4

FACTOR 1: EXPERIENCE ON SIMILAR CONTRACTS

SECTION 00 22 00 - 5

This factor will evaluate the extent of an offeror’s successful experience and proposed team’s experience (key subcontractors) on projects of similar type, scope, magnitude and complexity as compared to the work that is required under this RFP.

FACTOR #2 TECHNICAL APPROACH, METHODS AND PROCEDURES

Proposals will be evaluated as to the offeror’s ability to perform and satisfy all construction contract requirements. Responses to this factor must discuss the offeror’s technical understanding of the work requirements and their commitment to accomplish all the work in accordance with the solicitation requirements and integrated construction schedule.

FACTOR #3 PAST PERFORMANCE

This factor will assess the offeror’s past performance, evaluate whether the offeror’s past performance is relevant or not relevant to that effort to be acquired, and determine contractor capability to successfully perform the proposed effort.

FACTOR #4 CORPORATE/MANAGEMENT STRUCTURE

Proposals will be evaluated as to the offeror’s ability to satisfy all contract requirements within its Corporate Management Structure. The Government will evaluate corporate and construction management structure, experience and qualifications of the key personnel and major subcontractors proposed for the project to include the capability to staff, manage, resource and control successful projects. Personnel will be evaluated on their overall professional experience and on specific experience on projects of similar type, scope, and complexity to the work required under this RFP.

FACTOR #5 SCHEDULE

Proposals will be evaluated as to the offeror’s ability to schedule the construction of the project. The schedule shall show construction activities in a way that minimizes the impact to the government following the phased approach the government has outlined within this RFP. The construction schedule shall clearly show long lead items, indicate the sequence of events and allow for submittals, inspections, and other key activities at the end of the construction cycle including but not limited to as-built drawings, O&M manuals, training, and 1354 Real Property preparation.

V. Proposal Cover Sheet:

The proposal cover sheet is required by FAR 52.215-1(c)(i)-(v). This provision, titled “Instructions to Offerors—Competitive Acquisition,” has been provided in full text in Section 00 21 16. The format is as follows:

PROPOSAL COVER SHEET

1. Solicitation Number: W912PL-18-R-0087

2. The name, address, and telephone and facsimile numbers of the Offeror and electronic address (if available):

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.

4. Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation:

SECTION 00 22 00 - 6

5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

SECTION 00 22 00 - 7

PERFORMANCE ASSESSMENT REPORT

(To be completed by Offeror)

1. Contractor (Firm being evaluated):

Name: Address:

2. Contract Number/ Task Order (TO) (if Applicable):

3. Solicitation Type: Negotiated or Sealed Bid

4. Contract/TO Type: Fixed-Price Cost, Reimbursement, Hybrid (explain)

5. Routine Difficult (low to high) Complexity of Work 1 2 3 4 5

6. Contract/TO Dollar Value:

7. Contract/TO Status: Active, Complete, Completion Date (w/ extensions):

8. Description, location & relevancy of work:

9. Warranty or other problems encountered and how resolved

10. Name, Address, Telephone Number and E-mail of the Procuring Contracting Officer and/or the Contracting Officer’s Representative (COR) (and other references, e.g., Administrative Contracting Officer, if applicable):

11. Ch eck one of the following blocks:

A written performance evaluation was received for this project and is attached.

A written performance evaluation was not received for this project. A Past Performance Questionnaire (PPQ) has been sent to the reference(s) listed in Block 10, with a letter requesting that the completed questionnaire be returned directly to the U.S. Army Corps of Engineers by the closing date for this solicitation.

SECTION 00 22 00 - 8

Retrofit Bldg 228, Nellis AFB, Nevada

Amendment 0003

SAMPLE COVER LETTER

Date

SUBJECT: NAVFAC/USACE Past Performance Questionnaire

Name and Address of Reference

Ladies and Gentlemen:

The U.S. Army Corps of Engineers, Los Angeles District, is conducting a review of our past performance history as part of an upcoming source selection acquisition.

Please complete the attached NAVFAC/USACE Past Performance Questionnaire to aid the Government in its evaluation of our past performance and FAX it directly to the U.S. Army Corps of Engineers, ATTN:

S a n d y O q u i t a at 213-452-3249. If you prefer, you may provide the requested information by email to sandyoquita@usace.army.mil.

The Government is requesting receipt of this information by 10:00 a.m. on S e p t e m b e r 2 7 t h , 2 0 1 8 .

You are advised that it is Government policy that the identity of sources providing past performance information will not be released outside the Government.

We appreciate your efforts to help the Government fairly evaluate our record of past performance. Should you have any questions related to this matter, please contact Sandy Oquita at telephone 213-452-3249.

Sincerely, Contractor

Attachment

SECTION 00 22 00 - 8 Amendment 0003

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire ws completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS.

CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, SECTION 00 22 00 - 9 Amendment 0003

QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.

SECTION 00 22 00 - 10 Amendment 0003

RATING DEFINITION NOTE

FACTOR 3 RATING SCHEME

PAST PERFORMANCE EVALUATION, RATING SCHEME

RATING DESCRIPTION

ACCEPTABLE

Based on the offerors’s past performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s past performance is unknown. (See note below)*

UNACCEPTABLE

Based on the offeror’s past performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort

FACTORS 1, 2, 4, 5 RATING SCHEME

RATING DESCRIPTION

ACCEPTABLE

Proposal meets the minimum requirements of the solicitation.

UNACCEPTABLE

Proposal does not meet the minimum requirements of the solicitation.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N

5. COST/FINANCIAL MANAGEMENT

SECTION 00 22 00 - 11 Amendment 0003

a) Ability to meet the terms and conditions within the contractually agreed price(s)? E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E

VG

S

M

U

N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes

No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes

d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

SECTION 00 22 00 - 12 Amendment 0003