Am3_Specs_W912PL-15-B-0005.pdf

PDF 327 KB Posted

Attached to
MURRIETA CREEK- PHASE 2, SANTA MARGARITA RIVER WATERSHED, RIVERSIDE COUNTY, CALIFORNIA
Solicitation number
W912PL-15-B-0005
Issued by

About this file

Amendment 3 - Specification. Bid Date extended see SF-1442. Changes to 5 specification sections.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

0003 May 14, 2015

U.S. Army Corps of Engineers Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W

W912PL-15-B-0005

Apr 10, 2015

Murrieta Creek - Phase 2. W912PL-15-B-0005. Bid due date is extended to May 20, 2015.

The following Specification Sections are amended. Replace in their entirety.

* SF 1442 - Solicitation, Offer and Award

* 00 10 00 - Contract Line Items Schedule: Changes to line items 34, 35 and 36.

* 00 73 46 - Wage Rates

* 01 22 00 - Measurement and Payment

* 01 50 00 - Temporary Construction Facilities and Controls

* 31 00 00 - Earthwork Drawings: Remove and Replace the following 9 sheets: T-2, C-9, C-10, C-11, C-12, C-27, C-28, C-29, C-30.

Murrieta Creek – Phase 2 W912PL-15-B-0005 Riverside County, CA

TABLE OF CONTENTS - 1 Amendment 3

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SF1442 SOLICITATION, OFFER AND AWARD (SF1442) Am2 Am3

00 01 15 CERTIFICATION PAGE

00 10 00 SOLICITATION, CONTRACT LINE ITEMS SCHEDULE Am1 Am2 Am3

00 21 00 INSTRUCTIONS

00 21 13 INSTRUCTIONS TO BIDDERS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONTRACT CLAUSES Am2 00 73 00 SUPPLEMENTARY CONDITIONS Am2 00 73 46 WAGE RATES Am3

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK Am1 Am2 01 22 00 MEASUREMENT AND PAYMENT Am1 Am2 Am3

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 00a Submittal Register 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS Am1

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 QUALITY CONTROL SYSTEM (QCS)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS Am3 01 50 00a Signs

01 57 20 ENVIRONMENTAL PROTECTION

01 57 20a CRWQCB Permit 01 57 20b Pechanga Tribal Monitoring Agreement

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 13 00 DIVERSION AND CONTROL OF WATER

DIVISION 03 - CONCRETE

03 25 00 SOIL CEMENT

03 30 07 CONCRETE FOR MINOR STRUCTURES

03 36 00 GROUTING STONE PROTECTION

DIVISION 05 - METALS

05 50 15 CIVIL WORKS FABRICATIONS

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK Am3

31 05 22 GEOTEXTILES USED AS FILTERS

31 32 11 SOIL SURFACE EROSION CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE

32 11 30 DECOMPOSED GRANITE

TABLE OF CONTENTS - 2 Amendment 3

32 11 34 PORTLAND CEMENT-STABILIZED BASE OR SUBBASE COURSE

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 31 13 CHAIN LINK FENCES AND GATES

32 84 24 IRRIGATION SPRINKLER SYSTEMS

32 84 25 ELECTRICAL SERVICE (IRRIGATION)

32 92 19 HYDROSEEDING

32 93 00 EXTERIOR PLANTS

DIVISION 33 - UTILITIES

33 21 00 MONUMENTATION AND INSTRUMENTATION Am1

33 40 00 STORM DRAINAGE UTILITIES

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE PROTECTION

-- End of Project Table of Contents --

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

9. FOR INFORMATION CALL

A. NAME B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

Designed using Perform Pro, WHS/DIOR, Oct 96

1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

Amendment 3

W912PL-15-B-0005 X 04/10/2015 1 OF 2

U.S. Army Corps of Engineers Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W

See Item 7

Lubna Khilfeh/Patricia Bonilla 213/452-3308 or 3255

Murrieta Creek, Phase 2, Riverside County, California

The project consists of Channel Improvements of the Murrieta Creek channel extending from downstream of First Street Bridge to the downstream of Rancho California Road approximately 4,300 feet in length. Work includes widening and deepening by excavation, grading, and compacted fill; disposal of excess excavated material; installing about 1.6 miles of riprap and soil cement slope protection, maintenance and bicycle trails, drainage culverts, landscaping and mitigation planting, A.C. paving, access ramps, safety railing and appurtenant work. Location of this work is the Murrieta Creek channel within the City of Temecula in southern Riverside County, CA.

The estimated cost range of construction is between $10,000,000 and $25,000,000. This solicitation is an unrestricted procurement and will be issued under Full and Open Competition.

This procurement will be conducted under FSC CODE: Z299, NAICS Code: 237990. The size standard for this code is $36,500,000. Contract Clause No. FAR 52.219-4, entitled, Price Evaluation Preference for HUBZone Small Business Concerns will be applied to this procurement. The acquisition will use FAR Part 14 Sealed Bidding procedures for award.

BIDDERS PLEASE NOTE: The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of all the items in the Bidding Schedule. This project may be delayed, cancelled, or revised at any time prior to award.

10 *

X X *Section 00 73 00

X 10

0 1:00 PM

20 MAY 2015

X

OFFER (Must be fully completed by offeror)

STANDARD FORM 1442 BACK (REV. 4-85)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24.SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and

(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN

(Type or print)

30B. SIGNATURE 30C. DATE

31A. NAME OF CONTRACTING OFFICER (Type or print)

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

Amendment 3

DUNS NO.: TAX ID NO.:

CAGE CODE NO.:

( ) - ; FAX ( ) -

SECTION 00 10 00 Page 1 Amendment 3

SECTION 00 10 00

SOLICITATION, CONTRACT LINE ITEMS SCHEDULE

PRICE SCHEDULE

Base Bid Items (STATION 59+00 TO STATION 102+00)

Item Description Quantity Unit Unit Price

Amount

0001 DIVERSION AND CONTROL OF WATER 1 Job LS ________

0002 CLEAR SITE AND REMOVE

OBSTRUCTIONS 1 Job LS

0003 DISPOSAL OF DEBRIS 16,000 TON _______ ________

0004 DEMOLITION 1 Job LS ________

0005 EXCAVATION, CHANNEL 250,000 CY _______ ________

0006 CHANNEL EXCAVATION SHORING 1 Job LS ________

0007 COMPACTED FILL 2,000 CY _______ ________

0008 MISCELLANEOUS FILL 3,000 CY _______ ________

0009 COMPACTED FILL, STRUCTURAL 46,600 CY _______ ________

0010 GEOTEXTILE 3,800 SY _______ ________

0011 TURF REINFORCEMENT MAT 4,500 SY _______ ________

0012 TEMPORARY END PROTECTION 1 Job LS ________

0013 ACCESS RAMP, STA 90+20 1 Job LS ________

0014 ACCESS UNDERCROSSING, 1ST STREET 1 Job LS ________

0015 15-,18-, 24-, AND 36-INCH RIPRAP 2,800 TON _______ ________

0016 SOIL CEMENT EMBANKMENT 81,500 CY _______ ________

0017 SIDE DRAIN, STA 60+97 LT 1 Job LS ________

0018 SIDE DRAIN, STA 67+62 RT 1 Job LS ________

SECTION 00 10 00 Page 2 Amendment 3

0019 SIDE DRAIN, STA 69+45 LT 1 Job LS ________

0020 SIDE DRAIN, STA 69+50 RT 1 Job LS ________

0021 SIDE DRAIN, STA 76+37 LT 1 Job LS ________

0022 SIDE DRAIN, STA 81+21 RT 1 Job LS ________

0023 SIDE DRAIN, STA 82+17 LT 1 Job LS ________

0024 SIDE DRAIN, STA 84+10 LT 1 Job LS ________

0025 SIDE DRAIN, STA 86+53 RT 1 Job LS ________

0026 SIDE DRAIN, STA 86+83 RT 1 Job LS ________

0027 SIDE DRAIN, STA 87+54 LT 1 Job LS ________

0028 SIDE DRAIN, STA 91+47 LT 1 Job LS ________

0029 SIDE DRAIN, STA 91+60 RT 1 Job LS ________

0030 SIDE DRAIN, STA 92+27 RT 1 Job LS ________

0031 SIDE DRAIN, STA 92+77 RT 1 Job LS ________

0032 SIDE DRAIN, STA 96+36 RT 1 Job LS ________

0033 (DELETED)

0034 DECOMPOSED GRANITE SURFACING 600 TON _______ ________

0035 AGGREGATE BASE COURSE 2100 TON _______ ________

0036 ASPHALT CONCRETE PAVEMENT 650 TON _______ ________

0037 TOP OF BANK: LANDSCAPING 1 Job LS ________

0038 TOP OF BANK: IRRIGATION SYSTEM 1 Job LS ________

0039 TOP OF BANK: ESTABLISHMENT 1 Job LS ________

0040 CHANNEL REVEGETATION:LANDSCAPING 1 Job LS

SECTION 00 10 00 Page 3 Amendment 3

0041 CHANNEL REVEGETATION: IRRIGATION

SYSTEM 1 Job LS

0042 CHANNEL REVEGETATION:

ESTABLISHMENT 1 Job LS

0043 PIPE ACCESS GATE 1 EA _______ ________

0044 SAFETY RAILING 7,000 LF _______ ________

0045 AS-BUILT DRAWINGS 1 Job LS ________

0046 SETTLEMENT MONUMENT 18 EA _______ ________

0047 PIER NOSE SCOUR PROTECTION –

FIRST STREET 1 Job LS

0048 CONCRETE OVERFLOW DITCH 1 Job LS ________

0049 CONCRETE EDGING 800 LF _______ ________

0050 ORIGINAL AND FINAL SURVEYS 1 Job LS ________

Total Estimated Amount (0001 to 0050): $ ____________

Abbreviations:

LF = Linear Foot CY = Cubic Yard TON = Ton (1 Ton equals to 2000 pounds) EA = Each LS = Lump Sum SY = Square Yard RT = Right LT = Left

SECTION 00 10 00 Page 4 Amendment 3

ADDITIONAL BIDDER'S NOTES:

1. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.

2. If a modification to a bid based on unit prices is submitted which provides for a lump sum adjustment to the total estimated amount, the application of the lump sum adjustment to each unit price in the Price Schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the Price Schedule.

3. Prices must be submitted on all individual items of the Price Schedule, otherwise the bid will be considered non-responsive and will be rejected.

4. For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the Price Schedule as submitted by the bidder:

a. Obviously misplaced decimal points will be corrected;

b. In case of discrepancy between the unit price and the extended price, the unit price will govern;

c. Apparent errors in extensions of unit prices will be corrected;

d. Apparent errors in addition of lump sum and extended prices will be corrected.

5. For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends the bid to be evaluated on the basis of unit prices the totals arrived at by the resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

6. The lump sum "LS" line items in the Price Schedule are not "Estimated Quantity" line items and are not subject to the "Variation in Estimated Quantity" contract clause.

7. The Contract Clause 52.232-27, "Prompt Payment for Construction Contracts" requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.

8. Principal Contracting Officer. The Contracting Officer who signs this contract will be the Principal Contracting Officer for this contract.

However, any Contracting Officer assigned to the Los Angeles District, Contracting within his authority, may take formal action on this contract when the Principal Contracting Officer is unavailable and the action needs to be taken.

9. Amounts and prices shall be indicated in either words or figures, NOT

BOTH.

10. The bidder shall distribute his indirect costs (overhead, profit, bond, etc.,) over all items in the Price Schedule. The Government will review all submitted Price Schedules for any unbalancing of the items. Any submitted Price Schedule determined to be unbalanced may be considered nonresponsive and cause the bidder to be ineligible for contract award.

SECTION 00 10 00 Page 5 Amendment 3

11. The bidder shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract in include all attachments thereto.

12. Some quantities are ESTIMATED, the bidders prices MUST BE FIRM.

13. Bidder is cautioned to check his Price Schedule carefully prior to submission. If the Price Schedule contains unit prices, they should be round off to the second decimal point only NOT EXTENDED FURTHER.

15. Contractor is required to fill in Cage code, TIN and DUNS Number in Block No. 14 on Standard Form 1442, the Name and Address Block.

-- End of Section –

SECTION 00 73 46

WAGE DETERMINATION SCHEDULE - 1 Amendment 3

General Decision Number: CA150036 05/08/2015 CA36

Superseded General Decision Number: CA20140036

State: California

Construction Types: Building, Heavy (Heavy and Dredging) and Highway

County: Riverside County in California.

BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS

Note: Executive Order (EO) 13658 establishes an hourly minimum wage of $10.10 for 2015 that applies to all contracts subject to the Davis-Bacon Act for which the solicitation is issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.10 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/02/2015 1 01/16/2015 2 01/23/2015 3 02/20/2015 4 03/27/2015 5 05/08/2015

ASBE0005-002 06/30/2014

Rates Fringes

Asbestos Workers/Insulator (Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems).....$ 35.44 19.36 Fire Stop Technician (Application of Firestopping Materials for wall openings and penetrations in walls, floors, ceilings and curtain walls)...........................$ 24.34 16.09

ASBE0005-004 06/24/2013

WAGE DETERMINATION SCHEDULE - 2 Amendment 3

Rates Fringes

Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 16.95 10.23

BOIL0092-003 10/01/2012

Rates Fringes

BOILERMAKER......................$ 41.17 28.27

* BRCA0004-011 05/01/2015

Rates Fringes

BRICKLAYER; MARBLE SETTER........$ 37.15 13.02

*The wage scale for prevailing wage projects performed in Blythe, China lake, Death Valley, Fort Irwin, Twenty-Nine Palms, Needles and 1-15 corridor (Barstow to the Nevada State Line) will be Three Dollars ($3.00) above the standard San Bernardino/Riverside County hourly wage rate

BRCA0018-004 06/01/2014

Rates Fringes

MARBLE FINISHER..................$ 28.45 11.38

TILE FINISHER....................$ 23.78 9.84

TILE LAYER.......................$ 35.14 14.33

BRCA0018-010 09/01/2013

Rates Fringes

TERRAZZO FINISHER................$ 26.59 10.34

TERRAZZO WORKER/SETTER...........$ 33.63 11.13

CARP0409-001 07/01/2010

Rates Fringes

CARPENTER

(1) Carpenter, Cabinet Installer, Insulation Installer, Hardwood Floor Worker and acoustical installer...................$ 37.35 11.08

WAGE DETERMINATION SCHEDULE - 3 Amendment 3

(2) Millwright..............$ 37.85 11.08

(3) Piledrivermen/Derrick Bargeman, Bridge or Dock Carpenter, Heavy Framer, Rock Bargeman or Scowman, Rockslinger, Shingler (Commercial)................$ 37.48 11.08

(4) Pneumatic Nailer, Power Stapler...............$ 37.60 11.08

(5) Sawfiler...............$ 37.44 11.08

(6) Scaffold Builder.......$ 28.55 11.08

(7) Table Power Saw Operator....................$ 37.45 11.08

FOOTNOTE: Work of forming in the construction of open cut sewers or storm drains, on operations in which horizontal lagging is used in conjunction with steel H-Beams driven or placed in pre- drilled holes, for that portion of a lagged trench against which concrete is poured, namely, as a substitute for back forms (which work is performed by piledrivers): $0.13 per hour additional.

CARP0409-002 07/01/2008

Rates Fringes

Diver

(1) Wet.....................$ 663.68 9.82

(2) Standby.................$ 331.84 9.82

(3) Tender..................$ 323.84 9.82

(4) Assistant Tender........$ 299.84 9.82

Amounts in "Rates' column are per day

CARP0409-005 07/01/2010

Rates Fringes

Drywall

DRYWALL INSTALLER/LATHER....$ 37.35 11.08

STOCKER/SCRAPPER............$ 10.00 6.67

CARP0409-008 08/01/2010

Rates Fringes

Modular Furniture Installer......$ 17.00 7.41

ELEC0440-001 12/01/2014

Rates Fringes

ELECTRICIAN

INSIDE ELECTRICIAN..........$ 36.09 22.07

INTELLIGENT TRANSPORTATION

SYSTEMS

WAGE DETERMINATION SCHEDULE - 4 Amendment 3

Electrician................$ 36.09 22.07 Technician.................$ 27.07 21.80

ZONE PAY: Zone A: Free travel zone for all contractors performing work in Zone A.

Zone B:Any work performed in Zone (B) shall add $12.00 per hour to the current wage scale. Zone (B) shall be the area from the eastern perimeter of Zone (A) to a line which runs north and south begininng at Little Morongo Canyon (San Bernardino/Riverside County Line), Southeast along the Coachella Tunnels, Colorado River Aqueduct and Mecca Tunnels to Pinkham Wash then South to Box Canyon Road, then southwest along Box Canyon Road to Highway 195 west onto 195 south to Highway 86 to Riverside/Imperial County Line.

ELEC0440-004 05/26/2014

COMMUNICATIONS AND SYSTEMS WORK

Rates Fringes

Communications System Installer...................$ 28.38 4%+11.45 Technician..................$ 30.18 4%+11.45

SCOPE OF WORK:

Installation, testing, service and maintenance of systems utilizing the transmission and/or transference of voice, sound, vision and digital for commercial, educational, security and entertainment purposes for the following: TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call systems, radio page, school intercom and sound, burglar alarms, fire alarms, and low voltage master clock systems in commercial buildings. Communication Systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding all other data systems or multiple systems which include control function or power supply; excluding installation of raceway systems, conduit systems, line voltage work, and energy management systems. Does not cover work performed at China Lake Naval Ordnance Test Station.

ELEC1245-001 06/01/2013

Rates Fringes

LINE CONSTRUCTION

(1) Lineman; Cable splicer..$ 50.30 15.00

(2) Equipment specialist (operates crawler tractors, commercial motor

WAGE DETERMINATION SCHEDULE - 5 Amendment 3 vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)...........$ 40.17 14.56

(3) Groundman...............$ 30.73 13.48

(4) Powderman...............$ 44.91 13.48

HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day

ELEV0018-001 01/01/2015

Rates Fringes

ELEVATOR MECHANIC................$ 49.90 28.38

FOOTNOTE:

PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service.

PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.

ENGI0012-003 07/07/2014

Rates Fringes

OPERATOR: Power Equipment (All Other Work)

GROUP 1....................$ 39.05 22.25

GROUP 2....................$ 39.83 22.25

GROUP 3....................$ 40.12 22.25

GROUP 4....................$ 41.61 22.25

GROUP 5....................$ 41.86 22.25

GROUP 6....................$ 41.83 22.25

GROUP 8....................$ 41.94 22.25

GROUP 9....................$ 42.19 22.25

GROUP 10....................$ 42.06 22.25

GROUP 11....................$ 42.31 22.25

GROUP 12....................$ 42.23 22.25

GROUP 13....................$ 42.33 22.25

GROUP 14....................$ 42.36 22.25

GROUP 15....................$ 42.44 22.25

GROUP 16....................$ 42.56 22.25

GROUP 17....................$ 42.73 22.25

GROUP 18....................$ 42.83 22.25

GROUP 19....................$ 42.94 22.25

GROUP 20....................$ 43.06 22.25

GROUP 21....................$ 43.23 22.25

GROUP 22....................$ 43.33 22.25

GROUP 23....................$ 43.44 22.25

GROUP 24....................$ 43.56 22.25

WAGE DETERMINATION SCHEDULE - 6 Amendment 3

GROUP 25....................$ 43.73 22.25

OPERATOR: Power Equipment (Cranes, Piledriving & Hoisting)

GROUP 1....................$ 40.40 22.25

GROUP 2....................$ 41.18 22.25

GROUP 3....................$ 41.47 22.25

GROUP 4....................$ 41.61 22.25

GROUP 5....................$ 41.83 22.25

GROUP 6....................$ 41.94 22.25

GROUP 7....................$ 42.06 22.25

GROUP 8....................$ 42.23 22.25

GROUP 9....................$ 42.40 22.25

GROUP 10....................$ 43.40 22.25

GROUP 11....................$ 44.40 22.25

GROUP 12....................$ 45.40 22.25

GROUP 13....................$ 46.40 22.25

OPERATOR: Power Equipment (Tunnel Work)

GROUP 1....................$ 40.90 22.25

GROUP 2....................$ 41.68 22.25

GROUP 3....................$ 41.97 22.25

GROUP 4....................$ 42.11 22.25

GROUP 5....................$ 42.33 22.25

GROUP 6....................$ 42.44 22.25

GROUP 7....................$ 42.56 22.25

PREMIUM PAY:

$3.75 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton

Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator.

SEE ZONE DEFINITIONS AFTER CLASSIFICATIONS

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Bargeman; Brakeman; Compressor operator; Ditch Witch, with seat or similar type equipment; Elevator operator-inside; Engineer Oiler; Forklift operator (includes loed, lull or similar types under 5 tons;

Generator operator; Generator, pump or compressor plant operator; Pump operator; Signalman; Switchman

GROUP 2: Asphalt-rubber plant operator (nurse tank operator);

Concrete mixer operator-skip type; Conveyor operator;

Fireman; Forklift operator (includes loed, lull or similar types over 5 tons; Hydrostatic pump operator; oiler crusher (asphalt or concrete plant); Petromat laydown machine; PJU side dum jack; Screening and conveyor machine operator (or

WAGE DETERMINATION SCHEDULE - 7 Amendment 3 similar types); Skiploader (wheel type up to 3/4 yd.

without attachment); Tar pot fireman; Temporary heating plant operator; Trenching machine oiler

GROUP 3: Asphalt-rubber blend operator; Bobcat or similar type (Skid steer); Equipment greaser (rack); Ford Ferguson (with dragtype attachments); Helicopter radioman (ground);

Stationary pipe wrapping and cleaning machine operator

GROUP 4: Asphalt plant fireman; Backhoe operator (mini-max or similar type); Boring machine operator; Boxman or mixerman (asphalt or concrete); Chip spreading machine operator;

Concrete cleaning decontamination machine operator;

Concrete Pump Operator (small portable); Drilling machine operator, small auger types (Texoma super economatic or similar types - Hughes 100 or 200 or similar types -drilling depth of 30' maximum); Equipment greaser (grease truck); Guard rail post driver operator; Highline cableway signalman; Hydra-hammer-aero stomper; Micro Tunneling (above ground tunnel); Power concrete curing machine operator; Power concrete saw operator; Power-driven jumbo form setter operator; Power sweeper operator; Rock Wheel Saw/Trencher; Roller operator (compacting); Screed operator (asphalt or concrete); Trenching machine operator (up to 6 ft.); Vacuum or much truck

GROUP 5: Equipment Greaser (Grease Truck/Multi Shift).

GROUP 6: Articulating material hauler; Asphalt plant engineer; Batch plant operator; Bit sharpener; Concrete joint machine operator (canal and similar type); Concrete planer operator; Dandy digger; Deck engine operator;

Derrickman (oilfield type); Drilling machine operator, bucket or auger types (Calweld 100 bucket or similar types

- Watson 1000 auger or similar types - Texoma 330, 500 or 600 auger or similar types - drilling depth of 45' maximum); Drilling machine operator; Hydrographic seeder machine operator (straw, pulp or seed), Jackson track maintainer, or similar type; Kalamazoo Switch tamper, or similar type; Machine tool operator; Maginnis internal full slab vibrator, Mechanical berm, curb or gutter(concrete or asphalt); Mechanical finisher operator (concrete, Clary-Johnson-Bidwell or similar); Micro tunnel system (below ground); Pavement breaker operator (truck mounted);

Road oil mixing machine operator; Roller operator (asphalt or finish), rubber-tired earth moving equipment (single engine, up to and including 25 yds. struck); Self-propelled tar pipelining machine operator; Skiploader operator (crawler and wheel type, over 3/4 yd. and up to and including 1-1/2 yds.); Slip form pump operator (power driven hydraulic lifting device for concrete forms);

Tractor operator-bulldozer, tamper-scraper (single engine, up to 100 h.p. flywheel and similar types, up to and including D-5 and similar types); Tugger hoist operator (1 drum); Ultra high pressure waterjet cutting tool system operator; Vacuum blasting machine operator

WAGE DETERMINATION SCHEDULE - 8 Amendment 3

GROUP 8: Asphalt or concrete spreading operator (tamping or finishing); Asphalt paving machine operator (Barber Greene or similar type); Asphalt-rubber distribution operator;

Backhoe operator (up to and including 3/4 yd.), small ford, Case or similar; Cast-in-place pipe laying machine operator; Combination mixer and compressor operator (gunite work); Compactor operator (self-propelled); Concrete mixer operator (paving); Crushing plant operator; Drill Doctor;

Drilling machine operator, Bucket or auger types (Calweld 150 bucket or similar types - Watson 1500, 2000 2500 auger or similar types - Texoma 700, 800 auger or similar types -drilling depth of 60' maximum); Elevating grader operator;

Grade checker; Gradall operator; Grouting machine operator;

Heavy-duty repairman; Heavy equipment robotics operator;

Kalamazoo balliste regulator or similar type; Kolman belt loader and similar type; Le Tourneau blob compactor or similar type; Loader operator (Athey, Euclid, Sierra and similar types); Mobark Chipper or similar; Ozzie padder or similar types; P.C. slot saw; Pneumatic concrete placing machine operator (Hackley-Presswell or similar type);

Pumpcrete gun operator; Rock Drill or similar types; Rotary drill operator (excluding caisson type); Rubber-tired earth-moving equipment operator (single engine, caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. up to and including 50 cu.

yds. struck); Rubber-tired earth-moving equipment operator (multiple engine up to and including 25 yds. struck);

Rubber-tired scraper operator (self-loading paddle wheel type-John Deere, 1040 and similar single unit); Self-propelled curb and gutter machine operator; Shuttle buggy;

Skiploader operator (crawler and wheel type over 1-1/2 yds.

up to and including 6-1/2 yds.); Soil remediation plant operator; Surface heaters and planer operator; Tractor compressor drill combination operator; Tractor operator (any type larger than D-5 - 100 flywheel h.p. and over, or similar-bulldozer, tamper, scraper and push tractor single engine); Tractor operator (boom attachments), Traveling pipe wrapping, cleaning and bendng machine operator;

Trenching machine operator (over 6 ft. depth capacity, manufacturer's rating); trenching Machine with Road Miner attachment (over 6 ft depth capacity): Ultra high pressure waterjet cutting tool system mechanic; Water pull (compaction) operator

GROUP 9: Heavy Duty Repairman

GROUP 10: Drilling machine operator, Bucket or auger types (Calweld 200 B bucket or similar types-Watson 3000 or 5000 auger or similar types-Texoma 900 auger or similar types-drilling depth of 105' maximum); Dual drum mixer, dynamic compactor LDC350 (or similar types); Monorail locomotive operator (diesel, gas or electric); Motor patrol-blade operator (single engine); Multiple engine tractor operator (Euclid and similar type-except Quad 9 cat.); Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Pneumatic pipe ramming tool and similar types; Prestressed wrapping machine operator;

WAGE DETERMINATION SCHEDULE - 9 Amendment 3

Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Rubber tired earth moving equipment operator (multiple engine, Euclid, caterpillar and similar over 25 yds. and up to 50 yds. struck), Tower crane repairman; Tractor loader operator (crawler and wheel type over 6-1/2 yds.); Woods mixer operator (and similar Pugmill equipment)

GROUP 11: Heavy Duty Repairman - Welder Combination, Welder - Certified.

GROUP 12: Auto grader operator; Automatic slip form operator;

Drilling machine operator, bucket or auger types (Calweld, auger 200 CA or similar types - Watson, auger 6000 or similar types - Hughes Super Duty, auger 200 or similar types - drilling depth of 175' maximum); Hoe ram or similar with compressor; Mass excavator operator less tha 750 cu.

yards; Mechanical finishing machine operator; Mobile form traveler operator; Motor patrol operator (multi-engine);

Pipe mobile machine operator; Rubber-tired earth- moving equipment operator (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck); Rubber-tired self- loading scraper operator (paddle-wheel-auger type self-loading - two (2) or more units)

GROUP 13: Rubber-tired earth-moving equipment operator operating equipment with push-pull system (single engine, up to and including 25 yds. struck)

GROUP 14: Canal liner operator; Canal trimmer operator;

Remote- control earth-moving equipment operator (operating a second piece of equipment: $1.00 per hour additional);

Wheel excavator operator (over 750 cu. yds.)

GROUP 15: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine-up to and including 25 yds. struck)

GROUP 16: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)

GROUP 17: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 50 cu. yds. struck);

Tandem tractor operator (operating crawler type tractors in tandem - Quad 9 and similar type)

GROUP 18: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar

WAGE DETERMINATION SCHEDULE - 10 Amendment 3 types in any combination, excluding compaction units -single engine, up to and including 25 yds. struck)

GROUP 19: Rotex concrete belt operator (or similar types);

Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds.and up to and including 50

cu. yds. struck); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units - multiple engine, up to and including 25 yds. struck)

GROUP 20: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps, and similar types in any combination, excluding compaction units - multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)

GROUP 21: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction units -multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)

GROUP 22: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, up to and including 25 yds. struck)

GROUP 23: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating with the tandem push-pull system (multiple engine, up to and including 25 yds. struck)

GROUP 24: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds.

struck)

GROUP 25: Concrete pump operator-truck mounted; Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)

CRANES, PILEDRIVING AND HOISTING EQUIPMENT CLASSIFICATIONS

WAGE DETERMINATION SCHEDULE - 11 Amendment 3

GROUP 1: Engineer oiler; Fork lift operator (includes loed, lull or similar types)

GROUP 2: Truck crane oiler

GROUP 3: A-frame or winch truck operator; Ross carrier operator (jobsite)

GROUP 4: Bridge-type unloader and turntable operator;

Helicopter hoist operator

GROUP 5: Hydraulic boom truck; Stinger crane (Austin-Western or similar type); Tugger hoist operator (1 drum)

GROUP 6: Bridge crane operator; Cretor crane operator; Hoist operator (Chicago boom and similar type); Lift mobile operator; Lift slab machine operator (Vagtborg and similar types); Material hoist and/or manlift operator; Polar gantry crane operator; Self Climbing scaffold (or similar type); Shovel, backhoe, dragline, clamshell operator (over 3/4 yd. and up to 5 cu. yds. mrc); Tugger hoist operator

GROUP 7: Pedestal crane operator; Shovel, backhoe, dragline, clamshell operator (over 5 cu. yds. mrc); Tower crane repair; Tugger hoist operator (3 drum)

GROUP 8: Crane operator (up to and including 25 ton capacity); Crawler transporter operator; Derrick barge operator (up to and including 25 ton capacity); Hoist operator, stiff legs, Guy derrick or similar type (up to and including 25 ton capacity); Shovel, backhoe, dragline, clamshell operator (over 7 cu. yds., M.R.C.)

GROUP 9: Crane operator (over 25 tons and up to and including 50 tons mrc); Derrick barge operator (over 25 tons up to and including 50 tons mrc); Highline cableway operator;

Hoist operator, stiff legs, Guy derrick or similar type (over 25 tons up to and including 50 tons mrc); K-crane operator; Polar crane operator; Self erecting tower crane operator maximum lifting capacity ten tons

GROUP 10: Crane operator (over 50 tons and up to and including 100 tons mrc); Derrick barge operator (over 50 tons up to and including 100 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 50 tons up to and including 100 tons mrc), Mobile tower crane operator (over 50 tons, up to and including 100 tons M.R.C.); Tower crane operator and tower gantry

GROUP 11: Crane operator (over 100 tons and up to and including 200 tons mrc); Derrick barge operator (over 100 tons up to and including 200 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 100 tons up to and including 200 tons mrc); Mobile tower crane operator (over 100 tons up to and including 200 tons mrc)

WAGE DETERMINATION SCHEDULE - 12 Amendment 3

GROUP 12: Crane operator (over 200 tons up to and including 300 tons mrc); Derrick barge operator (over 200 tons up to and including 300 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 200 tons, up to and including 300 tons mrc); Mobile tower crane operator (over 200 tons, up to and including 300 tons mrc)

GROUP 13: Crane operator (over 300 tons); Derrick barge operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons);

Mobile tower crane operator (over 300 tons)

TUNNEL CLASSIFICATIONS

GROUP 1: Skiploader (wheel type up to 3/4 yd. without attachment)

GROUP 2: Power-driven jumbo form setter operator

GROUP 3: Dinkey locomotive or motorperson (up to and including 10 tons)

GROUP 4: Bit sharpener; Equipment greaser (grease truck);

Slip form pump operator (power-driven hydraulic lifting device for concrete forms); Tugger hoist operator (1 drum);

Tunnel locomotive operator (over 10 and up to and including 30 tons)

GROUP 5: Backhoe operator (up to and including 3/4 yd.);

Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shield operator; Heavy-duty repairperson;

Loader operator (Athey, Euclid, Sierra and similar types);

Mucking machine operator (1/4 yd., rubber-tired, rail or track type); Pneumatic concrete placing machine operator (Hackley-Presswell or similar type); Pneumatic heading shield (tunnel); Pumpcrete gun operator; Tractor compressor drill combination operator; Tugger hoist operator (2 drum);

Tunnel locomotive operator (over 30 tons)

GROUP 6: Heavy Duty Repairman

GROUP 7: Tunnel mole boring machine operator

ENGINEERS ZONES

$1.00 additional per hour for all of IMPERIAL County and the portions of KERN, RIVERSIDE & SAN BERNARDINO Counties as defined below:

That area within the following Boundary: Begin in San Bernardino County, approximately 3 miles NE of the intersection of I-15 and the California State line at that point which is the NW corner of Section 1, T17N,m R14E, San Bernardino Meridian. Continue W in a straight line to that point which is the SW corner of the northwest quarter of Section 6, T27S, R42E, Mt. Diablo Meridian. Continue North to the intersection with the Inyo County Boundary at that point which is the NE

WAGE DETERMINATION SCHEDULE - 13 Amendment 3 corner of the western half of the northern quarter of Section 6, T25S, R42E, MDM. Continue W along the Inyo and San Bernardino County boundary until the intersection with Kern County, as that point which is the SE corner of Section 34, T24S, R40E, MDM. Continue W along the Inyo and Kern County boundary until the intersection with Tulare County, at that point which is the SW corner of the SE quarter of Section 32, T24S, R37E, MDM. Continue W along the Kern and Tulare County boundary, until that point which is the NW corner of T25S, R32E, MDM. Continue S following R32E lines to the NW corner of T31S, R32E, MDM. Continue W to the NW corner of T31S, R31E, MDM. Continue S to the SW corner of T32S, R31E, MDM. Continue W to SW corner of SE quarter of Section 34, T32S, R30E, MDM.

Continue S to SW corner of T11N, R17W, SBM. Continue E along south boundary of T11N, SBM to SW corner of T11N, R7W, SBM.

Continue S to SW corner of T9N, R7W, SBM. Continue E along south boundary of T9N, SBM to SW corner of T9N, R1E, SBM.

Continue S along west boundary of R1E, SMB to Riverside County line at the SW corner of T1S, R1E, SBM. Continue E along south boundary of T1s, SBM (Riverside County Line) to SW corner of T1S, R10E, SBM. Continue S along west boundary of R10E, SBM to Imperial County line at the SW corner of T8S, R10E, SBM.

Continue W along Imperial and Riverside county line to NW corner of T9S, R9E, SBM. Continue S along the boundary between Imperial and San Diego Counties, along the west edge of R9E, SBM to the south boundary of Imperial County/California state line. Follow the California state line west to Arizona state line, then north to Nevada state line, then continuing NW back to start at the point which is the NW corner of Section 1, T17N, R14E, SBM

$1.00 additional per hour for portions of SAN LUIS OBISPO, KERN, SANTA BARBARA & VENTURA as defined below:

That area within the following Boundary: Begin approximately 5 miles north of the community of Cholame, on the Monterey County and San Luis Obispo County boundary at the NW corner of T25S, R16E, Mt. Diablo Meridian. Continue south along the west side of R16E to the SW corner of T30S, R16E, MDM. Continue E to SW corner of T30S, R17E, MDM. Continue S to SW corner of T31S, R17E, MDM. Continue E to SW corner of T31S, R18E, MDM.

Continue S along West side of R18E, MDM as it crosses into San Bernardino Meridian numbering area and becomes R30W. Follow the west side of R30W, SBM to the SW corner of T9N, R30W, SBM.

Continue E along the south edge of T9N, SBM to the Santa Barbara County and Ventura County boundary at that point whch is the SW corner of Section 34.T9N, R24W, SBM, continue S along the Ventura County line to that point which is the SW corner of the SE quarter of Section 32, T7N, R24W, SBM. Continue E along the south edge of T7N, SBM to the SE corner to T7N, R21W, SBM. Continue N along East side of R21W, SBM to Ventura County and Kern County boundary at the NE corner of T8N, R21W.

Continue W along the Ventura County and Kern County boundary to the SE corner of T9N, R21W. Continue North along the East edge of R21W, SBM to the NE corner of T12N, R21W, SBM. Continue West along the north edge of T12N, SBM to the SE corner of T32S, R21E, MDM. [T12N SBM is a think strip between T11N SBM

WAGE DETERMINATION SCHEDULE - 14 Amendment 3 and T32S MDM]. Continue North along the East side of R21E, MDM to the Kings County and Kern County border at the NE corner of T25S, R21E, MDM, continue West along the Kings County and Kern County Boundary until the intersection of San Luis Obispo County. Continue west along the Kings County and San Luis Obispo County boundary until the intersection with Monterey County. Continue West along the Monterey County and San Luis Obispo County boundary to the beginning point at the NW corner of T25S, R16E, MDM.

$2.00 additional per hour for INYO and MONO Counties and the Northern portion of SAN BERNARDINO County as defined below:

That area within the following Boundary: Begin at the intersection of the northern boundary of Mono County and the California state line at the point which is the center of Section 17, T10N, R22E, Mt. Diablo Meridian. Continue S then SE along the entire western boundary of Mono County, until it reaches Inyo County at the point which is the NE corner of the Western half of the NW quarter of Section 2, T8S, R29E, MDM.

Continue SSE along the entire western boundary of Inyo County, until the intersection with Kern County at the point which is the SW corner of the SE 1/4 of Section 32, T24S, R37E, MDM.

Continue E along the Inyo and Kern County boundary until the intersection with San Bernardino County at that point which is the SE corner of section 34, T24S, R40E, MDM. Continue E along the Inyo and San Bernardino County boundary until the point which is the NE corner of the Western half of the NW quarter of Section 6, T25S, R42E, MDM. Continue S to that point which is the SW corner of the NW quarter of Section 6, T27S, R42E, MDM.

Continue E in a straight line to the California and Nevada state border at the point which is the NW corner of…

This is the start of the file's text. The full file is on GovTribe.