CONTRACTOR TOTAL BID (Base plus Options)

Vido Artukovich & Son, Inc./Vidmar, Inc. A JV $2,477,440.00

GRFCO, Inc. $2,670,670.00

CJW Construction, Inc. $2,945,775.00

ACE Engineering, Inc. $4,669,053.96

Government Estimate $2,153,247.00

Base Bid Plus 6 Option Items

WEST BASIN MUNICIPAL WATER DISTRICT

CARSON, LOS ANGELES COUNTY, CA

BID ABSTRACT

IFB W912PL-15-B-0002

CARSON MALL LATERAL - PHASE 2

RECYCLED WATER SYSTEM EXPANSION PROJECT

Bid Opening Date: January 13, 2015

CARSON MALL LATERAL-PHASE 2 W912PL-15-B-0002

BID SCHEDULE

FAIR AND REASONABLE GOVERNMENT ESTIMATE

ESTIMATED

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Bid Items

1 MOBILIZATION, PERMITS AND DEMOBILIZATION 1 JOB $142,000.00 142,000.00

2 CONSTRUCT 12-INCH PVC PIPE 4,415 LF $146.00 644,590.00

3 CONSTRUCT 12-INCH DI PIPE 229 LF $173.00 39,617.00

4 CONSTRUCT 12-INCH RW GATE VALVE 3 EA $5,300.00 15,900.00

5 CONSTRUCT 1-INCH COMBINATION AIR VALVE ASSEMBLY 6 EA $5,500.00 33,000.00

6 CONSTRUCT 4-INCH BLOW-OFF ASSEMBLY 4 EA $10,500.00 42,000.00

7 CONSTRUCT BORE & JACK WITH 24-INCH STEEL CASING 115 LF $2,600.00 299,000.00

8 CONNECTION TO EXISTING 12-INCH RW MAIN AT JIM DEAR BLVD 1 EA $9,200.00 9,200.00 9 CONSTRUCT 3-INCH RW SERVICE LATERAL PER WBMWD STD. DWG. RW 4 1 EA $16,300.00 16,300.00 10 CONSTRUCT 2-INCH RW SERVICE LATERAL PER WBMWD STD. DWG.RW 3 1 EA $4,500.00 4,500.00

11 REMOVAL AND REPLACEMENT OF AC PAVEMENT AND AB BASE 9,500 SF $13.00 123,500.00

12 REMOVAL AND REPLACEMENT OF AC PAVEMENT OVER PCC ROAD 12,500 SF $23.00 287,500.00

13 SLURRY SEAL OF STREET 276,000 SF $0.65 179,400.00

14 REPLACE TRAFFIC LOOPS DAMAGED BY CONSTRUCTION 1 JOB $11,000.00 11,000.00

15 TRAFFIC STRIPING AND MARKING 1 JOB $17,000.00 17,000.00

16 HYDROSTATIC TESTING 1 JOB $10,000.00 10,000.00

17 TRAFFIC CONTROL 1 JOB $103,000.00 103,000.00

18 FURNISH AND INSTALL SAFETY MEASURES 1 JOB $32,000.00 32,000.00

19 AS-BUILT DRAWINGS 1 JOB $5,000.00 5,000.00

REMOVE & REPLACE CONCRETE SIDEWALK, CURB, GUTTERS, LANDSCAPING,

IRRIGATION, & CENTER MEDIANS 1 JOB $45,000.00 45,000.00

TOTAL BASE BID AMOUNT: $2,059,507.00

Optional Bid Items

OPTION 1: CONSTRUCT DEAD END WITH TEMPORARY 2-INCH BLOW-OFF PER

WBMWD STD. DWG. RW 12 AT STA. 56+55± 1 JOB $4,000.00 $4,000.00

OPTION 2: CONNECT TO EXISTING 12-INCH PVC RECYCLED WATER

CONSTRUCTED BY THE CITY OF CARSON AT CARSON ST. 1 JOB $9,200.00 $9,200.00

OPTION 3: RELOCATE WORK HEADING (TO ACCOMMODATE CONTAMINATED

SOIL REMEDIATION WORK) 2 EA $14,600.00 $29,200.00

OPTION 4: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS (CLASS I

DISPOSAL) 200 CY $203.00 $40,600.00

OPTION 5: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS-POCKETS

OF HYDROCARBON (CLASS III DISPOSAL) 20 CY $102.00 $2,040.00

26 OPTION 6: SUBGRADE STABILIZATION 50 CY $174.00 $8,700.00

TOTAL OPTIONAL BID AMOUNT: $93,740.00

TOTAL BASE AND OPTIONAL BID AMOUNT: $2,153,247.00

VIDO ARTUKOVICH & SON, INC./VIDMAR, INC. A JV

ESTIMATED

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Bid Items

1 MOBILIZATION, PERMITS AND DEMOBILIZATION 1 JOB $150,000.00 150,000.00

2 CONSTRUCT 12-INCH PVC PIPE 4,415 LF $290.00 1,280,350.00

3 CONSTRUCT 12-INCH DI PIPE 229 LF $310.00 70,990.00

4 CONSTRUCT 12-INCH RW GATE VALVE 3 EA $4,000.00 12,000.00

5 CONSTRUCT 1-INCH COMBINATION AIR VALVE ASSEMBLY 6 EA $3,500.00 21,000.00

6 CONSTRUCT 4-INCH BLOW-OFF ASSEMBLY 4 EA $5,000.00 20,000.00

7 CONSTRUCT BORE & JACK WITH 24-INCH STEEL CASING 115 LF $700.00 80,500.00

8 CONNECTION TO EXISTING 12-INCH RW MAIN AT JIM DEAR BLVD 1 EA $3,500.00 3,500.00 9 CONSTRUCT 3-INCH RW SERVICE LATERAL PER WBMWD STD. DWG. RW 4 1 EA $4,500.00 4,500.00 10 CONSTRUCT 2-INCH RW SERVICE LATERAL PER WBMWD STD. DWG.RW 3 1 EA $3,500.00 3,500.00

11 REMOVAL AND REPLACEMENT OF AC PAVEMENT AND AB BASE 9,500 SF $10.00 95,000.00

12 REMOVAL AND REPLACEMENT OF AC PAVEMENT OVER PCC ROAD 12,500 SF $20.00 250,000.00

13 SLURRY SEAL OF STREET 276,000 SF $0.60 165,600.00

14 REPLACE TRAFFIC LOOPS DAMAGED BY CONSTRUCTION 1 JOB $30,000.00 30,000.00

15 TRAFFIC STRIPING AND MARKING 1 JOB $20,000.00 20,000.00

16 HYDROSTATIC TESTING 1 JOB $10,000.00 10,000.00

17 TRAFFIC CONTROL 1 JOB $75,000.00 75,000.00

18 FURNISH AND INSTALL SAFETY MEASURES 1 JOB $75,000.00 75,000.00

19 AS-BUILT DRAWINGS 1 JOB $5,000.00 5,000.00

REMOVE & REPLACE CONCRETE SIDEWALK, CURB, GUTTERS, LANDSCAPING,

IRRIGATION, & CENTER MEDIANS 1 JOB $15,000.00 15,000.00

TOTAL BASE BID AMOUNT: $2,386,940.00

Optional Bid Items

OPTION 1: CONSTRUCT DEAD END WITH TEMPORARY 2-INCH BLOW-OFF PER

WBMWD STD. DWG. RW 12 AT STA. 56+55± 1 JOB $3,000.00 $3,000.00

OPTION 2: CONNECT TO EXISTING 12-INCH PVC RECYCLED WATER

CONSTRUCTED BY THE CITY OF CARSON AT CARSON ST. 1 JOB $5,000.00 $5,000.00

OPTION 3: RELOCATE WORK HEADING (TO ACCOMMODATE CONTAMINATED

SOIL REMEDIATION WORK) 2 EA $5,000.00 $10,000.00

OPTION 4: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS (CLASS I

DISPOSAL) 200 CY $300.00 $60,000.00

OPTION 5: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS-POCKETS

OF HYDROCARBON (CLASS III DISPOSAL) 20 CY $500.00 $10,000.00

26 OPTION 6: SUBGRADE STABILIZATION 50 CY $50.00 $2,500.00

TOTAL OPTIONAL BID AMOUNT: $90,500.00

TOTAL BASE AND OPTIONAL BID AMOUNT: $2,477,440.00

GRFCO, INC.

ESTIMATED

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Bid Items

1 MOBILIZATION, PERMITS AND DEMOBILIZATION 1 JOB $15,000.00 15,000.00

2 CONSTRUCT 12-INCH PVC PIPE 4,415 LF $200.00 883,000.00

3 CONSTRUCT 12-INCH DI PIPE 229 LF $230.00 52,670.00

4 CONSTRUCT 12-INCH RW GATE VALVE 3 EA $2,500.00 7,500.00

5 CONSTRUCT 1-INCH COMBINATION AIR VALVE ASSEMBLY 6 EA $4,000.00 24,000.00

6 CONSTRUCT 4-INCH BLOW-OFF ASSEMBLY 4 EA $7,000.00 28,000.00

7 CONSTRUCT BORE & JACK WITH 24-INCH STEEL CASING 115 LF $4,500.00 517,500.00

8 CONNECTION TO EXISTING 12-INCH RW MAIN AT JIM DEAR BLVD 1 EA $15,000.00 15,000.00 9 CONSTRUCT 3-INCH RW SERVICE LATERAL PER WBMWD STD. DWG. RW 4 1 EA $15,000.00 15,000.00 10 CONSTRUCT 2-INCH RW SERVICE LATERAL PER WBMWD STD. DWG.RW 3 1 EA $8,000.00 8,000.00

11 REMOVAL AND REPLACEMENT OF AC PAVEMENT AND AB BASE 9,500 SF $4.00 38,000.00

12 REMOVAL AND REPLACEMENT OF AC PAVEMENT OVER PCC ROAD 12,500 SF $6.00 75,000.00

13 SLURRY SEAL OF STREET 276,000 SF $0.25 69,000.00

14 REPLACE TRAFFIC LOOPS DAMAGED BY CONSTRUCTION 1 JOB $12,000.00 12,000.00

15 TRAFFIC STRIPING AND MARKING 1 JOB $5,000.00 5,000.00

16 HYDROSTATIC TESTING 1 JOB $5,000.00 5,000.00

17 TRAFFIC CONTROL 1 JOB $15,000.00 15,000.00

18 FURNISH AND INSTALL SAFETY MEASURES 1 JOB $780,000.00 780,000.00

19 AS-BUILT DRAWINGS 1 JOB $1,000.00 1,000.00

REMOVE & REPLACE CONCRETE SIDEWALK, CURB, GUTTERS, LANDSCAPING,

IRRIGATION, & CENTER MEDIANS 1 JOB $30,000.00 30,000.00

TOTAL BASE BID AMOUNT: $2,595,670.00

Optional Bid Items

OPTION 1: CONSTRUCT DEAD END WITH TEMPORARY 2-INCH BLOW-OFF PER

WBMWD STD. DWG. RW 12 AT STA. 56+55± 1 JOB $3,000.00 $3,000.00

OPTION 2: CONNECT TO EXISTING 12-INCH PVC RECYCLED WATER

CONSTRUCTED BY THE CITY OF CARSON AT CARSON ST. 1 JOB $15,000.00 $15,000.00

OPTION 3: RELOCATE WORK HEADING (TO ACCOMMODATE CONTAMINATED

SOIL REMEDIATION WORK) 2 EA $5,000.00 $10,000.00

OPTION 4: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS (CLASS I

DISPOSAL) 200 CY $200.00 $40,000.00

OPTION 5: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS-POCKETS

OF HYDROCARBON (CLASS III DISPOSAL) 20 CY $200.00 $4,000.00

26 OPTION 6: SUBGRADE STABILIZATION 50 CY $60.00 $3,000.00

TOTAL OPTIONAL BID AMOUNT: $75,000.00

TOTAL BASE AND OPTIONAL BID AMOUNT: $2,670,670.00

CJW CONSTRUCTION

ESTIMATED

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Bid Items

1 MOBILIZATION, PERMITS AND DEMOBILIZATION 1 JOB $200,000.00 200,000.00

2 CONSTRUCT 12-INCH PVC PIPE 4,415 LF $313.00 1,381,895.00

3 CONSTRUCT 12-INCH DI PIPE 229 LF $330.00 75,570.00

4 CONSTRUCT 12-INCH RW GATE VALVE 3 EA $3,900.00 11,700.00

5 CONSTRUCT 1-INCH COMBINATION AIR VALVE ASSEMBLY 6 EA $4,300.00 25,800.00

6 CONSTRUCT 4-INCH BLOW-OFF ASSEMBLY 4 EA $10,150.00 40,600.00

7 CONSTRUCT BORE & JACK WITH 24-INCH STEEL CASING 115 LF $1,400.00 161,000.00

8 CONNECTION TO EXISTING 12-INCH RW MAIN AT JIM DEAR BLVD 1 EA $5,100.00 5,100.00 9 CONSTRUCT 3-INCH RW SERVICE LATERAL PER WBMWD STD. DWG. RW 4 1 EA $18,500.00 18,500.00 10 CONSTRUCT 2-INCH RW SERVICE LATERAL PER WBMWD STD. DWG.RW 3 1 EA $9,500.00 9,500.00

11 REMOVAL AND REPLACEMENT OF AC PAVEMENT AND AB BASE 9,500 SF $16.25 154,375.00

12 REMOVAL AND REPLACEMENT OF AC PAVEMENT OVER PCC ROAD 12,500 SF $23.20 290,000.00

13 SLURRY SEAL OF STREET 276,000 SF $0.36 99,360.00

14 REPLACE TRAFFIC LOOPS DAMAGED BY CONSTRUCTION 1 JOB $5,400.00 5,400.00

15 TRAFFIC STRIPING AND MARKING 1 JOB $15,300.00 15,300.00

16 HYDROSTATIC TESTING 1 JOB $18,800.00 18,800.00

17 TRAFFIC CONTROL 1 JOB $175,000.00 175,000.00

18 FURNISH AND INSTALL SAFETY MEASURES 1 JOB $108,000.00 108,000.00

19 AS-BUILT DRAWINGS 1 JOB $3,800.00 3,800.00

REMOVE & REPLACE CONCRETE SIDEWALK, CURB, GUTTERS, LANDSCAPING,

IRRIGATION, & CENTER MEDIANS 1 JOB $70,000.00 70,000.00

TOTAL BASE BID AMOUNT: $2,869,700.00

Optional Bid Items

OPTION 1: CONSTRUCT DEAD END WITH TEMPORARY 2-INCH BLOW-OFF PER

WBMWD STD. DWG. RW 12 AT STA. 56+55± 1 JOB $4,400.00 $4,400.00

OPTION 2: CONNECT TO EXISTING 12-INCH PVC RECYCLED WATER

CONSTRUCTED BY THE CITY OF CARSON AT CARSON ST. 1 JOB $3,125.00 $3,125.00

OPTION 3: RELOCATE WORK HEADING (TO ACCOMMODATE CONTAMINATED

SOIL REMEDIATION WORK) 2 EA $10,300.00 $20,600.00

OPTION 4: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS (CLASS I

DISPOSAL) 200 CY $240.00 $48,000.00

OPTION 5: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS-POCKETS

OF HYDROCARBON (CLASS III DISPOSAL) 20 CY $160.00 $3,200.00

26 OPTION 6: SUBGRADE STABILIZATION 50 CY $115.00 $5,750.00

TOTAL OPTIONAL BID AMOUNT: $85,075.00

TOTAL BASE AND OPTIONAL BID AMOUNT: $2,954,775.00

ACE ENGINEERING

ESTIMATED

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Bid Items

1 MOBILIZATION, PERMITS AND DEMOBILIZATION 1 JOB $815,774.35 815,774.35

2 CONSTRUCT 12-INCH PVC PIPE 4,415 LF $135.79 599,512.85

3 CONSTRUCT 12-INCH DI PIPE 229 LF $408.77 93,608.33

4 CONSTRUCT 12-INCH RW GATE VALVE 3 EA $12,138.42 36,415.26

5 CONSTRUCT 1-INCH COMBINATION AIR VALVE ASSEMBLY 6 EA $8,987.10 53,922.60

6 CONSTRUCT 4-INCH BLOW-OFF ASSEMBLY 4 EA $10,562.76 42,251.04

7 CONSTRUCT BORE & JACK WITH 24-INCH STEEL CASING 115 LF $869.57 100,000.55

8 CONNECTION TO EXISTING 12-INCH RW MAIN AT JIM DEAR BLVD 1 EA $95,940.22 95,940.22 9 CONSTRUCT 3-INCH RW SERVICE LATERAL PER WBMWD STD. DWG. RW 4 1 EA $60,925.54 60,925.54 10 CONSTRUCT 2-INCH RW SERVICE LATERAL PER WBMWD STD. DWG.RW 3 1 EA $60,925.54 60,925.54

11 REMOVAL AND REPLACEMENT OF AC PAVEMENT AND AB BASE 9,500 SF $14.74 140,030.00

12 REMOVAL AND REPLACEMENT OF AC PAVEMENT OVER PCC ROAD 12,500 SF $14.01 175,125.00

13 SLURRY SEAL OF STREET 276,000 SF $1.17 322,920.00

14 REPLACE TRAFFIC LOOPS DAMAGED BY CONSTRUCTION 1 JOB $58,357.80 58,357.80

15 TRAFFIC STRIPING AND MARKING 1 JOB $70,029.36 70,029.36

16 HYDROSTATIC TESTING 1 JOB $58,357.80 58,357.80

17 TRAFFIC CONTROL 1 JOB $408,504.60 408,504.60

18 FURNISH AND INSTALL SAFETY MEASURES 1 JOB $583,578.00 583,578.00

19 AS-BUILT DRAWINGS 1 JOB $11,671.56 11,671.56

REMOVE & REPLACE CONCRETE SIDEWALK, CURB, GUTTERS, LANDSCAPING,

IRRIGATION, & CENTER MEDIANS 1 JOB $583,578.00 583,578.00

TOTAL BASE BID AMOUNT: $4,371,428.40

Optional Bid Items

OPTION 1: CONSTRUCT DEAD END WITH TEMPORARY 2-INCH BLOW-OFF PER

WBMWD STD. DWG. RW 12 AT STA. 56+55± 1 JOB $58,357.80 $58,357.80

OPTION 2: CONNECT TO EXISTING 12-INCH PVC RECYCLED WATER

CONSTRUCTED BY THE CITY OF CARSON AT CARSON ST. 1 JOB $58,357.80 $58,357.80

OPTION 3: RELOCATE WORK HEADING (TO ACCOMMODATE CONTAMINATED

SOIL REMEDIATION WORK) 2 EA $35,014.68 $70,029.36

OPTION 4: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS (CLASS I

DISPOSAL) 200 CY $350.15 $70,030.00

OPTION 5: EXCAVATION AND REMOVAL OF CONTAMINATED SOILS-POCKETS

OF HYDROCARBON (CLASS III DISPOSAL) 20 CY $583.58 $11,671.60

26 OPTION 6: SUBGRADE STABILIZATION 50 CY $583.58 $29,179.00

TOTAL OPTIONAL BID AMOUNT: $297,625.56

TOTAL BASE AND OPTIONAL BID AMOUNT: $4,669,053.96