Bid Abstract from bids opened on September 5th 2014.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912PL-14-B-0003
ABSTRACT OF BIDS
Invitation for Bids - # W912PL-14-B-0003 for
California Institution for Women (CIW) Dike – Santa Ana River Mainstem
Riverside County, California
With 2 Amendments
Bid Opening Date: 5 September, 2014
1. West-Tech Contracting, Inc. Escondido, CA $ 8,999,491.81
2. North Star Magnus Pacific JV Yuba City, CA $ 12,661,832.00
3. LB Civil Construction, Inc. San Diego, CA $ 12,935,542.00
4. Sierra Mountain Construction, Inc. Sonora, CA $ 13,786,655.00
5. Martin Brothers Construction Sacramento, CA $ 14,777,777.00
6. CJW Construction, Inc. Santa Ana, CA $ 15,506,705.00
7. Reyes / JF, a Joint Venture Pomona, CA $ 16,384,805.27
8. ZPSCO Contractors, Inc. Ogden, UT $ 16,965,706.90
Government Estimate $ 14,774,227.00
West-Tech Contracting Inc.
568 North Tulip Street Escondido, CA 92025
Item Description Quantity Unit Unit Price Amount
1 Diversion and Control of Water 1 Job LS $17,328.44 2 Clear Site and Remove Obstructions 1 Job LS $547,309.25 3 Environmental Provisions 1 Job LS $270,893.29 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $5,086.33
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $3,465.28
6 Remove Irrigation Pump And Valve 2 EA $2,813.86 $5,627.72 7 Remove Monitoring Wells 2 EA $2,888.07 $5,776.14 8 Construction of Overflow Parking Lot 1 Job LS $702,686.05 9 Storm Drain/Sewer Modifications 1 Job LS $7,623.36
10 Settlement Monuments 38 EA $4,736.44 $179,984.72 11 Settlement Base 4 EA $4,736.44 $18,945.76 12 Piezometer 1 EA $4,736.44 $4,736.44 13 Grade Monitoring Wells 2 EA $1,351.95 $2,703.90 14 Stripping
(a) a. First 44,000 CY 44,000 CY $2.03 $89,320.00
(b) b. Over 38,300 CY 38,300 CY $2.03 $77,749.00 15 Excavation 201,000 CY $3.10 $623,100.00 16 Compacted Fill, Zone 1 72,000 CY $3.13 $225,360.00 17 Compacted Fill, Zone 2 253,000 CY $3.13 $791,890.00 18 Compacted Fill, Select Zone 2 30,000 CY $36.68 $1,100,400.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $3.79 $75,800.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $3.79 $13,265.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $1.69 $38,025.00 22 Riprap 26,000 TON $43.18 $1,122,680.00 23 Stone for Grouted Stone 170 TON $41.58 $7,068.60 24 Grouting 30 CY $577.58 $17,327.40 25 Aggregate Base Course 7,100 TON $20.86 $148,106.00 26 Geotextile Filter Fabric 41,540 SY $1.90 $78,926.00 27 Concrete Culvert STA 26+00 1 Job LS $256,228.61 28 Concrete Culvert STA 51+60 1 Job LS $243,513.80 29 Concrete Ditch 4,430 LF $86.64 $383,815.20 30 Swing Gate 2 EA $2,310.46 $4,620.92 31 Guard Cable Fence 5,970 LF $10.97 $65,490.90 32 Hydroseed, Dike Seed Mix 39 ACRE $6,310.34 $246,103.26 33 Hydroseed, Native Plant Mix 32 ACRE $5,731.64 $183,412.48
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
Base Bid Items for Station 13+00 to Station 72+20
1 - West-Tech
34 Hydroseed, Borrow Site 47 ACRE $7,467.75 $350,984.25 35 24" Box Trees 33 EA $288.81 $9,530.73 36 Security Guard Service 1 Job LS $28,880.74 37 Prado Office Maintenance 15 Month $1,155.23 $17,328.45 38 As Built Drawings 1 Job LS $6,007.19 39 Chain Link Fence 5,190 LF $28.88 $149,887.20
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $34,796.39
Sub Total Line Items 1 - 40 (Base Bid) $8,161,783.80
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $11,552.29 42 Clear Site and Remove Obstructions 1 Job LS $14,440.37 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $47,040.07 44 Settlement Monuments 1 EA $4,620.92 $4,620.92 45 Stripping 2,800 CY $2.03 $5,684.00 46 Excavation 42,000 CY $4.64 $194,880.00 47 Compacted Fill, Zone 1 5,700 CY $3.13 $17,841.00 48 Compacted Fill, Zone 2 40,000 CY $3.13 $125,200.00 49 Compacted Fill, Select Zone 2 2,800 CY $36.68 $102,704.00 50 Top Soil (Non Compacted Fill) 2,200 CY $3.46 $7,612.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $3.79 $1,137.00 52 Riprap 2,500 TON $41.58 $103,950.00 53 Aggregate Base Course 1,250 TON $20.86 $26,075.00 54 Geotextile Filter Fabric 3,600 SY $1.90 $6,840.00 55 Concrete Ditch 350 LF $86.64 $30,324.00 56 Swing Gate 1 EA $2,405.55 $2,405.55 57 Guard Cable fence 610 LF $10.97 $6,691.70 58 Chain Link Fence 336 LF $28.88 $9,703.68 59 Hydroseed, Dike Seed Mix 0.5 ACRE $7,753.90 $3,876.95 60 Hydroseed, Native Plant Mix 2.5 ACRE $5,731.79 $14,329.48
Sub Total Line Items 41 - 60 (Option 1 Items) $736,908.01
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $33,600.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $33,600.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $33,600.00
$8,999,491.81Total Estimate Amount (Base Bid plus Options 1 through 4)
2 - West-Tech
North Start Magnus Pacific JV 1282 Stabler Lane #603-109 Yuba City, CA 95993
1 Diversion and Control of Water 1 Job LS $723,900.00 2 Clear Site and Remove Obstructions 1 Job LS $70,270.00 3 Environmental Provisions 1 Job LS $190,700.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $6,300.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $2,900.00
6 Remove Irrigation Pump And Valve 2 EA $17,510.00 $35,020.00 7 Remove Monitoring Wells 2 EA $12,610.00 $25,220.00 8 Construction of Overflow Parking Lot 1 Job LS $621,300.00 9 Storm Drain/Sewer Modifications 1 Job LS $79,990.00
10 Settlement Monuments 38 EA $940.00 $35,720.00 11 Settlement Base 4 EA $4,900.00 $19,600.00 12 Piezometer 1 EA $10,510.00 $10,510.00 13 Grade Monitoring Wells 2 EA $3,500.00 $7,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $3.80 $167,200.00
(b) b. Over 38,300 CY 38,300 CY $2.39 $91,537.00 15 Excavation 201,000 CY $3.93 $789,930.00 16 Compacted Fill, Zone 1 72,000 CY $5.84 $420,480.00 17 Compacted Fill, Zone 2 253,000 CY $4.80 $1,214,400.00 18 Compacted Fill, Select Zone 2 30,000 CY $51.70 $1,551,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $5.27 $105,400.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $10.80 $37,800.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $3.12 $70,200.00 22 Riprap 26,000 TON $41.90 $1,089,400.00 23 Stone for Grouted Stone 170 TON $41.90 $7,123.00 24 Grouting 30 CY $570.00 $17,100.00 25 Aggregate Base Course 7,100 TON $26.10 $185,310.00 26 Geotextile Filter Fabric 41,540 SY $1.90 $78,926.00 27 Concrete Culvert STA 26+00 1 Job LS $420,300.00 28 Concrete Culvert STA 51+60 1 Job LS $490,400.00 29 Concrete Ditch 4,430 LF $91.10 $403,573.00 30 Swing Gate 2 EA $5,500.00 $11,000.00 31 Guard Cable Fence 5,970 LF $9.60 $57,312.00 32 Hydroseed, Dike Seed Mix 39 ACRE $20,960.00 $817,440.00 33 Hydroseed, Native Plant Mix 32 ACRE $18,140.00 $580,480.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
3 - North Star Magnus Pacific JV
34 Hydroseed, Borrow Site 47 ACRE $17,040.00 $800,880.00 35 24" Box Trees 33 EA $730.00 $24,090.00 36 Security Guard Service 1 Job LS $159,400.00 37 Prado Office Maintenance 15 Month $5,000.00 $75,000.00 38 As Built Drawings 1 Job LS $109,500.00 39 Chain Link Fence 5,190 LF $27.40 $142,206.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $10,000.00
Sub Total Line Items 1 - 40 (Base Bid) $11,755,817.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $22,850.00 42 Clear Site and Remove Obstructions 1 Job LS $80,460.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $17,700.00 44 Settlement Monuments 1 EA $1,000.00 $1,000.00 45 Stripping 2,800 CY $4.22 $11,816.00 46 Excavation 42,000 CY $4.45 $186,900.00 47 Compacted Fill, Zone 1 5,700 CY $8.27 $47,139.00 48 Compacted Fill, Zone 2 40,000 CY $4.00 $160,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $44.90 $125,720.00 50 Top Soil (Non Compacted Fill) 2,200 CY $5.95 $13,090.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $8.15 $2,445.00 52 Riprap 2,500 TON $31.80 $79,500.00 53 Aggregate Base Course 1,250 TON $22.50 $28,125.00 54 Geotextile Filter Fabric 3,600 SY $2.07 $7,452.00 55 Concrete Ditch 350 LF $76.70 $26,845.00 56 Swing Gate 1 EA $9,300.00 $9,300.00 57 Guard Cable fence 610 LF $8.00 $4,880.00 58 Chain Link Fence 336 LF $23.00 $7,728.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $15,430.00 $7,715.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $19,060.00 $47,650.00
Sub Total Line Items 41 - 60 (Option 1 Items) $888,315.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $5,900.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $5,900.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $5,900.00
$12,661,832.00Total Estimate Amount (Base Bid plus Options 1 through 4)
4 - North Star Magnus Pacific JV
LB Civil Construction, Inc.
11585 Sorrento Valley Rd. # 104 San Diego, CA 92121
1 Diversion and Control of Water 1 Job LS $50,000.00 2 Clear Site and Remove Obstructions 1 Job LS $425,000.00 3 Environmental Provisions 1 Job LS $300,000.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $10,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $4,000.00
6 Remove Irrigation Pump And Valve 2 EA $3,000.00 $6,000.00 7 Remove Monitoring Wells 2 EA $4,000.00 $8,000.00 8 Construction of Overflow Parking Lot 1 Job LS $550,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $50,000.00
10 Settlement Monuments 38 EA $2,000.00 $76,000.00 11 Settlement Base 4 EA $7,000.00 $28,000.00 12 Piezometer 1 EA $20,000.00 $20,000.00 13 Grade Monitoring Wells 2 EA $2,000.00 $4,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $9.00 $396,000.00
(b) b. Over 38,300 CY 38,300 CY $6.00 $229,800.00 15 Excavation 201,000 CY $5.50 $1,105,500.00 16 Compacted Fill, Zone 1 72,000 CY $6.00 $432,000.00 17 Compacted Fill, Zone 2 253,000 CY $6.00 $1,518,000.00 18 Compacted Fill, Select Zone 2 30,000 CY $50.00 $1,500,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $5.00 $100,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $16.00 $56,000.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $4.00 $90,000.00 22 Riprap 26,000 TON $40.00 $1,040,000.00 23 Stone for Grouted Stone 170 TON $80.00 $13,600.00 24 Grouting 30 CY $300.00 $9,000.00 25 Aggregate Base Course 7,100 TON $30.00 $213,000.00 26 Geotextile Filter Fabric 41,540 SY $1.50 $62,310.00 27 Concrete Culvert STA 26+00 1 Job LS $287,000.00 28 Concrete Culvert STA 51+60 1 Job LS $287,000.00 29 Concrete Ditch 4,430 LF $65.00 $287,950.00 30 Swing Gate 2 EA $5,000.00 $10,000.00 31 Guard Cable Fence 5,970 LF $9.00 $53,730.00 32 Hydroseed, Dike Seed Mix 39 ACRE $20,000.00 $780,000.00 33 Hydroseed, Native Plant Mix 32 ACRE $20,000.00 $640,000.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
5 - LB Civil Construction
34 Hydroseed, Borrow Site 47 ACRE $19,000.00 $893,000.00 35 24" Box Trees 33 EA $700.00 $23,100.00 36 Security Guard Service 1 Job LS $150,000.00 37 Prado Office Maintenance 15 Month $2,800.00 $42,000.00 38 As Built Drawings 1 Job LS $5,000.00 39 Chain Link Fence 5,190 LF $22.00 $114,180.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $15,000.00
Sub Total Line Items 1 - 40 (Base Bid) $11,884,170.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $25,000.00 42 Clear Site and Remove Obstructions 1 Job LS $15,000.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $5,000.00 44 Settlement Monuments 1 EA $2,000.00 $2,000.00 45 Stripping 2,800 CY $7.00 $19,600.00 46 Excavation 42,000 CY $5.00 $210,000.00 47 Compacted Fill, Zone 1 5,700 CY $6.00 $34,200.00 48 Compacted Fill, Zone 2 40,000 CY $7.00 $280,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $50.00 $140,000.00 50 Top Soil (Non Compacted Fill) 2,200 CY $6.00 $13,200.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $14.00 $4,200.00 52 Riprap 2,500 TON $40.00 $100,000.00 53 Aggregate Base Course 1,250 TON $35.00 $43,750.00 54 Geotextile Filter Fabric 3,600 SY $1.50 $5,400.00 55 Concrete Ditch 350 LF $65.00 $22,750.00 56 Swing Gate 1 EA $5,000.00 $5,000.00 57 Guard Cable fence 610 LF $8.00 $4,880.00 58 Chain Link Fence 336 LF $22.00 $7,392.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $20,000.00 $10,000.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $20,000.00 $50,000.00
Sub Total Line Items 41 - 60 (Option 1 Items) $997,372.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $18,000.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $18,000.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $18,000.00
$12,935,542.00Total Estimate Amount (Base Bid plus Options 1 through 4)
6 - LB Civil Construction
Sierra Mountain Construction, Inc.
16355 Yosemite Road Sonora, CA 95370
1 Diversion and Control of Water 1 Job LS $1,200,000.00 2 Clear Site and Remove Obstructions 1 Job LS $100,000.00 3 Environmental Provisions 1 Job LS $500,000.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $40,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $5,000.00
6 Remove Irrigation Pump And Valve 2 EA $22,000.00 $44,000.00 7 Remove Monitoring Wells 2 EA $3,250.00 $6,500.00 8 Construction of Overflow Parking Lot 1 Job LS $650,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $40,000.00
10 Settlement Monuments 38 EA $1,000.00 $38,000.00 11 Settlement Base 4 EA $5,500.00 $22,000.00 12 Piezometer 1 EA $10,000.00 $10,000.00 13 Grade Monitoring Wells 2 EA $2,000.00 $4,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $4.75 $209,000.00
(b) b. Over 38,300 CY 38,300 CY $4.75 $181,925.00 15 Excavation 201,000 CY $5.25 $1,055,250.00 16 Compacted Fill, Zone 1 72,000 CY $7.00 $504,000.00 17 Compacted Fill, Zone 2 253,000 CY $7.50 $1,897,500.00 18 Compacted Fill, Select Zone 2 30,000 CY $69.00 $2,070,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $6.90 $138,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $47.00 $164,500.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $5.30 $119,250.00 22 Riprap 26,000 TON $50.00 $1,300,000.00 23 Stone for Grouted Stone 170 TON $70.00 $11,900.00 24 Grouting 30 CY $250.00 $7,500.00 25 Aggregate Base Course 7,100 TON $38.00 $269,800.00 26 Geotextile Filter Fabric 41,540 SY $2.00 $83,080.00 27 Concrete Culvert STA 26+00 1 Job LS $265,000.00 28 Concrete Culvert STA 51+60 1 Job $300,000.00 29 Concrete Ditch 4,430 LF $115.00 $509,450.00 30 Swing Gate 2 EA $4,500.00 $9,000.00 31 Guard Cable Fence 5,970 LF $7.50 $44,775.00 32 Hydroseed, Dike Seed Mix 39 ACRE $4,900.00 $191,100.00 33 Hydroseed, Native Plant Mix 32 ACRE $3,500.00 $112,000.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
7 - Sierra Mountain Construction
34 Hydroseed, Borrow Site 47 ACRE $3,000.00 $141,000.00 35 24" Box Trees 33 EA $850.00 $28,050.00 36 Security Guard Service 1 Job LS $200,000.00 37 Prado Office Maintenance 15 Month $3,500.00 $52,500.00 38 As Built Drawings 1 Job LS $10,000.00 39 Chain Link Fence 5,190 LF $20.00 $103,800.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $7,500.00
Sub Total Line Items 1 - 40 (Base Bid) $12,645,380.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $60,000.00 42 Clear Site and Remove Obstructions 1 Job LS $10,000.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $5,000.00 44 Settlement Monuments 1 EA $1,000.00 $1,000.00 45 Stripping 2,800 CY $5.00 $14,000.00 46 Excavation 42,000 CY $5.50 $231,000.00 47 Compacted Fill, Zone 1 5,700 CY $7.50 $42,750.00 48 Compacted Fill, Zone 2 40,000 CY $7.75 $310,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $65.00 $182,000.00 50 Top Soil (Non Compacted Fill) 2,200 CY $6.90 $15,180.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $47.00 $14,100.00 52 Riprap 2,500 TON $50.00 $125,000.00 53 Aggregate Base Course 1,250 TON $38.00 $47,500.00 54 Geotextile Filter Fabric 3,600 SY $2.00 $7,200.00 55 Concrete Ditch 350 LF $115.00 $40,250.00 56 Swing Gate 1 EA $4,250.00 $4,250.00 57 Guard Cable fence 610 LF $7.50 $4,575.00 58 Chain Link Fence 336 LF $20.00 $6,720.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $6,500.00 $3,250.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $3,800.00 $9,500.00
Sub Total Line Items 41 - 60 (Option 1 Items) $1,133,275.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $6,500.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $750.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $750.00
$13,786,655.00Total Estimate Amount (Base Bid plus Options 1 through 4)
8 - Sierra Mountain Construction
Martin Brothers Construction 8801 Folsom Blvd Suite 260 Sacramento, CA 95826
1 Diversion and Control of Water 1 Job LS $1,597,690.00 2 Clear Site and Remove Obstructions 1 Job LS $395,150.50 3 Environmental Provisions 1 Job LS $1,821,325.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $24,048.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $1,002.00
6 Remove Irrigation Pump And Valve 2 EA $1,002.00 $2,004.00 7 Remove Monitoring Wells 2 EA $6,012.00 $12,024.00 8 Construction of Overflow Parking Lot 1 Job LS $359,358.00 9 Storm Drain/Sewer Modifications 1 Job LS $30,060.00
10 Settlement Monuments 38 EA $404.00 $15,352.00 11 Settlement Base 4 EA $5,611.00 $22,444.00 12 Piezometer 1 EA $19,539.00 $19,539.00 13 Grade Monitoring Wells 2 EA $1,503.00 $3,006.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $2.50 $110,000.00
(b) b. Over 38,300 CY 38,300 CY $2.70 $103,410.00 15 Excavation 201,000 CY $1.45 $291,450.00 16 Compacted Fill, Zone 1 72,000 CY $4.25 $306,000.00 17 Compacted Fill, Zone 2 253,000 CY $4.25 $1,075,250.00 18 Compacted Fill, Select Zone 2 30,000 CY $47.10 $1,413,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $6.00 $120,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $48.25 $168,875.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $3.60 $81,000.00 22 Riprap 26,000 TON $73.30 $1,905,800.00 23 Stone for Grouted Stone 170 TON $130.00 $22,100.00 24 Grouting 30 CY $212.00 $6,360.00 25 Aggregate Base Course 7,100 TON $49.20 $349,320.00 26 Geotextile Filter Fabric 41,540 SY $5.70 $236,778.00 27 Concrete Culvert STA 26+00 1 Job LS $297,394.00 28 Concrete Culvert STA 51+60 1 Job LS $263,847.00 29 Concrete Ditch 4,430 LF $63.90 $283,077.00 30 Swing Gate 2 EA $4,108.00 $8,216.00 31 Guard Cable Fence 5,970 LF $6.90 $41,193.00 32 Hydroseed, Dike Seed Mix 39 ACRE $18,788.00 $732,732.00 33 Hydroseed, Native Plant Mix 32 ACRE $16,261.00 $520,352.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
9 - Martin Brothers
34 Hydroseed, Borrow Site 47 ACRE $15,272.00 $717,784.00 35 24" Box Trees 33 EA $571.00 $18,843.00 36 Security Guard Service 1 Job LS $60,120.00 37 Prado Office Maintenance 15 Month $3,271.00 $49,065.00 38 As Built Drawings 1 Job LS $65,130.00 39 Chain Link Fence 5,190 LF $19.05 $98,869.50
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $26,974.00
Sub Total Line Items 1 - 40 (Base Bid) $13,675,942.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $6,012.00 42 Clear Site and Remove Obstructions 1 Job LS $17,535.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $7,014.00 44 Settlement Monuments 1 EA $501.00 $501.00 45 Stripping 2,800 CY $3.70 $10,360.00 46 Excavation 42,000 CY $6.25 $262,500.00 47 Compacted Fill, Zone 1 5,700 CY $7.00 $39,900.00 48 Compacted Fill, Zone 2 40,000 CY $5.50 $220,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $49.10 $137,480.00 50 Top Soil (Non Compacted Fill) 2,200 CY $6.00 $13,200.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $60.20 $18,060.00 52 Riprap 2,500 TON $73.30 $183,250.00 53 Aggregate Base Course 1,250 TON $48.20 $60,250.00 54 Geotextile Filter Fabric 3,600 SY $5.60 $20,160.00 55 Concrete Ditch 350 LF $63.90 $22,365.00 56 Swing Gate 1 EA $4,108.00 $4,108.00 57 Guard Cable fence 610 LF $6.90 $4,209.00 58 Chain Link Fence 336 LF $19.00 $6,384.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $16,371.00 $8,185.50 60 Hydroseed, Native Plant Mix 2.5 ACRE $20,217.00 $50,542.50
Sub Total Line Items 41 - 60 (Option 1 Items) $1,092,016.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $5,411.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $2,204.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $2,204.00
$14,777,777.00Total Estimate Amount (Base Bid plus Options 1 through 4)
10 - Martin Brothers
CJW Construction, Inc.
841 E. Washington Ave, Suite B Santa Ana, CA 92701
1 Diversion and Control of Water 1 Job LS $2,900,000.00 2 Clear Site and Remove Obstructions 1 Job LS $2,700,000.00 3 Environmental Provisions 1 Job LS $100,000.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $15,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $5,000.00
6 Remove Irrigation Pump And Valve 2 EA $5,000.00 $10,000.00 7 Remove Monitoring Wells 2 EA $5,000.00 $10,000.00 8 Construction of Overflow Parking Lot 1 Job LS $550,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $65,000.00
10 Settlement Monuments 38 EA $1,000.00 $38,000.00 11 Settlement Base 4 EA $10,000.00 $40,000.00 12 Piezometer 1 EA $50,000.00 $50,000.00 13 Grade Monitoring Wells 2 EA $2,000.00 $4,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $9.50 $418,000.00
(b) b. Over 38,300 CY 38,300 CY $3.00 $114,900.00 15 Excavation 201,000 CY $4.00 $804,000.00 16 Compacted Fill, Zone 1 72,000 CY $3.00 $216,000.00 17 Compacted Fill, Zone 2 253,000 CY $2.60 $657,800.00 18 Compacted Fill, Select Zone 2 30,000 CY $47.00 $1,410,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $7.00 $140,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $21.00 $73,500.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $7.00 $157,500.00 22 Riprap 26,000 TON $45.00 $1,170,000.00 23 Stone for Grouted Stone 170 TON $100.00 $17,000.00 24 Grouting 30 CY $325.00 $9,750.00 25 Aggregate Base Course 7,100 TON $40.00 $284,000.00 26 Geotextile Filter Fabric 41,540 SY $5.00 $207,700.00 27 Concrete Culvert STA 26+00 1 Job LS $425,000.00 28 Concrete Culvert STA 51+60 1 Job LS $450,000.00 29 Concrete Ditch 4,430 LF $100.00 $443,000.00 30 Swing Gate 2 EA $5,000.00 $10,000.00 31 Guard Cable Fence 5,970 LF $11.00 $65,670.00 32 Hydroseed, Dike Seed Mix 39 ACRE $5,000.00 $195,000.00 33 Hydroseed, Native Plant Mix 32 ACRE $5,000.00 $160,000.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
11 - CJW Construction
34 Hydroseed, Borrow Site 47 ACRE $5,000.00 $235,000.00 35 24" Box Trees 33 EA $500.00 $16,500.00 36 Security Guard Service 1 Job LS $230,000.00 37 Prado Office Maintenance 15 Month $10,000.00 $150,000.00 38 As Built Drawings 1 Job LS $5,000.00 39 Chain Link Fence 5,190 LF $25.00 $129,750.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $20,000.00
Sub Total Line Items 1 - 40 (Base Bid) $14,702,070.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $25,000.00 42 Clear Site and Remove Obstructions 1 Job LS $75,000.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $12,000.00 44 Settlement Monuments 1 EA $1,000.00 $1,000.00 45 Stripping 2,800 CY $9.50 $26,600.00 46 Excavation 42,000 CY $4.00 $168,000.00 47 Compacted Fill, Zone 1 5,700 CY $4.25 $24,225.00 48 Compacted Fill, Zone 2 40,000 CY $2.50 $100,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $48.00 $134,400.00 50 Top Soil (Non Compacted Fill) 2,200 CY $1.50 $3,300.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $80.00 $24,000.00 52 Riprap 2,500 TON $28.00 $70,000.00 53 Aggregate Base Course 1,250 TON $40.00 $50,000.00 54 Geotextile Filter Fabric 3,600 SY $5.00 $18,000.00 55 Concrete Ditch 350 LF $100.00 $35,000.00 56 Swing Gate 1 EA $5,000.00 $5,000.00 57 Guard Cable fence 610 LF $11.00 $6,710.00 58 Chain Link Fence 336 LF $25.00 $8,400.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $4,000.00 $2,000.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $4,000.00 $10,000.00
Sub Total Line Items 41 - 60 (Option 1 Items) $798,635.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $2,000.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $2,000.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $2,000.00
$15,506,705.00Total Estimate Amount (Base Bid plus Options 1 through 4)
12 - CJW Construction
Reyes/JF, a Joint Venture Company 1539 East Grand Ave Pomona, CA 91766
1 Diversion and Control of Water 1 Job LS $1,214,185.00 2 Clear Site and Remove Obstructions 1 Job LS $590,000.00 3 Environmental Provisions 1 Job LS $850,000.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $30,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $3,000.00
6 Remove Irrigation Pump And Valve 2 EA $1,200.00 $2,400.00 7 Remove Monitoring Wells 2 EA $2,000.00 $4,000.00 8 Construction of Overflow Parking Lot 1 Job LS $710,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $74,801.91
10 Settlement Monuments 38 EA $2,000.00 $76,000.00 11 Settlement Base 4 EA $7,000.00 $28,000.00 12 Piezometer 1 EA $15,000.00 $15,000.00 13 Grade Monitoring Wells 2 EA $5,000.00 $10,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $3.00 $132,000.00
(b) b. Over 38,300 CY 38,300 CY $3.00 $114,900.00 15 Excavation 201,000 CY $7.00 $1,407,000.00 16 Compacted Fill, Zone 1 72,000 CY $7.00 $504,000.00 17 Compacted Fill, Zone 2 253,000 CY $12.00 $3,036,000.00 18 Compacted Fill, Select Zone 2 30,000 CY $50.00 $1,500,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $3.00 $60,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $31.00 $108,500.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $3.00 $67,500.00 22 Riprap 26,000 TON $40.00 $1,040,000.00 23 Stone for Grouted Stone 170 TON $100.00 $17,000.00 24 Grouting 30 CY $400.00 $12,000.00 25 Aggregate Base Course 7,100 TON $26.00 $184,600.00 26 Geotextile Filter Fabric 41,540 SY $1.50 $62,310.00 27 Concrete Culvert STA 26+00 1 Job LS $250,000.00 28 Concrete Culvert STA 51+60 1 Job LS $200,000.00 29 Concrete Ditch 4,430 LF $64.00 $283,520.00 30 Swing Gate 2 EA $7,000.00 $14,000.00 31 Guard Cable Fence 5,970 LF $15.00 $89,550.00 32 Hydroseed, Dike Seed Mix 39 ACRE $18,000.00 $702,000.00 33 Hydroseed, Native Plant Mix 32 ACRE $15,000.00 $480,000.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
13 - Reyes / JF
34 Hydroseed, Borrow Site 47 ACRE $15,000.00 $705,000.00 35 24" Box Trees 33 EA $640.00 $21,120.00 36 Security Guard Service 1 Job LS $140,000.00 37 Prado Office Maintenance 15 Month $6,500.00 $97,500.00 38 As Built Drawings 1 Job LS $5,000.00 39 Chain Link Fence 5,190 LF $35.00 $181,650.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $8,638.36
Sub Total Line Items 1 - 40 (Base Bid) $15,031,175.27
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $55,000.00 42 Clear Site and Remove Obstructions 1 Job LS $38,000.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $5,000.00 44 Settlement Monuments 1 EA $750.00 $750.00 45 Stripping 2,800 CY $3.00 $8,400.00 46 Excavation 42,000 CY $6.00 $252,000.00 47 Compacted Fill, Zone 1 5,700 CY $12.00 $68,400.00 48 Compacted Fill, Zone 2 40,000 CY $10.00 $400,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $40.00 $112,000.00 50 Top Soil (Non Compacted Fill) 2,200 CY $5.00 $11,000.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $34.00 $10,200.00 52 Riprap 2,500 TON $33.00 $82,500.00 53 Aggregate Base Course 1,250 TON $25.00 $31,250.00 54 Geotextile Filter Fabric 3,600 SY $1.50 $5,400.00 55 Concrete Ditch 350 LF $65.00 $22,750.00 56 Swing Gate 1 EA $7,000.00 $7,000.00 57 Guard Cable fence 610 LF $15.00 $9,150.00 58 Chain Link Fence 336 LF $30.00 $10,080.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $18,500.00 $9,250.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $15,000.00 $37,500.00
Sub Total Line Items 41 - 60 (Option 1 Items) $1,175,630.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $46,000.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $66,000.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $66,000.00
$16,384,805.27Total Estimate Amount (Base Bid plus Options 1 through 4)
14 - Reyes / JF
ZPSCO Contractors Inc.
176 West 21st Street, Suite C Ogden, UT 84401
1 Diversion and Control of Water 1 Job LS $903,000.00 2 Clear Site and Remove Obstructions 1 Job LS $513,000.00 3 Environmental Provisions 1 Job LS $425,000.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $18,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $6,300.00
6 Remove Irrigation Pump And Valve 2 EA $14,300.00 $28,600.00 7 Remove Monitoring Wells 2 EA $4,600.00 $9,200.00 8 Construction of Overflow Parking Lot 1 Job LS $700,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $90,000.00
10 Settlement Monuments 38 EA $1,500.00 $57,000.00 11 Settlement Base 4 EA $8,800.00 $35,200.00 12 Piezometer 1 EA $20,000.00 $20,000.00 13 Grade Monitoring Wells 2 EA $3,500.00 $7,000.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $2.95 $129,800.00
(b) b. Over 38,300 CY 38,300 CY $2.95 $112,985.00 15 Excavation 201,000 CY $6.00 $1,206,000.00 16 Compacted Fill, Zone 1 72,000 CY $7.62 $548,640.00 17 Compacted Fill, Zone 2 253,000 CY $10.84 $2,742,520.00 18 Compacted Fill, Select Zone 2 30,000 CY $59.80 $1,794,000.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $3.83 $76,600.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $32.34 $113,190.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $3.12 $70,200.00 22 Riprap 26,000 TON $40.00 $1,040,000.00 23 Stone for Grouted Stone 170 TON $52.00 $8,840.00 24 Grouting 30 CY $260.00 $7,800.00 25 Aggregate Base Course 7,100 TON $32.50 $230,750.00 26 Geotextile Filter Fabric 41,540 SY $2.00 $83,080.00 27 Concrete Culvert STA 26+00 1 Job LS $460,000.00 28 Concrete Culvert STA 51+60 1 Job LS $428,000.00 29 Concrete Ditch 4,430 LF $90.00 $398,700.00 30 Swing Gate 2 EA $14,000.00 $28,000.00 31 Guard Cable Fence 5,970 LF $20.00 $119,400.00 32 Hydroseed, Dike Seed Mix 39 ACRE $20,000.00 $780,000.00 33 Hydroseed, Native Plant Mix 32 ACRE $17,000.00 $544,000.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
15 - ZPSCO
34 Hydroseed, Borrow Site 47 ACRE $16,000.00 $752,000.00 35 24" Box Trees 33 EA $650.00 $21,450.00 36 Security Guard Service 1 Job LS $103,000.00 37 Prado Office Maintenance 15 Month $1,700.00 $25,500.00 38 As Built Drawings 1 Job LS $3,000.00 39 Chain Link Fence 5,190 LF $29.00 $150,510.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $8,900.00
Sub Total Line Items 1 - 40 (Base Bid) $14,799,165.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $172,000.00 42 Clear Site and Remove Obstructions 1 Job LS $45,000.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $3,500.00 44 Settlement Monuments 1 EA $1,500.00 $1,500.00 45 Stripping 2,800 CY $2.95 $8,260.00 46 Excavation 42,000 CY $8.17 $343,140.00 47 Compacted Fill, Zone 1 5,700 CY $15.26 $86,982.00 48 Compacted Fill, Zone 2 40,000 CY $13.12 $524,800.00 49 Compacted Fill, Select Zone 2 2,800 CY $51.46 $144,088.00 50 Top Soil (Non Compacted Fill) 2,200 CY $6.94 $15,268.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $43.93 $13,179.00 52 Riprap 2,500 TON $40.71 $101,775.00 53 Aggregate Base Course 1,250 TON $34.02 $42,525.00 54 Geotextile Filter Fabric 3,600 SY $2.00 $7,200.00 55 Concrete Ditch 350 LF $92.00 $32,200.00 56 Swing Gate 1 EA $13,000.00 $13,000.00 57 Guard Cable fence 610 LF $21.09 $12,864.90 58 Chain Link Fence 336 LF $35.00 $11,760.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $21,000.00 $10,500.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $18,000.00 $45,000.00
Sub Total Line Items 41 - 60 (Option 1 Items) $1,634,541.90
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $152,000.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $190,000.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $190,000.00
$16,965,706.90Total Estimate Amount (Base Bid plus Options 1 through 4)
16 - ZPSCO
Corps of Engineers / Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, CA 90017-3489
1 Diversion and Control of Water 1 Job LS $428,000.00 2 Clear Site and Remove Obstructions 1 Job LS $69,000.00 3 Environmental Provisions 1 Job LS $115,300.00 4 Remove Abandoned Sewer Line With 2 Manholes 1 Job LS $8,000.00
Remove Exist. Settlement Pipe Casing And Concrete Settlement Base
1 Job LS $4,500.00
6 Remove Irrigation Pump And Valve 2 EA $1,800.00 $3,600.00 7 Remove Monitoring Wells 2 EA $3,260.00 $6,520.00 8 Construction of Overflow Parking Lot 1 Job LS $823,000.00 9 Storm Drain/Sewer Modifications 1 Job LS $67,300.00
10 Settlement Monuments 38 EA $1,150.00 $43,700.00 11 Settlement Base 4 EA $9,500.00 $38,000.00 12 Piezometer 1 EA $13,000.00 $13,000.00 13 Grade Monitoring Wells 2 EA $4,400.00 $8,800.00 14 Stripping
(a) a. First 44,000 CY 44,000 CY $3.79 $166,760.00
(b) b. Over 38,300 CY 38,300 CY $3.81 $145,923.00 15 Excavation 201,000 CY $6.12 $1,230,120.00 16 Compacted Fill, Zone 1 72,000 CY $11.20 $806,400.00 17 Compacted Fill, Zone 2 253,000 CY $11.07 $2,800,710.00 18 Compacted Fill, Select Zone 2 30,000 CY $41.89 $1,256,700.00 19 Top Soil (Non-Compacted Fill) 20,000 CY $4.95 $99,000.00 20 Non Compacted, Zone 2 Under Reservoir Side Riprap 3,500 CY $6.87 $24,045.00 21 Non Compacted Fill, Miscellaneous Fill 22,500 CY $7.00 $157,500.00 22 Riprap 26,000 TON $36.45 $947,700.00 23 Stone for Grouted Stone 170 TON $53.00 $9,010.00 24 Grouting 30 CY $135.00 $4,050.00 25 Aggregate Base Course 7,100 TON $37.00 $262,700.00 26 Geotextile Filter Fabric 41,540 SY $2.90 $120,466.00 27 Concrete Culvert STA 26+00 1 Job LS $225,000.00 28 Concrete Culvert STA 51+60 1 Job LS $213,000.00 29 Concrete Ditch 4,430 LF $58.30 $258,269.00 30 Swing Gate 2 EA $4,000.00 $8,000.00 31 Guard Cable Fence 5,970 LF $39.60 $236,412.00 32 Hydroseed, Dike Seed Mix 39 ACRE $14,350.00 $559,650.00 33 Hydroseed, Native Plant Mix 32 ACRE $16,300.00 $521,600.00
W912PL-14-B-0003
California Institution for Women (CIW) Dike - Santa Ana River Mainstem
2 Amendments - Bid Opening of 5 September 2014
17 - IGE
34 Hydroseed, Borrow Site 47 ACRE $15,100.00 $709,700.00 35 24" Box Trees 33 EA $1,000.00 $33,000.00 36 Security Guard Service 1 Job LS $297,000.00 37 Prado Office Maintenance 15 Month $5,545.00 $83,175.00 38 As Built Drawings 1 Job LS $12,300.00 39 Chain Link Fence 5,190 LF $68.20 $353,958.00
Test Section, Subgrade Preparation and Compaction between STA 13+00 and 37+00
1 Job LS $10,000.00
Sub Total Line Items 1 - 40 (Base Bid) $13,180,868.00
Option 1 Items - For Station 6+90 to 13+00 41 Diversion and Control of Water 1 Job LS $240,000.00 42 Clear Site and Remove Obstructions 1 Job LS $31,500.00 43 Remove Existing Utility Features @ STA 9+00 1 Job LS $12,000.00 44 Settlement Monuments 1 EA $1,300.00 $1,300.00 45 Stripping 2,800 CY $3.86 $10,808.00 46 Excavation 42,000 CY $6.13 $257,460.00 47 Compacted Fill, Zone 1 5,700 CY $14.40 $82,080.00 48 Compacted Fill, Zone 2 40,000 CY $13.70 $548,000.00 49 Compacted Fill, Select Zone 2 2,800 CY $42.30 $118,440.00 50 Top Soil (Non Compacted Fill) 2,200 CY $4.95 $10,890.00 51 Non Compacted Zone 2 Under Reservoir Side Riprap 300 CY $9.10 $2,730.00 52 Riprap 2,500 TON $36.45 $91,125.00 53 Aggregate Base Course 1,250 TON $37.00 $46,250.00 54 Geotextile Filter Fabric 3,600 SY $3.00 $10,800.00 55 Concrete Ditch 350 LF $58.00 $20,300.00 56 Swing Gate 1 EA $3,700.00 $3,700.00 57 Guard Cable fence 610 LF $47.00 $28,670.00 58 Chain Link Fence 336 LF $71.00 $23,856.00 59 Hydroseed, Dike Seed Mix 0.5 ACRE $15,100.00 $7,550.00 60 Hydroseed, Native Plant Mix 2.5 ACRE $16,200.00 $40,500.00
Sub Total Line Items 41 - 60 (Option 1 Items) $1,587,959.00
Option 2 Item 61 Additional Rolling (2 Passes) 1 Job LS $1,800.00
Option 3 Item - For Station 6+90 to 13+00 62 Additional Rolling (2 Passes) 1 Job LS $1,800.00
Option 4 Item - For Station 6+90 to 13+00 63 Additional Rolling (2 Passes) 1 Job LS $1,800.00
$14,774,227.00Total Estimate Amount (Base Bid plus Options 1 through 4)
18 - IGE
| ABSTRACT OF BIDS |
| 1_bidAbstract_CIW_Dike_14-B-0003_West-Tech.pdf |
| West-Tech Contracting, Inc |