IFB No.: W912PL-12-B-0007

Yorba Slaughter Adobe Protection

City of Chino San Bernardino County, California

100% Small Business Set-Aside

Construction Solicitation and Specifications August 2012

This page was intentionally left blank for duplex printing.

YORBA SLAUGHTER ADOBE PROTECTION W912PL-12-B-0007

TOC - 1

PROJECT TABLE OF CONTENTS

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACT FORMS AND CONTRACT CONDITIONS

SF1442 SOLICITATION, OFFER and AWARD

00010 BID SCHEDULE

00100 INSTRUCTIONS TO BIDDERS

00600 REPRESENTATIONS & CERTIFICATIONS OF OFFERORS

00700 CONTRACT CLAUSES

00800 SPECIAL CONTRACT REQUIREMENTS

00850 DAVIS BACON WAGE DECISION

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)

01 45 01 CONTRACTOR QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 57 23 STORM WATER POLLUTION PREVENTION MEASURES

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 13 00 DIVERSION AND CONTROL OF WATER

DIVISION 03 – CONCRETE

03 30 07.10 CONCRETE FOR MINOR STRUCTURES

03 36 00 GROUTING STONE PROTECTION

DIVISION 05 – METALS

05 50 15 CIVIL WORKS FABRICATIONS

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

31 05 21 GEOGRID SOIL REINFORCEMENT

31 11 00 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE

32 11 30 DECOMPOSED GRANITE

32 12 12 BITUMINOUS PAVING

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 92 19.16 HYDROSEEDING

32 93 00 EXTERIOR PLANTING

YORBA SLAUGHTER ADOBE PROTECTION W912PL-12-B-0007

TOC - 2

DIVISION 33 – UTILITIES

33 21 00 MONUMENTATION AND INSTRUMENTATION

33 40 00 STORM DRAINAGE UTILITIES

33 42 26 REINFORCED CONCRETE PRESSURE PIPE, STEEL-CYLINDER TYPE

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR STRUCTURES

-- End of Project Table of Contents –

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

9. FOR INFORMATION CALL

A. NAME B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

Designed using Perform Pro, WHS/DIOR, Oct 96

1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

W912PL-12-B-0007 X 03 Aug 2012 1 OF 2

USACE, Los Angeles District Contracting Division, West Region Branch 915 Wilshire Blvd P. O. Box 532711 Los Angeles, CA 90053-2325

See Item 7

Julie Ayala/Patricia Bonilla 213/452-3241 or 213/452-3255

Yorba Slaughter Adobe Protection, City of Chino, San Bernardino County, California

Project consists of geogrid reinforced earthen riprap dike and road realignment that will encircle the Adobe site, providing permanent flood protection from a flood up to the 566 elevation.

This is a 100% Small Business Set-Aside procurement.

The estimated cost range of this acquisition is $1,000,000 - $5,000,000.

BIDDERS PLEASE NOTE: This project may be delayed, cancelled or revised at any time prior to award.

10 *Sect00800

X X *Section 00800

X 10

0 1:00 PM

04 September 2012

X

OFFER (Must be fully completed by offeror)

STANDARD FORM 1442 BACK (REV. 4-85)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24.SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and

(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN

(Type or print)

30B. SIGNATURE 30C. DATE

31A. NAME OF CONTRACTING OFFICER (Type or print)

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

DUNS NO.: TAX ID NO.:

CAGE CODE NO.:

( ) - ; FAX ( ) -

SEE PRICING SCHEDULE

USACE, FINANCE CENTER

5722 INTEGRITY DRIVE, ATTN: CEFCO-AO-P

MILLINGTON, TN 38054-5005

Yorba Slaughter Adobe Protection W912PL-12-B-0007 City of Chino, San Bernardino County, California

00010 - 1

SECTION 00010

CERTIFICATE OF OFFEROR’S PRINCIPAL

(1) IF THE OFFEROR IS PARTNERSHIP OR JOINT VENTURE, LIST FULL NAME OF ALL

PARTNERS/ JOINT VENTURERS (Add addendum as necessary):

(Company Name) (Signature) (Title)

(2) IF THE OFFEROR IS A CORPORATION, THE FOLLOWING CERTIFICATION SHOULD BE

COMPLETED:

CERTIFICATION AS TO CORPORATE PRINCIPAL

I, ______________________________, certify that I am the Secretary of the corporation named as principal in the within SF 1442; that ________________________________, who signed the SF 1442 at Block

20B on behalf of the principal, was the _________________________________of the corporation; that I know the individual’s signature and that his/her signature is genuine; and that said Offer was duly signed, sealed and attested for on behalf of said corporation by authority of its governing body.

CORPORATE PRINCIPAL

CORPORATE SEAL _________________________________

SECRETARY

(3) IF THE OFFEROR IS A LIMITED LIABILITY COMPANY/PARTNERSHIP, LIST FULL NAME OF

ALL MANAGERS BELOW (Add addendum as necessary). SIGNATURES BY ALL MANAGERS HERE SIGNIFY THAT THAT THE INDIVIDUAL WHO SIGNED THE OFFER IN BLOCK 20B OF THE SF 1442

HAS THE AUTHORITY TO BIND THE LIMITED LIABILITY COMPANY/PARTNERSHIP.

(Officer’s Name) (Signature) (Title)

Yorba Slaughter Adobe Protection W912PL-12-B-0007

00010 - 2

SECTION 00010

BID SCHEDULE

Estimated Unit Item Description Quantity Unit Price Amount

0001 DIVERSION AND CONTROL OF WATER 1 JOB LS $__________

0002 SARI LINE PROTECTION 1 JOB LS $__________

0003 AS-BUILT DRAWINGS 1 JOB LS $__________

0004 ENVIRONMENTAL PROVISIONS 1 JOB LS $__________

0005 BORROW AREA ACTIVITY 1 JOB LS $__________

0006 MAINTENANCE ROADS, A & B 1 JOB LS $__________

Phase 1

1001 CLEAR SITE AND REMOVE OBSTRUCTIONS 1 JOB LS $__________

1002 1' STRIPPING 3,650 CY $______ $__________

1003 1' STRIPPING, ROADWAY 4,450 CY $______ $__________

1004 FOUNDATION EXCAVATION 7,200 CY $______ $__________

1005 OVER EXCAVATION, ROADWAY 2,700 CY $______ $__________

1006 COMPACTED FILL 38,000 CY $______ $__________

1007 COMPACTED FILL, ROADWAY 38,500 CY $______ $__________

1008 SURCHARGE FILL, ROADWAY 4,400 CY $______ $__________

1009 15-INCH RIPRAP 3,500 TON $______ $__________

1010 BEDDING MATERIAL 2,000 TON $______ $__________

1011 GEOGRID 5,200 SY $______ $__________

1012 GROUT 50 CY $______ $__________

1013 SEGMENTAL CONCRETE BLOCK RETAINING WALL 1 JOB LS $__________

1014 POMONA-RINCON ROAD DETOUR 1 JOB LS $__________

1015 36-INCH CULVERT, DIKE STA 4+20 1 JOB LS $__________

1016 INSTRUMENTATION 1 JOB LS $__________

Yorba Slaughter Adobe Protection W912PL-12-B-0007

00010 - 3

Phase 2

2001 CLEAR SITE AND REMOVE OBSTRUCTIONS 1 JOB LS $__________

2002 SITE PREPARATION 1 JOB LS $__________

2003 1' STRIPPING 1,200 CY $______ $__________

2004 1' STRIPPING, ROADWAY 3,300 CY $______ $__________

2005 FOUNDATION EXCAVATION 3,800 CY $______ $__________

2006 COMPACTED FILL 25,250 CY $______ $__________

2007 COMPACTED FILL, ROADWAY 6,350 CY $______ $__________

2008 24-INCH RIPRAP 2,700 TON $______ $__________

2009 BEDDING MATERIAL 1,100 TON $______ $__________

2010 ASPHALT CONCRETE PAVEMENT, 2,500 TON $______ $__________

ROADWAY

2011 ASPHALT CONCRETE PAVEMENT 300 TON $______ $__________

2012 AGGREGATE BASE COURSE, 3,700 TON $______ $__________

ROADWAY

2013 AGGREGATE BASE COURSE 540 TON $______ $__________

2014 PAINT STRIPING & SIGNS, ROADWAY 1 JOB LS $__________

2015 ROADWAY IMPROVEMENTS 1 JOB LS $__________

2016 36-INCH CULVERT, DIKE STA 12+42.11 1 JOB LS $__________

2017 GUARD CABLE FENCING 2,655 LF $______ $__________

2018 SWING GATES 4 EA $______ $__________

2019 INSTRUMENTATION 1 JOB LS $__________

2020 MUSEUM PARKING LOT AND RAMP 1 JOB LS $__________

2021 10-INCH FORCE MAIN RELOCATION 1 JOB LS $__________

2022 DRY UTILITY JOINT TRENCH 1 JOB LS $__________

2023 HYDROSEEDING, DIKE 10.5 AC $______ $__________

Yorba Slaughter Adobe Protection W912PL-12-B-0007

00010 - 4

2024 HYDROSEEDING MAINTENANCE, DIKE AREA 10.5 AC $______ $__________

2025 TOPSOIL FOR ESTHETIC TREATMENT, 1500 CY $______ $__________

DIKE AREA

2026 ASH TREE REMOVAL AND PLANTING 1 JOB LS $__________

2027 VIEWING AREA WORK 1 JOB LS $__________

TOTAL ESTIMATED AMOUNT: $______________

AC = Acre CY = Cubic Yard EA = Each LF = Linear Feet LS = Lump Sum SY = Square Yard

City of Chino San Bernardino County, California

00010 - 5

BIDDERS NOTES:

1. Prices must be submitted on all individual line items of the Price Schedule, Base and Options; otherwise, the Offer may be considered nonresponsive and shall be rejected.

2. The lump sum “LS” line items in the Price Schedule are not “Estimated Quantity” line items and are not subject to the “Variation in Estimated Quantity” contract clause.

3. Contract Clause 52.232-27, “Prompt Payment for Construction Contracts” requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.

4. The Contracting Officer who signs the task order will be the Principal Contracting Officer for the task order. However, any Contracting Officer assigned to the Los Angeles District, contracting within their authority, may take formal action on the task order when the Principal Contracting Officer is unavailable and the action needs to be taken.

5. Amounts and prices shall be indicated in either words or figures, NOT BOTH.

6. Payment of Electronic Funds Transfer (EFT) is the mandatory method of payment. The Contractor’s attention is directed to Contract Clause 52.232-33 “Mandatory Information for Electronic Funds Transfer.”

7. The Offeror shall distribute indirect costs (overhead, profit etc.,) over all items in the Price Schedule. The Government will review all submitted Price Schedules for any unbalancing of the items. Any submitted Price Schedule determined to be unbalanced may be considered unacceptable and may cause the Offeror to be ineligible for award.

8. The Contractor shall furnish all plant, labor, material, equipment, etc., (excluding any Government furnished material that is detailed within this IFB), necessary to perform all work in strict accordance with the terms and conditions set forth in this solicitation, to include all attachments thereto.

9. All extensions of the unit prices shown will be subject to verification by the Government. In cases of variation between the unit price and extension, the unit price will be considered to be the bid.

10. If a bid or modification to a bid based on unit prices is submitted which provides for a lump sum adjustment to the total amount, the application of the lump sum adjustment to each unit price in the Schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro-rata basis to every unit price in the Schedule.

11. All quantities not identified as Lump Sum are considered to be estimated.

(End of Section)

00100-1

Section 00100 - Instructions to Bidders

Clauses Incorporated by Full Text

52.0000-4010 INQUIRIES

52.0000-4023 SAFETY REQUIREMENTS

52.204-6 DATA UNIVERSAL NUMBERING SYSTEM (DUNS) NUMBER (APR 2008)

52.209-4501 CONTRACTOR REPONSIBILITY, PRE-AWARD SURVEY

52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29

52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM

DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION

INFORMATION SYSTEM (ASSIST) (JAN 2006)

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY

PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 1989)

52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)

52.214-5 SUBMISSION OF BIDS (MAR 1997)

52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)

52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999) 7

52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)

52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)

52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)

52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)

52.0214-5001 DIRECTIONS FOR SUBMITING BIDS (APR 2002)

52.214-5000 ARITHMETIC DISCREPANCIES EFARS 52.214-5000

52.0214-4583 TELEGRAPHIC BIDS/OFFERS ARE NOT ACCEPTABLE

52.214-4584 FACSIMILE BIDS/OFFERS

52.0214-4599 EVALUATION FOR AWARD

52.216-1 TYPE OF CONTRACT (APR 1984)

52.219-4003 SMALL BUSINESS AND SMALL DISADVANTAGED BUSINESS

SUBCONTRACTING

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (JUN 2003)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

52.225-10 NOTICE OF BUY AMERICAN ACT REQUIREMENT--CONSTRUCTION MATERIALS

(FEB 2009)

52.228-1 BID GUARANTEE (SEP 1996)

52.233-2 SERVICE OF PROTEST (SEP 2006)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

252.204-7001 COMMERCIAL AND GOVERNMENT ENTITY (CAGE) CODE REPORTING (AUG

1999)

252.204-7004 CENTRAL CONTRACTOR REGISTRATION (52.204-7) ALTERNATE A (SEP 2007)

252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING

REPORTS (MAR 2008)

00100-2

52.0000-4010 INQUIRIES

Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders/offerors before submission of their bids/offers. Oral explanations or instructions given before award of a contract are not binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting offers or if lack of it would be prejudicial to other prospective bidders/offerors.

1. All inquiries relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

A. To submit and review bid inquiry items, bidders will need to be a current registered user or self register into the system. To self register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

Please Note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected.

B. From this page, you may view all bidder inquiries or add inquiry.

C. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by the technical team.

D. The Solicitation Number is: W912PL-12-B-0007 E. The Bidder Inquiry Key is: J8Q61D-9XQRYN

2. The Bidder Inquiry System will be unavailable for new inquiries 5 business days prior to proposal submission in order to ensure adequate time allotted to form an appropriate response and amend the solicitation if necessary.

3. Offerors are requested to review the specifications in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

4. The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

52.0000-4023 SAFETY REQUIREMENTS

The bidder's attention is directed to the latest version of U.S Army Corps of Engineers Safety and Health Manual, EM 385-1-1, which will be strictly enforced. This publication may be obtained online and is available for download at: http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx . Hard Copies are available from the Associated General Contractors of America, (Item #3607). The U.S.

Government Printing Office is sold out of its inventory of the manual. Any other Safety and Occupational specific questions can be addressed to the US Army Engineer District, Los Angeles, ATTN: Safety Office, P.O. Box 53211, Los Angeles CA 90053-2325 http://www.projnet.org/projnet�

00100-3

52.204-6 DATA UNIVERSAL NUMBERING SYSTEM (DUNS)

NUMBER (APR 2008)

(a) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS number or “DUNS+4” that identifies the offeror's name and address exactly as stated in the offer. The DUNS number is a nine-digit number assigned by Dun and Bradstreet, Inc. The DUNS+4 is the DUNS number plus a 4-character suffix that may be assigned at the discretion of the offeror to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see Subpart 32.11) for the same concern.

(b) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number--

(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(End of provision)

00100-4

52.209-4501 CONTRACTOR REPONSIBILITY, PRE-AWARD

SURVEY

In accordance with FAR 9.103(a)…”contracts shall be awarded to responsible, prospective contractors only.” In order to determine a contractor’s responsibility for purposes of contract award in accordance with FAR Part 9, a statement regarding previous experience in performing comparable work, and/or plant to be used in performing the work is required. Please provide the following information in order to perform a preaward survey on your firm with your bid:

1. List of projects completed for the past three years, including dollar amount of each contract.

2. List of projects in progress, percentage of work completed, including dollar value of each contract.

3. The name and qualifications of the employee designated to act as the Project

Superintendent/Manager for this contract.

4. Copy of latest financial statement.

5. General description of your firm.

52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN

THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS

AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-

29 (AUG 1998)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--GSA Federal Supply Service, Specifications Section, Suite 8100, 470 East L'Enfant Plaza, SW, Washington, DC 20407, Telephone (202) 619-8925, Facsimile

(202) 619-8978.

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS,

AND DATA ITEM DESCRIPTIONS LISTED IN THE

ACQUISITION STREAMLINING AND STANDARDIZATION

INFORMATION SYSTEM (ASSIST) (JAN 2006)

(a) Most unclassified Defense specifications and standards may be downloaded from the following ASSIST websites:

00100-5

(1) ASSIST (http://assist.daps.dla.mil);

(2) Quick Search (http://assist.daps.dla.mil/quicksearch);

(3) ASSISTdocs.com (http://assistdocs.com).

(b) Documents not available from ASSIST may be ordered from the Department of Defense Single Stock Point (DoDSSP) by--

(1) Using the ASSIST Shopping Wizard (http://assist.daps.dla.mil/wizard);

(2) Phoning the DoDSSP Customer Service Desk (215) 697-2179, Mon-Fri, 0730 to 1600 EST; or

(3) Ordering from DoDSSP, Building 4, Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5094, Telephone (215) 697-2667/2179, Facsimile (215) 697-1462.

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL

DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY

PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]

52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC

1989)

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.

(b) Bidders shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date in the space provided for this purpose on the form for submitting a bid, (3) by letter or telegram, or (4) by facsimile, if facsimile bids are authorized in the solicitation. The Government must receive the acknowledgment by the time and at the place specified for receipt of bids.

00100-6

52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)

Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments. The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.

52.214-5 SUBMISSION OF BIDS (MAR 1997)

(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.

(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.

(c) Telegraphic bids will not be considered unless authorized by the solicitation; however, bids may be modified or withdrawn by written or telegraphic notice.

(d) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.

(e) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.

52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR

1984)

Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.

00100-7

52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND

WITHDRAWALS OF BIDS (NOV 1999)

(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.

(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--

(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or

(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.

(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.

52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR

1984)

(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and

(2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.

00100-8

(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--

(1) Lump sum bidding;

(2) Alternate prices;

(3) Units of construction; or

(4) Any combination of subparagraphs (1) through (3) above.

(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.

(d) Alternate bids will not be considered unless this solicitation authorizes their submission.

52.214-19 CONTRACT AWARD--SEALED BIDDING--

CONSTRUCTION (AUG 1996)

(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.

(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.

(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.

(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.

52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH

LANGUAGE (APR 1991)

Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.

00100-9

52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY

(APR 1991)

Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S. dollars shall be rejected.

52.0214-5001 DIRECTIONS FOR SUBMITING BIDS (APR

2002)

Envelopes containing bids must be sealed, marked and addressed as follows:

MARK ENVELOPES:

Bid under IFB No. W912PL-12-B-0007 Bid Opening Date: Refer to SF 1442, “Solicitation, Offer & Award” Block No.13A

ADDRESS ENVELOPES TO:

Department of the Army U. S. Army Engineer District, Los Angeles ATTN: Contracting Division C/O: Julie Ayala 915 Wilshire Blvd Los Angeles, CA 90017

SPECIAL INSTRUCTIONS PERTAINING TO HAND-CARRIED BIDS:

Due to security precautions, all Corps of Engineers visitors/couriers are now required to check in at the Security Office, Suite 1101, 915 Wilshire Blvd, Los Angeles, CA 90017. Bidders are no longer permitted to hand-carry their bids directly to Contacting Division. Bids may NOT be left unattended at the Security Office, Suite1101.

Bidders who desire to hand-deliver their bids prior to the scheduled bid opening time/date must notify the Contracting Division to arrange for receipt of their bid by Contracting Division personnel. Normally the contact will be the Contract Specialist(s) designated above Julie Ayala at 213/452-3241or Anna Lopez at 213/452-3206, or Lubna Khilfeh at 213/452-3308.

10 minutes prior to the scheduled bid opening time/date, the Bid Opening Officer will be in the Security Office, Suite 1101 to accept bids. After visitor in-processing, all bidders will subsequently be escorted to Bid Opening Room, where the bids will be publicly opened and read.

00100-10

The offeror is responsible for compliance with the security requirements and shall ensure that any company representative, courier or delivery personnel are aware of these special procedures pertaining to hand carried bids.

52.214-5000 ARITHMETIC DISCREPANCIES EFARS

52.214-5000

(a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the bidding schedule as submitted by bidders:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump sum and extended prices will be corrected.

(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends his bid to be evaluated on the basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

(End of statement)

52.0214-4583 TELEGRAPHIC BIDS/OFFERS ARE NOT

ACCEPTABLE

Any telegram to modify or withdraw a bid/offer sent to this office must be physically delivered to the office designated for receipt of bid/offer by the date and time set for bid opening/receipt of proposals.

No one from this office will be dispatched to the local telegraph office to pick up any telegram for any reason.

52.214-4584 FACSIMILE BIDS/OFFERS

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

00100-11

52.0214-4599 EVALUATION FOR AWARD

The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of all the items in the Bidding Schedule.

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of clause)

52.219-4003 SMALL BUSINESS AND SMALL

DISADVANTAGED BUSINESS SUBCONTRACTING

Offerors are cautioned that failure to comply in good faith with the CONTRACT CLAUSE entitled (1) "Utilization of Small, Small Disadvantaged and Women-Owned Small Business Concerns, FAR 52-219-8" and (2) Small, Small Disadvantaged and Women-Owned Small Business Subcontracting Plan, FAR 52.219-9 (Alternate I)," when applicable, will be a material breach of contract. In order to assist prime contractors in developing a source list of Small and Small Disadvantaged Business Concerns, you are encouraged to contact Minority Contractor Associations, the Minority Business Development Agency, and the appropriate General Business Service Centers in your standard Metropolitan Statistical Area, addresses of which may be obtain from:

Write: US Army Engineer District, Los Angeles

ATTN: CESPL-DD-B

P.O. Box 532711 Los Angeles, California 90053-2325

Telephone: Mary Spencer Small and Disadvantaged Business Utilization Specialist Area Code (213) 452-3938

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE

(JUN 2003)

(a) Definition.

"Small business concern," as used in this clause, means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.

00100-12

(b) General. (1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

(c) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas. If this procurement is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, a small business concern may furnish the product of any domestic firm. This paragraph does not apply to construction or service contracts.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE

ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY

FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

24% - 30% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.

Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.

The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

00100-13

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is San Bernardino County, California

52.225-10 NOTICE OF BUY AMERICAN ACT

REQUIREMENT--CONSTRUCTION MATERIALS (FEB 2009)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act--Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

00100-14

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs

(c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of provision)

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be (20%) twenty percent of the bid price or $3,000,000.00, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Tina A. Frazier, Contracting Officer, C/O Julie Ayala, USACE-Los Angeles District, P.O. Box 532711, Los Angeles, CA 90053-2325, 213.452.3240.

00100-15

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-3, Site Investigation and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) A site visit is scheduled for August 10th, 2012 commencing at 10:00a.m. at the Yorba Slaughter Adobe Museum parking lot. Physical address: 17127 Pomona Rincon Road, Chino, CA 91708.

Persons interested in attending the site visit should contact Joe Flynn, with an email. The e-mail is to be received by Corps of Engineers personnel no later than 10:00 a.m. Pacific Time, the day preceding the site visit. The e-mail shall include a day-time telephone number. If there are any changes to the site visit date or location, people who have registered to attend the site visit shall be informed. The USACE e-mail addresses:

Joseph.a.flynn@usace.army.mil Joseph Flynn’s phone number is 651.898.6151

(c) All personnel attending the site visit must have a valid ID.

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows: None

252.204-7001 COMMERCIAL AND GOVERNMENT ENTITY

(CAGE) CODE REPORTING (AUG 1999)

(a) The offeror is requested to enter its CAGE code on its offer in the block with its name and address. The CAGE code entered must be for that name and address. Enter “CAGE” before the number.

(b) If the offeror does not have a CAGE code, it may ask the Contracting Officer to request one from the Defense Logistics Information Service (DLIS). The Contracting Officer will--

(1) Ask the Contractor to complete section B of a DD Form 2051, Request for Assignment of a Commercial and Government Entity (CAGE) Code;

mailto:Joseph.a.flynn@usace.army.mil�

00100-16

(2) Complete section A and forward the form to DLIS; and

(3) Notify the Contractor of its assigned CAGE code.

(c) Do not delay submission of the offer pending receipt of a CAGE code.

252.204-7004 CENTRAL CONTRACTOR REGISTRATION

(52.204-7) ALTERNATE A (SEP 2007)

(a) Definitions. As used in this clause--

“Central Contractor Registration (CCR) database” means the primary Government repository for contractor information required for the conduct of business with the Government.

“Commercial and Government Entity (CAGE) code” means--

(1) A code assigned by the Defense Logistics Information Service (DLIS) to identify a commercial or Government entity; or

(2) A code assigned by a member of the North Atlantic Treaty Organization that DLIS records and maintains in the CAGE master file. This type of code is known as an “NCAGE code.”

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see Subpart 32.11 of the Federal Acquisition Regulation) for the same parent concern.

“Registered in the CCR database” means that--

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database;

(2) The Contractor's CAGE code is in the CCR database; and

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service, and has marked the records ``Active.'' The Contractor will be required to provide consent for TIN validation to the Government as part of the CCR registration process.

(b)(1) By submission of an offer, the offeror…

This is the start of the file's text. The full file is on GovTribe.