W912PF18R0016-0001.pdf

PDF 370 KB Posted

Attached to
REPAIR THEATRE FLOOR AND CHAIRS
Solicitation number
W912PF18R0016
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
Amendment_0003_signed.pdf PDF
5._EZ-00021-6J_Bid_Schedule_20180629_rev.pdf PDF
Amendment_0002.pdf PDF
5._EZ-00021-6J_Bid_Schedule_20180613.xlsx XLSX spreadsheet
SOW_REVISED.pdf PDF
W912PF18R0016-0001.pdf PDF
Attachment2-BidSchedule.xlsx XLSX spreadsheet
W912PF18R0016.pdf PDF
Enclosure1-Construction_Project_Information_Sheet.docx DOCX document
Attachment1-SOW.pdf PDF
Enclosure4-Format_of_a_Bid_Bond.doc DOC document
Enclosure2-PPQ.docx DOCX document
Enclosure3-Self_Certification_for_Antimafia.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011187281 EZ-00021-6J

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this maendment is to include FAR clause 52.211-10, Commencement, Prosecution and Completion of Work into the solicitation.

Other terms and conditions of the solicitation remain unchanged.

See continuation page for details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-May-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912PF18R0016

X 9B. DATED (SEE ITEM 11)

25-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-May-2018

CODE

414TH CSB - PARC AFRICA

ATTN: PATRIZIA MELONI

VIA DELLA PACE #197

36100 VICENZA (VI)

ITALY

W912PF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PF18R0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The Issued By organization has changed from

414TH CSB - PARC AFRICA

VIA DELLA PACE #197

VICENZA (VI) 36100

to

414TH CSB - PARC AFRICA

ATTN: PATRIZIA MELONI

VIA DELLA PACE #197

VICENZA (VI) 36100

SECTION F - DELIVERIES OR PERFORMANCE

The following have been added by full text:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use as stated below:

Performance schedule for project is 304 calendar days split as follows:

90 calendar days to design the project, from Notice to Proceed 14 calendar days for DPW to review the project;

200 calendar days to perform the construction.

(End of clause)

(End of Summary of Changes)

File details come from the government source that posted it.