BASE CONTRACT ––Project E8-44013-4J Installation of Water Softener, Bldg. # 53, Del Din, Vicenza.
STATEMENT OF WORK
PART 1
GENERAL INFORMATION
1. GENERAL: This is a contract to install a Water Softener system into a new Pre-Fab.
Building near existing Water Plant, bldg. #53, Del Din site, Vicenza, Italy.
1.1 Description of Services/Introduction: This is a design building project to install a Water Softener system at the Water Plant bldg. #53 to lower the water hardness actually supplied by the city of Vicenza. The system shall be placed inside a pre-fab building.
1.2 Background: At Del Din site the water supply is granted by “Acque Vicentine s.p.a.”
In detail the water supplied is pumped from the wells located in “Via Lago di Como” and distributed through the circuit named “Laghetto-Polegge”. This water has a hardness of 31 French degrees according with “Acque Vicentine”. This hardness level is within the law limit, but actually is creating problems to the heat exchangers and we retain a next future that could also damage other equipment. For this reason, with this project we intend to soften the water bringing the actual level of 31 to 15 French degrees.
1.3 Objectives: Decrease the water hardness rate from the actual 31 to 15 French degrees.
1.4 Scope: Design and Construction
1.5 Period of Performance: The period of performance shall be as follows:
1.5.1 Design phase: Install a Water Softener system into a new Pre-Fab Building.
Performance period 30 calendar days from notice to proceed.
1.5.2 Construction phase: Install a Water Softener system into a new Pre-Fab Building.
Performance period 60 calendar days from notice to proceed.
1.6 General Information
1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.
Quality Control Plan (QCP) shall be attached to bid offer. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his Quality Control (QC) system.
1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.6.3 Work Schedule:
Name of Holiday Date New Year’s Day January 1st Martin Luther King Jr.’s Birthday 3rd Monday in January President’s Day 3rd Monday in February Memorial Day Last Monday in May Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veterans’ Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
Name of the Italian Holidays Date
New Year’s Day 1 January Epiphany Day 6 January Easter Monday Varies yearly Liberation Day 25 April Labor Day 1 May Republic Day 2 June Assumption Day 15 August Local Holiday 8 September All Saints’ Day 1 November Immaculate Conception Day 8 December Christmas Day 25 December Saint Stephen’s Day 26 December
1.6.4 Hours of Operation: The hours of operation for routine work shall be 0800 thru 1700 hours Monday thru Friday. Work shall not be performed on Italian and American holidays occurring during the normal work week. Work shall not be performed on local holidays occurring during the normal work week. When an American holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively. Work during other than normal hours shall not be performed without prior written approval of the Contracting Officer Representative. The Contractor shall submit request for such approval to the Contracting Officer Representative at least 24 hours in advance.
1.6.5 Place of Performance: The work to be performed under this contract will be performed in Water Plant area near Building # 53 (Pump House) located on Del Din site, Vicenza, Italy
1.6.6 Type of Contract: The government will award a firm Fixed Price Contract.
1.6.7 Access and General Protection/Security Policy and Procedures: The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.6.7.1 Physical Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.
1.6.7.2 Contractor Identification: Prior to commencement of contract performance, the Contractor shall furnish the COR in writing and in triplicate, a list of the personnel identified for work under the contract. The list shall contain:
A. Name and address of each employee.
B. Identification Document or driving license number of each employee.
C. Copy of personnel register.
D. “Centro per l’impiego” Identification Document
E. The contractor shall furnish a list of private and commercial vehicles which will be used in conjunction with contract work. The list shall be submitted together with the list of personnel and shall contain:
(1) Make of vehicle;
(2) Model and year of manufacture; and
(3) License Plate Number.
1.6.7.3 iWATCH/iSALUTE Training: The contractor and all associated subcontractors will brief all employees on the local iWATCH/iSALUTE program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days after the contract is awarded and within 30 calendar days after new employees commence contract performance, with the results reported to the COR.
1.6.7.4 AT Level I Training: All Contractor employees, including Subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas will complete AT Level I awareness training within 30 calendar days after the Contract start-date. The Contractor will submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR or to the Contracting Officer, prior to issuance of Installation Access Passes. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.
1.6.7.5 According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.
1.6.8 Special Qualifications: PSC: ____ NAICS: ____
1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
1.6.10 For any excavations deeper than 6" (15 cm.), the Contractor must request to the COR for a digging permit. This form will be furnished to the Contractor at the pre-construction conference.
1.6.11 Asbestos or other contaminants: If asbestos or other contaminants are found, the contractor (with a mod) shall treat and dispose it. When the presence of asbestos or other contaminants are suspected but it couldn’t be visible during the site visit, the awarding firm shall have (with this basic contract) an analysis performed at his expense by an authorized laboratory, and in the case of a positive result, shall promptly inform the COR.
With a further modification shall be provided a disposal of it by a specialized firm.
1.6.12 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.13 Key Personnel: The follow personnel are considered key personnel by the government: The contractor shall provide a contract manager or supervisor who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.
The contract manager or alternate shall be available between Tuesday thru Sunday except Federal holidays or when the government facility is closed for administrative reasons.
1.6.14 Construction Site Conditions: The work area shall be made available for the Contractor with the following conditions:
1.6.14.1 The work site area, as necessary for the execution of each single construction phase, will be available to the Contractor. The site shall be temporarily fenced on the area indicated by the Contracting Officer; signs in the two languages: “Work Area - No Entry / Vietato l' ingresso - Lavori in corso”. The fencing shall be removed at work completion. Obstruction lights shall be used from sunset to dawn anywhere, where necessary. The area could be crossed by undetected lines, not shown on the project drawings. The Contractor shall proceed with care in all operations involving excavations and soil removal. If any line, object or material will be found under the ground the Contracting Officer shall be promptly informed for his successive action. Any relocation or repair of such obstacles damaged during excavation shall be at the Contractor's expense. Detailed utility drawings are available at the Engineering Office.
1.6.14.2 During the performance of work, special care is to be taken not to interfere with ongoing activities on nearby facilities. Materials shall be loaded/ unloaded inside the work site. Access to other buildings shall not be hindered by Contractor’s personnel, vehicles or stored materials. Vehicles for the transport of materials can be temporarily parked near the building site to load/unload materials if they do not obstruct traffic.
1.6.14.3 Protect materials and equipment that need to remain in the areas of work with plastic sheets or some other approved method. Hazardous material shall be stored properly (IAW applicable regulations) to avoid leakage, spills or releases. Any materials, or equipment damaged by the Contractor during the work shall be repaired or substituted at the Contractor’s expense. Contractor shall remove and reinstall non-fixed equipment as indicated and approved by the Contracting Officer.
1.6.14.4 Before starting any work, submit to the Contracting Officer a schedule indicating in detail each phase of work, safety precautions and protection of property.
Schedule of work shall be approved by the Contracting Officer.
1.6.14.5 Utilities and Services: The Contractor shall be provided, for the sole scope of work, with electricity and water services available in the area. All temporary connections shall be cleared to the Contractor, as shall be the restoration of said utilities to original conditions at the completion of the project. The connection shall comply with pertinent U.S. and Italian safety of work and CEI norms. All machinery and equipment shall be properly grounded.
1.6.14.6 Salvageable Materials: If there are any specified items within these technical specifications to be salvaged, it shall be the responsibility of the Contractor to remove the salvageable items with the maximum care to avoid any damages and to transport and deposit the same to the storage area within the Caserma Ederle areas. The Contracting Officer shall identify salvageable items during the demolition phase. All discarded materials shall be recycled or disposed of to the dump authorized by the Regional and National regulation according to the typology of the related material; the contractor shall be the generator of waste. The transport shall be extended, if required, even outside Caserma Ederle City Council Territory. It shall be the responsibility of the Contractor to provide containers for material disposal (i.e. glass, steel, windows, doors, etc.) and/or transportation of salvageable items to either DRMO or to the appropriate facility as specified above. The Contractor shall also provide all documents (and coordination work) necessary to obtain the authorization from the Local Environmental Authority for the eventual disposal of materials, for which the normal disposal procedures are not sufficient.
1.6.15 ENVIRONMENTAL MANAGEMENT SYSTEM: The USAG Italy implements an EMS in accordance with EO13693, ISO 14001:2004(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. The USAG Italy EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities and authorities while supporting the USAG Italy mission. Contractors and their personnel are required to be aware of, and comply with, the USAG Italy Environmental policy and legal and other requirements when performing work at an installation. The contractor will provide the following information semi-annually to be used by the Government to address environmental performance relative to the goals of the USAG Italy Environmental Management System. Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-December will be submitted by 15 January each year.
Media Report Element #1 Report Element #2
Non-Hazardous Solid Waste Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Construction Debris/Demolition Materials
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Compostable/Organic Material
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Hazardous Materials Total Used (Kg)
Hazardous Waste Total Generated (Kg) Total Recycled (Kg)
Energy Consumption - Electricity
Total Energy Consumed (MBtu)
Energy Consumption - Fuel Total Fuel Consumed (L)
Renewable/Alternative Energy
Total Consumed (MW)
Facility Construction/Renovation
Number of Buildings LEED Certified Silver or Higher
SqFt of buildings LEED Certified
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1 DEFINITIONS:
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations.
This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor.
The Government does not have privity of contract with the subcontractor.
2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2 ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QC Quality Control QCP Quality Control Program TE Technical Exhibit
PART 3
GENERAL SUBMITTAL REQUIREMENTS
3. General Submittal Requirements: Government approval is required for design, critical materials, deviations, O&M manuals or equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled “Specifications and Drawings for Construction,” they are considered to be “shop drawings.” The Contracting Officer’s approval of submittals shall not be construed as a complete check, but will indicate that the general methods of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the contractor is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.
3.0.1 Submit, prior to beginning of construction work, a completed design signed by one of the following as appropriate: Italian Registered Engineer, Architect, Geometra, Perito, Geologo as required by Italian Law. The US Government will appoint, with separate contract, a qualified technician as final tester (Collaudatore), as required by Italian law 425/95 and 1086/71. The technician shall respond to US Government for necessary Official Paperwork.
3.0.2 Construction drawings must be prepared and signed by professional engineers, within their respective expertise, registered in Italy, who will accept responsibility in accordance with Italian laws.
3.0.3 All documents shall be submitted in electronic format AutoCAD compatible for drawing, MS office compatible for documents and in TIFF/PDF format for raster and pictures.
3.0.4 Utilities lines shown in DPW utilities maps are meant for reference only and may not be completely accurate for the purposes of excavation. It shall be contractor’s responsibility to verify the location of all utilities and reroute the utilities lines as necessary at no additional expense to the Government.
3.0.5 The contractor, prior to start any work on site shall submit final construction drawings and technical reports (HARD COPY AND ELECTRONIC COPY 100% COMPLETED). Partial submittals shall not be accepted. The material can be submitted after the acceptance of the construction drawings, but shall be submitted together, partial material submittals shall not be accepted.
3.0.6 FINAL ACCEPTANCE TESTS AND CERTIFICATIONS: All installed civil, mechanical, electrical and communication equipment shall have the required Italian Marks of Quality (Marchio di Qualita') and three copies of relevant certificates will be furnished to the Contracting Officer for each item of equipment installed. At the end of works, the contractor shall provide the Government with three copies of the following documents:
3.0.7 Installation Certificate of Compliance for structures, electrical and mechanical systems (i.e. Statement of Conformance of the installer regarding these systems (Certificato di Conformita’).
3.0.8 Thermal Efficiency Certificate in accordance with Italian law n. 311 dated 29/12/2006 art. 6, D.M. 26 giugno 2009 e modifiche (con il D.M. 22 novembre 2012) and related updates.
3.0.9 Final acoustical classification Certificate in accordance with Italian law Legge Quadro 477/95, NORMA UNI 11367 del 22 luglio 2010, UNI 11444/2012, DPCM
5/12/1997, DPCM 14/11/1997
3.0.10 Filled forms: MOD. 3 and MOD. 4 Allegato A DGRV 2424/2008 and D.Lgs.152/2006
3.0.11 Final AS BUILTS drawings and documents.
3.0.12 Final as Built Photo report. The report will put in evidence, through colored photos (minimum dimension 10x12 cm) all technical details shown in the SPECIFIC TASK DESIGN. It shall be printed and signed by a qualified professional technician and by the builder. In particular, photos will show all foundations layers and materials installed, waterproof membrane installation, thickness of insulation panels installed on foundation, walls and roof, stratigraphy of foundation, walls, intermediate joist and final roof, gutters, downspouts, flashing installation, all underground utilities conduits, manholes, pipes, point of connection with existing lines, special encased equipment, windows and doors installation and connection with wall in order to avoid thermal bridges, minimum six interior views and four exterior view (one for each elevation)
3.0.13 The contractor shall prepare as built drawings as described in contract clause:
“RECORD DRAWINGS”. In addition, contractor shall update government As-Built drawings, showing all the utilities, building and structures involved in his contract. The Government will furnish the contractor available basic document to be updated.
3.0.14 All necessary documents requested by final tester for the final Collaudo (which shall be done by a professional engineer designated directly by U.S. Government.)
3.1 SPECIFIC TASK DESIGN: This first phase of the work consists of designing the details, providing calculations and whatever necessary to define in scale all parts of work required to fulfill the scope of work as described in “SPECIFIC TASK CONSTRUCTION” below in this document, and in accordance with Italian Law 170/2005 art. 56 and 66. Documents required to accomplish this specific task prior to building construction are as follows:
3.1.1 Demolition analysis of the existing structures which interfere with the construction, including utilities lines and any other findings during the survey. All existing site conditions and underground utilities shall be verified and documented in the demolition analysis. The analysis, in two copies, shall include all loads, computations, assumptions, and codes on which the design is based.
3.1.2 Soil investigations and related reports (analisi geologica e geotecnica), per Italian law DM 14.01.2008, D.Lgs.152/2006 and Circ.Min.LL.PP. 02/02/2009 n. 617
3.1.3 Soil analysis and related evaluation (analisi geoambientale del sito per la gestione delle terre e rocce da scavo), per Italian law DM 161/2012, D.Lgs.152/2006, DGRV 2424/2008 and DGRV 794/2009
3.1.4 Filled forms: MOD. 1 and MOD. 2 Allegato A DGRV 2424/2008 and D.Lgs.152/2006
3.1.5 Analysis of the mechanical, electrical systems, security and safety, including underground utilities rerouting minimizing service interruptions. The analysis, in two copies, shall include all loads, computations, assumptions, and codes on which the design is based.
3.1.6 Detailed design (plans, sections and elevations in scale 1:10-1:20), as demonstration of technical resolution of all thermal bridging.
3.1.7 Structural analysis including seismic analysis resistance as per current Italian law NTC 14 gennaio 2008 and related updates. The structures shall be designed considering the specific seismic rate in accordance with current Italian code in force. The analysis, in two copies, includes all drawings, loads, computations, assumptions, and codes on which the design is based.
3.1.8 Inspection and evaluation of the existing building structure to determine potential earthquake, blast hazards and determine the seismic upgrading requirements in accordance with current Italian NTC 14 gennaio 2008 art.8 and US norms. The analysis, in two copies, includes all loads, computations, assumptions, and codes on which the design is based
3.1.9 Acoustical analysis for noise abatement and reduction, as per Italian Law NORMA UNI 11367 del 22 luglio 2010, UNI 11444/2012, DPCM 5/12/1997, DPCM 14/11/1997 and U.S. Code. The analysis, in two copies, includes all loads, computations, assumptions, and codes on which the design is based.
3.1.10 Building thermal analysis (involucro edilizio and impianti installati) as per D.Lgs.
28 del 3 marzo 2011, D.Lgs. n.311 del 29 Dicembre 2006 ad integrazione del D.Lgs.
192/2005 e DPR 2 aprile 2009 n.59
3.1.11 Sets of construction drawings on 119.0 x 84.1 cm. sheets (ISO A0 form).
Drawings, at a minimum, must contain the following:
3.1.11.1 Cover sheet and index of drawings including vicinity map as shown at the attachments, and a general location plan at 1:500.
3.1.11.2 Location layout indicating the route of all new utility lines with indicated point of connection with existing lines.
3.1.11.3 Demolition plan. Material disposal documents shall be in accordance with Italian Law Dlgs. N.152 dated 3 Apr 2006 “Norme in materia ambientale”.
3.1.11.4 Foundation plans and details;
3.1.11.5 Floor plans and details;
3.1.11.6 Roof plans and details;
3.1.11.7 Elevations and details;
3.1.11.8 Interior layout plan with various finishing details;
3.1.11.9 Ceiling plans and details;
3.1.11.10 Section and details;
3.1.11.11 Flow diagram water softener system;
3.1.11.12 Layout water softener equipment and piping distribution with stand-off distance;
3.1.11.13 Layout underground piping system from the water softener to the connection to the existing water line. Detail of the connection;
3.1.11.14 Thermal control functional scheme;
3.1.11.15 Electrical system: construction and control details;
3.1.11.15.1 Diagram and schematics of electrical power supply and distribution panels;
3.1.11.15.2 Single-line diagram of the electrical panels;
3.1.11.15.3 Electrical feeders layout and details;
3.1.11.15.4 Lighting, power, and grounding systems, wiring and details;
3.1.11.16 Single-line diagram electrical panel.
3.1.12 Location plan shall be drawn at 1:200 minimum; other plans and elevations shall be drawn at 1:100 and/or 1:50 and details shall be shown at 1:l0 and/or 1:20. Dimensions and material identifications shall be clearly indicated. Drawings shall include all necessary notes and legends. All wording shall be in both English and Italian.
3.1.13 Sets of detailed technical report (in English and Italian) to include the following:
3.1.13.1 Detailed description of all works to be accomplished;
3.1.13.2 Method of accomplishment;
3.1.13.3 Materials and finishes; and
3.1.13.4 Reference to norms and laws in force.
PART 4
SPECIFIC TASK CONSTRUCTION
4. GENERAL. All work shall be done in accordance with applicable laws, decrees and technical norms, as shown in, but not limited to, section 6 - Applicable Publications.
4.1 SPECIFIC TASK BASE CONTRACT CONSTRUCTION:
4.2 CONCRETE PLATFORM AND SIDEWALK AND PRE-FAB
4.2.1 Site preparation shall include, but not be limited to, scaffolding assembly, worksite fencing installation and any other items as required to accomplish this specific task.
Remove only that material approved by the Contracting Officer’s Representative (COR).
Materials to be salvaged will be delivered to a site in Caserma Del Din as directed by the COR. All other material will be removed immediately from the installation by the contractor and disposed of in a legal landfill in compliance with the Italian laws.
4.2.2 Reinforced concrete platform construction to host the water softener equipment and reinforced concrete duct way for new water lines from the aqueduct. Provide forms, shoring, and scaffolding for concrete placement. Place the concrete as soon as practicable after the forms and the reinforcing have been inspected. Prior to placing concrete, remove dirt, and construction debris from the forms. Provide reinforcing bars, wire fabric, wire ties, supports, and other devices necessary to install and secure the reinforcement. Reinforcement shall not have rust, scale, oil, grease, clay, or foreign substances that would reduce the bond. After reinforcing is placed, it must be secured with galvanized or non corrodible ties, spacers, or metal hangers. Provide geotextile below the floor slab. Use the greatest foil size possible to eliminate joints and eventually lap joints a minimum of 100 mm.
4.2.2.1 Reinforced concrete sidewalk dimension and finishing as specified in contract drawings. The new sidewalk shall be connected with the existing sidewalk by creating appropriate slope without steps
4.2.3 The prefabricated metal shed shall have the structure in galvanized steel FE 360.
The perimeter walls shall be sandwich type panel 50 mm. thick, pre-varnished steel insulated inside with polyurethane foam. The roof shall be corrugated metal sheet insulation and finishing as the perimeter walls.
4.3 WATER SOFTENER:
4.3.1.1 The water softener system shall be sized to treat a maximum daily flow of 700 c/mt and shall soften the water bringing the actual level of 31 to 15 French degrees.
4.3.1.2 The filtering system shall be self washing type and will start through the activation of an electronic brushing system of the inox cartridge and the opening of the waste solenoid valve. The system shall be totally automatic and shall grant the possibility to set frequency of self washing per week (from 1 to 28 washing per week), with the possibility to choose the day in which to activate the filter washing; frequency of self washing by day (from 1 to 4 time by day).
4.3.1.3 The softener of this contract shall be (duplex type 1+1 column) supplying softened water 24/H a day. The automatic control device for the regeneration shall be able to invert the column n. 1 by replacing the operating column with the other (n.2) already regenerated and ready to be used.
4.3.1.4 The softeners shall be equipped with an electronic valve with a microprocessor allowing the resins to be regenerated on prefixed date and hour or after a prefixed volume of water used. The resin tank shall be suitable for drinking water.
4.3.1.5 The brine tanks shall be in polyethylene properly sized.
4.3.2 The new softener system shall be connected to the existing aqueduct pipe up-stream of the water tank. The pipes shall be HPDE size and nominal pressure according with the required flow of water and with the running pressure of 10 bar. By pass valves shall be installed in the connection point and shall be hosted in a new concrete pit with cast-iron cover. Shut-off valves shall be installed inside the softener plant. All the new lines shall be hydraulically tested.
4.4 ELECTRICAL SYSTEM:
4.4.1.1 The lighting system shall include wirings and equipment; the fluorescent light fixtures shall be equipped with electronic ballast, adequate to achieve a minimum light level averages in accordance with UFC 3-530-01 7-2. Light switch shall be provided at entrance of the rooms. The electrical circuits and connections for the light system shall have a minimum size of 2.5 mm2, unless larger sizes are required.
4.4.1.2 Main distribution electrical panel complete with voltmeter, ammeter, commutator etc. complete with main and branch circuit breaker, distribution bars and accessories, the new panel shall have enough circuits to meet the needs of existing equipment plus 30% of spare spaces, shall have circuit breakers installed in all spaces and be adequate ampere capacity for all circuits.
4.4.1.3 Install two outlets 2P+G 16A, 230V Schucko type and two outlets 3P +G 16A, 230 CEE (industrial) type.
4.4.1.4 Provide new underground conduit from the main electrical panel located in Building 53 to the new MDP in which a new electrical feeder (Three phase, Neutral, and Ground), type FG70R 0,6/1KV, shall be wired, shall be Contractor’s responsibility to provide the size of feeder (sq.mm.) and the circuit breaker frame (Ampere) based on the project load calculation (Total - KW - connected). The new feeder line shall be protected by an adequate thermal magnetic ground fault breaker (with an Idn= 30mA)
4.4.1.5 The Contractor shall perform all the electrical connections to the new softener equipments, to new lighting system and to outlets. All work shall be done in accordance with CEI norms (Class. CEI 64-8/3 - CT 64 - Fascicolo 11958 - Anno 2012, CEI 20 - CT 20 - Fascicolo 6210 - Anno 2001 - Edizione Terza) and applicable NEC and NEMA standards
4.5 DIGGING AND BACKFILLING:
4.5.1 Digging and grass restoration: The contractor shall perform all the necessary excavation to install the water pipes and electrical line. The contractor shall have particular care do not damage the grass area. The contractor will have to take care not to damage the existing turf. He will have to protect the turf by wooden planks to go through with excavation machines. The contractor shall have particular care to compact the back-filling soil of the trenches to prevent future settlements. The turf damaged area shall be restored with new turf rolls. The contractor will be responsible for the care of the grassland restored to the full taking root.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1 All work performed by the Contractor shall be performed in accordance with all applicable U.S. and Host Nation laws and regulations, whichever is more restrictive at contract award date. This includes any required certification by engineers licensed in Italy and in particular:
Italian DECRETO DEL PRESIDENTE DELLA REPUBBLICA 19 aprile 2005, n.170 “Regolamento concernente disciplina delle attivita' del Genio Militare”.
Italian DECRETO MINISTERIALE 22 Gennaio 2008, n. 37 (Utilities
Certifications) and related updates.
Italian law n. 477/95 “Legge Quadro su inquinamento Acustico”.
Italian “Decreto Legislativo 9 Aprile 2008 update November 2012 n. 81 “TESTO UNICO SULLA SALUTE E SICUREZZA SUL LAVORO” and Legge Regionale 61/85 art.79bis modificata dalla Legge Regionale 4/2008 art.12.
Italian law 425/1995, Legge n. 64 del 2 FEB 1974, Legge 5 novembre 1971 n.1086 (Reinforced Concrete Structures), NTC 14 gennaio 2008 and all related updates
Italian D.M.LL.PP. del 16/01/1996 “Norme tecniche relative ai Criteri generali per la verifica di sicurezza delle costruzioni e dei carichi e sovraccarichi.”
Italian Law Dlgs. N.152 dated 3 Apr 2006 “Norme in materia ambientale”.
Italian “Decreto del Presidente della Repubblica n. 59 del 2 Aprile 2009”, D.Lgs.
n. 28 del 3 marzo 2011 “, D.Lgs. n.311 del 29 Dicembre 2006 ad integrazione del D.Lgs. 192/2005;
D.P.C.M. 5 Dicembre 1997 “Determinazione dei requisiti acustici passivi degli edifici”, D.P.C.M. 14 novembre 1997,UNI 11367 del 22 luglio 2010,UNI 11444/2012;
“Circolare Regione Veneto n. 13/97 ” Regulation in Health provision for buildings;
Italian DGRV 2424/2008 and D.Lgs. 152/2006, DM 161/2012, DGRV 794/2009, DM 14.01.2008 and Circ .Min. LL.PP. 02/02/2009 n. 617 (Gestione terre e rocce di scavo)
UNI 9737 Polyethylene pipe welding procedures
Legge 46 del 05/-03/90 water treatment potable water
DL 31 del 02/02/2001 water treatment potable water
DPR 59 del 02/04/2009 water treatment
DM 25 del 07/02/2012 water treatment
Norme UNI 8065 water treatment
DM 443 – 1990 equipment for water traetment potable water
DM 174 – 2004 equipment for water traetment potable water
Norme UNI EN 729 welding quality
Norme UNI EN ISO 15607 welding procedures
Norme UNI EN 287 welders qualifications
Italian DM 24-11-1984 for welding procedures
UNI 10208-2 norm for welding procedures
UNI-ISO 6761 pipe preparation for welding.
UNI 5132 electrodes homologation.
UNI 4663 certification for hard and arc welders.
UNI 5770 certification for oxyacetylene welders.
D.Lgs 152-2006 (VAS-VIA)
Safety and Health requirements will be performed in accordance with US Army Corps of Engineers EM 385-1-1, or Italian Law whichever is the most stringent.
All work shall be done in accordance with CEI norms and applicable NEC and NEMA standards.
CEI 64-8/3 - CT 64 - Fascicolo 11958 - Anno 2012
CEI 20 - CT 20 - Fascicolo 6210 - Anno 2001 - Edizione Terza
END