W912PF-16-R-0023_Amendment_0001.pdf

PDF 6 MB Posted

Attached to
Construct running track, Darby Military Community, Italy Federal contract opportunity
Solicitation number
W912PF-16-R-0022
Issued by
Department of the Army Materiel Command Expeditionary Contracting Command Regional Contracting Office Vicenza-Africa 414th CSB

About this file

Amendment 001 with replacement Attachment 1 and Attachment 4

View the file

Other files for this federal contract opportunity

Other files attached to Construct running track, Darby Military Community, Italy, newest first.
File Type Posted
Technical_Specifications.pdf PDF
Attachment10RequistiGeneraliBIS.pdf PDF
Attachment7PPQuestionnaire.pdf PDF
Attachment4SatelliteViewTrackField-4_lanes-A3-1-500.pdf PDF
Attachment6ConstructionPExQuest.pdf PDF
Attachment1StatementOfWork.pdf PDF
Attachment9RequistiGenerali.pdf PDF
Attachment3GeoSurvey.pdf PDF
SolicitationW912PF16R0023.pdf PDF
Attachment8WiringDiagramPanelsSC3SC8.pdf PDF
Attachment2AreaforConstruction.pdf PDF
Attachment5DesignPExQuest.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010895430

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1) To answ er a vendor request for information as show n on page 2 of this Amendment,

2) To add "Addendum 001" to "Attachment 1 Statement of Work", and

3) To replace "Attachment 4 Satellite View Track Field - 4 Lanes - A3 - 1-500" w ith a new version entitled "Attachment 4 Satellite View Track and Field - 4 Lanes - A3 - 1-500 REV 1" A replacement copy of Attachment 1 and Attachment 4 are included w ith this Amendment and replace the previously posted copies.

Offerors are permitted to return a signed copy of this Amendment to the address listed in Block 7 of the solicitation SF 1442 or by e-mail to elisa.orsini2.ln@mail.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-Aug-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF-16-R-0023

X 9B. DATED (SEE ITEM 11)

14-Jul-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Aug-2016

CODE

414TH CSB RCO ITALY SUBOFFICE LIVORNO

VIA AURELIA, EDIFICIO 5131

ZONA DEPOSITO

56128 TIRRENIA (PISA)

W912PF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PF-16-R-0023

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been added by full text:

AMENDMENT 0001

This following information is provided in response to a vendor request for information:

Question 1 : Can companies use a Joint Venture (Italian ATI) to satisfy the solicitation requirements?

Response: For the purposes of this contract and in accordance with FAR 9.603 the Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in an offer or, for arrangements entered into after submission of an offer, before the arrangement becomes effective.

“Contractor team arrangement,” as used in FAR 9.601, means an arrangement in which— A. Two or more companies form a partnership or joint venture to act as a potential prime contractor B. A potential prime contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program.

Joint Venture offerors shall furnish with their proposal a notarized legal document (or an agreement signed by both parties) that establishes the Joint Venture. The Joint Venture Agreement shall take effect upon the submission of the proposal and remain irrevocable until two (2) years after the work has been finally inspected and accepted by the Government. The Joint Venture Agreement shall include, at a minimum, the following:

A. Name of firms that form the Joint Venture and the name of the Joint Venture.

B. Name and title of the corporate officials signing in behalf of each party. The lead or prime Company has to be registered in SAM.

C. Solicitation number.

D. The statement "The composition and structure of the Joint Venture will remain unchanged from award to two (2) year after the work has been finally inspected and accepted by the Government.”.

E. Date of issuance of the agreement (and notarized signature of the corporate officials) signing in behalf of each party. The U.S. Government reserves the right to review the actual Joint Venture agreement to determine its basis and compliance with the applicable laws. Any internal agreements affecting the internal composition of the existing Joint Venture and its potential liabilities in relation to the contract (bonds, insurance, etc) will be sent to the Contracting Officer to provide notice of the same. Any change in the composition of the Joint Venture will require the Joint Venture to formally request a Novation Agreement in accordance with FAR 42.12, which will be approved/disapproved at the discretion of the Contracting Officer.

Question 2: Are "external" design firms allowed?

Response: Yes, an "external" design firm is allowable. The design firm's past experience must meet the experience requirements of Solicitation Sections L/M and provide a signed Letter of Intent. If the design work will be performed "in-house" by the prime contractor, a letter must be submitted stating this fact.

(End of Summary of Changes)

CARABINIERI

PREFABRICATED CONTAINER

WIND INDICATOR POLE

GYM EQUIPMENT

SC4

ELECTRICAL PANEL

DP

ELECTRICAL PANEL BUS STOP

PANEL SC5

ELECTRICAL

TELEPHONE POLE

LIGHTING POLE 1

LIGHTING POLE 2

FLOWERS CONCRETE VASES

LIGHTING POLE 3

HELICOPTER LANDING PAD

VARIOUS FACILITIES

SC3

ELECTRICAL PANEL

SC6

ELECTRICAL PANEL

SC7

ELECTRICAL PANEL

SC8

ELECTRICAL PANEL

HANDHOLE

COMMUNICATION

HANDHOLE

COMMUNICATION

HANDHOLE

COMMUNICATION

COMMUNICATION LINES DIRECTLY BURIED

WATER FAUCET

PANEL

OUTLETS

ELECTRIC

TRAFFIC LIGHTS

INSPECTION

PORTABLE

LV ELECTRICAL LINES

MANHOLE

COMMUNICATION

MODULE

PREFABRICATED

MANHOLE 1

ELECTRIC

2 AND 3

MANHOLES

ELECTRIC

MANHOLE 5

ELECTRIC

MANHOLE 6

ELECTRIC

GATE

ELECTRICAL PANEL

MANHOLE 4

ELECTRIC

BARRIER

W912PF-16-R-0023 Amendment 0001
Attachment1StatementOfWorkwAddendum0001
Attachment1StatementOfWork
Add1 to SOW DB RT

Attachment4Satellite View Track Field - 4 lanes - A3 - 1-500 REV 1