0010830192-0001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amendment 0001 to Solicitation W912PF-16-R-0019 is as follow s:
1. Incorporate Industry Questions and Government Answ ers to the questions w hich is included as an attachment to the Amendment Package. Reference “W912PF-16-R-0019_Government Responses to Industry Questions (dtd 08 July 2016).”
2. Update the language pertaining to Materials under Attachment 1, PERFORMANCE WORK STATEMENT (PWS), SECTION I DESCRIPTION OF SERVICES, 1.7.4 Maintenance and Repair Works – Scheduled & Emergency.
3. Update Attachment 1, PERFORMANCE WORK STATEMENT (PWS), SECTION IV GENERAL INFORMATION, 4.1. CONTRACTOR QUALIFICATIONS, subparagraph 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 20
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Jul-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PF-16-R-0019
X 9B. DATED (SEE ITEM 11)
17-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Jul-2016
CODE
414TH CSB RCO ITALY SUBOFFICE LIVORNO
VIA AURELIA, EDIFICIO 5131
ZONA DEPOSITO
56128 TIRRENIA (PISA)
W912PF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PF-16-R-0019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
PWS
PERFORMANCE WORK STATEMENT (PWS)
FOR
Maintenance and Repair Electrical Distribution Systems, UPSs & Inverter Drives within USAG Italy DMC
USAG Italy, Darby Military Community Livorno
Public Works Offices, Utilities
February 22nd, 2016
TABLE OF CONTENTS
SECTION PARAGRAPH TITLE
I DESCRIPTION OF SERVICES
1.1. Scope of Work
1.2. Location of Services
1.3. Hours of Operation
1.4. Absences (Reserved)
1.5. Confidentiality (Reserved)
1.6. General Contract Services
1.7. Specific Tasks
1.8. Conduct
1.9. Payments
1.10. Safety
1.11 Contractor Manpower Reporting (CMR)
II SERVICE DELIVERY SUMMARY
III GOVERNMENT-FURNISHED PROPERTY & SERVICES
3.1 General Information (Reserved)
3.2 Government-Furnished Property (Reserved)
3.3 Contractor-Furnished Property
3.4 Government-Furnished Services
3.5 Government Provided Training (Reserved)
IV GENERAL INFORMATION
4.1. Contractor Qualifications
4.2. Contractor Personnel
4.3. Quality Control
4.4. Quality Assurance
4.5. Physical Security
4.6. Hours of Operation
4.7. Conservation of Utilities
4.8. Records
V TECHNICAL EXHIBITS
5.1 Workload Estimates (Reserved)
5.2 Publications & Forms (Reserved)
5.3 Required Reports
SECTION I
DESCRIPTION OF SERVICES
1.1. SCOPE OF WORK: Contractor shall manage and provide all equipment, tools and labor necessary to performance the services called for by these specifications.
1.2. LOCATION OF SERVICES: Service will be performed at Camp Darby, Depot, Ammunition Storage Area
(ASA), Poggio Lecceta, Livorno Training Area (LTA).
1.3. HOURS OF OPERATION: The normal working hours shall be from 8:00-17:00, Monday through Friday excluding Italian and U.S. Federal Holidays. For operation reason, it may happen that the COR requires to perform the service on Sunday and in other than above mentioned hours.
1.4. ABSENCES: Reserved.
1.5. CONFIDENTIALITY: Reserved.
1.6. GENERAL CONTRACT SERVICES: The Contractor shall accomplish the following in conjunction with the specific contract services detailed herein:
(a) Contractor shall report immediately any serious incident (e.g. accidents, abuse of Government property) to the COR.
(b) The use of tools equipment and all works specified by these specifications shall be performed in strict compliance with the INAIL (Superior Accident Prevention and Job Security Institute) standards, CEI (Italian Electrical Committee) standards and each other applicable Italian law.
(c) This contract shall be performed in Government buildings and plants. All buildings will be occupied during the performance of work, therefore the Contractor might accomplish the work within the hours previously coordinated and programmed with COR
Technical laws and norms having a strict reference to these specifications are following described:
- D.Lgs n.81-2008 e smi: “Testo Unico in Materia di Sicurezza”;
- D.M. n.37-2008: “Regolamento concernente l’attuazione dell’art.11-quaterdicies, comma 13, lettera a), della Legge n.248 del 02/12/2005, recante riordino delle disposizioni in material di attività di installazione degli impianti all’interno degli edifici”;
- CEI 64-8: “Impianti Elettrici utilizzatori a tensione nominale non superioe a 1000V in c.a. e 1500V in c.c.”;
- CEI 11-1: “Impianti Elettrici con tensione superior a 1kV in c.a. e Impianti di terra in relazione alle tensioni”;
- CEI EN 50110-1: “Esercizio degli Impianti Elettrici”;
- NEC: “American National Electric Code”;
- Any other applicable safety and technical law and norm;
- Standards Operating and Owner’s Manuals.
1.6.1 ANTITERRORISM/OPERATIONS SECURITY
a. AT Level I Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas will complete AT Level I awareness training within 30 calendar days after the contract start-date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, prior to issuance of Installation Access Passes. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.
b. Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
c. iWATCH/iSALUTE Training. The contractor and all associated subcontractors will brief all employees on the local iWATCH/iSALUTE program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days after the contract is awarded and within 30 calendar days after new employees commence contract performance, with the results reported to the COR.
d. Contractor Employees Who Require Access to Government Information Systems. All contractor employees with access to a Government information system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete DOD information assurance awareness training before access to the information system and then annually thereafter
e. OPSEC Training. According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.
1.7. SPECIFIC TASKS
The contractor shall provide all necessary tools, equipments and workforce to perform services under this specification. The contractor is considered the waste generator of all salvage, re-usable, recyclable and disposable material derived from the service called for in these specifications. The above material will be managed under contractor’s expense and responsibility.
1.7.1 Scheduled Maintenance on 190 Electrical Junction Boxes
Once per year, the contractor shall inspect, clean, control and lubricate the cables connections of 190 electrical junction boxes (window hinges and locks included) installed at nr.190 buildings within Camp Darby, Depot and ASA areas.
In addition, for any connection box, the contractor shall verify the status of the neutral and grounding conductors, identifying the grounding pits around the building, conducting measures of the resistance to earth.
For any inspection, the contractor shall provide a report of the activities accomplished with a description of the deficiencies found.
Reference CDRL 0001 under exhibit 5.3 of this PWS for further direction on submission.
1.7.2 Scheduled Maintenance for Inverter Drives - nr.2 Six Months Services
The contractor shall perform nr.2 six-months services to inspect, clean and set the inverter drives installed at USAG Italy DMC. List of equipment is described in the enclosed table nr.1.
Table.nr.1
NR. BUILDING NR. INVERTER DRIVE (OMA)
Electrical Panel Room 147M
Honeywell HVAC400-18P-21 - 18.5 kW
Electrical Panel Room 41M
Honeywell HVAC400-3P0-21 - 3 kW
Electrical Panel Room 41M
TREND VSD2H-3C0038B2000 - 18.5 kW
4 402 ATV61 - 45kW 5 405 ATV212HD18M3X - 18.5kW 6 405 ATV212HD18M3X - 18.5kW 7 405 ATV212HD18M3X - 18.5kW 8 405 ATV212HD11M3X - 11 kW 9 405 ATV61 - 37kW
10 405 ATV61 - 30kW 11 905 OMRON U7 - 5.5 kW 12 905 OMRON U7 - 5.5 kW 13 905 OMRON VS MINI S7 - 2.2 kW 14 905 OMRON VS MINI S7 - 2.2 kW 15 5042 ATV61 - 30kW 16 5042 ATV61 - 30kW
17 5156 UTA-1 ACH550-01-03A3-4
18 5156 Kitchen Hood ACH550-01-04A1-4 19 5156 Kitchen Hood ACH550-01-04A1-4
20 5156 UTA-2 OUT ACH550-01-08A8-4
21 5156 UTA-2 IN ACH550-01-023A-4
22 5672 ATV312HU22N4 - 2.2 kW 23 5672 GT700E - 2.2 kW 24 5861 AHU ATV61HD11N4 - 11 kW 25 5881 AHU-1 ATV61 - 1.5 kW 26 5881 VFD-P4 ATV61 - 5.5 kW 27 5881 VFD-P5 ATV61 - 5.5 kW 28 5881 VFD-P6 ATV61 - 5.5 kW 29 5881 AHU-2 ATV61 - 11 kW
30 5881 AHU-5 ALTISTART 48 ATS48D47Q
At the end of the above service, the contractor shall use the above chart in order to refer potential deficiencies or non-compliances for each equipment maintained. Any required minor or major urgent repair shall be managed in accordance with PWS paragraph 1.7.4.
Reference CDRL 0002 under exhibit 5.3 of this PWS for further direction on submission.
1.7.3 Scheduled Maintenance for UPS - nr.2 Six Months Services
The contractor shall perform nr.2 six-months services, in accordance with NFPA 110, EN 50091-1, IEC 60896-2, EN 60529 EN 62040-3, ENV 50091-3 and CEI 62040-1,2,3 or updated regulations, to inspect, clean and check the functioning and the efficiency of each UPSs installed at USAG Italy DMC. List of equipment is described in the enclosed table nr.2.
This service shall be performed only by an authorized service center, with reference to each UPS manufacturer.
Table.nr.2
NR. BUILDING NR. UPS
Electrical Panel Room 41M
GROUPS 1000A 220V
S/N 40216201310 INPUT 220/240Vac 5A Max
OUTPUT 230V 600W
2 731
POWERTRONIX
PTX 70 - 10Kva - 2004 Batteries 12Ah - 12V (Year 2010) S/N 0302191026
3 5078
SOCOMEC Model NETSYS NRT-OP-MBP INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160057 life expectancy sealed lead batteries (Year 2015)
4 5099
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160014 life expectancy sealed lead batteries (Year 2015)
5 5083
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160082 life expectancy sealed lead batteries (Year 2015)
6 5109
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160079 life expectancy7sealed lead batteries (Year 2015)
7 5112
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160063 life expectancy sealed lead batteries (Year 2015)
8 5113
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160083 life expectancy sealed lead batteries (Year 2015)
9 5671
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15160078 life expectancy sealed lead batteries (Year 2015)
10 5882
SOCOMEC NETYS NRT-OP-MBP
INPUT 200/208/220/230240Vac 50/60Hz OUTPUT 200/208/220/230240Vac 50/60HZ
MAX 63A 11000VA,8000W NUMBER OF
PHASES 1 S/N XD15210239 life expectancy sealed lead batteries (Year 2015)
11 5801
GROUPS 1000VA DL 220V
S/N 40022361506 + UBP3003621GR 36V 21Ah
12 5802
GROUPS 1000VA DL 220V
S/N 40022341506 + UBP3003621GR 36V 21Ah
13 5803
GROUPS 1000VA DL 220V
S/N 40022221506 + UBP3003621GR 36V 21Ah
14 5804
GROUPS 1000VA DL 220V
S/N 40022321506 + UBP3003621GR 36V 21Ah
15 5805
GROUPS 1000VA DL 220V
S/N 40022251506 + UBP3003621GR 36V 21Ah
16 5806
GROUPS 1000VA DL 220V
S/N 40022231506 + UBP3003621GR 36V 21Ah
17 5807
GROUPS 1000VA DL 220V
S/N 40022311506 + UBP3003621GR 36V 21Ah
18 Substation RIELLO Sentinel Pro
S/N CSEP1K51RU
IN 220-240V 1W+N+PE 6.5A
OUT 220/230/240 1W+N+PE 1500VA/1200W
(Year 2016)
NR. BUILDING NR. UPS (AFSB)
5051*
(see note below)
Schneider Electric APC Model Galaxy TM 5000 S/N 1P0L12158 40 KVA UPS with internal by-pass, 400V 3F+N 50 Hz Incoming power rectified, Neutral isolated from the chassis; n.42 batteries 50Ah - 12V, Power factor = 0.8 (Year 2010)
NR. BUILDING NR. UPS (AFN)
92*
(see note below)
SOCOMEC Mastersys MC Model
MAS2MC360T-00 S/N P198927001 60KVA
with internal bypass, 400V 3F+N 50 Hz;
Incoming power rectified, Neutral isolated from the chassis; advanced graphics display for total system control; RS232/485 serial port and RJ-45 TCP/IP/SNMP Communications Port, 10 year life expectancy sealed lead batteries with sufficient reserves to maintain full power load for 13 minutes; IGBT rectifier with n.42 batteries 50Ah - 12V (Year 2010)
At the end of each service, the Contractor shall provide a report not limited to describe the following data:
date of the service, model and serial number of the UPS checked, internal and external cleaning status, metered in-let and out-let voltage and current, status of batteries, inverters, fans, connections, static switches, display, alarms, verification of manual and automatic by-pass, etc… The contractor shall describe in addition the list of deficiencies found and suggested corrective actions needed to restore the operating status of each defected equipment.
Any required minor or major urgent repair shall be managed in accordance with PWS paragraph 1.7.4 but, only for buildings 5051* and 92*, the contractor shall provide a global maintenance service which includes any potential repairs and replacement, providing all the spare parts needed (transformers and batteries excluded).
Reference CDRL 0003 under exhibit 5.3 of this PWS for further direction on submission.
1.7.4 Maintenance and Repair Works – Scheduled & Emergency
The Government will ask the contractor to perform services for maintenance, repair, urgency repair, upgrade, renewal, replacement, substitution, code compliance or renovating for the following systems and their components in order to provide the systems with full and safe operating conditions.
This might include but will not be limited to the following systems:
- power and electrical distribution systems (from the medium voltage point of delivery, to the final customer);
- electrical, electronic and automation systems;
- electrical substations;
- Medium Voltage/Low Voltage electrical cabins;
- power and electronic distribution systems of generic buildings;
- UPS, voltage stabilizers, inverter drives, batteries, etc…
- grounding and LPS systems;
- exterior and interior lighting systems;
- electrical systems of water and sewage treatment plants;
- electrical systems of boiler plants;
- auxiliary systems of electrical plants and their components;
- any other equipment, component, circuit or plant powered by an electrical system or strictly connected with an electrical or electronic system.
For any request, the Contractor shall prepare a proposal, with hours and materials costs, that shall be submitted to the Contracting Officer (KO) and the Contracting Officer Representative (COR) for review and KO final approval.
Only after have received the KO final approval, the contractor might start to work: any activity on work site must be coordinated and scheduled with the COR.
The contractor shall perform 100% of the work under this service with its own workforce. Only the technical assistance provided by authorized service centers technicians is allowed in order to perform services on proprietary systems, services requiring direct manufacturer support or specialized labor; copy of the supplier’s invoice or quote it shall be provided to the KO and the COR.
Labor will be charged at contract rate, while the materials used shall be priced in accordance with contract clauses.
Minimum acceptable discount percentage that the Contractor shall apply to the standard price lists shall be 25%. The Contractor shall be reimbursed for the actual cost (less any available discount) of the approved material. Each quote must contain the market price for material listed in standard price lists, indicating the applied discount. In case of material not included inside standard price lists, each quote/invoice must be detailed and accompanied with copy of the quote (or the invoice) submitted by the material manufacturer or supplier.
During the annual service may happen to perform activities that need of a cherry picker: its related cost shall be charged at labor rate described on contract award.
Calls for Unscheduled and Urgent Repairs can be placed at any time required including duty hours, non-duty hours, American and Italian holidays. Calls for Unscheduled and Urgent Repairs can be placed for a malfunction or problem that poses an imminent danger to life and/or property or which impedes or prevents accomplishment of operations. During normal duty hours the COR will determine if a repair is an urgency. After normal duty hours, the contractor shall accept calls directly from the KO, COR or a designated individual. The contractor shall respond to the urgency call within twelve (12) hours. Response to these calls means the contractor will have qualified person at the repair site prepared to make necessary repairs to eliminate the imminent danger to life and/or property or to reestablish user operations. The quote for the above repair shall be provided to the KO and the COR within 48 hrs since their completing for final review, negotiation and approval. The intent of the Government is to bring the equipment to an acceptable level of maintainability and, at the same time, keep the equipment operating in a safe, efficient manner with minimum disruptions.
At the end of any working day, the contractor is responsible to provide a daily report to the COR which describes the time-in and the time-out and the activities performed.
Reference CDRL 0004 under exhibit 5.3 of this PWS for further direction on submission.
When applicable, in accordance with D.M. #37-2008, the contractor must provide the final certification, Dichiarazione di Conformità, completed of all related enclosures, stamped and signed by a registered professional/technician in accordance with Italian D.M. #37-2008 art.7.
Reference CDRL 0005 under exhibit 5.3 of this PWS for further direction on submission.
1.7.5 Safety Requirements
As per D.Lgs n.81/2008 requirements, the contractor shall provide to the COR the following documents prior to start with any maintenance activity and within 10 days from contract award:
- copy of DVR (“Documento Valutazione Rischi”, in accordance with D.Lgs n.81-2008) before starting with any work under this contract;
- C.C.I.A.A. Certificate;
- Declaration which attest the use of equipments and tools “CE” marked, included their list;
- List of DPIs provided to the workers;
- Operator’s qualifications “PES”, “PAV”, “PEI” and “Addetto ai Lavori in Quota”;
- Worker’s sanitary certifications (for any operator employed);
- DURC;
- Copy of owner’s certification about “Dichiarazione di non essere oggetto di provvedimenti di sospensione o interdittivi di cui all’art.14 del D.Lgs n.81-2008”.
Reference CDRL 0006 under exhibit 5.3 of this PWS for further direction on submission.
1.7.5 Environmental Management System
1184928201.mil Highlight
The contractor is considered as the waste generator of all salvage, re-usable, recyclable, disposable and hazardous materials delivered from the works included in this contract. All the above wastes, also special wastes, hazardous and not hazardous, they shall be delivered, by contractor expense, to the authorized disposal landfill.
The contractor shall verify and prepare the documentation related to the material to be disposed as per current Italian and US regulations, in particular with reference to the D.Lgs n.152/2006.
All materials identified as “reusable”, it shall be turned in to DRMO with their assistance/coordination (materials to be delivered to DRMO through DD Form 1348-1a).
The USAG Italy implements an EMS in accordance with EO13693, ISO 14001:2004(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. The USAG Italy EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities and authorities while supporting the USAG Italy mission. Contractors and their personnel are required to be aware of, and comply with, the USAG Italy Environmental policy and legal and other requirements when performing work at an installation.
The contractor will provide the following information semi-annually to be used by the Government to address environmental performance relative to the goals of the USAG Italy Environmental Management System. Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-December will be submitted by 15 January each year.
Media Report Element #1 Report Element #2
Non-Hazardous Solid Waste Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Construction Debris/Demolition Materials
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Compostable/Organic Material Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Hazardous Materials Total Used (Kg)
Hazardous Waste Total Generated (Kg) Total Recycled (Kg)
Energy Consumption - Electricity
Total Energy Consumed (MBtu)
Energy Consumption - Fuel Total Fuel Consumed (L)
Renewable/Alternative Energy Total Consumed (MW)
Facility Construction/Renovation
Number of Buildings LEED Certified Silver or Higher
SqFt of buildings LEED Certified
1.8. CONDUCT: The Contractor shall:
1.8.1. Wear a name tag (provided at Contractor cost) identifying her/himself as a Contractor, and ensure that in all correspondence the Contractor identifies her/himself as a Contractor in accordance with D.Leg # 81/9 April 2008, ART 20 par. 3.
1.9. PAYMENT: The Contractor will submit invoices to the COR who will certify that the services were provided and submit the invoice to the Finance Office for payment.
1.10. SAFETY: The Contractor shall be aware of local safety requirements and ensure that all reasonable efforts are made to protect all persons from harm and U.S. Government property from damage.
1.11. CONTRACTOR MANPOWER REPORTING (CMR) (CLIN 7500): The Contractor is responsible for providing input into the CMR system in accordance with the information provided herein. The Contractor is required to report all Contractor manpower required for the performance of this contract. The Contractor is required to completely fill in all the required fields in the reporting system using the following web address:
https://cmra.army.mil/. The requiring activity will assist the Contractor with the reporting requirement as necessary.
The Contractor may enter reports at any time during the reporting period, which is defined as the period of performance not to exceed 12 months ending 30 September of each Government fiscal year. Reporting must be completed no later than 31 Oct for every year or part of a year for which the contract is in place. Failure to comply with this reporting requirement will result in contract termination. Contractor shall notify the COR in writing on the last business day of October of each year with status of the CMR compliance or non-compliance via E-mail.
Reference CDRL 0007 under exhibit 5.3 of this PWS for further direction on submission.
SECTION II
SERVICE DELIVERY SUMMARY
REQUIRED SERVICE PWS
PERFORMANCE
STANDARD
SURVEILLANCE
PERFORMANCE
COMPLIANCE
REMEDIES
Respect scheduled plan for Quotes and Maintenance
Operations
1.7.4
IAW to contract standards
100% Inspection
In accordance with contract requirements
Withholding the
10% of the invoice payment
Respect the 12 hrs call for urgent/unexpected repairs
20 % withholding of the invoice amount related to requested service
Provide daily report
100% withholding of the entire daily work
Final Certification
IAW DM #37-2008
Withholding of the payment until in compliance
Quality Control Plan
4.3
CDRL
5.3
SECTION III
GOVERNMENT FURNISHED PROPERTY AND SERVICES
3.1. GENERAL INFORMATION. Reserved.
3.2. GOVERNMENT-FURNISHED PROPERTY.
3.2.1. Facilities. Reserved.
3.2.2. Equipment. Reserved.
3.2.3 Facility Keys. Reserved.
3.3.4. Equipment Inventory. Reserved.
3.3. CONTRACTOR FURNISHED PROPERTY (CFP). The Contractor shall provide her/his own transportation and all necessary equipment to fulfill this contract. Supplies not available through Government channels can be purchased by the Contractor at its expenses. The Government will not be responsible in any way for damages to the Contractor’s supplies, materials, equipment, or to personal property as a result of fire, theft, accident, natural disaster, or other events.
3.4. GOVERNMENT-FURNISHED SERVICES. The contractor will not be required to reimburse the Government for the cost of the following services. Notwithstanding the services listed below, the contractor shall perform all tasks identified in this contract.
3.4.1. Government-Furnished Utilities. Including electricity, water, sewage, and refuse collection.
3.4.2. Security Police and Fire Protection.
3.5. GOVERNMENT PROVIDED TRAINING: RESERVED.
SECTION IV
GENERAL INFORMATION
4.1. CONTRACTOR QUALIFICATIONS. The contractor shall provide qualified personnel who meet the minimum qualifying criteria at the beginning of their employment. If a changeover of personnel occurs, the contractor must ensure a replacement is hired and in place prior to the departure of the incumbent. The Contractor or sub-contractor must possess the following:
1. Copy of “Certificato Iscrizione Camera di Commercio, Industria, Agricoltura ed Artigianato” which demonstrates the qualification to execute electrical works as defined by Italian D.M.n.37-2008, letter “a” and “b”.
2. Contractor must be ISO 9001:2015 certified or SOA certified (categories OG10-OS30 class I).
3. For each work team, at least one of the workers operating must be specialized as 3º Livello Artigianato or
4º Livello Industria”.
The Contractor shall furnish all labor, equipment and supervision necessary to perform the service called by these specifications. The US Government, at no cost, will furnish electricity and water to the Contractor.
1184928201.mil Highlight
4.2. CONTRACTOR PERSONNEL.
4.2.1. The contractor shall not employ any person for work under this contract if such person is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well being or operational mission of the installation and its population. The contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest.
In the event it becomes necessary to replace any contract personnel for any of the above reasons, the contractor shall not be reimbursed for costs associated with such removal including the costs for replacement of any personnel so removed. The contractor shall inform the COR in writing within 5 working days of any incidents of misconduct by their employees that violate laws of the USA or the Host Nation.
4.2.2. The contractor shall be responsible for obtaining any necessary licenses and permits to comply with any applicable U.S. and host nation laws, codes, and regulations. The contractor shall ensure that employees have current and valid professional certifications before starting work as required in this PWS. The contractor shall ensure all employees driving on base are required to have a valid driver’s license. The contractor shall ensure that employees maintain proper personal hygiene and a neat, professional appearance while in the performance of their duties. The contractor’s employees shall be recognizable by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges, which contain the company name and employee name.
4.2.3. Reference Federal Acquisition Regulation 37.114(c). “All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials, unless, in the judgment of the agency, no harm can come from failing to identify themselves. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.”
4.3. QUALITY CONTROL PLAN.
4.3.1. The contractor shall provide a Quality Control Plan. This plan shall describe in detail the contractor’s Quality Control Program and shall be submitted no later than 10 calendar days after contract start. The plan shall become a compliance document after review and acceptance by the Contracting Officer.
Reference CDRL 0008 under exhibit 5.3 of this PWS for further direction on submission.
Quality Control will include the following as a minimum:
(a) Procedures covering key control;
(b) Procedures covering the tests certificate and its format.
4.4. QUALITY ASSURANCE.
4.4.1. The Government will evaluate the contractor’s performance under this contract according to contract clause “52.212-4 -- Contract Terms and Conditions -- Commercial Items”, the Quality Assurance Surveillance Plan and the contractors’ Quality Control Plan.
4.4.2. Inspections/Evaluations/Reviews by Other than COR. The contractor shall permit Department of Defense inspection visits, COR team visits, host base visits, other required functional reviews, evaluations or inspections as required by the Government, to include Army Head Quarters Europe, Defense Information Systems Agency, General Accounting Office or other Government agencies. The inspection teams may make unannounced visits and shall be provided unescorted access to facilities and equipment. The contractor will be given the purpose of the visit and copies of any reports created. The contractor shall take necessary actions and coordinate with the Government to resolve any discrepancies found as part of these inspections.
4.5. PHYSICAL SECURITY. The contractor shall be responsible for safeguarding and protecting all Government property provided for contractor use.
4.6. HOURS OF OPERATIONS
4.6.1. Normal Hours. The contractor shall perform the services required under this contract during the following hours: Monday through Friday, 0700 – 1800 hours.
4.6.2. Extended Service Hours. RESERVED
4.6.3. Recognized Holidays. Reference contract clause CCE 204-4000, “U.S. AND HOST NATION
HOLIDAYS”
4.7. CONSERVATION OF UTILITIES.
4.7.1. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions, which preclude all waste of utilities.
4.7.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor.
4.8. RECORDS.
4.8.1. The contractor shall be responsible for creating, maintaining, and disposing of only those Government required records that are specifically cited in this PWS or those required by the provisions of a mandatory directive listed in Technical Exhibit 5.2. Publications & Forms. If requested by the Government, the contractor shall provide the original record, or a reproducible copy of any such record within 5 working days from receipt of the request.
4.8.2. Records Management Documentation created or received by the contractor in performance of this contract are considered Government records, and the contractor shall be responsible for their maintenance.
4.8.3. Maintaining Records. Reserved.
SECTION V
TECHNICAL EXHIBITS
5.1. WORKLOAD ESTIMATES
Variation in Workload. Reserved.
5.2. PUBLICATIONS AND FORMS
5.2.1. GENERAL. Reserved.
5.2.2. PUBLICATIONS : Reserved.
5.2.3. FORMS: Reserved.
5.3. REQUIRED REPORTS
CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Scheduled Maintenance on 190 Electrical Junction Boxes
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
1.7.1
6. REQUIRING OFFICE
DPW UTILITIES DIVISION – COR
7. DD 250 REQ
NO
9. DIST STATEMENT
REQUIRED
A
10. FREQUENCY
ONCE PER YEAR
12. DATE OF FIRST SUBMISSION
N/A
14. DISTRIBUTION
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
16. REMARKS
Provide report for the maintenance of nr.190 Electrical Junction Boxes
COR 0 1 0
15. TOTAL 0 1 0
DD FORM 1423, AUG 96
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Scheduled Maintenance for Inverter Drives
1.7.2
DPW UTILITIES DIVISION - COR
ONCE A YEAR
b. COPIES
Draft Final
Provide maintenance reports at the end of the service.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Scheduled Maintenance for UPS
1.7.3
ONCE A YEAR
b. COPIES
Draft Final
Provide UPS maintenance reports at the end of the service.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Daily Report
b. COPIES
Draft Final
Provide the daily report at the end of any working day.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Certification IAW DM #37-2008
b. COPIES
Draft Final
Provide certification and related enclosures at the end of any maintenance activity.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Safety Requirements
1.7.5
b. COPIES
Draft Final
Provide documents IAW PWS requirements.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
CMR
1.11
DPW UTILITIES DIVISION - COR
Draft Final
Report must be completed no later than 31 October of any fiscal year.
The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Quality Control Plan
4.3
DPW UTILITIES DIVISION - COR
Draft Final
Quality Control Program shall be submitted no later than 10 calendar days after contract award.
(End of Summary of Changes)