03 Attachment II ELINs Price Sheet.xls
XLS spreadsheet 64 KB Posted
- Attached to
- Inspection of Railroad Facilities
- Solicitation number
- W912PB24R3003
About this file
This document is an Excel price sheet attachment for the federal contract opportunity titled "Inspection of Railroad Facilities".
The solicitation, issued by the 409th Contracting Command, 928th Contracting Battalion (CBN) / Regional Contracting Office Bavaria (RCO), is to award a commercial, single-award, requirements-type (firm-fixed-price), indefinite delivery contract for the inspection of railroad facilities at USAG Bavaria (Grafenwoehr, Vilseck), Germany. The evaluation will use low price technically acceptable factors to determine the successful offeror. The period of performance is a one-year base period with four one-year option periods. The place of performance is destination Germany.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ATTACHMENT II | ||||||
| ELIN SHEET - Base Year | ||||||
| Inspection of Railroad Facilities at USAG Bavaria | ||||||
| Base Year | ||||||
| Item | ELIN | Description | Qty/EA | Unit | Unit € | Total € |
| 0001 | A001 | Main inspection railroad bridges | 3 | Job | ||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| A002 | Subsidiary inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| A003 | Visual inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| A004 | Special inspection railroad bridges | 1 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| A005 | Main inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| A006 | Subsidiary inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| A007 | Visual inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| A008 | Special inspection railroad culverts | 1 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| A009 | Main inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| A010 | Subsidiary inspection embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| A011 | Visual inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| A012 | Special inspection railroad embankments | 1 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| A013 | Inspection railroad crossing km 0.962 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| A014 | Inspection railroad crossing km 1.725 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| A015 | Inspection non-secured railroad crossings | 16 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| A016 | Stand by service railroad crossings | 1 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| A017 | Minor repairs at secured railroad crossings | 5 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| A018 | Inspection/measurement railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| A019 | Special inspection railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| A020 | Inspection railroad signal systems | 1 | Job | |||
| according to paragraph 4.2.3.8. Attachment 1 | ||||||
| A021 | Inspection railroad loading ramps | 1 | Job | |||
| according to paragraph 4.2.3.9. Attachment 1 | ||||||
| A022 | Inspection railroad buffers | 4 | Job | |||
| according to paragraph 4.2.3.10. Attachment 1 | ||||||
| A023 | Inspection railroad switches/derailers | 3 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| A024 | Measurement railroad switches | 1 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| A025 | Inspection railroad vehicle/crane/mulcher | 1 | Job | |||
| according to paragraph 4.2.3.12. Attachment 1 | ||||||
| A026 | Training personnel at railroad vehicle | 1 | Job | |||
| according to paragraph 4.2.3.13. Attachment 1 | ||||||
| A027 | Training, safety direction personnel | 2 | Job | |||
| according to paragraph 4.2.3.14. Attachment 1 | ||||||
| A028 | Training personnel at railroad crossings | 2 | Job | |||
| according to paragraph 4.2.3.15. Attachment 1 | ||||||
| A029 | Preparation annual inspection report | 1 | Job | |||
| according to paragraph 4.2.3.16. Attachment 1 | ||||||
| Total | ||||||
| ELIN SHEET - First Option Year | ||||||
| Inspection of Railroad Facilities at USAG Bavaria | ||||||
| First Option Year | ||||||
| Item | ELIN | Description | Qty/EA | Unit | Unit € | Total € |
| 1001 | B001 | Main inspection railroad bridges | 3 | Job | ||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| B002 | Subsidiary inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| B003 | Visual inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| B004 | Special inspection railroad bridges | 1 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| B005 | Main inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| B006 | Subsidiary inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| B007 | Visual inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| B008 | Special inspection railroad culverts | 1 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| B009 | Main inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| B010 | Subsidiary inspection embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| B011 | Visual inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| B012 | Special inspection railroad embankments | 1 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| B013 | Inspection railroad crossing km 0.962 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| B014 | Inspection railroad crossing km 1.725 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| B015 | Inspection non-secured railroad crossings | 16 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| B016 | Stand by service railroad crossings | 1 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| B017 | Minor repairs at secured railroad crossings | 5 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| B018 | Inspection/measurement railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| B019 | Special inspection railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| B020 | Inspection railroad signal systems | 1 | Job | |||
| according to paragraph 4.2.3.8. Attachment 1 | ||||||
| B021 | Inspection railroad loading ramps | 1 | Job | |||
| according to paragraph 4.2.3.9. Attachment 1 | ||||||
| B022 | Inspection railroad buffers | 4 | Job | |||
| according to paragraph 4.2.3.10.Attachment 1 | ||||||
| B023 | Inspection railroad switches/derailers | 3 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| B024 | Measurement railroad switches | 1 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| B025 | Inspection railroad vehicle/crane/mulcher | 1 | Job | |||
| according to paragraph 4.2.3.12. Attachment 1 | ||||||
| B026 | Training personnel at railroad vehicle | 1 | Job | |||
| according to paragraph 4.2.3.13. Attachment 1 | ||||||
| B027 | Training, safety direction personnel | 2 | Job | |||
| according to paragraph 4.2.3.14. Attachment 1 | ||||||
| B028 | Training personnel at railroad crossings | 2 | Job | |||
| according to paragraph 4.2.3.15. Attachment 1 | ||||||
| B029 | Preparation annual inspection report | 1 | Job | |||
| according to paragraph 4.2.3.16. Attachment 1 | ||||||
| Total | ||||||
| ELIN SHEET - Second Option Year | ||||||
| Inspection of Railroad Facilities at USAG Bavaria | ||||||
| Second Option Year | ||||||
| Item | ELIN | Description | Qty/EA | Unit | Unit € | Total € |
| 2001 | C001 | Main inspection railroad bridges | 3 | Job | ||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| C002 | Subsidiary inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| C003 | Visual inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| C004 | Special inspection railroad bridges | 1 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| C005 | Main inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| C006 | Subsidiary inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| C007 | Visual inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| C008 | Special inspection railroad culverts | 1 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| C009 | Main inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| C010 | Subsidiary inspection embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| C011 | Visual inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| C012 | Special inspection railroad embankments | 1 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| C013 | Inspection railroad crossing km 0.962 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| C014 | Inspection railroad crossing km 1.725 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| C015 | Inspection non-secured railroad crossings | 16 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| C016 | Stand by service railroad crossings | 1 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| C017 | Minor repairs at secured railroad crossings | 5 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| C018 | Inspection/measurement railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| C019 | Special inspection railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| C020 | Inspection railroad signal systems | 1 | Job | |||
| according to paragraph 4.2.3.8. Attachment 1 | ||||||
| C021 | Inspection railroad loading ramps | 1 | Job | |||
| according to paragraph 4.2.3.9. Attachment 1 | ||||||
| C022 | Inspection railroad buffers | 4 | Job | |||
| according to paragraph 4.2.3.10. Attachment 1 | ||||||
| C023 | Inspection railroad switches/derailers | 3 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| C024 | Measurement railroad switches | 1 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| C025 | Inspection railroad vehicle/crane/mulcher | 1 | Job | |||
| according to paragraph 4.2.3.12. Attachment 1 | ||||||
| C026 | Training personnel at railroad vehicle | 1 | Job | |||
| according to paragraph 4.2.3.13. Attachment 1 | ||||||
| C027 | Training, safety direction personnel | 2 | Job | |||
| according to paragraph 4.2.3.14. Attachment 1 | ||||||
| C028 | Training personnel at railroad crossings | 2 | Job | |||
| according to paragraph 4.2.3.15. Attachment 1 | ||||||
| C029 | Preparation annual inspection report | 1 | Job | |||
| according to paragraph 4.2.3.16. Attachment 1 | ||||||
| Total | ||||||
| ELIN SHEET - Third Option Year | ||||||
| Inspection of Railroad Facilities at USAG Bavaria | ||||||
| Third Option Year | ||||||
| Item | ELIN | Description | Qty/EA | Unit | Unit € | Total € |
| 3001 | D001 | Main inspection railroad bridges | 3 | Job | ||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| D002 | Subsidiary inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| D003 | Visual inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| D004 | Special inspection railroad bridges | 1 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| D005 | Main inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| D006 | Subsidiary inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| D007 | Visual inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| D008 | Special inspection railroad culverts | 1 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| D009 | Main inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| D010 | Subsidiary inspection embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| D011 | Visual inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| D012 | Special inspection railroad embankments | 1 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| D013 | Inspection railroad crossing km 0.962 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| D014 | Inspection railroad crossing km 1.725 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| D015 | Inspection non-secured railroad crossings | 16 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| D016 | Stand by service railroad crossings | 1 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| D017 | Minor repairs at secured railroad crossings | 5 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| D018 | Inspection/measurement railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| D019 | Special inspection railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| D020 | Inspection railroad signal systems | 1 | Job | |||
| according to paragraph 4.2.3.8. Attachment 1 | ||||||
| D021 | Inspection railroad loading ramps | 1 | Job | |||
| according to paragraph 4.2.3.9. Attachment 1 | ||||||
| D022 | Inspection railroad buffers | 4 | Job | |||
| according to paragraph 4.2.3.10. Attachment 1 | ||||||
| D023 | Inspection railroad switches/derailers | 3 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| D024 | Measurement railroad switches | 1 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| D025 | Inspection railroad vehicle/crane/mulcher | 1 | Job | |||
| according to paragraph 4.2.3.12. Attachment 1 | ||||||
| D026 | Training personnel at railroad vehicle | 1 | Job | |||
| according to paragraph 4.2.3.13. Attachment 1 | ||||||
| D027 | Training, safety direction personnel | 2 | Job | |||
| according to paragraph 4.2.3.14. Attachment 1 | ||||||
| D028 | Training personnel at railroad crossings | 2 | Job | |||
| according to paragraph 4.2.3.15. Attachment 1 | ||||||
| D029 | Preparation annual inspection report | 1 | Job | |||
| according to paragraph 4.2.3.16. Attachment 1 | ||||||
| Total | ||||||
| ELIN SHEET - Fourth Option Year | ||||||
| Inspection of Railroad Facilities at USAG Bavaria | ||||||
| Fourth Option Year | ||||||
| Item | ELIN | Description | Qty/EA | Unit | Unit € | Total € |
| 4001 | E001 | Main inspection railroad bridges | 3 | Job | ||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| E002 | Subsidiary inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| E003 | Visual inspection railroad bridges | 3 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| E004 | Special inspection railroad bridges | 1 | Job | |||
| according to paragraph 4.2.3.1. Attachment 1 | ||||||
| E005 | Main inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| E006 | Subsidiary inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| E007 | Visual inspection railroad culverts | 30 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| E008 | Special inspection railroad culverts | 1 | Job | |||
| according to paragraph 4.2.3.2. Attachment 1 | ||||||
| E009 | Main inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| E010 | Subsidiary inspection embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| E011 | Visual inspection railroad embankments | 20 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| E012 | Special inspection railroad embankments | 1 | Job | |||
| according to paragraph 4.2.3.3. Attachment 1 | ||||||
| E013 | Inspection railroad crossing km 0.962 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| E014 | Inspection railroad crossing km 1.725 | 2 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| E015 | Inspection non-secured railroad crossings | 16 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| E016 | Stand by service railroad crossings | 1 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| E017 | Minor repairs at secured railroad crossings | 5 | Job | |||
| according to paragraph 4.2.3.5. Attachment 1 | ||||||
| E018 | Inspection/measurement railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| E019 | Special inspection railroad tracks | 1 | Job | |||
| according to paragraph 4.2.3.7. Attachment 1 | ||||||
| E020 | Inspection railroad signal systems | 1 | Job | |||
| according to paragraph 4.2.3.8. Attachment 1 | ||||||
| E021 | Inspection railroad loading ramps | 1 | Job | |||
| according to paragraph 4.2.3.9. Attachment 1 | ||||||
| E022 | Inspection railroad buffers | 4 | Job | |||
| according to paragraph 4.2.3.10. Attachment 1 | ||||||
| E023 | Inspection railroad switches/derailers | 3 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| E024 | Measurement railroad switches | 1 | Job | |||
| according to paragraph 4.2.3.11. Attachment 1 | ||||||
| E025 | Inspection railroad vehicle/crane/mulcher | 1 | Job | |||
| according to paragraph 4.2.3.12. Attachment 1 | ||||||
| E026 | Training personnel at railroad vehicle | 1 | Job | |||
| according to paragraph 4.2.3.13. Attachment 1 | ||||||
| E027 | Training, safety direction personnel | 2 | Job | |||
| according to paragraph 4.2.3.14. Attachment 1 | ||||||
| E028 | Training personnel at railroad crossings | 2 | Job | |||
| according to paragraph 4.2.3.15. Attachment 1 | ||||||
| E029 | Preparation annual inspection report | 1 | Job | |||
| according to paragraph 4.2.3.16. Attachment 1 | ||||||
| Total | ||||||
| ELIN SHEET - Total of all Years | ||||||
| Total Amount Base Year | ||||||
| Total Amount First Option Year | ||||||
| Total Amount Second Option Year | ||||||
| Total Amount Third Option Year | ||||||
| Total Amount Fourth Option Year | ||||||
| Total Amount Base + Four Option Years |