Attachment_I_Specs.docx
DOCX document 188 KB Posted
- Solicitation number
- W912PB16B8001
About this file
Attachment I - Specification 16 Dec 15
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Info_for_Offerors.doc | DOC document | |
| Amdmt_0001.pdf | ||
| Sol_b8001_0001.pdf | ||
| 02.docx | DOCX document | |
| JandA.pdf | ||
| 03.pdf | ||
| 05.xlsx | XLSX spreadsheet | |
| 01.pdf | ||
| 04.docx | DOCX document | |
| 06.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| ITEM NO | DESCRIPTION | |
| Position Nr. | Beschreibung |
ATTACHMENT # I
DEPARTMENT OF THE ARMY
UNITED STATES ARMY GARRISON BAVARIA
DIRECTORATE OF PUBLIC WORKS
UNIT 28216
APO AE 09173
| 22 May 2015 |
| Revised: 16 Dec 2015 |
S P E C I F I C A T I O N
Repair, Replace and Install Long Distance Heating Lines within USAG Bavaria, Hohenfels Military Community and Local Training Area Amberg.
L E I S T U N G S B E S C H R E I B U N G
Reparatur, Austausch und Einbau von Fernheizleitungen in der USAG Bavaria, Hohenfels Military Community und der Local Training Area Amberg.
In the event of a disagreement between the English text and the courtesy translation of this specification the English text shall govern.
Im Falle einer Unstimmigkeit zwischen dem englischen Text der Leistungsbeschreibung und der Gefälligkeitsüber-setzung ist der englische Text maßgebend.
Item No. Description Pos. Nr. Beschreibung
GENERAL DESCRIPTION
This project specifies the following work:
Repair, replacement and installation of underground remote heating lines in the Training Area of USAG Bavaria, Hohenfels Military Community and the Local Training Area (LTA) Amberg.
ALLGEMEINE BESCHREIBUNG
Dieses Projekt umfasst folgende Arbeiten:
Reparatur, Austausch und Einbau von erdverlegten Fernheizleitungen im Truppenübungsplatz der USAG Bavaria, Hohenfels Military Community und der Local Training Area (LTA) Amberg.
General Preamble
Allgemeine Vorbemerkungen
1. Regulations
Work to be performed and material to be furnished shall be in accordance with the following standards and regulations:
a. DIN standards of VOB Part C, identified below are governing:
| DIN 18 299 | General Regulations for all kinds of Construction Work | |
| DIN 18 300 | Earth Work | |
| DIN 18 303 | Sheathing Work | |
| DIN 18 307 | Underground Pressure Pipe Work Outside of Buildings | |
| DIN 18 315 | Traffic Routes Construction Work, Top Courses without Binding Agent | |
| DIN 18 316 | Traffic Routes Construction Work, Top Courses with Hydraulic Binding Agents | |
| DIN 18 317 | Traffic Routes Construction Work, Top Courses of Asphalt | |
| DIN 18 318 | Traffic Routes Construction Work, Unconnected Stone Paving and Tile Covering, | Bordering |
| DIN 18 320 | Landscape Construction Work | |
| DIN 18 330 | Masonry Work | |
| DIN 18 331 | Concrete Work | |
| DIN 18 352 | Tile and Slab Work | |
| DIN 18 353 | Floor Finishing Work | |
| DIN 18 360 | Metal Construction Work | |
| DIN 18 363 | Painting and Enameling Work | |
| DIN 18 380 | Heating and Centralized Water Heating Systems | |
| DIN 18 382 | Low and Medium Voltage Systems with Nominal Voltage up to 36 kV | |
| DIN 18 384 | Lightning Protection Systems | |
| DIN 18 386 | Building Automation | |
| DIN 18 421 | Thermal Insulation at Technical Systems | |
| DIN 18 459 | Demolition and Deconstruction |
b. Other regulations:
VDE Regulation No. 0105 Operation of power installations VDE Regulation No. 0800 Information technology - Cabling installation EN ISO 16484 Building Control Systems (BACS)
Pertinent accident prevention regulations of the employer’s liability insurance association.
Regulations for Road Construction:
| ZTV Asphalt Stb 94 | Additional Technical Contract Conditions and Guidelines for the Construction of |
| Road Covers of Asphalt |
| ZTV Beton-Stb | Additional Technical Contract Conditions and Guidelines for the Construction of | |
| Road Covers of Concrete |
| ZTV Fug 3-Stb | Additional Technical Contract Conditions and Guidelines for Joint Fillings in | |
| Traffic Surfaces; Joint fillings in Traffic Surfaces of Concrete with compressible | ||
| elastic profiles |
ZTVT-StB Additional Technical Contract Conditions and Guidelines for Base Courses in Road Construction
RG Min-Stb Guidelines for Quality Supervision of Mineral Materials for Road Construction
TL Min-Stb Technical Delivery Conditions for Mineral Materials for Road Construction
| ZTVE StB | Additional Technical Regulations and Guidelines for Earth Work for Road |
| Construction |
ZV-Stra Additional Conditions of Contract for the Execution of Construction Work on Roads
| TVT 72 | Technical Regulations and Guidelines for the Performance of Base Courses for |
| Road Construction |
TL MIN 78 Mineral Materials for Road Construction
US Regulations:
Technical design guidelines of USAG Hohenfels “Technische Planungsgrundlage zur Errichtung elektrischer Anlagen sowie Einrichtungen zur Fernüberwachung (UEMCS) in USAG Hohenfels“. Available at USAG Hohenfels / DPW / Eng Division / Design Branch, Tel. 09472-83-2525.
1. Vorschriften
Die auszuführenden Arbeiten und zu liefernden Materialen müssen den folgenden Bestimmungen und Vorschriften entsprechen:
a. DIN Bestimmungen der VOB, Teil C, wie nachfolgend aufgeführt, sind gültig:
| DIN 18 299 | Allgemeine Regelungen für Bauarbeiten jeder Art | ||
| DIN 18 300 | Erdarbeiten | ||
| DIN 18 303 | Verbauarbeiten | ||
| DIN 18 307 | Druckrohrleitungsarbeiten außerhalb von Gebäuden | ||
| DIN 18 315 | Verkehrswegebauarbeiten, Oberbauschichten ohne Bindemittel | ||
| DIN 18 316 | Verkehrswegebauarbeiten, Oberbauschichten mit hydraulischen Bindemitteln | ||
| DIN 18 317 | Verkehrswegebauarbeiten, Oberbauschichten aus Asphalt | ||
| DIN 18 318 | Verkehrswegebauarbeiten, Pflasterdecken und Plattenbeläge in ungebundener | Ausführung, Einfassungen | |
| DIN 18 320 | Landschaftsbauarbeiten | ||
| DIN 18 330 | Mauerarbeiten | ||
| DIN 18 331 | Betonarbeiten | ||
| DIN 18 352 | Fliesen- und Plattenarbeiten | ||
| DIN 18 353 | Estricharbeiten | ||
| DIN 18 360 | Metallbauarbeiten | ||
| DIN 18 363 | Maler- und Lackierarbeiten | ||
| DIN 18 380 | Heizanlagen und zentrale Wassererwärmungsanlagen | ||
| DIN 18 382 | Nieder- und Mittelspannungsanlagen mit Nennspannungen bis 36 kV | ||
| DIN 18 384 | Blitzschutzanlagen | ||
| DIN 18 386 | Gebäudeautomation | ||
| DIN 18 421 | Dämmarbeiten an Technischen Anlagen | ||
| DIN 18 459 | Abbruch- und Rückbauarbeiten |
b. Sonstige Bestimmungen:
VDE Bestimmung Nr. 0105 Betrieb von Starkstromanlagen VDE Bestimmung Nr. 0800 Informationstechnik - Installation von Kommunikationsverkabelung EN ISO 16484 Systeme der Gebäudeautomation (GA)
Einschlägigen Unfallverhütungvorschriften der Berufsgenossenschaften.
Straßenbauvorschriften:
| ZTV Asphalt Stb 94 | Zusätzliche technische Vertragsbedingungen und Richtlinien für den Bau von |
| Fahrbahndecken aus Asphalt |
| ZTV Beton-Stb | Zusätzliche technische Vertragsbedingungen und Richtlinien für den Bau von |
| Fahrbahndecken aus Beton |
| ZTV Fug 3-Stb | Zusätzliche technische Vertragsbedingungen und Richtlinien für Fugenfüllungen in |
| Verkehrsflächen; Fugenfüllungen in Verkehrsflächen aus Beton mit komprimierbaren elastischen Profilen |
ZTVT-StB Zusätzliche technische Vertragsbedingungen und Richtlinien für Tragschichten im Straßenbau
RG Min-Stb Richtlinien für Güteüberwachung von Mineralstoffen im Straßenbau
TL Min-Stb Technische Lieferbedingungen für Mineralstoffe im Straßenbau
ZTVE StB Zusätzliche technische Vorschriften und Richtlinien für Erdarbeiten im Straßenbau.
ZV-Stra Zusätzliche Vertragsbedingungen für die Ausführung von Bauleistungen auf Straßen.
TVT 72 Technische Vorschriften und Richtlinien für die Ausführung von Tragschichten im Straßenbau.
TL MIN 78 Mineralstoffe im Straßenbau.
US-Vorschriften:
Technische Planungsgrundlage der USAG Hohenfels “Technische Planungsgrundlage zur Errichtung elektrischer Anlagen sowie Einrichtungen zur Fernüberwachung (UEMCS)in USAG Hohenfels”, neueste Ausgabe. Erhältlich bei USAG Hohenfels / DPW / Eng Division / Design Branch, Tel. 09472-83-2525.
2. Disposal of Debris
a. The Sanitary Landfill Hohenfels will not accept demolition material, such as asphalt, concrete, wood, construction debris, metal, branches, rootstocks, cardboard, special waste (cleaning agents, paints etc), dismantled material (cables, pipes, installation material etc.) or soil excavation. This material becomes property of the contractor and shall be disposed of in accordance with German laws and regulations (Closed Cycle and Waste Management Act, Ordinance of Waste Wood Management, Guideline 3.4/1 of the Bavarian Water Board for tar debris, etc). If applicable, the contractor must commission a certified laboratory to analyse representative samples for classification.
b. Waste wood resulting from demolition work shall be disassembled individually and stored separate from other debris. The disposal shall be in compliance with the German Ordinance on the Management of Waste wood ("Altholzverordnung"). Waste wood shall be categorized and disposed of based on the Ordinance on the Management of Waste wood.
c. The dismantled material shall be stored in water-tight covered containers until removal or shall be disposed of at least once a week.
d. Within USAG Hohenfels there is a separate sewer system for rain water and waste water. Therefore, arising waste water s be disposed of via waste water duct in coordination with the COR.
2. Bauschuttabfuhr
a. Abbruchmaterial, wie Teeraufbruch, Beton, Holz, Bauschutt, Metall, Äste, Wurzelstöcke, Kartonagen, Sondermüll (Reiniger, Farben, etc.), ausgebaute Materialien (Kabel, Rohre, Installationsmaterialien, etc.) oder Erdaushub werden nicht an der Mülldeponie im Lager Hohenfels angenommen. Diese Materialien werden Eigentum des Auftragnehmers und sind gemäß deutschen Gesetzen und Vorschriften (Kreislaufwirtschaftgesetz, Altholzverordnung, Merkblatt 3.4/1 des Bayerischen Landesamt für Wasserwirtschaft für Teeraufbruch, etc.) zu entsorgen. Gegebenenfalls muss der Auftragnehmer ein zertifiziertes Labor beauftragen, repräsentative Proben zu untersuchen und entsprechend einzustufen.
b. Fallen im Zuge der Abbrucharbeiten Holzabfälle an, sind diese separat zurück zu bauen und von den übrigen Abfällen getrennt zur Entsorgung bereit zu stellen. Die Entsorgung ist in der Altholzverordnung geregelt. Der anfallende Holzabfall ist gemäß den Kategorien der Altholzverordung einzuteilen und zu entsorgen.
c. Bauabfälle sind bis zur Abfuhr in wasserdicht abgedeckten Containern zu lagern oder mindestens einmal pro Woche abzufahren.
d. Im Bereich des USAG Hohenfels besteht ein Trennsystem für Regenwasser und Schmutzwasser.
Anfallendes Schmutzwasser muß deshalb nach Angabe des COR über den Schmutzwasserkanal entsorgt werden.
3. Disposal of Contaminated Soil
Organoleptically conspicuous excavated soil shall be lab-examined for contamination according to the criteria of LAGA (Working Group of the Federal States on Waste). For this purpose, the contractor shall take three (3) representative mixed samples, combined from at least 5 single samples (recesses) per 500 cbm excavated soil. The installation classes shall be determined in accordance with the identified parameters of the respective classification values and the material shall be disposed of accordingly. The contractor shall coordinate with the COR the soil sampling needed for the analysis and test report.
3. Entsorgung von kontaminiertem Erdreich
Organoleptisch auffälliges, ausgehobenes Erdmaterial muß auf Kontamination gemäß LAGA-Kriterien (Länderarbeitsgemeinschaft Abfall) untersucht werden. Hierzu sind drei (3) repräsentative Mischproben, erstellt aus jeweils mindesten 5 Einzelproben (Einstichen) pro 500 cbm Aushub zu entnehmen. Nach den ermittelten Parametern der Zuordnungswerte sind die Einbauklassen festzulegen und das Material entsprechend zu entsorgen. Zur Entnahme der Proben durch den Auftragnehmer für die Erstellung der Analyse und des Testberichtes hat der Auftragnehmer mit dem COR Kontakt aufzunehmen.
4. Hazardous Waste
Hazardous waste (e. g. glue, containers of chemical products and materials) shall be disposed of at the appropriate waste disposal site in accordance with German law and regulation by the contractor. Hazardous waste shall not be stored or dumped on U. S. Army controlled property. Costs for hazardous waste disposal shall not be separately priced, unless specifically stated otherwise. A copy of the waste consignment document, accompanying papers and weight certificate shall be provided to the COR.
4. Sondermüll
Sondermüll (z. B. Kleber, Behälter von chemischen Produkten und Materialien) muß auf einem geeigneten Entsorgungsplatz nach deutschen Gesetzen und Vorschriften deponiert werden. Der Sondermüll darf vom Auftragnehmer nicht auf dem Territorium der U. S. Armee deponiert werden. Die Kosten für die Sondermüllabfuhr sind nicht gesondert aufzuführen, außer wenn dies ausdrücklich verlangt wird. Eine Kopie des Entsorgungsnachweises, Begleitschein und Wiegeschein muß dem COR ausgehändigt werden.
5. Job Site Equipment and Storage
The contractor is responsible for the safe storage of material and equipment. With the approval of the COR and at their own risk the contractor is allowed to erect a containers for personnel and construction equipment/material according to the valid German workplace ordinance. These containers must be a minimum of 25 meters away from any building occupied by 10 or more personnel. Construction materials and other equipment shall not be stored in U.S. buildings. After completion of work the contractor shall clean the storage area and bring it back to its original condition.
5. Baustelleneinrichtung und Materiallagerung
Der Auftragnehmer ist für eine sichere Lagerung der Materialien und Geräte selbst verantwortlich. Er darf mit Genehmigung des COR und auf eigene Gefahr Container fuer Personal und Baugeraete/Material gemaess der Arbeitstaettenverordnung aufstellen. Diese Container muessen mindestens 25m von allen Gebaeuden entfernt sein, in denen sich 10 oder mehr Personen aufhalten. Baumaterial und sonstige Gegenstände dürfen nicht in U.S. Gebäuden gelagert werden. Nach Beendigung der Arbeiten ist der Lagerplatz zu reinigen und wieder in den ursprünglichen Zustand zu versetzen.
6. Material to be Turned-In
a. Dismantled material becomes contractor’s property and shall be disposed of according to German laws and regulations, unless otherwise indicated in the individual items.
b. Dismantled material indicated for turn-in by this specification shall be turned-in to the Warehouse Hohenfels, Building #12 or #1286, or at the respective shops with the approval of the COR (distance from job site max 15 km). Operating hours of the Warehouse Hohenfels: Monday - Friday from 0800 - 1200 hours and from 1230 - 1600 hours. The material to be turned-in must be unloaded and stacked safely.
6. Einzulieferndes Material
a. Ausgebaute Materialien werden Eigentum des Auftragnehmers und sind nach deutschen Gesetzen und Vorschriften zu entsorgen, sofern in den einzelnen Positionen nichts gegenteiliges gefordert wird.
b. Ausgebaute Materialien, die laut Leistungsbeschreibung abzuliefern sind, müssen in das Warenhaus Hohenfels, Gebäude #12, bzw. #1286, oder bei den jeweiligen Betriebswerkstaetten mit Genehmigung des COR eingeliefert werden (Entfernung von der Baustelle max. 15 km). Öffnungszeiten im Warenhaus Hohenfels: Montag bis Freitag von 07.30 - 12.00 Uhr und von 12.30 - 16.00 Uhr. Das einzuliefernde Material ist abzuladen und sicher aufzustapeln.
7. Coordination of Switch-off Times for Medium and Low Voltage
Switch-off times shall be kept to a minimum and must be announced in writing and coordinated with the COR at least three days in advance.
7. Abschaltvereinbarungen für Mittel- und Niederspannung
Abschaltzeiten sind auf ein Minimum zu begrenzen und mindestens drei Tage vorher schriftlich beim COR anzumelden und zu koordinieren.
8. Traffic Control
The contractor shall ensure that traffic flow interruptions, due to construction work, will be kept to a minimum. No construction work shall impede traffic between 0630 and 0730 hours and between 1530 and 1630 hours. The contractor is responsible for traffic control; if necessary, traffic lights shall be used.
8. Verkehrsregelung
Der Auftragnehmer hat dafuer Sorge zu tragen, dass die Bauarbeiten den fließenden Verkehr nicht übermäßig behindern. Deshalb sind zwischen 06.30 und 07.30 Uhr und zwischen 15.30 und 16.30 Uhr Bauarbeiten, die den Verkehr behindern, zu unterbrechen. Für die Verkehrsregelung ist Sorge zu tragen, notfalls mit einer Ampelanlage.
9. Construction Performance
The contractor is responsible for locating underground electrical, heating, water and telephone lines by means of cable searching devices or similar equipment. Damage caused by the contractor shall be repaired by the contractor at their own expense.
9. Bauausführung
Der Auftragnehmer ist dafür verantwortlich, die Elektro-, Heizungs-, Wasser- und Telefonleitungen im Erdreich mittels Kabelsuchgeräten oder ähnlichem zu lokalisieren. Eventuelle Beschädigungen müssen von ihm auf seine Kosten behoben werden.
10. Water and Electrical Power Supply
a. Water and electrical power required for the execution of this project will be made available to the contractor without charge in accordance with FAR clause 52.236-14 "AVAILABILITY AND USE OF UTILITY SERVICES". Necessary connections to lines shall be made and a meter shall be provided by the contractor without additional cost to the U.S. Government.
b. The connection of job site distributions is authorized only in the presence of personnel from the Electrical Shop, Utilities Branch, DPW. Arbitrary opening of cable distributions or low-voltage switchgears is not authorized. The necessary coordination shall be made with the COR in writing.
c. Electrical systems at job sites must be controlled regularly (specifically after relocation) by a skilled electrical employee according to BGV A3 (regulation of the employer's liability insurance association). Contractor shall keep measurement reports and test certificates in the construction office and shall present those records upon demand. Electrical connections or temporary installations shall be in accordance with all VDE regulations.
d. Use of electrical heaters on job site is prohibited. If heating is necessary, other fuel sources shall be used instead and shall be coordinated with the COR in writing.
e. Provision of construction water or water required for other temporary purposes shall be arranged with the staff of the DPW Utilities Branch, Plumber Shop. The necessary coordination shall be made with the COR in writing. DIN EN 1717 defines the requirements concerning the protection of drinking water within drinking water systems as well as the general requirements for safety arrangements to prevent pollution of drinking water caused by backflow. DIN EN 1717 shall be absolutely observed.
f. The contractor shall use stand pipe meters or hydrant meters for temporary water abstraction from hydrants. This equipment must be approved by the "Deutsche Vereinigung des Gas- und Wasserfachs" DVGW. Ending of the temporary water extraction must be immediately reported to the Plumber Shop via the COR.
10. Wasser- und Baustromversorgung
a. Wasser und Baustrom, die für die Ausführung dieses Projekts nötig sind, werden dem Auftragnehmer gemäß FAR Klausel 52.236-14 "VERFÜGBARKEIT UND BENUTZUNG VON VERSORGUNGS- LEISTUNGEN" kostenlos zur Verfügung gestellt. Der Auftragnehmer muss notwendige Anschlüsse an Leitungen vornehmen und einen Zwischenzähler bereitstellen, ohne dass der U.S. Regierung zusätzliche Kosten entstehen.
b. Das Anschließen von Baustellenverteilern darf nur im Beisein von Mitarbeitern des DPW, Utilities Branch, Elektroshop erfolgen. Eigenmächtiges Öffnen von Kabelverteilern oder Niederspannungsschaltanlagen ist nicht erlaubt. Die notwendige Koordination erfolgt schriftlich über den COR.
c. Baustromanlagen sind einer regelmäßigen Prüfung nach BGV A3 (Berufsgenossenschaftliche Vorschrift) durch eine Elektrofachkraft zu unterziehen (insbesondere nach Umsetzen). Die Mess- und Prüfprotokolle sind im Baubüro zu hinterlegen und auf Verlangen vorzuzeigen. Elektrische Anschlüsse oder vorläufige Einrichtungen müssen den VDE Vorschriften entsprechen.
d. Die Verwendung von Elektroheizungen auf Baustellen ist nicht erlaubt. Wenn eine Heizung erforderlich ist, müssen andere Brennstoffe verwendet werden. Dies ist mit dem COR schriftlich zu koordinieren.
e. Der Bezug von Bauwasser oder Wasser für sonstige vorübergehende Zwecke ist mit den Mitarbeitern des DPW, Utilities Branch Plumber Shop abzusprechen. Die notwendige Koordination erfolgt schriftlich über den COR. Die DIN EN 1717 definiert die Anforderungen zum Schutz des Trinkwassers vor Verunreinigungen in Trinkwasserinstallationen und die allgemeinen Anforderungen an Sicherheitseinrichtungen zur Verhütung von Trinkwasserverunreinigungen durch Rückfließen. Die DIN EN 1717 ist dringenst einzuhalten.
f. Für die vorübergehende Wasserentnahme aus Hydranten sind Standrohrzähler oder Hydrantenzähler vom Auftragnehmer zu verwenden. Diese Einrichtungen müssen von der Deutschen Vereinigung des Gas- und Wasserfachs DVGW geprüft sein. Die Beendigung der vorübergehenden Wasserentnahme ist dem Plumber Shop über den COR umgehend zu melden.
11. Water and Electrical Power Supply (for job sites located in peripheral areas)
Water and electrical power are not available at job sites located in peripheral areas. If required, water and electrical power shall be provided by the contractor (e. g. emergency power aggregate, water containers).
11. Wasser- und Baustromversorgung (bei in Aussenbereichen liegenden Baustellen)
Wasser und Baustrom sind an den im Aussenbereich liegenden Baustellen nicht vorhanden. Falls erforderlich, muss beides vom Auftragnehmer gestellt werden. (z. B. Notstromaggregat, Wasserbehälter).
12. Welding and Cutting Work
Contractors who are responsible for welding and cutting work shall coordinate with the COR in writing the attendance of the mandatory safety briefing at the local Fire Station prior to start of work. After the briefing, a Hot Work Permit (DA Form 5383) will be issued to the welders.
12. Schweiss- und Schneidarbeiten
Auftragnehmer, die für Schweiss- und Schneidarbeiten zuständig sind, müssen mit dem COR schriftlich die Teilnahme an der obligatorischen Sicherheitsbesprechung bei der örtlichen U. S. Feuerwehr vor Beginn der Arbeiten koordinieren. Nach der Besprechung wird ein Erlaubnisschein für Schweissarbeiten (Hot Work Permit, DA Form 5383) an die Schweisser ausgegeben.
13. Behavior on Ranges and their Danger Zones
Prior to start of work, the contractor's personnel working on this project must attend a briefing concerning the behavior on ranges and their danger zones. The briefing must be attended upon coordination with the COR and will be certified in writing. Interruptions caused by training operations are to be expected.
13. Verhalten auf Schießbahnen und deren Gefahrenbereiche
Vor Baubeginn haben sich die an diesem Projekt beteiligten Personen des Auftragnehmers einer Belehrung über das Verhalten auf Schießbahnen und deren Gefahrenbereiche zu unterziehen. Die Belehrung muss nach Rücksprache mit dem COR absolviert werden und wird schriftlich bestätigt. Mit Stillstandszeiten, bedingt durch Trainingsbetrieb, ist zu rechnen.
14. Digging Work
Digging work may be performed only with approval of the COR. Therefore, a digging permit must be requested from the COR at the preconstruction conference.
14. Grabarbeiten
Grabarbeiten dürfen nur mit der Erlaubnis des COR vorgenommen werden. Aus diesem Grunde ist vom COR ein Erlaubnisschein (Digging Permit) bei der Bauvorbesprechung zu beantragen.
15. Refilling of the Heating Systems
Heating systems or parts of the systems which have been discharged may be filled only through the water treatment installed in the heating plant of E.ON Energy Corporation. The contractor shall give E.ON notice of the work. The contractor shall provide the chemicals required for the filling of the system. Prior to filling, the entire line system shall be rinsed twice very thoroughly, including cleaning of the filters and dirt traps. The COR shall be notified of the work to be performed two working days in advance. The cost of these measures must be included in the respective individual item(s).
15. Nachfüllen der Heizungsanlagen
Heizsysteme oder Teile davon, die entleert wurden, dürfen nur über die im Heizkraftwerk der E.ON Energie AG installierte Wasseraufbereitung gefüllt werden. Die Arbeiten sind bei der E.ON anzumelden. Die beim Füllen der Anlage benötigten Chemikalien gehen zu Lasten des Auftragnehmers. Vor dem Füllen ist ein gründliches zweimaliges Durchspülen des gesamten Leitungsnetzes einschließlich Säuberung der Filter und Schmutzfänger erforderlich. Die Durchführung der Leistung ist dem COR zwei Arbeitstage vorher anzuzeigen. Die Kosten für diese Maßnahmen sind in die entsprechenden einzelnen Positionen des Leistungsverzeichnisses einzurechnen.
16. Protection of trees, existing plants and planted areas at construction measures according to DIN 18 920
a. Protection of planted areas: In order to avoid damage, planted areas shall be surrounded with a fence which is at least 1.8 meter (m) high, lateral fence distance 1.5 m.
b. Protection of trees against mechanical damage:Trees within the construction site shall be protected against mechanical damage caused by vehicles, construction machines or any other construction processes by means of a fence as described in the previous paragraph "a". The fence must enclose the entire root area. Root area means the ground surface underneath the tree crown plus 1.5 m (in case of columnar trees add 5 m).
c. Soil excavation must not be performed in the root area.
d. Trenches, depressions or construction pits shall not be created in root areas. If excavation in this area is unavoidable in special cases, the excavation shall only be performed manually and only up to a distance of 2.5 m to the bottom end of the tree.
e. When excavating trenches, roots with a diameter greater than 3 cm shall not be cut. Damages to roots must be avoided and must be treated if necessary.
f. Roots shall be separated by cutting and cut surfaces shall be smoothed. Root ends with a diameter less than 2 cm shall be treated with growth-stimulating substances and root ends with a diameter greater than 2 cm with substances for wound treatment. Roots shall be protected against drying-out and frost.
16. Schutz von Bäumen, Pflanzenbeständen und Vegetationsflächen bei Baumaßnahmen nach DIN 18 920
a. Schutz von Vegetationsflächen: Zur Verhinderung von Schäden sind Vegetationsflächen mit einem mindestens 1.8 m hohen Zaun zu umgeben, seitlicher Zaunabstand 1.5 m.
b. Schutz von Bäumen gegen mechanische Schäden: Zum Schutz gegen mechanische Schäden durch Fahrzeuge, Baumaschinen und sonstige Bauvorgänge sind Bäume im Baubereich durch einen Zaun zu schützen, wie im vorhergehenden Paragraph "a" beschrieben. Der Zaun soll den gesamten Wurzelbereich umschließen. Als Wurzelbereich gilt die Bodenfläche unter der Krone von Bäumen (Kronentraufe) zuzüglich 1.5 m (bei Säulenform zuzüglich 5 m).
c. Im Wurzelbereich darf kein Boden abgetragen werden.
d. Im Wurzelbereich dürfen keine Gräben, Mulden oder Baugruben hergestellt werden. Ist dies im Einzelfall nicht zu vermeiden, darf die Herstellung nur in Handarbeit erfolgen und nicht näher als 2.5 m an den Stammfuß herangeführt werden.
e. Beim Aushub von Gräben dürfen Wurzeln mit einem Durchmesser größer als 3 cm nicht durchtrennt werden. Verletzungen sollen vermieden werden und sind gegebenenfalls zu behandeln.
f. Wurzeln sind schneidend zu durchtrennen und die Schnittstellen zu glätten. Wurzelenden mit einem Durchmesser von weniger als 2 cm sind mit wachstumsfördernden Stoffen, Wurzelenden mit einem Durchmesser größer als 2 cm mit Wundbehandlungsstoffen zu behandeln. Die Wurzeln sind gegen Austrocknung und Frosteinwirkung zu schützen.
17. Asbestos
a. If asbestos-containing materials are mentioned in the specifications / drawings, the contractor is responsible for the protection of their workers and other individuals during performance of work (in accordance with TRGS 519 (Technical rule for hazardous substances)).
b. If the contractor encounters material suspected of containing asbestos, the project manager shall immediately inform the COR. An immediate verbal notification is acceptable, however shall be communicated in writing within 2 working days. The contractor shall treat suspected material as if it contains asbestos and leave it in place until the results of the analysis are released.
17. Asbest
a. Wenn im Leistungsverzeichnis bzw. in den Zeichnungen asbesthaltige Materialien angegeben sind, so ist der Auftragnehmer verantwortlich für den Schutz der Arbeiter und anderer Personen während der Arbeitsausführung (gemäss TRGS 519 (Technische Regeln für Gefahrstoffe)).
b. Wenn der Auftragnehmer Material vorfindet, welches möglicherweise Asbest enthält, so muss der Bauleiter sofort den COR informieren. Eine sofortige mündliche Benachrichtigung ist akzeptabel. Eine schriftliche Benachrichtigung muss jedoch innerhalb 2 Arbeitstagen nachgereicht werden. Der Auftragnehmer hat dieses möglicherweise asbesthaltige Material als asbesthaltig zu betrachten und bis zum Vorliegen von Analyseergebnissen an Ort und Stelle zu belassen.
18. Spill reporting procedures for contractors working within the Training Area Hohenfels or Local Training Area (LTA) Amberg
a. Applicability: These procedures shall be followed in the event of a spill of hazardous substances caused by vehicles or equipment of contractors working within the Training Area Hohenfels or Local Training Area (LTA) Amberg.
b. Hazards for humans and environment:
- Release of hazardous substances (usually petroleum, oil and lubricant (POL products) during accidents
- Release of hazardous substances (usually POL products) caused by equipment failure
- Release of hazardous substances during transportation of hazardous substances/waste (not class 1, explosives)
c. Protective Measures and Procedures: The following requirements must be met to operate a vehicle within the Training Area Hohenfels or Local Training Area (LTA) Amberg.
| - | Valid driving license appropriate for the vehicle. |
| - Valid hazardous cargo driving license for the transportation of hazardous material / hazardous | waste |
- Follow the regulations of the Road Traffic Legislation:
· Road Traffic Law (StVG)
· Motor Vehicle Traffic Regulations (StVO)
· Federal Motor Vehicle Safety Standards (StVZO)
· European Treaty concerning the international transport of hazardous material (ADR)
- Securing of cargo according to VDI 2700 and ADR
- Provision of spill equipment (e.g. absorbent, absorbent pads etc.)
d. The following procedures shall be complied with in the event of failures or hazardous situations:
- Immediately notify the local US Fire Department, telephone 09472- 83-2117 if hazardous substances as well as hazardous waste or operational substances (Diesel, hydraulic fluid etc) are released due to failure of vehicles or construction equipment.
- In addition, notify the German Police if quantities released exceed 8 gallons (30 liters) or 110 lbs (50 kg)
- The contractor shall take immediate protective measures.
- The necessary spill clean up will be performed by the contractor or his subcontractors.
e. Emergency Procedures – First Aid:
- Secure accident site
- Inform Local Fire Department and Emergency First Responder
- Take care of injured individuals
f. Refueling, Maintenance, Disposal:
- During refueling of construction vehicles/equipment appropriate precautions need to be taken to prevent damage of the environment.
- Maintenance of vehicles and equipment is approved on paved surfaces only (concrete, asphalt).
- Disposal of hazardous operating fluids or contaminated soil caused by accidents or contractor’s vehicles/equipment must be performed by the contractor. The COR shall be provided with proof of proper disposal.
18. Verhaltensregeln für Auftragnehmer bei Freisetzung von Gefahrstoffen auf dem Truppenübungsplatz Hohenfels bzw. in der Local Training Area (LTA) Amberg
a. Anwendungsbereich: Verhalten bei Freisetzung von Gefahrstoffen während des Betriebs von Baufahrzeugen von auf dem Truppenübungsplatz Hohenfels bzw. in der Local Training Area (LTA) Amberg tätigen Auftragnehmern.
b. Gefahren für Mensch und Umwelt:
· Freisetzen von Gefahrstoffen (in der Regel Mineralöle) bei Unfällen.
· Freisetzen von Gefahrstoffen (in der Regel Mineralöle) durch defektes Gerät.
· Freisetzen von Gefahrstoffen bei Gefahrstofftransporten/Sondermülltransporten (nicht Klasse 1, Sprengstoffe).
c. Schutzmaßnahmen und Verhaltensregeln: Voraussetzung für das Fahren auf dem Truppenübungsplatz Hohenfels bzw. in der Local Training Area (LTA) Amberg:
· Gültige Fahrerlaubnis entsprechend dem Fahrzeug.
· Gültiger Gefahrgut-Führerschein beim Transport von Gefahrgut / Sondermüll.
· Einhalten der Vorschriften des Straßenverkehrsrechts:
· Straßenverkehrsgesetz (StVG).
· Straßenverkehrsverordnung (StVO).
· Straßenverkehrs-Zulassungsordnung (StVZO).
· Europäisches Abkommen zum internationalen Transport von Gefahrgütern auf Straßen (ADR).
· Ladungssicherung entsprechend VDI 2700 und ADR.
· Mitführen von geeigneten Betriebsmitteln für Sofortmaßnahmen (Bindemittel, Ölbindevlies etc).
d. Verhalten bei Störungen und im Gefahrfall:
· Bei Freisetzen von Gefahrstoffen (auch Sondermüll) oder Betriebsmitteln (Hydrauliköl, Diesel usw.) durch Defekte an Fahrzeugen bzw. Baumaschinen ist sofort die Standortfeuerwehr, Telefon (09472) 83-2117 zu verständigen.
· Bei Freisetzung von Mengen über 30 ltr bzw. 50 kg ist zusätzlich die deutsche Polizei zu verständigen.
· Der Unternehmer hat dafür zu sorgen, dass geeignete Sofortmaßnahmen getroffen werden
· Die anfallenden Reinigungsarbeiten sind vom Auftragnehmer bzw. den von ihm beauftragten Firmen durchzuführen.
e. Verhalten bei Unfällen - Erste Hilfe:
· Unfallstelle sichern.
· Ersthelfer und Standortfeuerwehr verständigen.
· Verletzte betreuen.
f. Betanken, Instandhaltung, Entsorgung:
· Beim Betanken von Baustellenfahrzeugen sind geeignete Vorsichtsmaßnahmen zu treffen, um Umweltschäden zu vermeiden.
· Instandhaltungsarbeiten an Fahrzeugen und Baumaschinen sind grundsätzlich nur auf befestigtem Untergrund (Beton, Asphalt) durchzuführen.
· Die Entsorgung von Betriebsmitteln oder von verunreinigtem Boden nach Unfällen oder von defekten Fahrzeugen/Baumaschinen ist vom Auftragnehmer selbst durchzuführen. Ein Nachweis über die ordnungsgemäße Entsorgung ist dem COR vorzulegen.
19. Security Checks
The contractor must consider stoppage and waiting times caused by several checks when entering and leaving the construction sites at US installations, as this will not be separately reimbursed.
19. Sicherheitskontrollen
Stillstands- und Wartezeiten bedingt durch mehrere Zugangskontrollen beim Betreten und Verlassen der Baustellen innerhalb von Liegenschaften der US-Armee sind vom Auftragnehmer zu berücksichtigen, da diese nicht extra bezahlt werden.
20. Anti-Terrorism/Operations Security (AT/OPSEC) Requirements
Contractors and sub-contractors shall comply with the following AT/OPSEC requirements:
a. Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
b. iWATCH / iSALUTE Training. The contractor and all associated subcontractors will brief all employees on the local iWATCH / iSALUTE program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 21 calendar days after the contract is awarded and within 21 calendar days after new employees commence contract performance, with the results reported to the COR within 21 calendar days after the contract is awarded.
20. Vorschriften zur Sicherheit und Anti-Terrormassnahmen (AT/OPSEC)
Auftragnehmer und Sub-Unternehmer sollen die folgenden AT/OPSEC Vorschriften erfüllen:
a. Vorschriften und Regelungen für den Zutritt zum Gelände und allgemeine Schutzmassnahmen. Der Vertragsnehmer und alle Subunternehmer müssen die gültigen Vorschriften und Anweisungen für den Zutritt zum Gelände und allgemeine Sicherheitsregeln befolgen (werden von einem Vertreter der US Armee ausgehändigt). Der Vertragsnehmer muß alle Unterlagen zur Durchführung einer Sicherheitsüberprüfung vorlegen, damit die Zutrittsvoraussetzungen der örtlichen Militärpolizei, der Abteilung für Katastrophenschutz sowie des Büros für Sicherheit erfüllt werden. Die Mitarbeiter der Vertragsfirma sind ausweispflichtig gemäß den Bestimmungen des U.S. Verteidigungsministeriums, des Hauptquartiers der U.S. Armee, und den Bestimmungen vor Ort. Zusätzlich zu Änderungen aufgrund der Änderungsklausel zu diesem Vertrag, kann die Regierung die Sicherheitsmassnahmen oder -vorschriften ändern, wenn sich die Sicherheitseinstufung (FPCON) eines Gebäudes oder Standorts ändert.
b. iWatch / iSalute Training. Der Vertragsnehmer und alle Subunternehmer müssen ihre Mitarbeiter über das örtliche iWATCH/iSALUTE Programm in Kenntnis setzen. Die erforderlichen Schulungsunterlagen werden vom Anti-Terrorismus-Bevollmächtigten der auftraggebenden Dienststelle zur Verfügung gestellt. Inhalt der Schulung ist es, die Mitarbeiter aufzuklären, gegenüber welchen ungewöhnlichen Umständen sie wachsam sein sollen, und welche sie an den COR melden sollen. Diese Schulung soll innerhalb eines Zeitraums von 21 Kalendertagen, nachdem der Vertrag vergeben und innerhalb 21 Kalendertagen nachdem neue Mitarbeiter die Arbeit gemäß Vertrag aufnehmen, stattfinden. Die Dokumentation darüber ist innerhalb von 21 Kalendertagen nach der Vertragsvergabe dem COR zu übergeben.
21. Working Hours
The contractor is allowed to enter the job site only between 07:30 and 16:00 hours. Additional working hours must be approved by the COR at the pre-construction conference or the contractor shall submit written request for such approval at least two working days in advance to the COR.
21. Arbeitszeiten
Der Auftragnehmer darf die Baustelle nur in der Zeit von 07:30 bis 16:00 Uhr betreten. Zusätzliche Arbeitszeiten müssen vom COR bei der Bauvorbesprechung genehmigt werden oder der Auftragnehmer muss einen schriftlichen Antrag fuer diese Genehmigung mindestens 2 Arbeitstage vorher beim COR einreichen.
22. Measurements in the specification
All dimensions (sizes, technical data, etc.) in the specification are only approximate values with a tolerance of about +/- 2 %. If exact measurements are necessary, this will be specifically indicated.
22. Maßangaben in der Leistungsbeschreibung
Alle Maßangaben (Abmessungen, technische Daten, usw.) in der Leistungsbeschreibung sind Circa-Angaben mit einer Toleranz von etwa +/- 2 %. Sollten genaue Maße erforderlich sein, so wird dies gesondert angegeben.
23. Abbreviations
| AGI | = Working Committee of Industrial Construction |
| COR | = Contracting Officer’s Representative |
| cbm | = cubic meter |
| cm | = centimeter |
| DN | = nominal diameter |
| ea | = each |
| EPDM | = Ethylene Propylene Diene Monomer |
| IAW | = in accordance with |
| kg | = kilogram |
| LED | = light emitting diode |
| ls | = lump sum |
| m | = meter |
| mm | = millimeter |
| PN | = nominal pressure |
| sqm | = square meter |
| UEMCS | = Utility energy monitoring and control system |
| (l/w/h) | = (length/width/height) |
| (h/w/d) | = (height/width/depth) |
| (h/w) | = (height/width) |
23. Abkürzungen
| AGI | = | Arbeitsgemeinschaft Industriebau | |
| cbm | = Kubikmeter | ||
| cm | = centimeter | ||
| DN | = Nenndurchmesser | ||
| EPDM | = Ethylen-Propylen-Dien-Kautschuk | ||
| kg | = Kilogramm | ||
| LED | = Leuchtdiode | ||
| m | = Meter | ||
| mm | = millimeter | ||
| MSR | = Messen-Steuern-Regeln | ||
| qm | = Quadratmete | ||
| PN | = Nenndruck | ||
| PS | = pauschal | ||
| Stck | = Stück | ||
| UEMCS | = Gebäudeautomation | ||
| (L/B/H) | = (Länge/Breite/Höhe) | ||
| (H/B/T) | = (Höhe/Breite/Tiefe) | ||
| (H/B) | = (Höhe/Breite) |
25. Table of contents of the Exhibit Line Items (ELINs)
25. Inhaltsangabe der Positionen
001 Earth Work / Erdarbeiten
002 Sewer Work / Kanalbauarbeiten
003 Walkway & Road Construction Work / Wege & Trassenbauarbeiten
004 Concrete- and Steel-Concrete Work / Beton- und Stahlbetonarbeiten
005 Screed Work / Estricharbeiten
006 Tile and slab work / Fliesen- und Plattenarbeiten
007 Metal Construction Work / Metallbauarbeiten
008 Electrical Work / Elektroarbeiten
009 Distance-Heating-Lines Work / Fernheizleitungsarbeiten
010 Valves and Components / Armaturen und Einbauteile
011 Leak Detection System / Leckageüberwachungssystem
012 Miscellaneous / Sonstiges
| Page 21 of 71 |
| Seite 21 von 71 |
26. Description of exhibit line items (ELINs)
26. Beschreibung der Positionen
| A/B/C/D/E 001 |
| Earthwork / Erdarbeiten |
| A/B/C/D/E |
| 001 |
| AA |
| Excavate top soil, thickness average approximately 20 cm and store laterally. Re-apply top soil after completion of construction and prepare final grade to edges, walkways and pavement surfaces. Sow lawn 25 g/m². |
Oberboden abheben, Stärke im Mittel ca. 20 cm und seitlich lagern. Nach Beendigung der Bauarbeiten Oberboden wieder aufbringen und Planum an Kanten, Wegen und Platzbelege herstellen. Ansäen von Spielrasen 25 g/m².
| A/B/C/D/E |
| 001 |
| AB |
| Excavate and laterally store existing bushes. After refilling of the cable trench re-plant bushes proper at the original place. The maintenance during the interim storage is included in this item. |
Vorhandenes Buschwerk ausgraben und seitlich lagern. Nach Wiederverfüllung des Grabens sind die Büsche wieder fachgerecht am Ursprungsort einzupflanzen. Die Pflege während der Zwischenlagerung ist in der Position enthalten.
| A/B/C/D/E |
| 001 |
| AC |
| Cut down of tree, remove roots, load, transport and dispose of material as debris as specified in the general preamble. |
Baum fällen, Wurzelstock beseitigen, Material laden, abfahren und entsorgen wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AD |
| Excavate trench true to profile and expose distance heating lines, excavation depth up to 1.25 m, bottom width 0.5 up to 1.0 m, soil class 3 up to 5, including additional excavationwork in the area of shafts and for work spaces at pipe connections. Store excavated material laterally. Refill trenches with excavated material and compact in layers. Dispose of unusable material as specified in the general preamble |
Rohrgraben profilgerecht ausheben und Fernwärmeleitungen freilegen, Aushubtiefe bis 1,25 m, Sohlenbreite 0,5 bis 1,0 m, Bodenklasse 3 bis 5, inklusive Mehraushub im Bereich der Schächte und für Arbeitsräume bei Rohrverbindungen. Aushub seitlich lagern. Verfüllen der Gräben mit Aushubmaterial und lagenweise verdichten. Unbrauchbares Material entsorgen, wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AE |
| Excavate trench true to profile and expose distance heating lines, excavation depth up to 1.25 m, bottom width 1.0 up to 1.5 m, soil class 3 up to 5, including additional excavation work in the area of shafts and for work spaces at pipe connections. Store excavated material laterally. Refill trenches with excavated material and compact in layers. Dispose of unusable material as specified in the general preamble. |
Rohrgraben profilgerecht ausheben und Fernwärmeleitungen freilegen, Aushubtiefe bis 1,25 m, Sohlenbreite 1,0 bis 1,5 m, Bodenklasse 3 bis 5, inklusive Mehraushub im Bereich der Schächte und für Arbeitsräume bei Rohrverbindungen. Aushub seitlich lagern. Verfüllen der Gräben mit Aushubmaterial und lagenweise verdichten. Unbrauchbares Material entsorgen, wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AF |
| Excavate trench true to profile and expose distance heating lines, excavation depth up to 2.0 m, bottom width 0.5 up to 1.0 m, soil class 3 up to 5, including additional excavation work in the area of shafts and for work spaces at pipe connections. Store excavated material laterally. Refill trenches with excavated material and compact in layers. Dispose of unusable material as specified in the general preamble. |
Rohrgraben profilgerecht ausheben und Fernwärmeleitungen freilegen, Aushubtiefe bis 2,0 m, Sohlenbreite 0,5 bis 1,0 m, Bodenklasse 3 bis 5, inklusive Mehraushub im Bereich der Schächte und für Arbeitsräume bei Rohrverbindungen. Aushub seitlich lagern. Verfüllen der Gräben mit Aushubmaterial und lagenweise verdichten. Unbrauchbares Material entsorgen, wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AG |
| Excavate trench true to profile and expose distance heating lines, excavation depth up to 2.0 m, bottom width 1.0 up to 1.5 m, soil class 3 up to 5, including additional excavation work in the area of shafts and for work spaces at pipe connections. Store excavated material laterally. Refill trenches with excavated material and compact in layers. Dispose of unusable material as specified in the general preamble. |
Rohrgraben profilgerecht ausheben und Fernwärmeleitungen freilegen, Aushubtiefe bis 2,0 m, Sohlenbreite 1,0 bis 1,5 m, Bodenklasse 3 bis 5, inklusive Mehraushub im Bereich der Schächte und für Arbeitsräume bei Rohrverbindungen. Aushub seitlich lagern. Verfüllen der Gräben mit Aushubmaterial und lagenweise verdichten. Unbrauchbares Material entsorgen, wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AH |
| Excavate trench true to profile and expose distance heating lines, excavation depth up to 3.0 m, bottom width 0.5 up to 1.0 m, soil class 3 up to 5, including additional excavation work in the area of shafts and for work spaces at pipe connections. Store excavated material laterally. Refill trenches with excavated material and compact in layers. Dispose of unusable material as specified in the general preamble. |
Rohrgraben profilgerecht ausheben und Fernwärmeleitungen freilegen, Aushubtiefe bis 3,0 m, Sohlenbreite 0,5 bis 1,0 m, Bodenklasse 3 bis 5, inklusive Mehraushub im Bereich der Schächte und für Arbeitsräume bei Rohrverbindungen. Aushub seitlich lagern. Verfüllen der Gräben mit Aushubmaterial und lagenweise verdichten. Unbrauchbares Material entsorgen, wie in den allgemeinen Vorbemerkungen beschrieben.
| A/B/C/D/E |
| 001 |
| AJ |
| Addition to items A/B/C/D/E001AD to A/B/C/D/E001AH for exposing of distance heating lines, however in soil class 7 |
Zuschlag zu Positionen A/B/C/D/E001AD bis A/B/C/D/E001AH, zum Freilegen von Fernwärmeleitungen jedoch in Bodenklasse 7.
| A/B/C/D/E |
| 001 |
| AK |
| Addition to items A/B/C/D/E001AD to A/B/C/D/E001AH for exposing distance heating lines by manual excavation. The manual excavation up to a distance of 1m to the building exterior edge is included when exposing building connections. |
Zuschlag zu den Positionen A/B/C/D/E001AD bis A/B/C/D/E001AH für Handschachtung zum Freilegen von Fernwärmeleitungen. Bei Freilegung von Gebäudeanschlüssen wird Handschachtung bis zum Abstand von 1 m ab Gebäudeaussenkante vergütet.
| A/B/C/D/E |
| 001 |
| AL |
| Construct and remove trench shoring with panels DIN 4124, for trenches, height up to 3.0 m and bottom width up to 1.5 m. |
Verbau mit Verbauplatten DIN 4124, für Gräben, Höhe bis 3,0 m und Sohlenbreite bis 1,5 m herstellen und wieder rückbauen.
| A/B/C/D/E |
| 001 |
| AM |
| Deliver and install according to pipe manufacturer’s instructions gravel-sand mixture, compacted in layers for embedding distance heating pipes up to DN 200 in trenches. Gravel size 0-4 mm, layer thickness up to 50 cm. |
Kies-Sand Gemisch zur Einbettung von Fernwärmeleitungen bis DN 200 in Gräben liefern, nach Angaben des Rohrherstellers einbauen und lagenweise verdichten. Körnung 0-4 mm, Schichtdicke bis zu 50 cm.
| A/B/C/D/E |
| 001 |
| AN |
| Deliver and install compactable filling material, stone-free, gravel size 0-6 mm and compact in layers. Dispose unusable backfill material in accordance with the general preamble. |
Auffüllmaterial, verdichtungsfähig, steinfrei, Körnung 0-6 mm liefern, einbauen und lagenweise verdichten. Unbrauchbares Auffüllmaterial ist gemaess den allgemeinen Vorbemerkungen zu entsorgen.
| A/B/C/D/E |
| 001 |
| AP |
| Deliver and install cable warning tape 40 cm above pipe crown. Inscription: „ACHTUNG-FERNHEIZLEITUNG“. (Warning – Distance Heating Line) |
Trassenwarnband liefern und 40 cm über Rohrscheitel verlegen. Aufschrift: "ACHTUNG-FERNHEIZLEITUNG".
| A/B/C/D/E 002 |
| Sewer Work / Kanalbauarbeiten |
| A/B/C/D/E |
| 002 |
| AA |
| Dismantle vitrified clay fitting such as bends of all angular degrees, T-branches and connector joints up to a length of 250 mm, DN 100 - 125, including rubber sealings, which are cleared from backfill material such as sand, gravel, crushed stones and soil, including protection of end vitrified clay connector against damage and if applicable safeguarding of the incoming sleeveless SML-cast iron pipe DN 100. |
Q: is clearing to be performed under this item?
Steinzeugformstück wie Bögen aller Winkelgrade, T-Abzweig und Gelenkstück bis L 250 mm, DN 100 - 125, einschlieslich Gummidichtungen, freigelegt von Auffüllmaterial, wie Sand, Kies, Schotter, Erdreich, einschliesslich Schutz der Anfangssteinzeugmuffe vor Beschädigung und ggf. Sicherung des einlaufenden muffelosen SML-Gussrohrs DN 100, demontieren.
| A/B/C/D/E |
| 002 |
| AB |
| Dispose of vitrified clay fitting such as bends of all angular degrees, T-branch and connector joint up to L 250 mm, DN 100 / 125, inclusive rubber sealing in accordance with the general preamble. |
Steinzeugformstück wie Boegen aller Winkelgrade, T-Abzweig und Gelenkstück bis L 250 mm, DN 100 / 125, einschl. Gummidichtungen gemaess den allgemeinen Vormerkungen entsorgen.
| A/B/C/D/E |
| 002 |
| AC |
| Deliver and install rubber equalizing ring for the connection of KG-pipe at vitrified clay sleeve pipe DN 100. |
Gummi-Ausgleichsring zum Anschluss von KG-Rohr an Muffensteinzeugrohr DN 100, liefern und montieren.
| A/B/C/D/E |
| 002 |
| AD |
| Deliver and install KG-transition piece, from PVC pipe to vitrified clay pipe sleeve, with sealing ring, DN 100 / 100. |
KG-Übergangsstück von PVC-Rohr auf Steinzeugrohrmuffe, mit Dichtungsring, DN 100 / 100, liefern und montieren.
| A/B/C/D/E |
| 002 |
| AE |
| Deliver and install KG-pipe,(including wall-thickened sleeve, including sealing and/or flanging ring, DN 100, L 500 mm. |
KG-Rohr mit wandverdickten Muffe, inclusive Dichtungs- bzw. Sickenring, DN 100, L 500 mm, liefern und montieren.
| A/B/C/D/E |
| 002 |
| AF |
| Deliver and install KG-bend including sealing and/or flanging ring, DN 100, 15 - 67°. |
KG-Bogen inclusive Dichtungs- bzw. Sickenring, DN 100, 15 - 67°, liefern und montieren.
| A/B/C/D/E |
| 002 |
| AG |