About this file
Request for Proposals
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_-_IDIQ_Finishing_work.pdf | ||
| Priced_ELINs_Schedule.pdf | ||
| W912PA19D0004.pdf | ||
| SOW_-_IDIQ_Finishing_work_(10_May_19).doc | DOC document | |
| IDIQ_Finishing_works-ELIN_schedule.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011279859
PROJECT: Finishing Works (repair interior and exterior painting, f loor and w all covering, false ceiling and partitions) throughout Belgium.
MAGNITUDE: Estimated betw een $ 1,500,000.00 and $ 5,000.000.00 for one (1) Base Period of 9 months and three (3) Option Years.
INSTRUCTION TO OFFERORS: Offerors shall submit the documentation requested in Section L, Instructions to Offerors, as w ell as complete the Representations and Certif ications (Reps & Certs) in Section K. Section K shall be completed and returned in its entirety.
SITE VISIT: An organized site visit has been scheduled for Friday 05 July 2019 at 10.00 hrs.
Participants w ill meet at Gate 14, Chievres Air Base, 7950 CHIEVRES (Belgium)
Point of Contact: Christophe POTTIEZ Phone: +32 68 27 56 83 Email: christophe.pottiez.ln@mail.mil
MINIMUM GUARANTEE: $ 1,000.00
GENEVIEVE PEIFFER +3227179613
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
21-Jun-2019
(RFP)
(IFB)
X
CALL:
Finishing Works throughout Belgium
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53 236 1( )
11. The Contractor shall begin performance w ithin _______5 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________08 Aug 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
RCO BENELUX
LEUVENSESTEENWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
W912PA
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
R-CH-O2D-18399-18
8. ADDRESS OFFER TO (If Other Than Item 7)
00-32-2-7179610FAX:TEL: TEL: FAX:
W912PA19R0002 61
20B. SIGNATURE
(REV 4 85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540 01 155 3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 60 Job Finishing Work throughout Belgium
FFP
in accordance with the enclosed specifications and ELINs schedule.
The project consists in the interior and exterior repainting, and/or replacement of floor coverings (vinyl), and/or replacement of wall papers, and/or repair of false ceilings, and/or construction of partitions.
BASE PERIOD: 01 September 2019 through 31 May 2020 FOB: Destination
PURCHASE REQUEST NUMBER: 0011279859
PSC CD: Z1JZ
MAX
NET AMT
UNIT UNIT PRICE MAX AMOUNT
1001 60 Job OPTION Finishing Work throughout Belgium
FFP
in accordance with the enclosed specifications and ELINs schedule.
The project consists in the interior and exterior repainting, and/or replacement of floor coverings (vinyl), and/or replacement of wall papers, and/or repair of false ceilings, and/or construction of partitions.
FIRST OPTION YEAR: 01 June 2020 through 31 May 2021 FOB: Destination
UNIT UNIT PRICE MAX AMOUNT
2001 60 Job OPTION Finishing Work throughout Belgium
FFP
in accordance with the enclosed specifications and ELINs schedule.
The project consists in the interior and exterior repainting, and/or replacement of floor coverings (vinyl), and/or replacement of wall papers, and/or repair of false ceilings, and/or construction of partitions.
SECOND OPTION YEAR: 01 June 2021 through 31 May 2022
UNIT UNIT PRICE MAX AMOUNT
3001 60 Job OPTION Finishing Work throughout Belgium
FFP
in accordance with the enclosed specifications and ELINs schedule.
The project consists in the interior and exterior repainting, and/or replacement of floor coverings (vinyl), and/or replacement of wall papers, and/or repair of false ceilings, and/or construction of partitions.
THIRD OPTION YEAR: 01 June 2022 through 31 May 2023
CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE
The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$1,000.00 $5,000,000.00
DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE
The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
$1,000.00 $500,000.00
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
ELINS SCHEDULE
See Attachment 2: ELINs Schedule
Section C - Descriptions and Specifications
STATEMENT OF WORK (SOW)
See Attachment 1: Statement of Work (SOW)
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 1001 Destination Government Destination Government 2001 Destination Government Destination Government 3001 Destination Government Destination Government
CLAUSES INCORPORATED BY FULL TEXT
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(End of clause)
CONVENTIONAL FORCES EUROPE
CONVENTIONAL FORCES EUROPE (CFE) TREATY VERIFICATION INSPECTION
Contractor-owned or controlled structures and containers located on U.S. Government installations are subject to short-notice inspections by CFE treaty inspection teams. The Government will endeavor to provide the Contractor as much notice as possible in the event of such inspections. The contractor shall provide access to such structures and containers at the request of the Government. The Contractor shall report such inspections to the Contracting Officer in writing within ten (10) calendar days of completion of the inspection. Contractor-owned or controlled structures and/or containers on U.S. installations may have to be inspected to comply with the CFE treaty even if Contractor personnel are unavailable to provide access. Any costs borne by the Contractor or any impact on contract performance as a result of the inspection will be a matter of negotiation between the Contractor and the Contracting Officer.
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN PERIOD OF
PERFORMANCE
QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-SEP-2019 TO
31-MAY-2020
N/A US MILITARY FORCES - USAG BENELUX
- DPW
GRAND RUE 56
7950 CHIEVRES
BELGIUM
WK3E47
1001 POP 01-JUN-2020 TO
31-MAY-2021
N/A (SAME AS PREVIOUS LOCATION)
2001 POP 01-JUN-2021 TO
31-MAY-2022
N/A (SAME AS PREVIOUS LOCATION)
3001 POP 01-JUN-2022 TO
31-MAY-2023
N/A (SAME AS PREVIOUS LOCATION)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within five (5) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the date established in the Notice to Proceed for each Task Order issued. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of € 437.95 per day for the first calendar day of delay and € 397.52 for each calendar day of delay thereafter until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.
However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
252.216-7006 ORDERING (MAY 2011)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule. Such orders may be issued at any time within the effective period of the contract.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c)(1) If issued electronically, the order is considered ``issued'' when a copy has been posted to the Electronic Document Access system, and notice has been sent to the Contractor.
(2) If mailed or transmitted by facsimile, a delivery order or task order is considered ``issued'' when the Government deposits the order in the mail or transmits by facsimile. Mailing includes transmittal by U.S. mail or private delivery services.
(3) Orders may be issued orally only if authorized in the schedule.
(4) Orders will be decentralized and issued by duly appointed Ordering Officers within their authorized limit.
(End of Clause)
NOTICE TO PROCEED
The Notice to Proceed will be provided as indicated below:
[ ] The effective date of the contract will constitute the date of Notice to Proceed.
[X] A Notice to Proceed will be executed for each Delivery/Task Order issued.
[ ] The date of the letter transmitting the contract will constitute the date of the Notice to
Proceed.
Section G - Contract Administration Data
SAM / WAWF
SYSTEM FOR AWARD MANAGEMENT (SAM)
Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of this solicitation.
See Section L – Instructions, Conditions and Notices to Bidders
WIDE AREA WORKFLOW (WAWF) SYSTEM
Payment for this acquisition will be made through the Wide Area Workflow (WAWF) system. Contractors shall be registered in WAWF. See web site https://wawf.eb.mil for registration. Additional WAWF information is included in FAR Clauses 252.232-7003 & 252.232-7006
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(DEC 2018)
(a) Definitions. As used in this clause--
Contract financing payment means an authorized Government disbursement of monies to a contractor prior to acceptance of supplies or services by the Government.
(1) Contract financing payments include--
(i) Advance payments;
(ii) Performance-based payments;
(iii) Commercial advance and interim payments;
(iv) Progress payments based on cost under the clause at Federal Acquisition Regulation (FAR) 52.232-16, Progress Payments;
(v) Progress payments based on a percentage or stage of completion (see FAR 32.102(e)), except those made under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, or the clause at FAR 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts; and
(vi) Interim payments under a cost reimbursement contract, except for a cost reimbursement contract for services when Alternate I of the clause at FAR 52.232-25, Prompt Payment, is used.
(2) Contract financing payments do not include--
(i) Invoice payments;
(ii) Payments for partial deliveries; or
(iii) Lease and rental payments.
Electronic form means any automated system that transmits information electronically from the initiating system to affected systems.
Invoice payment means a Government disbursement of monies to a contractor under a contract or other authorization for supplies or services accepted by the Government.
(1) Invoice payments include--
(i) Payments for partial deliveries that have been accepted by the Government;
(ii) Final cost or fee payments where amounts owed have been settled between the Government and the contractor;
(iii) For purposes of subpart 32.9 only, all payments made under the clause at 52.232-5, Payments Under Fixed- Price Construction Contracts, and the clause at 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts; and
(iv) Interim payments under a cost-reimbursement contract for services when Alternate I of the clause at 52.232-25, Prompt Payment, is used.
(2) Invoice payments do not include contract financing payments.
Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract or task or delivery order.
Receiving report means the data prepared in the manner and to the extent required by Appendix F, Material Inspection and Receiving Report, of the Defense Federal Acquisition Regulation Supplement.
(b) Except as provided in paragraph (d) of this clause, the Contractor shall submit payment requests and receiving reports in electronic form using Wide Area WorkFlow (WAWF). The Contractor shall prepare and furnish to the Government a receiving report at the time of each delivery of supplies or services under this contract or task or delivery order.
(c) Submit payment requests and receiving reports to WAWF in one of the following electronic formats:
(1) Electronic Data Interchange.
(2) Secure File Transfer Protocol.
(3) Direct input through the WAWF website.
(d) The Contractor may submit a payment request and receiving report using methods other than WAWF only when-
(1) The Contractor has requested permission in writing to do so, and the Contracting Officer has provided instructions for a temporary alternative method of submission of payment requests and receiving reports in the contract administration data section of this contract or task or delivery order;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment on a contract or task or delivery order for rendered health care services using the TRICARE Encounter Data System; or
(4) The Governmentwide commercial purchase card is used as the method of payment, in which case submission of only the receiving report in WAWF is required.
(e) Information regarding WAWF is available at https://wawf.eb.mil/.
(f) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
Construction Invoice https://wawf.eb.mil/ https://www.sam.gov/
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
Not Applicable
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC W56FJX Issue By DoDAAC W912PA Admin DoDAAC** W912PA Inspect By DoDAAC WK3E47 Ship To Code WK3E47 Ship From Code N/A Mark For Code N/A Service Approver (DoDAAC) WK3E47 Service Acceptor (DoDAAC) WK3E47 Accept at Other DoDAAC WK3E47 LPO DoDAAC N/A DCAA Auditor DoDAAC N/A Other DoDAAC(s) N/A
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
Acceptor: Jean-Luc DUVIVIER, jeanluc.duvivier.ln@mail.mil Contract Specialist: Genevieve PEIFFER, genevieve.m.peiffer.ln@mail.mil mailto:jeanluc.duvivier.ln@mail.mil mailto:genevieve.m.peiffer.ln@mail.mil
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
Marie-Dominique COURTOIS, mariedominique.courtois1.ln@mail.mil
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
mailto:mariedominique.courtois1.ln@mail.mil
Section H - Special Contract Requirements
5152.225-4001 INSTALLATION CLEARANCE RERQUIREMENTS (May 2017)
(a) Access to U.S. installations and controlled areas is limited to personnel who meet security criteria and are authorized by Host Nation law to work in that country. Failure to submit required information/data and obtain required documentation or clearances in accordance with AE Regulation 190-16, Installation Access Control, will be grounds for denying access to U.S. installations and controlled areas. The Contractor is responsible to ensure that any Subcontractor used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any Subcontractor utilized by the contractor, are made aware of and comply with these requirements.
(b) The Contractor is responsible for being aware of and complying with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control (IAC) processing requirements.
(c) The Contractor is responsible for returning installation passes to the issuing Installation Access Control Office (IACO) when the contract is completed or when a contractor employee no longer requires access.
(d) AE Regulation 190-16 (and AE Regulation 190-16-G German translation) can be found on the following websites:
http://www.409csb.army.mil/library/AER-190-16.pdf and http://www.409csb.army.mil/Library/AER-190-16-G.pdf.
(e) Below is the responsible Organizational Sponsor & Installation Access Control Office for this contract:
Organizational Sponsor: Jean-Luc DUVIVIER Location: USAG Benelux – DPW Building No: Hangar # 6 – Chievres Air Base DSN Phone No: 361 - 5644 Commercial Phone No: 068 / 27 56 44 Installation Access Control Office:
Location: USAG Benelux – PMO Building No: 134 DSN Phone No: 361 - 5433 Commercial Phone No: 068 / 27 54 33
SPECIAL INSTRUCTIONS
TRANSLATION
Drawings, specifications, instructions, or other documents furnished to the Contractor by the Government in connection with the performance of the work shall be in the English language only. Such translations thereof as are necessary or proper for the performance of the work shall be provided by the Contractor. Errors or omissions in such translations from the Government furnished drawings, specifications, instructions or other documents shall be the responsibility of the Contractor. The English text shall apply in the event of disagreements occasioned by differences between the text and the Contractor’s translation of drawings, specifications, instructions or other documents furnished by the Government pursuant to the provisions of the contract. All correspondence, drawings, and other documents submitted by the Contractor shall be entirely in English, except as otherwise provided in the contract.
LIABILITY
For the purpose of this contract the Contractor is considered as an independent Contractor and not as an agent of the US Government. During the performance the Contractor shall be liable and will indemnify and hold harmless the Government, its agents and employees against any actions or claims for all damages to persons or property, including death arising or resulting from fault, negligence, wrongful act or wrongful omission of the Contractor.
http://www.409csb.army.mil/library/AER-190-16.pdf http://www.409csb.army.mil/Library/AER-190-16-G.pdf
SAFETY AND CONTRACTOR LIABILITY AT WORK SITE
(a) Fire protection and Prevention. The contractor shall comply with the fire protection and prevention regulation and fire defense plan prescribed for buildings in which work is to be performed. A copy of the regulation and plan is on file with the Contracting Officer or his representative.
NOTE: Under no circumstances shall contractor store flammable material within Government buildings.
(b) Lost Articles. Except when loss arises out of causes beyond the control of the contractor, the contractor is absolutely liable for any loss to Government property. This excludes Government buildings, equipment, and vegetation covered under FAR clause 52.237-2 entitled “Protection of Government Buildings, Equipment, and Vegetation” (see section I). The contractor is also absolutely liable for any lost, damaged or missing personal property except when loss or damage arises out of causes beyond the control of the contractor. The Contracting Officer, upon receipt of a claim for missing Government property or personal property missing, damaged or destroyed may deduct the amount of the claim using a depreciated value as determined by Army Regulation (AR 735-11), or related claims procedures, from any invoice under this contract. Personal property is defined as property owned or leased by U.S. Government employees for their own personal use located in the same Quarters building where the contractor is cleaning pursuant to this contract. All lost or misplaced articles found by his employees shall be turned in to the Contracting Officer or the COR.
(c) Building Security. Contractor personnel shall assure that all equipment is stored in designated storage areas together with supplies upon completion of work in accordance with applicable U.S. Government security procedures (see section H, “Pre-Performance Conference”). When buildings are unoccupied, lights, water outlets and blowers shall be turned off and windows closed and locked on a floor-to-floor basis as work progresses, followed by locking of all exterior doors upon completion of work. The contractor shall be responsible for any losses or damages arising from his failure to secure buildings during and after working hours. The contractor will be required to sign for keys in accordance with applicable U.S. Government procedures. The contractor shall remain liable for replacement of lost U.S. Government keys or for replacement of locks except where such loss articles out of causes beyond the control of the contractor.
ACCESS OF CONTRACTOR’S PERSONNEL TO COMMISSARY AND PX
The Contractor’s personnel can have access during the duration of the contract to the Army and Air Force Exchange Service (AAFES) food court or food van. Contractor’s personnel are not entitled to commissary and PX privileges and will not attempt to obtain, in any way, duty-free merchandise. A violation of this restriction will result in immediate removal of the personnel involved.
ENVIRONMENT LAWS.
All materials should meet regional, provincial, national and local ecology laws in respect to all materials and their disposal. Contractor will be insured against and solely responsible for any ecological damage caused both to US and Host Nation interested parties. Furthermore, the Contractor agrees to hold the US Government harmless in any lawsuit concerning ecological damages.
WEATHER DELAYS
Reference paragraph (b) (1), FAR 52.249-10 Clause “DEFAULT (FIXED PRICE CONSTRUCTION) (APR 1984)”.
Unless unusually severe (seasonal) weather conditions prevails, no extension will be granted for delays experienced by the Contractor. A log book shall be kept by the Contractor to record weather conditions, and any eventual inclemency’s which may preclude the continuation of work in accordance with the requirements of tender document “Marchés Publics – 1978, chapter I, Item 28” (for BELGIUM) or “ABB 1968” (for THE NETHERLANDS). This log book shall be presented as a summary of the work performed, the weather conditions and the report on personnel attendance on the work site. It shall serve as a base for determining the final completion date of the works.
PERFORMANCE STANDARDS
(i) In the event of conflict between the applicable standards and any requirement or condition of the specifications and the contract, the specifications and the contract shall govern.
(ii) Copies of the applicable Belgian standards and regulations will not be furnished with the specifications. US
Army, Government specifications, regulations and other publications made part of this contract by reference herein are available for reading at the local facilities engineering office located at :
USAG BENELUX
Directorate of Public Works Hangar # 6, Chievres Air Base B - 7950 Chievres Belgium
MEASUREMENTS AND QUANTITIES
Unless stated otherwise, all quantities and measurements listed in the specifications, drawings, and price breakdown are estimates only. The offeror themselves shall familiarize with the job site, determine the extent, nature and scope of work as appropriate.
QUALITY CONTROL PROGRAM
The contractor shall establish and maintain a complete quality control program to assure the requirements. THE
CONTRACTOR’S QUALITY CONTROL PROGRAM SHALL BE SUBMITTED TO THE CONTRACTING
OFFICER WITHIN FIVE (5) DAYS AFTER AWARD and thereafter as changes occur. In addition to requirements in the specification or statements of work, the Contractor’s quality control plan must have as a minimum:
(i) Identification and clearly defined authority of key personnel under the Contractor’s organization.
(ii) A quality control inspection system covering general and specific tasks included in the contract scope of work. It should specify tasks or areas to be inspected on either a scheduled or unscheduled basis, and the manner in which inspections are to be conducted.
(iii) The names of firms or individuals tasked to perform inspections and the extent of their authority. This may be in the form of an organization chart or other form approved by the Contracting Officer.
(iv) Proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests must be specified.
(v) A method of identifying deficiencies in the quality of services or construction performed before the level of performance becomes unacceptable.
(vi) A method of documenting and enforcing quality control operations of prime or subcontractor work, including inspection and testing.
(vii) Key control, internal control, or security procedures, if applicable.
(viii) Any winterization plans and procedures for outdoor and exposed contractor and Government furnished equipment, if applicable.
(ix) A method of identifying deficiencies in the quality of manufacturing, services, or construction performed before the level of performance becomes unacceptable.
(x) Detailed information specifying the types of action the contractor will take to correct deficiencies and prevent their recurrence.
(xi) Detailed information on the inspection methods used and proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests must be specified.
CONTRACTOR RESPONSIBILITY (CONSTRUCTION)
(i) Contractor Supervision. Pursuant to FAR 52.236-6 Clause “SUPERINTENDENCE BY THE
CONTRACTOR (APRIL 1984)”, contractor shall supervise his/her employees to ensure compliance with contract standards. Contractor or his/her representative shall be present at all times during work performance at contract site.
(ii) Host Nation Safety Requirements. In addition to the safety requirements set forth in FAR 52.236-13
Clause “ACCIDENT PREVENTION (APRIL 1984)”, Contractor shall comply with Host Nation Safety Regulations. In case of conflict between Host Nation and US Standards, the more stringent standards shall govern.
(iii) Fire Protection and Prevention. The Contractor shall comply with fire protection and prevention regulation and fire defense plan prescribed for buildings in which work is to be performed. A copy of the regulation and plan is on file with the Contracting Officer or Contracting Officer Representative (COR).
NOTE: UNDER NO CIRCUMSTANCES SHALL CONTRACTOR STORE FLAMMABLE MATERIAL
WITHIN GOVERNMENT BUILDINGS.
(iv) Lost Articles. Contractor shall be responsible in the event of theft by his personnel of Government property or personal property of Government personnel, civilian or military. All lost or misplaced articles found by his/her employees shall be turned in to the COR.
(v) Protective Measures. In addition to FAR 52.236-9 “PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APRIL 1984)”, Contractor shall provide barricades and precaution signs in both English and the Host Nation language for the safety of inhabitants and passers-by. Contractor shall be responsible for removal of furnishings and equipment as required for preparation of work sites as well as for reinstallation thereof. Contractor shall replace any furnishings and equipment at their original locations upon completion of contract work.
(vi) Building Security. Contractor employees shall assure that all equipment is de-energized and stored in designated storage areas together with supplies upon completion of work. When buildings are unoccupied
– lights, water outlets, and blowers shall be turned off and windows closed and locked on a floor-to-floor basis as work progresses, followed by locking of all exterior doors upon completion of work. Keys to buildings shall be deposited with the COR. Contractor shall be responsible for any losses or damages arising from failure to secure buildings during and after working hours by his/her personnel.
(vii) Clean Up. In accordance with Contract Clause FAR 52.236-12 “CLEANING UP (APRIL 1984)”, Contractor shall be responsible for cleaning up. Accumulated dirt and debris shall be hauled off, and disposed of in accordance with Host Nation Law, at least once a week by the Contractor. Stairwells used by the Contractor during execution of work shall be cleaned daily. Cloths, mops, and brushes containing combustible materials shall be disposed of or stored outside of the buildings in tight, covered, metal containers. Paints and thinners shall not be poured into inlets of the interior or exterior sewage system.
Paints, stains, and other residues on adjacent surfaces or fixtures caused by the Contractor shall be carefully removed and cleaned to original finish. Upon completion of the work, the Contractor shall remove all construction equipment, materials, and debris resulting from contract work. The entire work site and the area used by the Contractor personnel shall be left clean.
Turn-in Salvage Material. The Contractor shall be responsible for salvage. All dismantled materials indicated for turn-in by the specification or as directed by the COR shall be enumerated in a roster prepared by the Contractor and turned in to Government disposal office/yard selected by COR. Contractor shall obtain a hand receipt for the materials turned in and attach the hand receipt to his final invoice. Turn-in times shall be as directed by the COR.
PERMISSION TO EXCAVATE
(i) Contractor shall locate required excavation site and prior to excavation obtain COR's written permission to excavate.
(ii) COR will inform Contractor how to obtain and when to release permission for excavation.
(iii) The written permission to excavate will include the location of all known utility and communications lines not identified in the specifications/drawings and all physical data not covered in the specifications /drawings necessary to minimize utility and communication line outages.
In case Government representatives delay release permission of excavation or instruct Contractor to perform work not covered by contract, Contractor shall, immediately, in writing, inform the Contracting Officer.
GOVERNMENT-FURNISHED UTILITIES
(i) Utilities. Where reasonably available, water and electrical power required for the execution of this project will be made available to the Contractor without charge, in accordance with the contract clause “AVAILABILITY AND USE OF UTILITY SERVICES (APRIL 1984), FAR 52.236-14. Necessary connections to lines shall be made by the Contractor without additional cost to the Government. Electrical connections or temporary installations shall be made in accordance with VDE 0100. If not reasonably available on-site from existing outlets and supplies, the contractor is responsible for providing its own utilities. No other material, equipment, or services shall be furnished by the Government unless expressly stated elsewhere herein.
(ii) Telephones. Telephone facilities shall be made available without charge at a location designated by the
Contracting Officer to make calls within the military reservation areas only. Use of telephones in family quarters by the Contractor or his/her employees or Sub-Contractors is strictly prohibited.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.222-50 Alt I Combating Trafficking in Persons (JAN 2019) Alternate I MAR 2015 52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-25 Prohibition on Contracting with Entities Engaging in Certain
Activities or Transactions Relating to Iran-- Representation and Certifications.
AUG 2018
52.228-4 Workers' Compensation and War-Hazard Insurance Overseas APR 1984 52.229-6 Taxes--Foreign Fixed-Price Contracts FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.233-2 Service Of Protest SEP 2006 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-16 Quantity Surveys APR 1984 52.236-17 Layout of Work APR 1984
52.236-21 Specifications and Drawings for Construction FEB 1997 52.242-13 Bankruptcy JUL 1995 52.243-4 Changes JUN 2007 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements DEC 2010 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7005 Airfield Safety Precautions DEC 1991 252.236-7008 Contract Prices-Bidding Schedules DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.247-7023 Transportation of Supplies by Sea FEB 2019
52.211-13 TIME EXTENSIONS (SEP 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
(End of clause)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of an…