SOLICITATION W912PA-18-Q-0034 PROJECT: R-CH-O2-18233-18 MAGNITUDE: Estimated betw een $ 100,000.00 and $ 250,000.00 INSTRUCTIONS TO OFFERORS: Offerors shall submit the documentation requested in Section L of the SF1442, Instructions, Conditions and Notices to Bidders. SAM FOR AWARD MANAGEMENT (SAM): In order to be eligible for contract aw ard, the offeror must be registered in the System for Award Management (SAM) w ebsite (https://w w w .sam.gov). Detailed instructions for SAM registration are found in.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011207618
PROJECT: R-CH-O2-18233-18
MAGNITUDE: Estimated betw een $ 100,000.00 and $ 250,000.00
INSTRUCTIONS TO OFFERORS: Offerors shall submit the documentation requested in Section L of the SF1442, Instructions, Conditions and Notices to Bidders.
SAM FOR AWARD MANAGEMENT (SAM): In order to be eligible for contract aw ard, the offeror must be registered in the System for Aw ard Management (SAM) w ebsite (https://w w w .sam.gov). Detailed instructions for SAM registration are found in Section H of this solicitation.
SITE VISIT: A site visit has been scheduled for Wednesday, 5 September 2018 at 10.00 hrs. Participants w ill meet at Gate 14, Chievres Air Base, 7950 CHIEVRES, Belgium. POINT OF CONTACT (POC) for technical info and site visit: Please contact David Diricq to confirm attendance to the Site Visit at david.diricq.ln@mail.mil
ANIKA MOMIK 00-32-2-7179615
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Aug-2018
(RFP)
(IFB)
CALL:
Install street and parking lighting bldg. 20005, 20120
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______1 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________11 Sep 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
RCO BENELUX
ANIKA MOMIK
32-2-7179615 (FAX 9610)
LEUVENSESTEEWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
W912PA
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
11:59 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
R-CH- O2-18233-18
8. ADDRESS OFFER TO (If Other Than Item 7)
02-7179610FAX:TEL: 02-7179615 TEL: FAX:
W912PA18Q0034 45
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912PA18Q0034
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job As-Built drawings
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. G-05 FOB: Destination
PURCHASE REQUEST NUMBER: 0011207618
PSC CD: N062
NET AMT
0002 1 Job Preparation of the work site
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-1-02 FOB: Destination
0003 1 Job Dismounting
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-1-03 FOB: Destination
0004 1 Job Trenching in natural ground
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-2-01 FOB: Destination
0005 1 Job Drilling under the road
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-2-02 FOB: Destination
0006 1 Job Opening and closing of concrete overlays
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-2-03 FOB: Destination
0007 1 Job Opening and closing hydrocarbon overlay
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-2-04 FOB: Destination
0008 1 Job Earthwork for base
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-2-05 FOB: Destination
0009 1 Job Concrete work
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-3-01 FOB: Destination
0010 1 Job Lighting posts - Street
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-3-02 FOB: Destination
0011 1 Job Lighting posts - Parking
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-3-02 FOB: Destination
0012 1 Job Electrical installation
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-01 FOB: Destination
0013 1 Job Light fixture - Street
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-02 FOB: Destination
0014 1 Job Light fixture - Parking
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-02 FOB: Destination
0015 1 Job Control systems
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-02 FOB: Destination
0016 1 Job Cabling - Connections
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-03 FOB: Destination
0017 1 Job Cabling - Electrical cables
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-03 Identify type/s of EXVB cables (complete one or more items below):
EXVB type________________ EXVB type________________ EXVB type________________ FOB: Destination
0018 1 Job Cabling - Bare copper cable 35mm2
FFP
In Accordance With the Attachment I, Statement of Work (SOW), Par. TP-4-03 FOB: Destination
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government 0012 Destination Government Destination Government 0013 Destination Government Destination Government 0014 Destination Government Destination Government 0015 Destination Government Destination Government 0016 Destination Government Destination Government 0017 Destination Government Destination Government 0018 Destination Government Destination Government
CLAUSES INCORPORATED BY FULL TEXT
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(End of clause)
5152.204-4005 CONVENTIONAL FORCES EUROPE (CFE) TREATY VERIFICATION INSPECTION
(June 2016)
Contractor-owned or controlled structures and containers located on U.S. Government installations are subject to short-notice inspections by CFE treaty inspection teams. The Government will endeavor to provide the Contractor as much notice as possible in the event of such inspections. The contractor shall provide access to such structures and containers at the request of the Government. The Contractor shall report such inspections to the Contracting Officer in writing within ten (10) calendar days of completion of the inspection. Contractor-owned or controlled structures and/or containers on U.S. installations may have to be inspected to comply with the CFE treaty even if Contractor personnel are unavailable to provide access. Any costs borne by the Contractor or any impact on contract performance as a result of the inspection will be a matter of negotiation between the Contractor and the Contracting Officer.
Section F - Deliveries or Performance
NOTICE TO PROCEED
The notice to proceed will be provided as indicated below:
[__________] The effective date of contract will constitute the date of notice to proceed.
[___X______] A notice to proceed letter will be issued within sixty (60) calendar days after the effective date of contract.
[__________] The date of the letter transmitting the contract will constitute the date of the notice to proceed.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 180 dys. ANP 1 BENELUX
DAVID DIRICQ
56 GRAND RUE
7950 CHIEVRES
BELGIUM
++32 (0)68 27 54 46 FOB: Destination
WK3E47
0002 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0003 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0004 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0005 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0006 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0007 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0008 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0009 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0010 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0011 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0012 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0013 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0014 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0015 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0016 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0017 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0018 180 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
CLAUSES INCORPORATED BY REFERENCE
52.236-14 Availability and Use of Utility Services APR 1984
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within one (1) calendar day after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than one hundred and eighty (180) calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of three hundred twenty-nine U.S dollars ($329.00) or a converted foreign currency equivalent using 266th FINANCIAL MANAGEMENT SUPPORT CENTER for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.211-13 TIME EXTENSIONS (SEP 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997)
(a) "Hazardous material", as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.
Material Identification No.
(If none, insert "None")
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items.
Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to--
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
(End of clause)
ADDENDUM TO CLAUSE 52.223-3
A. Standard paragraph (b) has been amendend as follows:
The Contractor must list any hazardous material after the contract award as established in the Deliverables Schedule.
(End of addendum)
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.
However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
5152.225-4001 INSTALLATION CLEARANCE RERQUIREMENTS (May 2017)
(a) Access to U.S. installations and controlled areas is limited to personnel who meet security criteria and are authorized by Host Nation law to work in that country. Failure to submit required information/data and obtain required documentation or clearances in accordance with AE Regulation 190-16, Installation Access Control, will be grounds for denying access to U.S. installations and controlled areas. The Contractor is responsible to ensure that any Subcontractor used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any Subcontractor utilized by the contractor, are made aware of and comply with these requirements.
(b) The Contractor is responsible for being aware of and complying with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control (IAC) processing requirements.
(c) The Contractor is responsible for returning installation passes to the issuing Installation Access Control Office (IACO) when the contract is completed or when a contractor employee no longer requires access.
(d) AE Regulation 190-16 (and AE Regulation 190-16-G German translation) can be found on the following websites: http://www.409csb.army.mil/library/AER-190-16.pdf and http://www.409csb.army.mil/Library/AER-190-16-G.pdf.
(e) Below is the responsible Organizational Sponsor & Installation Access Control Office for this contract:
Organizational Sponsor: Mike Jensen Location: USAG Benelux – DPW Building No: Hangar#6 Chievres Air Base DSN Phone No: 361-5688 Commercial Phone No: 068 27 5688 Installation Access Control Office:
Location: USAG Benelux – PMO Building No:20134 DSN Phone No: 361-5433 Commercial Phone No: 068 27 5433
Section G - Contract Administration Data
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
252.204-7006 BILLING INSTRUCTIONS (OCT 2005)
When submitting a request for payment, the Contractor shall--
(a) Identify the contract line item(s) on the payment request that reasonably reflect contract work performance; and
(b) Separately identify a payment amount for each contract line item included in the payment request.
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type.
CONSTRUCTION INVOICE
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
USAG Benelux - DPW DoDAAC: WK3E47
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC W56FJX Issue By DoDAAC W912PA Admin DoDAAC W912PA Inspect By DoDAAC WK3E47 Ship To Code WK3E47 Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) WK3E47 Service Acceptor (DoDAAC) WK3E47 Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
michael.r.jensen2.civ@mail.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
anika.momik.ln@mail.mil
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
ADDENDUM TO CLAUSE 252.232-7006
A. Paragraph (h) has been added as follows:
Foreign vendors requesting payment via Electronic Funds Transfer (EFT) shall provide the following information on their invoice at time of invoice submission:
- Bank Name
- Bank Identification Code (BIC)
- International Bank Account Number (IBAN)
(End of addendum)
Section H - Special Contract Requirements
SPECIAL INSTRUCTIONS
A. SYSTEM FOR AWARD MANAGEMENT (SAM)
Only contractors who are registered and have an active account in the System for Award Management (SAM) may be awarded a contract as a result of this solicitation.
In order to better manage its expenditures, the U.S. Government requires all contractors, foreign, as well as domestic, to input basic company information into a central database. This means all vendors doing business with the Regional Contracting Office – Benelux are required to register in the System for Award Management (SAM) database.
In order to be eligible for contract award, the offeror must be registered in the System for Award Management (SAM) website (https://www.sam.gov). If the offeror is not yet registered in SAM, the detailed instructions for SAM registration are:
-> Non-US companies Step-1: Obtain a NATO Contractor and Government Entity (NCAGE) Code prior to logging onto the SAM website.
NCAGE Codes can be obtained on the following web site:
https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx
-> US companies & non-personal services contractors (e.g. Army Chapel & ACS offices) Step-1: Obtain a DUNS number by registering at: http://www.dnb.com At this website, you must first pick your country from the drop-down menu in the upper right-hand corner, then pick your language, and follow the directions.
[Background information: The U.S. Government system uses the Data Universal Numbering System (DUNS) number as your contractor identification number. This number consists of a nine-digit number assigned to your firm by Dun and Bradstreet Information Services.
Step-2 for both Non-US and US companies:
To complete mandatory SAM registration, please complete the following steps (3-5 business days after obtaining the DUNS number) :
(i) Go to SAM’s homepage: http://www.sam.gov
(ii) Click on “Start New Registration”
(iii) When prompted, enter your DUNS number. Click “Submit”
(iv) Input your specific information (mandatory information is marked in green with an asterisk (*) next to it)
(v) Click “Validate/Save” when finished entering all your information on each page.
Please note that the vendor must first have an active account in SAM before he/she can register and submit an invoice into WAWF.
B. PERMITS AND RESPONSIBILITIES
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable laws, codes, and regulations applicable to the performance of the work. The Contractor shall also take proper safety and health precautions to protect the work, the workers, the public, and the property of others. The Contractor shall be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work that may have been accepted under the contract.
C. LIABILITY
For the purpose of this contract the Contractor is considered as an independent Contractor and not as an agent of the US Government. During the performance the Contractor shall be liable and will indemnify and hold harmless the Government, its agents and employees against any actions or claims for all damages to persons or property, including death arising or resulting from fault, negligence, wrongful act or wrongful omission of the Contractor.
D. TRANSLATION
Drawings, specifications, instructions, or other documents furnished to the Contractor by the Government in connection with the performance of the work shall be in the English language only. Such translations thereof as are necessary or proper for the performance of the work shall be provided by the Contractor. Errors or omissions in such translations from the Government furnished drawings, specifications, instructions or other documents shall be the responsibility of the Contractor. The English text shall apply in the event of disagreements occasioned by differences between the text and the Contractor’s translation of drawings, specifications, instructions or other documents furnished by the Government pursuant to the provisions of the contract. All correspondence, drawings, and other documents submitted by the Contractor shall be entirely in English, except as otherwise provided in the contract.
E. ENVIRONMENTAL LAWS.
All materials should meet regional, provincial, national and local ecology laws in respect to all materials and their disposal. Contractor will be insured against and solely responsible for any ecological damage caused both to US and Host Nation interested parties. Furthermore, the Contractor agrees to hold the US Government harmless in any lawsuit concerning ecological damages.
F. WEATHER DELAYS
Reference paragraph (b) (1), FAR 52.249-10 Clause “DEFAULT (FIXED PRICE CONSTRUCTION)(APR 1984)”.
Unless unusually severe (seasonal) weather conditions prevails, no extension will be granted for delays experienced by the Contractor. A log book shall be kept by the Contractor to record weather conditions, and any eventual inclemency’s which may preclude the continuation of work in accordance with the requirements of tender document “Marchés Publics – 1978, chapter I, Item 28” (for BELGIUM). This log book shall be presented as a summary of the work performed, the weather conditions and the report on personnel attendance on the work site. It shall serve as a base for determining the final completion date of the works.
G. PERFORMANCE STANDARDS
(a) In the event of conflict between the applicable standards and any requirement or condition of the specifications and the contract, the specifications and the contract shall govern.
(b) Copies of the applicable Belgian standards and regulations will not be furnished with this specifications. US Army, Government specifications, regulations and other publications made part of this contract by reference herein are available for reading at the local facilities engineering office located at :
USAG BENELUX
Directorate of PublicWorks, Engineering Division Hangar #6 Chievres Air Base 7950 Chievres, Belgium
H. MEASUREMENTS AND QUANTITIES
Unless stated otherwise, all quantities and measurements listed in the specifications, drawings, and price breakdown are estimates only. The offeror themselves shall familiarize with the job site, determine the extent, nature and scope of work as appropriate.
I. CONSERVATION OF ELECTRICITY AND WATER
The United States Government will make available to the Contractor, from existing outlets and supplies, all reasonably required amounts of electricity and water free of charge to the Contractor. The Contractor shall carefully conserve utilities furnished without charge.
J. GOVERNMENT-FURNISHED UTILITIES
(a) Utilities. Water and electrical power required for the execution of this project will be made available to the Contractor without charge, in accordance with the contract clause “AVAILABILITY AND USE OF UTILITY SERVICES (APRIL 1984), FAR 52.236-14. Necessary connections to lines shall be made by the Contractor without additional cost to the Government. Electrical connections or temporary installations shall be made in accordance with VDE 0100. No other material, equipment, or services shall be furnished by the Government unless expressly stated elsewhere herein.
(b) Telephones. Telephone facilities shall be made available without charge at a location designated by the Contracting Officer to make calls within the military reservation areas only. Use of telephones in family quarters by the Contractor or his/her employees or Sub-Contractors is strictly prohibited.
K. WIDE AREA WORKFLOW (WAWF) SYSTEM
Payment for this acquisition will be made through the Wide Area Workflow (WAWF) system. Contractors shall be registered in WAWF. See web site https://wawf.eb.mil for registration. Additional WAWF information is included in FAR Clauses 252.232-7003 and 252.232-7006.
L. PREPARATION, SUBMISSION OF INVOICES AND PAYMENT
Contractor shall submit his invoice electronically through the Wide Area Workflow (WAWF) online application system for payment. WAWF Instructions are being provided to the Contractor under separate cover upon request. WAWF also provides online training: https://wawf.eb.mil/ Invoice must include the appropriate amount due, percentage of work completed, or an itemized listing of quantities (by building, if applicable) and a description of items and discounts accurate in accordance with the Schedule and the terms and conditions of the contract. In addition, the invoice shall specify the date on which all work, or to portion or percentage of work invoiced under the contract, was completed. Taxes and duties will be listed and excluded from invoice prices.
US AND HOST NATION HOLIDAYS
A. US HOLIDAYS
Work Shall Not be performed on U.S. holidays occurring during the normal workweek. When a U.S holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
The U.S. holidays are:
New Year's Day January 1st M L King Memorial Day 3d Monday in January Presidents' Day 3d Monday in February Memorial Day last Monday in May Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2d Monday in October Veterans' Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
B. HOST NATION HOLIDAYS
Work Shall Not be performed on local Host Nation* holidays occurring during the normal workweek.
* Local host nation holidays occur in the region/state where contract performance takes place.
The Belgium holidays are:
New Year’s Day 01 January Easter Monday varies yearly Labor Day 01 May Ascension Day varies yearly Bank Holiday varies yearly Whit-Monday varies yearly National Independence Day 21 July Assumption 15 August All Saints Day 01 November Armistice Day 11 November Dynasty Day varies yearly Christmas Day 25 December
Section I - Contract Clauses
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2016 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-29 Notification Of Visa Denial APR 2015 52.222-50 Alt I Combating Trafficking in Persons (MAR 2015) Alternate I MAR 2015 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
OCT 2015
52.228-3 Worker's Compensation Insurance (Defense Base Act) JUL 2014 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas APR 1984 52.229-6 Taxes--Foreign Fixed-Price Contracts FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-13 Notice Of Progress Payments APR 1984 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.243-4 Changes JUN 2007 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Items NOV 2017 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7007 Alternate A, Annual Representations and Certifications JAN 2015 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.215-7008 Only One Offer OCT 2013 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7041 Correspondence in English JUN 1997 252.225-7048 Export-Controlled Items JUN 2013 252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7005 Airfield Safety Precautions DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work.