This document is a Bid Abstract for the Wood River Relief Well #3 construction solicitation, Solicitation No. W912P924B0018. The solicitation was issued on June 24, 2024, with bids due by 10:00am CST on July 24, 2024. The government estimate for the project is $7,704,210.00. Three offerors submitted bids - Randy Kinder Excavating Inc., BCI Construction USA, Inc., and Magruder Construction Co Inc. The base schedule includes items such as mobilization, well drilling, well installation, pumping tests, piezometers, relief well collector and outlet pipes, paved ditches, road raise, outlet headwells, and levee ramp removal. An options schedule includes new well abandonment. Bid prices range from $9,644,520.00 to $11,929,491.05. The contracting agency is the U.S. Army Corps of Engineers, Engineering District St. Louis.

View the file

Other files

File Type Posted
B01. Abstract of Bids.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Abstract

Wood River Relief Well #3
Bid Abstract - Construction
Solicitation No: W912P924B0018
Date Issued: 24 June 2024
Amendments: 0001
Bids Due: 10:00am CST, 24 July 2024
Public Bid Opening: 2:30pm CST, 24 July 2024
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Contracting Officer
Whitney Dee
Government EstimateOfferor 1

Randy Kinder Excavating Inc

UEI: XMKUEVF3NMB5

CAGE: 0E9B3 Offeror 2 BCI Construction USA, Inc.

UEI: UM3PW6F8SCW1

CAGE: 0R551 Offeror 3 Magruder Construction Co Inc

UEI: LMH6DPYYPM15

CAGE: 0JHC5

Bid received by due date/time?XXX
Amendments Acknowledged?XXX
Bid Security (Type and amount)XXX
Grand Total Prices$7,704,210.00$11,929,491.05$9,684,578.53$9,644,520.00
CLINDescriptionQuantityU/MUnit PriceExtended AmountUnit PriceExtended AmountUnit PriceExtended AmountUnit PriceExtended Amount
BASE SCHEDULE
0001Mobilization and Demobilization1Job$198,500.00$198,500.00$1,588,585.16$1,588,585.16$1,060,054.00$1,060,054.00$450,000.00$450,000.00
0002Establishment of Turf1Job$47,000.00$47,000.00$144,108.54$144,108.54$42,987.00$42,987.00$92,000.00$92,000.00
0003Care of Water1Job$237,500.00$237,500.00$101,811.75$101,811.75$112,296.00$112,296.00$50,000.00$50,000.00
0004Clearing and Stripping1Job$19,800.00$19,800.00$81,474.35$81,474.35$14,731.00$14,731.00$88,000.00$88,000.00
0005Well Drilling2598LF$220.00$571,560.00$299.15$777,191.70$364.49$946,945.02$280.00$727,440.00
0006Well Installation2519LF$550.00$1,385,450.00$666.49$1,678,888.31$443.49$1,117,151.31$320.00$806,080.00
0007Well Development30EA$3,900.00$117,000.00$3,986.38$119,591.40$3,469.37$104,081.10$2,300.00$69,000.00
0008Pumping Tests30EA$2,500.00$75,000.00$5,070.63$152,118.90$3,469.37$104,081.10$2,300.00$69,000.00
0009Piezometers5EA$26,200.00$131,000.00$40,573.73$202,868.65$78,622.80$393,114.00$31,000.00$155,000.00
0010Relief Well Collector and Outlets Pipes1Job$267,100.00$267,100.00$614,419.47$614,419.47$597,032.00$597,032.00$1,090,000.00$1,090,000.00
0011Paved, Ditch, Gravity Drain Inlets, Disch1Job$2,173,000.00$2,173,000.00$2,701,255.31$2,701,255.31$2,501,831.00$2,501,831.00$2,485,000.00$2,485,000.00
0012Road Raise1Job$411,800.00$411,800.00$182,287.95$182,287.95$445,021.00$445,021.00$196,000.00$196,000.00
0013Outlet Headwells1Job$569,500.00$569,500.00$1,506,649.32$1,506,649.32$459,902.00$459,902.00$540,000.00$540,000.00
0014Gravity Drain Stone Protection1Job$1,148,000.00$1,148,000.00$1,573,964.70$1,573,964.70$1,547,012.00$1,547,012.00$2,110,000.00$2,110,000.00
0015Levee Ramp Removal1Job$218,000.00$218,000.00$318,161.71$318,161.71$158,918.00$158,918.00$515,000.00$515,000.00
0016Bonding1Job$115,000.00$115,000.00$178,502.83$178,502.83$64,650.00$64,650.00$190,000.00$190,000.00
BASE SCHEDULE SUBTOTAL$7,685,210.00$11,921,880.05$9,669,806.53$9,632,520.00
OPTIONS SCHEDULE
0017New Well Abandonment100LF$190.00$19,000.00$76.11$7,611.00$147.72$14,772.00$120.00$12,000.00
OPTIONS SCHEDULE SUBTOTAL$19,000.00$7,611.00$14,772.00$12,000.00

TOTAL BASE SCHEDULE AND OPTIONS SCHEDULE $7,704,210.00 $11,929,491.05 $9,684,578.53 $9,644,520.00