This document is a Bid Abstract for the Wood River Relief Well #3 construction solicitation, Solicitation No. W912P924B0018. The solicitation was issued on June 24, 2024, with bids due by 10:00am CST on July 24, 2024. The government estimate for the project is $7,704,210.00. Three offerors submitted bids - Randy Kinder Excavating Inc., BCI Construction USA, Inc., and Magruder Construction Co Inc. The base schedule includes items such as mobilization, well drilling, well installation, pumping tests, piezometers, relief well collector and outlet pipes, paved ditches, road raise, outlet headwells, and levee ramp removal. An options schedule includes new well abandonment. Bid prices range from $9,644,520.00 to $11,929,491.05. The contracting agency is the U.S. Army Corps of Engineers, Engineering District St. Louis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B01. Abstract of Bids.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Abstract
| Wood River Relief Well #3 | ||||
| Bid Abstract - Construction | ||||
| Solicitation No: W912P924B0018 | ||||
| Date Issued: 24 June 2024 | ||||
| Amendments: 0001 | ||||
| Bids Due: 10:00am CST, 24 July 2024 | ||||
| Public Bid Opening: 2:30pm CST, 24 July 2024 | ||||
| I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. | ||||
| Contracting Officer | ||||
| Whitney Dee | ||||
| Government Estimate | Offeror 1 |
Randy Kinder Excavating Inc
UEI: XMKUEVF3NMB5
CAGE: 0E9B3 Offeror 2 BCI Construction USA, Inc.
UEI: UM3PW6F8SCW1
CAGE: 0R551 Offeror 3 Magruder Construction Co Inc
UEI: LMH6DPYYPM15
CAGE: 0JHC5
| Bid received by due date/time? | X | X | X | ||||
| Amendments Acknowledged? | X | X | X | ||||
| Bid Security (Type and amount) | X | X | X | ||||
| Grand Total Prices | $7,704,210.00 | $11,929,491.05 | $9,684,578.53 | $9,644,520.00 |
| CLIN | Description | Quantity | U/M | Unit Price | Extended Amount | Unit Price | Extended Amount | Unit Price | Extended Amount | Unit Price | Extended Amount |
| BASE SCHEDULE | |||||||||||
| 0001 | Mobilization and Demobilization | 1 | Job | $198,500.00 | $198,500.00 | $1,588,585.16 | $1,588,585.16 | $1,060,054.00 | $1,060,054.00 | $450,000.00 | $450,000.00 |
| 0002 | Establishment of Turf | 1 | Job | $47,000.00 | $47,000.00 | $144,108.54 | $144,108.54 | $42,987.00 | $42,987.00 | $92,000.00 | $92,000.00 |
| 0003 | Care of Water | 1 | Job | $237,500.00 | $237,500.00 | $101,811.75 | $101,811.75 | $112,296.00 | $112,296.00 | $50,000.00 | $50,000.00 |
| 0004 | Clearing and Stripping | 1 | Job | $19,800.00 | $19,800.00 | $81,474.35 | $81,474.35 | $14,731.00 | $14,731.00 | $88,000.00 | $88,000.00 |
| 0005 | Well Drilling | 2598 | LF | $220.00 | $571,560.00 | $299.15 | $777,191.70 | $364.49 | $946,945.02 | $280.00 | $727,440.00 |
| 0006 | Well Installation | 2519 | LF | $550.00 | $1,385,450.00 | $666.49 | $1,678,888.31 | $443.49 | $1,117,151.31 | $320.00 | $806,080.00 |
| 0007 | Well Development | 30 | EA | $3,900.00 | $117,000.00 | $3,986.38 | $119,591.40 | $3,469.37 | $104,081.10 | $2,300.00 | $69,000.00 |
| 0008 | Pumping Tests | 30 | EA | $2,500.00 | $75,000.00 | $5,070.63 | $152,118.90 | $3,469.37 | $104,081.10 | $2,300.00 | $69,000.00 |
| 0009 | Piezometers | 5 | EA | $26,200.00 | $131,000.00 | $40,573.73 | $202,868.65 | $78,622.80 | $393,114.00 | $31,000.00 | $155,000.00 |
| 0010 | Relief Well Collector and Outlets Pipes | 1 | Job | $267,100.00 | $267,100.00 | $614,419.47 | $614,419.47 | $597,032.00 | $597,032.00 | $1,090,000.00 | $1,090,000.00 |
| 0011 | Paved, Ditch, Gravity Drain Inlets, Disch | 1 | Job | $2,173,000.00 | $2,173,000.00 | $2,701,255.31 | $2,701,255.31 | $2,501,831.00 | $2,501,831.00 | $2,485,000.00 | $2,485,000.00 |
| 0012 | Road Raise | 1 | Job | $411,800.00 | $411,800.00 | $182,287.95 | $182,287.95 | $445,021.00 | $445,021.00 | $196,000.00 | $196,000.00 |
| 0013 | Outlet Headwells | 1 | Job | $569,500.00 | $569,500.00 | $1,506,649.32 | $1,506,649.32 | $459,902.00 | $459,902.00 | $540,000.00 | $540,000.00 |
| 0014 | Gravity Drain Stone Protection | 1 | Job | $1,148,000.00 | $1,148,000.00 | $1,573,964.70 | $1,573,964.70 | $1,547,012.00 | $1,547,012.00 | $2,110,000.00 | $2,110,000.00 |
| 0015 | Levee Ramp Removal | 1 | Job | $218,000.00 | $218,000.00 | $318,161.71 | $318,161.71 | $158,918.00 | $158,918.00 | $515,000.00 | $515,000.00 |
| 0016 | Bonding | 1 | Job | $115,000.00 | $115,000.00 | $178,502.83 | $178,502.83 | $64,650.00 | $64,650.00 | $190,000.00 | $190,000.00 |
| BASE SCHEDULE SUBTOTAL | $7,685,210.00 | $11,921,880.05 | $9,669,806.53 | $9,632,520.00 | |||||||
| OPTIONS SCHEDULE | |||||||||||
| 0017 | New Well Abandonment | 100 | LF | $190.00 | $19,000.00 | $76.11 | $7,611.00 | $147.72 | $14,772.00 | $120.00 | $12,000.00 |
| OPTIONS SCHEDULE SUBTOTAL | $19,000.00 | $7,611.00 | $14,772.00 | $12,000.00 |
TOTAL BASE SCHEDULE AND OPTIONS SCHEDULE $7,704,210.00 $11,929,491.05 $9,684,578.53 $9,644,520.00