B01. Abstract of Bids.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Lower Wood River Drainage and Levee District Relief Well Package #3
Solicitation number
W912P924B0018
Issued by

About this file

This document is a Bid Abstract for the Harlow Island Stage 1 construction solicitation number W912P924B0019. The solicitation was issued on June 21, 2024 with a bid due date of July 24, 2024. Three offerors submitted bids, including Faulkner Contracting Group, Bloomsdale Excavating Co Inc, and Oak Hill Contractors LLC. The government estimate for the contract was $11,245,838.00. The low bid of $4,599,680.00 was submitted by Oak Hill Contractors LLC. The contract includes a base schedule for mobilization, earthwork, clearing and grubbing, seeding, and other construction items, as well as several optional item groups for additional earthwork, seeding, and temporary structures. Bid prices were provided for each contract line item. This solicitation is related to the Lower Wood River Drainage and Levee District Relief Well Package #3 contract opportunity issued by the U.S. Army Corps of Engineers, St. Louis District.

View the file

Other files

File Type Posted
B01. Abstract of Bids.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Abstract

Harlow Island Stage 1
Bid Abstract - Construction
Solicitation No: W912P924B0019
Date Issued: 21 June 2024
Amendments: 0001
Bids Due: 10:00am CST, 24 July 2024
Public Bid Opening: 2:00pm CST, 24 July 2024
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Contracting Officer
Whitney Dee
Government EstimateOfferor 1

Faulkner Contracting Group Bloomsdale, MO 63627

UEI: M8K2L9NG6PB8

CAGE: 8U6U8 Offeror 2 Bloomsdale Excavating Co Inc Bloomsdale, MO 63627

UEI: KJ3RCL48D213

CAGE: 0H2U7 Offeror 3 Oak Hill Contractors LLC Ewing, IL 62836

UEI: TKEJWZRFSL43

CAGE: 54UB9

Bid received by due date/time?YesYesYes
Amendments Acknowledged?YesYesYes
Bid Security (Type and amount)YesBid/20%YesBid/20%YesBid/20%
Grand Total Prices$11,245,838.00$6,871,941.00$4,599,680.00$7,789,260.00
CLINDescriptionQuantityU/MUnit PriceExtended AmountUnit PriceExtended AmountUnit PriceExtended AmountUnit PriceExtended Amount
BASE SCHEDULE
0001Mobilization & Demobilization1Job$153,000.00$153,000.00$250,000.00$250,000.00$690,000.00$690,000.00$389,765.00$389,765.00
0002AAEmbankment, Sediment Deflection Berm -STA 0+00 to 100+0074520CY$17.00$1,266,840.00$10.60$789,912.00$7.40$551,448.00$12.17$906,908.40
0002ABAll over 7452049680CY$17.20$854,496.00$9.70$481,896.00$7.40$367,632.00$12.17$604,605.60
0003AAStripping, Clearing, Grubbing - Construction Access and Staging Area, Sediment Deflection Berm STA
0+00 to 100+00 and Swale B STA 71+34 to 104+6558AC$9,000.00$522,000.00$6,686.00$387,788.00$2,955.00$171,390.00$3,675.00$213,150.00
0003ABAll over 58 Acres13AC$9,000.00$117,000.00$6,656.00$86,528.00$2,955.00$38,415.00$3,675.00$47,775.00
0004AASeeding and Mulching - Construction Access and Staging Area, Sediment Deflection Berm STA 0+00 TO 100+00 and
Swale B STA 71+34 to 104+6523AC$4,400.00$101,200.00$4,930.00$113,390.00$2,990.00$68,770.00$3,267.00$75,141.00
0004ABAll over 23 Acres5AC$4,400.00$22,000.00$4,855.00$24,275.00$2,990.00$14,950.00$3,267.00$16,335.00
0005Construction Access & Staging Area1Job$59,000.00$59,000.00$58,968.00$58,968.00$170,000.00$170,000.00$67,356.00$67,356.00
0006Temporary Construction Roads1Job$219,000.00$219,000.00$35,265.00$35,265.00$220,000.00$220,000.00$196,875.00$196,875.00
0007Test Pits2EA$27,000.00$54,000.00$8,278.00$16,556.00$4,800.00$9,600.00$3,675.00$7,350.00
0008Railroad Coordination1Job$312,000.00$312,000.00$13,917.00$13,917.00$39,000.00$39,000.00$67,778.00$67,778.00
BASE SCHEDULE SUBTOTAL$3,680,536.00$2,258,495.00$2,341,205.00$2,593,039.00
OPTIONAL ITEMS GROUP 1
0009Temporary Mobilization & Demobilization1Job$105,000.00$105,000.00$112,950.00$112,950.00$40,000.00$40,000.00$55,650.00$55,650.00
OPTIONAL ITEMS GROUP 2
0010Low Water Crossing Structure Demobilization1Job$27,100.00$27,100.00$18,741.00$18,741.00$11,000.00$11,000.00$10,500.00$10,500.00
0011Low Water Crossing Structure Replacement1Job$94,700.00$94,700.00$144,490.00$144,490.00$64,000.00$64,000.00$102,418.00$102,418.00
OPTIONAL ITEMS GROUP 3
0012Temporary Low Water Crossing Structure1Job$82,600.00$82,600.00$24,257.00$24,257.00$33,000.00$33,000.00$102,418.00$102,418.00
OPTIONAL ITEMS GROUP 4
0013AAStripping, Clearing, Grubbing - Swale B STA 104+65 to POE and Ridge A48AC$9,000.00$432,000.00$5,515.00$264,720.00$2,200.00$105,600.00$3,675.00$176,400.00
0013ABAll over 48 Acres11AC$9,000.00$99,000.00$5,944.00$65,384.00$2,200.00$24,200.00$3,675.00$40,425.00
OPTIONAL ITEMS GROUP 5
0014AAStripping, Clearing, Grubbing - Swale A and Ridge B44AC$9,000.00$396,000.00$5,802.00$255,288.00$2,200.00$96,800.00$3,675.00$161,700.00
0014ABAll over 44 Acres11AC$9,000.00$99,000.00$5,813.00$63,943.00$2,200.00$24,200.00$3,675.00$40,425.00
OPTIONAL ITEMS GROUP 6
0015AARidge A (Part 1)30000CY$17.70$531,000.00$8.90$267,000.00$4.10$123,000.00$12.17$365,100.00
0015ABAll over 30,000 Cubic Yards20,000CY$18.20$364,000.00$9.30$186,000.00$4.10$82,000.00$12.17$243,400.00
OPTIONAL ITEMS GROUP 7
0016AARidge A (Part 2)30000CY$17.70$531,000.00$8.90$267,000.00$4.10$123,000.00$12.17$365,100.00
0016ABAll over 30,000 Cubic Yards20,000CY$18.20$364,000.00$9.30$186,000.00$4.10$82,000.00$12.17$243,400.00
OPTIONAL ITEMS GROUP 8
0017AARidge A (Part 3)30000CY$17.70$531,000.00$8.90$267,000.00$4.95$148,500.00$12.17$365,100.00
0017ABAll over 30,000 Cubic Yards20,000CY$18.20$364,000.00$9.30$186,000.00$4.95$99,000.00$12.17$243,400.00
OPTIONAL ITEMS GROUP 9
0018AARidge A (Part 4)25380CY$17.90$454,302.00$9.20$233,496.00$4.95$125,631.00$12.17$308,874.60
0018ABAll over 25380 Cubic Yards16,920CY$18.50$313,020.00$9.75$164,970.00$4.95$83,754.00$12.17$205,916.40
0019AASeeding and Mulching - Swale B STA 104+65 to POE and Ridge A18AC$4,400.00$79,200.00$3,126.00$56,268.00$2,995.00$53,910.00$3,267.00$58,806.00
0019ABAll over 18 Acres4AC$4,400.00$17,600.00$3,126.00$12,504.00$2,995.00$11,980.00$3,267.00$13,068.00
OPTIONAL ITEMS GROUP 10
0020AARidge B (Part 1)30000CY$17.70$531,000.00$12.10$363,000.00$6.00$180,000.00$14.04$421,200.00
0020ABAll over 30,000 Cubic Yards20,000CY$18.20$364,000.00$12.45$249,000.00$6.00$120,000.00$14.04$280,800.00
OPTIONAL ITEMS GROUP 11
0021AARidge B (Part 2)30,000CY$17.70$531,000.00$12.10$363,000.00$6.00$180,000.00$14.04$421,200.00
0021ABAll over 30,000 Cubic Yards20,000CY$18.20$364,000.00$12.40$248,000.00$6.00$120,000.00$14.04$280,800.00
OPTIONAL ITEMS GROUP 12
0022AARidge B (Part 3)26700CY$17.80$475,260.00$12.35$329,745.00$6.00$160,200.00$14.04$374,868.00
0022ABAll over 26700 Cubic Yards17,800CY$18.40$327,520.00$12.35$219,830.00$6.00$106,800.00$14.04$249,912.00
0023AASeeding and Mulching - Swale A and Ridge B16AC$4,400.00$70,400.00$3,243.00$51,888.00$2,995.00$47,920.00$3,267.00$52,272.00
0023ABAll over 16 Acres4AC$4,400.00$17,600.00$3,243.00$12,972.00$2,995.00$11,980.00$3,267.00$13,068.00
OPTIONS SCHEDULE SUBTOTAL$7,565,302.00$4,613,446.00$2,258,475.00$5,196,221.00

TOTAL BASE SCHEDULE AND OPTIONS SCHEDULE $11,245,838.00 $6,871,941.00 $4,599,680.00 $7,789,260.00