W912P825R0005 AM_0006.pdf
PDF 243 KB Posted
- Solicitation number
- W912P825R0005
About this file
This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for the Roof Replacement New Orleans Headquarters Building project. The amendment establishes a new proposal due date of Tuesday, April 22, 2025, by 10AM CST, with a clear warning that additional questions will not be accepted and the proposal due date will not be extended. The solicitation is for a comprehensive roof replacement project involving demolition of the existing roof, installation of various roofing systems including concrete work, metal framing, insulation, modified bituminous and fluid-applied roofing, metal wall panels, flashing, doors, hardware, louvers, plumbing, and lightning protection systems.
The document includes a detailed Submittal Register spanning 17 pages, which outlines specific submission requirements for various project components across multiple specification sections. These submissions range from preconstruction submittals and shop drawings to product data, samples, test reports, certificates, and manufacturer's instructions. The register covers technical areas including structural steel, concrete, metal framing, roofing, insulation, wall panels, doors, hardware, and electrical systems, providing a comprehensive framework for documentation and approval processes throughout the project's execution.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P825R0005 AM_0005.pdf | ||
| W912P825R0005 AM_0004.pdf | ||
| W912P825R0005 AM_0003.pdf | ||
| W912P825R0005 AM_0002.pdf | ||
| W912P825R0005 AM_0001.pdf | ||
| W912P825R0005 Plans.pdf | ||
| W912P825R0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for Roof Replacement New Orleans Headquarters Building is hereby amended to provide revised specif ications and establish a new proposal due date.
Proposals are due NLT Tuesday, April 22, 2025, by 10AM CST. Late proposals w ill not be accepted.
ADDITIONAL QUESTIONS WILL NOT BE ACCEPTED AND THE PROPOSAL DUE DATE WILL NOT BE EXTENDED.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 20
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Apr-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P825R0005
X 9B. DATED (SEE ITEM 11)
31-Jan-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Apr-2025
CODE
CONTRACTING DIV- CHIEF
7400 LEAKE AVENUE, ROOM 172
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P825R0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
SECTION 05 50 13.00 28
1. Page 3, paragraph 1.2. Delete the reference AISC 207 in its entirety.
2. Page 6, paragraph 1.3.
a. Subitem SD-01. Delete the following:
“SD-01 Preconstruction Submittals
Erection and Erection Bracing Drawings”
b. Subitem SD-07. Delete the following:
“AISC Structural Steel Fabricator Quality Certification; G
AISC Structural Steel Erector Quality Certification; G”
3. Page 7, paragraph 1.4. Delete this paragraph in its entirety, and substitute “1.4 RESERVED”, therefore.
4. Page 7, paragraph 1.5.1.1. Delete this paragraph in its entirety, and substitute “1.5.1.1 Reserved”, therefore.
SUBMITTAL REGISTER
Delete the Submittal Register in its entirety and substitute the attached revised Submittal Register, therefore.
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 17 PAGES
District Headquarters Building Roof Replacement
01 32 01.00 12 SD-01 Preconstruction Submittals
1.4 GProject Scheduler Qualifications
3.4.1 GPreliminary Project Schedule
3.4.2 GInitial Project Schedule
3.6.2 GPeriodic Schedule Update
01 33 00 SD-01 Preconstruction Submittals
1.7 GSubmittal Register
01 35 26 SD-01 Preconstruction Submittals
1.8.1 GAPP - Construction
1.8 GAccident Prevention Plan (APP)
SD-06 Test Reports 1.5Monthly Exposure Reports 1.13Notifications and Reports
1.13.2 GAccident Reports
1.13.3LHE Inspection Reports
SD-07 Certificates 1.7.1.4Crane Operators/Riggers
1.8.3.2 GStandard Lift Plan
1.8.3.3 GCritical Lift Plan
1.9Activity Hazard Analysis (AHA) 1.10.1Confined Space Entry Permit 1.10.1Hot Work Permit 1.13.4Certificate of Compliance 1.15License Certificates
1.15.1 GRadiography Operation Planning
Work Sheet
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 17 PAGES
01 35 26 1.15.1 GPortable Gauge Operations Planning Worksheet
1.17Gas Protection 01 45 04.00 10 SD-01 Preconstruction Submittals
3.2 G CDContractor Quality Control Plan
01 57 20.00 12 SD-01 Preconstruction Submittals
1.6.1 GEnvironmental Protection Plan
3.2.3 GEnvironmental Protection Plan
1.6.1Environmental Pollution Control
Plan 3.2.3Environmental Pollution Control
Plan 01 78 02.00 10 SD-02 Shop Drawings
1.3.1 G'As-Built' Drawings
03 30 53.00 28 SD-01 Preconstruction Submittals
GCore Drilling Procedure SD-02 Shop Drawings
1.5 GInstallation Drawings
1.5 GInstallation Drawings
SD-03 Product Data 2.3Ready-Mix Concrete
2.1 GConcrete Mix Design
2.2.8 GCuring Materials
SD-05 Design Data 2.2.6Formwork
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 17 PAGES
03 30 53.00 28 3.9 GRepair, Rehabilitation And Removal Report
3.9.1Concrete Repair 3.2.4Concrete Imaging Report 3.2.4Concrete Imaging Report
SD-07 Certificates
3.8.1 GField Testing Technicians, Testing Agency, and Laboratory 03 41 16.08 28 SD-02 Shop Drawings
2.1Fabrication Drawings 2.1Installation Drawings
SD-03 Product Data
2.2.2 GCement Grout Joint Sealing
Materials
2.2.7 GConcrete Mix Design
SD-05 Design Data 2.2.1Design Analysis 2.1Handling And Placement
Procedure SD-06 Test Reports
3.2.2 GCompressive Strength Testing
3.2.2 GSlump
3.2.2 GAir Content
SD-07 Certificates 3.2.1Field Testing Technicians, Testing Agency, And Laboratory
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 17 PAGES
05 05 20.00 28 SD-01 Preconstruction Submittals
1.6.1.1 GInstaller Qualifications
1.6.1.2 GPost-Installed Anchor Special
Inspector Qualifications
3.1 GAnchor Installation
SD-03 Product Data
2.1.1.3 GMechanical Anchors in Concrete
2.1.1.4 GAdhesive Anchor System in
Concrete
3.1.3 GNon-Shrink, Non-Metallic Grout
SD-06 Test Reports
3.3.4 GPost-Installed Anchor Special
Inspections Report SD-08 Manufacturer’s Instructions
2.1.1.2 GManufacturer's Printed
Installation Instructions
05 40 00.00 28 SD-02 Shop Drawings
1.7.1 GFraming Components
SD-03 Product Data 2.1Studs
SD-05 Design Data
1.7.2 GMetal Framing Calculations
SD-06 Test Reports 3.2.1Nondestructive Testing (NDT)
Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 17 PAGES
05 40 00.00 28 1.5 GLoad-Bearing Cold-Formed Metal Framing
SD-07 Certificates 3.2.1Welds 3.2.1Certified Welding Procedure
Specifications (WPS) 3.2.1Welding Procedures And
Qualifications (WPQ) 3.2.1Certified Welding Inspector (CWI) 3.2.1Procedure Qualification Records
(PQR)
05 50 13.00 28 SD-02 Shop Drawings
1.5.1.2 GShop Drawings
SD-03 Product Data
2.4.1 GWelding Electrodes and Rods
2.3.2.3 GDirect Tension Indicator Washers
2.6Form Deck
SD-05 Design Data 1.5.1.2Shoring and Temporary Bracing
1.6.1 GPV Array Rack System
Calculations And Design Drawings
1.6.2 GRailing Calculations
SD-06 Test Reports
3.8.1.2 GWeld Inspection Reports
3.8.2.1 GDirect Tension Indicator Washer
Inspection Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 17 PAGES
05 50 13.00 28 SD-07 Certificates
1.5.2.1 GWelding Procedures and
Qualifications
2.4.1 GWelding Electrodes and Rods
3.8.1.1 GCertified Welding Inspector
3.8.1.2 GNDT Technician
3.6 GWelding Procedure Specifications
(WPS)
1.6.1 GPv Array Rack Designer And
Manufacturer Qualifications SD-08 Manufacturer’s Instructions
3.2Railing Manufacturer's Installation Instructions
07 01 50.10 28 SD-01 Preconstruction Submittals
1.6 GRoofing Removal and Disposal
Plan (General)
1.7 GDust and Debris Control Plan
07 22 00.00 28 SD-02 Shop Drawings
1.4 GInsulation Board Layout
1.4 GVerification of Existing Conditions
SD-03 Product Data
2.1 GInsulation
2.2 GBlanket Insulation
1.5 GCover Board
2.5 GFasteners
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 17 PAGES
07 22 00.00 28 2.2.2Recycled Content For Insulation Materials
2.7 GWood Nailers
SD-05 Design Data
1.8 GWind Resistance
SD-06 Test Reports
1.9.1 GFlame Spread Rating
SD-07 Certificates
1.7 GInstaller Qualifications
SD-08 Manufacturer’s Instructions
2.5 GFasteners
2.1 GInsulation
SD-10 Operation and Maintenance Data
2.1 GInsulation
07 42 13.00 28 SD-01 Preconstruction Submittals
1.7.3 GQualification of Manufacturer
1.7.4 GQualification of Installation
Contractor
1.11 GSample Warranty
SD-02 Shop Drawings
1.7.1 GInstallation Drawings
SD-03 Product Data
2.2.1 GWall Panels
2.2.2Factory Color Finish 1.7.5Closure Materials
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 17 PAGES
07 42 13.00 28 2.5.4.4Pressure Sensitive Tape 2.5.4.1Sealants and Caulking 2.5Accessories
SD-04 Samples
2.2.1 GWall Panels
1.7.3.1 GFasteners
2.5.3 GMetal Closure Strips
2.2.2.5 GColor chart
SD-06 Test Reports
1.5.2 GWind Load Tests
2.2.2.6 GCoating
2.2.2.6 GChalking
SD-07 Certificates
1.7.3.1 GCoil Stock
1.7.3.1 GFasteners
1.7.3.1 GEnamel Repair Paint
SD-08 Manufacturer’s Instructions
3.3 GWall Panel Installation
SD-10 Operation and Maintenance Data
1.9.1 GCleaning And Maintenance
SD-11 Closeout Submittals
1.11 GWarranty
1.7.6 GMaintenance Instructions
07 52 00.00 28 SD-01 Preconstruction Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 17 PAGES
07 52 00.00 28 1.5.7 GMinutes Of The Preroofing Conference
1.5.7 GContractor's Extreme Weather
Emergency Plan
SD-02 Shop Drawings
1.5.7 GRoof Plan
1.5.7Field Inspection and Existing
Conditions Report SD-03 Product Data
2.2 GVapor Retarder
2.3 GModified Bitumen Sheets
2.5 GCold-Applied Membrane
Adhesive
2.7 GPrimer
2.8 GModified Bitumen Roof Cement
2.11Pre-Manufactured Accessories
1.10 GSample Warranty
2.10Fasteners And Plates
SD-05 Design Data
1.5.6 GWind Uplift Calculations
SD-07 Certificates
1.5.1 GQualification of Manufacturer
1.5.2 GQualification of Applicator
1.5.3 GQualification of Torch Operator
1.5.4Qualification of Engineer of
Record
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 17 PAGES
07 52 00.00 28 1.5.6 GWind Uplift Resistance
1.5.5 GFire Resistance
SD-08 Manufacturer’s Instructions
3.3.5 GModified Bitumen Interply
Application
2.4 GModified Bitumen Membrane
Flashing 3.2.2.2Torches 2.7Primer
1.7 GCold Weather Installation
SD-10 Operation and Maintenance Data
2.3 GModified Bitumen Sheets
SD-11 Closeout Submittals
1.10 GWarranty
3.9 GInformation Card
3.8Instructions To Government
Personnel 07 56 00.10 28 SD-01 Preconstruction Submittals
1.5.3 GMinutes Of The Preroofing
Conference
1.5.3 GContractor's Extreme Weather
Emergency Plan
1.8.1 GSample Warranty
SD-02 Shop Drawings
1.9Membrane Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 17 PAGES
07 56 00.10 28 SD-03 Product Data
2.1 GFluid-applied membrane
2.3Membrane primer 2.5Elastomeric Sealant
SD-06 Test Reports
3.1.3 GAdhesion Testing
3.4.1 GMoisture Meter Testing
SD-07 Certificates
1.5.1 GQualification of Manufacturer
1.5.2 GQualification of Applicator
1.8.1 GSample Warranty
SD-08 Manufacturer’s Instructions 1.10Surface preparation, Primer, and
Fluid-applied membrane SD-10 Operation and Maintenance Data
2.1 GFluid-applied membrane
SD-11 Closeout Submittals
1.8.2 GWarranty
3.6Information Card 3.5Preventative Maintenance and
Care Instructions 07 60 00.00 28 SD-02 Shop Drawings
3.1.10 GGutters
3.1.11 GDownspouts
3.1.15 GExpansion Joints
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 17 PAGES
07 60 00.00 28 3.1.16 GFlashing at Roof Penetrations and Equipment Supports
3.1.18 GCopings
3.1.12 GEave Flashing
2.1Recycled Content
SD-03 Product Data
2.2.5 GCool Roof
2.2.8 GConcrete Splash Blocks
SD-04 Samples
1.5.2 GFinish Samples
SD-07 Certificates
2.2.4.2 GWarranty on Finishes
SD-08 Manufacturer’s Instructions
1.5.3 GInstructions for Installation
SD-10 Operation and Maintenance Data
1.5.3 GCleaning and Maintenance
07 61 14.00 28 SD-01 Preconstruction Submittals
1.7.1 GMinutes Of The Preroofing
Conference
SD-02 Shop Drawings
1.7.7 GRoofing System Shop Drawings
1.6 GIntermediate Support System
SD-03 Product Data
2.1 GSSMRS Roofing Panels
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 17 PAGES
07 61 14.00 28 2.1Energy Star Label for Steel Roofing Product
2.3Attachment Clips 2.2Intermediate Supports 2.4.1Closures 2.4Accessories 2.4.2Fasteners 2.4.3Sealants 2.5Insulation
1.8.1 GMetal Roof Panel Manufacturer
Warranty SD-04 Samples
2.1.3.2 GColor Chart
2.4Accessories 2.2Intermediate Supports
SD-05 Design Data
1.6 GDesign Calculations
SD-06 Test Reports 3.7Field Inspection 1.4.3Structural Performance 1.7.6Finish
SD-07 Certificates 1.7.3Manufacturer's Technical
Representative 1.7.4Installer's Qualifications
2.1 GCoil Stock
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 17 PAGES
07 61 14.00 28 2.1.1Recycled Content SD-08 Manufacturer’s Instructions
3.3 GRoof System Installation
SD-10 Operation and Maintenance Data
2.1 GSSMRS Roofing Panels
SD-11 Closeout Submittals
3.9 GInformation Card
1.8.1 GMetal Roof Panel Manufacturer
Warranty 07 72 00.00 28 SD-02 Shop Drawings
2.2 GRoof Access Hatch
SD-03 Product Data
2.2 GRoof Access Hatch
2.2.7 GHatch Guardrail System
2.3 GPrefabricated Insulated Roof
Curb SD-08 Manufacturer’s Instructions
2.2Roof Access Hatch 2.2.7Hatch Guardrail System 2.3Prefabricated Insulated Roof
Curb SD-10 Operation and Maintenance Data
1.7 GCleaning and Maintenance
SD-11 Closeout Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 17 PAGES
07 72 00.00 28 2.2.9 GRoof Access Hatch Warranty 07 92 00.00 28 SD-03 Product Data
2.1 GSealants
2.2 GPrimers
2.3 GBond Breakers
2.4 GBackstops
2.5 GCleaning Solvents
3.1 GField Adhesion
08 11 13.00 28 SD-02 Shop Drawings
2.1 GDoors
2.4 GFrames
SD-03 Product Data
2.1 GDoors
2.4 GFrames
SD-04 Samples
2.7 GFactory-applied Enamel Finish
SD-10 Operation and Maintenance Data
1.5 GAdjustments, Cleaning, and
Maintenance
08 71 00.00 28 SD-02 Shop Drawings
1.4 GManufacturer's Detail Drawings
1.4 GVerification of Existing Conditions
1.6 GHardware Schedule
SD-03 Product Data
2.2 GHardware Items
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 17 PAGES
08 71 00.00 28 SD-08 Manufacturer’s Instructions 3.1Installation
SD-10 Operation and Maintenance Data
1.6 GHardware Schedule
08 91 00.00 28 SD-02 Shop Drawings
1.5 GWall Louvers
SD-03 Product Data
2.2 GMetal Wall Louvers
SD-04 Samples
1.6 GWall Louver Samples
22 00 00 SD-03 Product Data
1.6Welding
2.1 G EDSPipe
2.1 G EDSPipe Fittings
2.3.1Roof Drains 2.3.1.1Replacement Roof Drain
Strainers 2.3.1.2Overflow Clamping Ring
SD-06 Test Reports
3.2TESTS
26 41 00 SD-02 Shop Drawings
1.5.1 GDrawings
SD-06 Test Reports
1.5.3 GLightning Protection and
Grounding System Test Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 17 PAGES
26 41 00 3.5.2 GGrounding Systems Testing SD-07 Certificates
1.5.2 GComponent UL Listed and
Labeled
1.5.4 GLightning Protection System
Inspection Certificate
3.1.1.1 GRoof Manufacturer's Warranty
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
| W912P825R0005 AM_0006.pdf |
| Am_0005__NOD Building Roof Replacement_Ed 24-017.pdf |
| Am_0005_NOD Building Roof Replacement_Ed 24-017 |
| 01 33 00_SUBMITTAL REGISTER |
File details come from the government source that posted it. Updated .