Answers to Questions 23Q0007.pdf
PDF 511 KB Posted
- Attached to
- TOWBOATS KENT & BIENVILLE DRY DOCK REPAIRS 2023
- Solicitation number
- W912P823Q0007
About this file
This document contains a request for quote for drydock repairs to two towboats, the Kent and Bienville, along with answers to questions from potential offerors. The U.S. Army Corps of Engineers, New Orleans District seeks a firm fixed-price contract to drydock the towboats at a facility within 175 miles of New Orleans by November 15, 2023, and complete repairs within 60 days per vessel. Offerors must demonstrate the availability and capacity of drydock facilities to handle the towboats, as well as satisfactory past performance on similar marine vessel repair contracts within the last three years. Proposals will be evaluated on technical acceptability, past performance, and price. The low-priced technically acceptable offer with satisfactory past performance will be selected for award. Proposals are due by June 21, 2023 and should be emailed to the address provided. This is a small business set-aside.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. The RFQ indicates a 45 calendar day completion for both vessels.
Looking at the scope of work we would like to request 120 calendar days per vessel for completion.
The government will extend the period of performance to 60 days per vessel.
2. The RFQ also indicates 21 days for completion of each vessel to be done consecutively Table 4.2.1 will be amended to 60 days per vessel.
Can the RFQ be modified to 120 calendar days for completion of each vessel, and can we work on the vessels concurrently and on the same drydock?
The government will extend the period of performance to 60 days per vessel.
The vessels cannot be worked on concurrently.
3. The RFQ indicates lead based paint is present and any repair pricing will have to cover the cost of possible lead abatement, cleaning, gas freeing, interference removals/replacements, scaffolding, etc.
Can we include exclusions in bid submittal making these unknowns subject to contract modifications?
No.
4. Can the bid due date be extended to July 6th?
Yes.
5. We haven’t found drawing 111-1013 Superstructure for the Kent.
Would it be possible to get this drawing?
Yes. Document is uploaded.
6. Item 2.25 Replacement of Main Engine Daily Service Tanks.
Are these part of the fuel system or the cooling system?
Cooling system.
7. Item 2.22 Port Engine Room Fan Replacement.
Are there any specs for this fan so we can accurately price?
No specs are available.
8. Item 2.8 Bearing Replacement.
Are these bearings press fit or poured in chock fast.
Epoxy filler (chock fast).
9. Item 3.15 Watertight Doors.
Are we cropping out the door frames or just hanging new doors?
Hanging new doors.
10. Item 3.19 Exhaust System Do you have any drawings or specs indicating pipe sizes and silencer specs?
Depending on the silencer models these long lead items.
This is the available information:
Port generator - Maxim M31 6” Marine Engine/Wet Exhaust Silencer (file from 2017).
Engines - Manufacturer: Riley Beard, model 3”M51 and 6”M31 Maxim (original silencers).
11. Item 3.19 Steering Linkage.
Do you have Shop Bill Sheets 76, 77 and 78?
Yes. Documents have been uploaded.
12. How much fluid will be in each of the tanks on both vessels upon delivery to the shipyard?
Kent – Fuel: 2k gallons, Water: 500 gallons Bienville – Fuel: 2k gallons, Water: 500 gallons
13. Items 2.9 and 3.9 Main Engine Alignment.
Do you have the make and model of the main engines and reduction gears for each vessel?
2.9 - Detroit Diesel 16V149NA marine engines; Twin Disc MG-540
3.9 – John Deere, PowerTech 12.5 L Engine, Model: 6125AFM75; Twin Disc MG-514