W912P823B0062 Amend 0002.pdf
PDF 405 KB Posted
- Solicitation number
- W912P823B0062
About this file
This document is an amendment to a federal solicitation providing revised estimated quantities for job items for the West Shore Lake Pontchartrain, LA Hurricane and Storm Damage Risk Reduction Project. The U.S. Army Corps of Engineers Engineering District New Orleans seeks bids for work including mobilization, temporary retaining structures, excavation, fill, bracing, traffic control, silt fencing, concrete floodwalls, drainage structures, fencing, piling, dewatering, embankment, geotextiles, clearing, canal excavation, preloading, wick drains, riprap, surfacing, seeding, lime, culverts, stoplogs, gates and various other items. Bidders are to use the revised estimated quantities provided in the amendment for their price proposals. The response date remains unchanged.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912P823B0062
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for West Shore Lake Pontchartrain, LA, Hurricane and Storm Damage Risk Reduction Project, WSLP 105, Perrilloux Drainage Structure, and Levee, St. John the Baptist Parish, LA has been amended to:
a) Provide answ ers to prior submitted questions.
b) Provide revised estimated quantities for Job Items.
1. CONTRACT ID CODE PAGE OF PAGES
1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Aug-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P823B0062
X 9B. DATED (SEE ITEM 11)
01-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Aug-2023
CODE
CONTRACTING DIV-PROJ EAST BR
CORPS OF ENGINEERS 7400 LEAKE AVENUE
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
00010-2 Ed 19-024
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0002
*Questions are numbered sequentially across all amendments
29. Question: Please extend the bid date by a week to allow adequate time following a Federal
Holiday to receive material and subcontractor quotes and prepare the bid package. It is understood that these projects must be awarded by the end of the fiscal year, but previous WSLP projects of smaller scope and magnitude have been extended several weeks past the original bid date.
Response: The bid submission date remains unchanged.
30. Question: How many stop logs are required on this project? Note 4 on Sheet S-108 calls for 6 stop logs to be furnished. The elevation of the stop logs on sheet S-108 shows them to be 3’- 6” tall. However, Amendment 1, “Job Quantities” on page 7 of 14 of the amendment states the requirements for 12 stop logs with a height of 3’-0” tall.
Please confirm the correct number and height of stop logs required on this project.
Response: The plans are correct. There are 6 stoplogs, each 3’-6” tall.
31. Question: Please review the take off quantities for CLIN 0006 Reinforced Concrete
Floodwall. The “Job Quantities” provided in Attachment 1 of Amendment 1 appear incorrect.
Our take off totals Stabilization Slab – 62 CY, Base Slab – 533 CY and T Wall Stems – 502 CY. It appears the Government’s take off is for 6 monoliths but this project has 8 monoliths.
We request corrections be issued to the estimated quantities given.
Response: See attached revised job item quantities.
32. Question: Please review the take off quantities for CLIN 0007 Reinforced Concrete Drainage
Structure. Our take off finds the wing wall base slabs are off by more than 20 CY. Also, there is no mention of any elevated slabs on the drainage structure which is approximately 160 CY.
We request corrections be issued to the estimated quantities given.
Response: See attached revised job item quantities. The quantity for walls includes the elevated slabs (160 CY elevated slabs and 475 CY walls for a total of 635 CY).
00010-3 Ed 19-024
33. Question: Please confirm the coating requirements for the steel sheet piling and steel h-piling in the Drainage Structure and its wing walls. There is no mention on these items in the table in section 09 97 02.01 12 Paragraph 3.5.
Response: No paint is required for drainage structure and wing wall h-piles and sheet piles.
34. Question: The steel grating is called out as 3” thick but contract drawing clearly calls this out as 2” grating. Is this a typo?
Response: 2” grating is correct.
35. Question: Aluminum stairs – 1 each is called out, however the only stairway shown on the contract drawings is the galvanized stairway shown on S-609.
Please clarify.
Response: There is only one set of stairs, which is shown on S-609 and S-610. The stairs are to be galvanized.
36. Question: Referencing the ladder quantity shown on S-607. Under the “Interior Access
Detail” it shows (12 required), but the plans only show 8.
Please clarify.
Response: The note on S-607 should read “8 required”.
00010-4 Ed 19-024
SECTION 00010 – BIDDING
SCHEDULE
Revised Estimated Quantities for Job Items Amendment 0002
Item DESCRIPTION Estimated Quantity
Unit Unit Price Estimated Amount
0001 Mobilization and Demobilization 1 JOB
0002 Temporary Retaining Structures 1 JOB
Piling, Steel Sheet, Type PZ-27 15,810 SF
Excavation 2,400 BCY
Sand Fill 3,600 TON
Steel Bracing, W30x191 Waler 200 LF
Steel Bracing, W27x164 Waler 140 LF
Steel Bracing, 18” Dia. Pipe 210 LF
Steel Bracing, 12” Dia. Pipe 115 LF
0003 Traffic Control and Coordination 1 JOB
0004 Silt Fence 700 LF
0005 Truck Wash-Down Racks 1 JOB
0006 Reinforced Concrete Floodwall 1 JOB
T-Wall Stabilization Slab 51 CY
T-Wall Base 533 CY
T-Wall Stem 502 CY
Water Stops 163 LF
0007 Reinforced Concrete Drainage Structures
1 JOB
Stabilization Slab 35 CY
Base 315 CY
00010-5 Ed 19-024
Walls 635 CY
Wing Wall Stabilization Slab 11 CY
Wing Wall Base 96 CY
Wing Wall Stem 75 CY
Water Stops 120 LF
Concrete Barrier Railing 30 LF
0008 Miscellaneous Metals 1 JOB
Aluminum Handrail 235 LF
Steel Ladders 90 VLF
Steel Grating (1 ½” Thick) 331 SF
Steel Grating (2” Thick) 92 SF
Hatches 8 EA
Stairs 1 EA
0009 Separator Geotextile 36,400 SY
0010 Reinforcement Geotextile (Reach 105-1)
84,000 SY
0011 Reinforcement Geotextile (Reach 105-3)
35,000 SY
0012 Clearing and Grubbing 1 JOB
Heavy Clearing and Grubbing 21 AC
Medium Clearing and Grubbing 71 AC
Light Clearing and Grubbing 68 AC
0013 Excavation, Drainage Canals 1 JOB
Interior Drainage Canals 193,200 BCY
Exterior Drainage Canals 1,000 BCY
Perrilloux Drainage Canal 7,800 BCY
Temporary Bypass Canal 6,200 BCY
00010-6 Ed 19-024
0014 Construction Dewatering 1 JOB
0015 Embankment, Compacted Fill 547,000 CY
0016 Sand Fill
0016AA First 336,000 TONS 336,000 TON
0016AB All Over 336,000 TONS 84,000 TON
0017 Soil Pre-Loading 1 JOB
Embankment 18,140 ECY
Sand 1,500 TON
0018 Vertical Wick Drain Installation 5,936,324 LF
0019 Horizontal Strip Drain Installation 401,192 LF
0020 Grouted Riprap 850 CY
0021 Piling, Steel Sheet, Type PZ-22 19,775 SF
Furnish 14"x14" Precast Concrete Piling 816 LF
Drive 14"x14" Precast Concrete Piling 816 LF
0024 Furnish HP14x73 Steel Piles 22,560 LF
0025 Drive HP14x73 Steel Piles 22,560 LF
0026 Surfacing
0026AA First 11,200 TON 11,200 TON
0026AB All Over 11,200 TON 2,800 TON
0027 Chain Link Fences and Gates 1 JOB
Chain Link Fences 110 LF
Chain Link Gates 4 EA
Drainage Structure Access Bridge
1 JOB
14’-8” x 20’ (14” Thick) Precast Bridge Panels 594 SF
14’-8” x 15’ (14” Thick) Precast Bridge Panels 490 SF
Concrete Barrier Railing 140 LF
24” x 28” Concrete Pile Bent 11 CY
0029 Seeding and Mulching 60 AC
00010-7 Ed 19-024
0030 Fertilizer
0030AA First 2,700 LBS 2,700 LBS
0030AB All Over 2,700 LBS 1,200 LBS
0031++ Lime Soil Amendment 60 TON
0032++ Sulfur Soil Amendment 30 TON
60-Inch CMP Culvert Installation 1 JOB
60-Inch CMP Culvert 665 LF
60-Inch CMP Culvert Bedding 405 TON
72-Inch CMP Culvert Installation 1 JOB
72-Inch CMP Culvert 525 LF
72-Inch CMP Culvert Bedding 405 TON
0035 Stoplogs 1 JOB
Stoplogs 6 EA
0036 Slide Gates and Hoists 1 JOB
10’x10’ Slide Gates and Hoists 4 EA
0037 Riprap 340 TON
0038 R-90 Riprap 420 TON
0039 Riprap Bedding 90 TON
TOTAL: $
(End of Summary of Changes)