W912P823B0044 Amend 0003.pdf
PDF 964 KB Posted
- Solicitation number
- W912P823B0044
About this file
This modification to solicitation W912P823B0044 provides updated plans and specifications, answers to prior questions, and extends the bid submission date to August 16, 2023 for the West Shore Lake Pontchartrain, LA Hurricane and Storm Damage Risk Reduction Project WSLP-108. The U.S. Army Corps of Engineers, New Orleans District, seeks bids to construct T-walls and drainage structures in St. John the Baptist Parish, Louisiana. Work includes reinforced concrete floodwalls, drainage structures, miscellaneous metals, geotextiles, excavation, embankments, piling, and other items. The solicitation includes base work and two optional items related to additional drainage structures and interior canal work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1
1. CON1RACTID CODE
I
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISillON/PURCHASE REQ. NO.
5. PROJECTNO.(Ifapplicable) 0003 02-Aug-2023
6.ISSUEDBY CODE VV912P8 7. ADMINISTERED BY (Ifother than item6) CODE I
CONTRACTING DIV-PROJ EAST BR
See Item 6 CORPS OF ENGINEERS 7400 LEAKE AVENUE
NEW ORLEANS LA 70118-3651
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, Cmmty, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
VV912P823B0044
X 9B. DATED (SEE ITEM 11)
22-Jun-2023 l0A. MOD. OF CONTRACT/ORDER NO.
l0B. DATED (SEE ITEM 13)
CODE IFACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
�The above nuni>ered solicitation is ammded as set li,rth in Item 14. The hour and date specified fur receipt ofO:lli,r 0 is extended, □ is not extended.
O:lli,r nnst acknowledge receipt of this ammdmmt prior to the hour and date specified in the solicitation or as ammded by one ofthe i>llowing mothods:
(a) By col1J)leting Item, 8 and 15, and returning 1 copies of the ammdmmt; (b) By acknowledging receipt of this ammdmmt on each copy of the o:lli,r submtted;
or(c)By separate letter or telegramwhich includes areli:rence to the solicitation and ammdmmt nuni>ers. FAILURE OF YOUR ACKNOWLEDGMENTTO BE RECEIVED AT 1HE PLACE DESIGN A TED FOR 1HE RECEIPT OF OFFERS PRIOR TO 1HE HOUR AND DA TE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER Ifby virtue of this ammdmmt you desire to change an o:lli,r already submtted, such change may be 1111de by telegram or letter, provided each telegram or letter !lllkes rei:rence to the solicitation and this ammdmmt, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS"ORDERS.
IT MODIFIES THE CONTRACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (�ecify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM l0A.
B. THE ABOVE NUMBERED CONTRACT /ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENT AL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER(�ecify type ofmodification and authority)
E. IMPORT ANT: Contractor D is not, □ is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT /MODIFICATION (Organized by UCF section headings, including solicitation/contract sul:!ject matter \\here feasible.)
The above nurrt>ered Solicitation for West Shore Lake Pontchartrain, LA, 1-llrricane and Storm Damage Risk Reduction A"oject, VIISLP- 108, T-Wall and Drainage Structure, St. John the Baptist Parish, Louisiana has been amended to:
a) A"ovide updated plans and specifications.
b) A"ovide answers to prior subrritted questions.
c) All questions are due NL T 11 :00AM CST on Aug 04, 2023
e) Bid submission date changed to 16 Aug 2023 at 1 :30RIII CST. A"ovide Virtual Bid opening instructions.
Except as provided herein, all temE and conditions of the docum,nt rei:renced in Item9A or I 0A, as heretofure changed, rermins unchanged and in full furce and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
TEl
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
30-105-04
16C. DATE SIGNED
02-Aug-2023
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR(48 CFR) 53.243
W912P823B0044
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
VIRTUAL BID OPENING DETAILS:
Join from the meeting link https://usace1.webex.com/usace1/j.php?MTID=mfc151d26d44ddf5797279b0a3bb590c4
Meeting number (access code): 2764 176 5438 Meeting password: Y2WfuCw36D@
Join by phone +1-844-800-2712 US Toll Free +1-669-234-1177 US Toll https://usace1.webex.com/usace1/j.php?MTID=mfc151d26d44ddf5797279b0a3bb590c4
RESPONSES TO QUESTIONS:
*Questions are continuous amoung all amendments
16. Question: Plan sheet D-505, detail 5 is the seal plates for the stop logs. Can more details be given on the gusset size and spacing as well as the anchor bolt spacing?
Response: This is to be contractor designed.
17. Question: Please provide the Government’s estimated quantities for job items.
Response: See attached job item quantities.
18. Question: How is the removal and disposal of muck from the required backfilling of the existing Mississippi Bayou and temporary Mississippi Bayou measured and paid?
Response: No separate measurement and payment will be made for mud/muck removal.
Payment for mud/muck removal shall be included in the contract item for which the work is incidental thereto.
19. Question: Please provide specification section for the electrical work required on plan sheet E- 001.
Response: Section 35 20 16.54 Slide Gates and Hoist.
20. Question: When will we receive the results from the “sister pile load tests” per response no. 5 in amendment 1?
Response: The sister site for WSLP 108 is the Reserve Relief site. Pile driving is underway but no testing has been performed yet, our estimate is 2-3 months for results.
21. Question: Section 31 62 16.16 -3.3.1.1 states only 2 test piles (hp14x73) will be subject to PDA monitoring, but the response to question 4 states a total of 4 PDA test piles please clarify.
Response: There should be 2 PDA test piles per pile depth, for a total of 4. The specification will be revised to clarify this.
22. Question: Addendum 0001 reduced the contract duration to 854 calendar days. Specification section 00010, note 7 provides 36 calendar days for OW1 and 188 calendar days for OW2.
Please confirm that if optional work is awarded, the total contract duration is 1,078 calendar days and not 854 calendar days.
Response: Yes, if both options are awarded the contract duration will be 1,078 calendar days.
23. Question: There are currently four West Shore projects solicitations, two bidding at the same time on 8/1, one bidding on 8/8, and one bidding on 8/9. Three of these projects are small business set-asides. Please consider spreading these projects out, where only one bids a week.
This would allow small businesses to be more competitive on all of the West Shore projects and provide the Government a lower overall project cost.
Response: Please see this SF30.
24. Question: Will the contractor be allowed payment for material stored offsite on h-piles, sheet piles, slide gates, stop logs, and the permanent precast concrete bridge?
Response: H-piles and sheet piles can be stored off site. The remainder cannot. Specification
Section 01100 will be revised.
25. Question: Specification section 01 53 00.02 12, paragraph 2.1 states “The sheet pile shall be hot rolled sheet pile as defined in Section 31 41 16.00 12 Steel Sheet Piling”. Are the temporary retaining structures sheet piles required to be new in accordance with section 31 41 16.00 12?
Response: This should be per the licensed engineer of record. However, the sheet piles shall be hot rolled.
26. Question: Drawing C-403 depicts 9 each 5’ diameter culverts at the existing temporary bypass canal culvert crossing which is required to be removed by this contract. The WSLP-107 project consisted of 10 each 5’ diameter culverts. Please clarify and provide an updated drawing so the items to be removed can be accurately determined.
Response: The drawing should show 10 each 5’ diameter culverts to match WSLP-107. The revised sheet C-403 is attached.
27. Question: Will the existing base for the temporary bypass canal culvert crossing consisting of the sand, limestone, and geotextile be required to be removed along with the culverts, which will require dewatering?
Response: Yes.
28. Question: Please provide a breakdown of all lump sum CLINs.
Response: See attached job item quantities.
29. Question: We request a bid opening extension.
Response: Please see this SF30.
SECTION 01100
Page 28. At the end of paragraph 33, add the following new paragraph as:
"34. PAYMENT FOR MATERIALS STORED OFFSITE
Pursuant to the FAR clause 52.232-5, PAYMENTS UNDER FIXED PRICED CONSTRUCTION CONTRACTS, materials delivered to the Contractor at locations other than the site of the work may be taken into consideration in making progress payments if included in invoices for payment estimates and if all the conditions of the Contract Clauses are fulfilled. Payment for items delivered to locations other than the work site shall be limited to materials that have been approved (if required by the Technical Specifications) and fabricated to the point where they are identifiable to an item of work required under this contract. Such payment shall be made only after receipt of paid or receipted invoices or invoices with canceled check showing title to the items by the prime contractor. These invoices must show the dollar value of the materials and labor incorporated into them. The delivery size shall be acceptable to the Government and the materials shall be available for inspection by the Government prior to any consideration for payment. Refer to FAR clauses 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS, and 52.236-7 PERMITS AND RESPONSIBILITIES regarding the Contractor’s retention of risk and liability for any loss or damage prior to incorporation of materials into the permanent work and acceptance. Payment for materials delivered offsite is limited to the following items: H-piles and sheet piles."
SECTION 31 62 16.16
Page 15, subparagraph 3.3.1.1. Delete this subparagraph in its entirety and substitute the following, therefore:
"3.3.1.1 Dynamic Pile Analysis
Submit a Pile Performance Report summarizing dynamic test results for test piles within 5 calendar days of completing field work.
Dynamic testing provides supplemental information for evaluating pile integrity, hammer and drive system performance, assess pile installation driving stresses, and pile capacities. dynamic testing will validate the dynamic testing results previously performed for the production piles at the Reserve relief canal location located at Northing 585150, Easting 353125. These results may require adjustments to the pile lengths. The pile load testing at the Reserve Relief canal included both static and dynamic load tests with the results used to determine the pile bid quantities. There will be two PDA tests per pile depth for two depths, resulting in four total PDA test piles. For estimating purposes assume the piles will be driven to el. -83 and to el. -73 at the locations indicated. The actual PDA test pile tip elevations will be based on the results of the pile load test program currently in progress. Perform dynamic testing on the HP14X73 test piles during the full length of the pile driving and during restrike a minimum of 14 days after initial driving. Upon completion of testing, the test piles can be pulled and reused as production piles provided that they are cleaned, painted and are in satisfactory condition as determined by the Contracting Officer's representative. Provide equipment to obtain dynamic measurements, record, reduce and display its data that meet the requirements of ASTM D4945. The equipment must have been calibrated within 6 months prior to the start of the testing operations and thereafter throughout the contract duration. Drive test piles at the locations indicated or at the locations selected by the Contracting Officer. Employ an independent inspection firm, hereinafter referred to as the Contractor's Geotechnical Consultant, experienced in the pile driving process, monitoring of test pile installation, and in the use of the Pile Driving Analyzer and its related equipment. Perform dynamic pile analysis as follows:"
DRAWINGS
SHEET IDENTIFICATION Nos. C-403. Delete this drawing in its entirety and substitute the attached revised drawing SHEET IDENTIFICATION Nos. C-403, therefore.
R E
V
IS
E D
C U
L V
E R
T A
N D
C R
O S
S
IN
G D
E T
A
IL
S
/2
/2
N O
R T
H P
L A
N
CANAL. PLEASE SEE SHEET C-404 FOR BACKFILL REQUIREMENTS.
IT SHALL BE THE RESPONSIBILITY OF THE WSLP-108 CONTRACTOR TO BACKFILL THE TEMPORARY BYPASS3.
PROJECT SITE.
SHALL VERIFY THE WSLP-107 CONTRACTOR NO LONGER REQUIRES THE CROSSING FOR ACCESS TO THEIR CONTRACTOR. PRIOR TO REMOVAL OF THE TEMPORARY BYPASS CROSSING, THE WSLP-108 CONTRACTOR CONTRACTOR. USE OF THE TEMPORARY BYPASS CROSSING SHALL BE SHARED WITH THE WSLP-107 REMOVAL OF THE TEMPORARY BYPASS CROSSING SHALL BE THE RESPONSIBILITY OF THE WSLP-108 2.
CONTRACOR AND ARE SHOWN FOR INFORMATIONAL PURPOSES ONLY.
THE TEMPORARY BYPASS CANAL AND CROSSING HAVE BEEN PREVIOUSLY CONSTRUCTED BY THE WSLP-1071.
NOTES:
C-403
H -8
-4
C -4
.d g n
10' 20'0
10' 20'0
D E
T A
IL
S
E X
IS
T
IN
G
T E
M P
O R
A R
Y B
Y P
A S
S C
A N
A L
C R
O S
S
IN
G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
S U
B M
IT
T
E D
B Y
C H
E C
K E
D B
Y
D R
A W
N B
Y
D E
S
IG
N E
D B
Y
C O
N T
R A
C T
N O
S O
L
IC
IT
A
T
IO
N N
O
IS
S
U E
D A
T E
S I Z
E
M A
R K
D E
S C
R
IP
T
IO
N D
A T
E
SHEET ID
®of Engineers
US Army Corps
N E
W O
R L
E A
N S
L A
L
E A
K E
A V
E N
E W
O R
L E
A N
S D
IS
T
R
IC
T U
.S A
R M
Y C
O R
P S
O F
E N
G
IN
E E
R S
F
IL
E N
A M
E
F
IL
E N
U M
B E
R
Z X
X X
X X
X X
X X
X X
A N
S I
D
S T
A
T O
M
IS
S
IS
S
IP
P I
B A
Y O
U D
R A
IN
A
G E
S T
R U
C T
U R
E A
N D
L E
V E
E W
S L
P
R M
H
H U
R R
IC
A
N E
A N
D S
T O
R M
D A
M A
G E
R
IS
K R
E D
U C
T
IO
N P
R O
J E
C T
W E
S T
S H
O R
E L
A K
E P
O N
T C
H A
R T
R A
IN
L
A
L J P
H J D
L J P
M E
T A
IR
IE
L
A
Z
E N
IT
H
A V
E
C O
N S
U L
T
IN
G E
N G
IN
E
E R
S
A
IM
S G
R O
U P
I N
C
H -8
-4
S T
J O
H N
T H
E B
A P
T
IS
T P
A R
IS
H
L
A
J U
L Y
W P
B
C/L TEMPORARY BYPASS CANAL
CRUSHED STONE ACCESS ROAD
CULVERT (TYP.)
(10) 5.0' DIA. CMP
SEPARATOR GEOTEXTILE FABRIC
SAND BACKFILL
#610 LIMESTONE BEDDING
INV. ELEV. -5.0 (TYP.)
GROUND ELEVATION
APPROXIMATE EXISTING
12" MIN. OVERLAP
SEPARATOR GEOTEXTILE FABRIC WRAP
68'-0"
1'-6" (MIN.)
M
IN
M
IN
BSECTION
ELEV. +5.00
EMBANKMENT, COMPACTED FILL
C
L A
Y C
A P
SCALE: 1" = 10'
C/L ACCESS ROAD
6H:1 V
40H:1V 40H:1V
6H:1V
SAND FILL
FABRIC
GEOTEXTILE
SEPARATOR
ACCESS ROAD
CRUSHED STONE
1' CLAY CAP (TYP.)
#610 LIMESTONE BEDDING
GROUND ELEVATION
APPROXIMATE EXISTING
M
IN
A
M
IN
SECTION
ELEV. +5.00
EMBANKMENT, COMPACTED FILL
CULVERTS (TYP)
(10) 5.0' DIA. CMP
30'-0"
(TYP.)
INV. ELEV. -5.0
SCALE: 1" = 10'
INV. ELEV. -5.0(TYP)
B
B
ACCESS ROAD
C/L TEMPORARY
ELEV. +5.00
A
20' 40'0
A
SCALE 1" = 20'
BYPASS CANAL
C/L TEMPORARY
EXISTING TEMPORARY BYPASS CANAL CROSSING PLAN
30'-0"
OVERLAP
FABRIC WRAP 12" MIN.
SEPARATOR GEOTEXTILE
00010-1 Ed 19-027
ESTIMATED QUANITIES ATTACHMENT
(NOT THE BID SCHEDULE)
Item DESCRIPTION Estimated Quantity
Unit Unit Price Estimated Amount
BASE WORK
0001 Mobilization and Demobilization 1 JOB
0002 Temporary Retaining Structures 1 JOB
Piling, Steel Sheet, Type PZ-27 15,810 SF
Excavation 2,200 BCY
Sand Fill 3,600 TON
Steel Bracing – W30x191 Waler 200 LF
Steel Bracing – W27x164 Waler 140 LF
Steel Bracing – 18”x3/4” Pipe 210 LF
Steel Bracing – 12”x5/8” Pipe 115 LF
0003 Traffic Control and Coordination 1 JOB
0004 Silt Fence 700 LF
0005 Truck Wash-Down Racks 1 JOB
0006 Reinforced Concrete Floodwall 1 JOB
Stabilization Slab 40 CY
Base 400 CY
Stem 365 CY
Water Stops 110 LF
Reinforced Concrete Drainage
1 JOB Structures
DS Stabilization Slab 35 CY
DS Base 315 CY
DS Walls 585 CY
00010-2 Ed 19-027
Wing Wall Stabilization Slab 9 CY
Wing Wall Base 76 CY
Wing Wall Stem 75 CY
Water Stops 120 LF
Concrete Barrier Railing 85
0008 Miscellaneous Metals 1 JOB
Aluminum Handrail 235 LF
Steel Ladders 90 VLF
Steel Grating (1-1/2” Thick) 331 SF
Steel Grating (3” Thick) 92 SF
Hatches 8 EA
Metal Stairs (EL. +6.0 to +17.9) 1 JOB
0009 Separator Geotextile 14,300 SY
0010 Reinforcement Geotextile 13,000 SY
0011 Clearing and Grubbing 1 JOB
Heavy Clearing and Grubbing 0.77 AC
Medium Clearing and Grubbing 25.02 AC
Light Clearing and Grubbing 26.81 AC
Removal of Existing Structures 1 LS
Removal of 60-Inch CMP Culvert 1 LS
0012 Excavation, Drainage Canals 1 JOB
Interior Drainage Canals 66,800 BCY
Exterior Drainage Canals 1,000 BCY
Discharge Canal 6,900 BCY
0013 Construction Dewatering 1 JOB
0014 Embankment, Compacted Fill 115,000 CY
0015 Sand Fill
0015AA First 74,000 TON 74,000 TON
0015AB All Over 74,000 TON 19,000 TON
00010-3 Ed 19-027
0016 Soil Pre-Loading 1 JOB
Embankment 15,600 ECY
Sand Fill 2,600 TON
0017 Vertical Wick Drain Installation 20,706 LF
Horizontal Strip Drain Installation 7,073 LF
0019 Grouted Riprap 495 CY
0020 Piling, Steel Sheet, Type PZ-22 11,760 SF
Furnish 14"x14" Square Precast Concrete Piling
840 LF
Drive 14"x14" Square Precast Concrete Piling
840 LF
0023 Furnish HP14x73 Steel Piles 13,420 LF
0024 Drive HP14x73 Steel Piles 13,420 LF
0025 Pile Driving Analyzer Testing 1 JOB
Pile Driving Analyzer Testing 4 EA
0026 Surfacing
0026AA First 4,500 TON 4,500 TON
0026AB All Over 4,500 TON 1,200 TON
0027 Chain Link Fences and Gates 1 JOB
Chain Link Fences 170 LF
Chain Link Gates 4 EA
Drainage Structure Access
1 JOB
Bridge
14’-8”x20’ Precast Bridge Panels 594 SF
14’-8”x15’ Precast Bridge Panels 490 SF
Concrete Barrier Railing 140 LF
24”x28” Concrete Pile Bent 11 CY
Single Thrie Beam 188 LF
Double Thrie Beam 100 LF
6”x8” Post Assembly 52 EA
Flared End Treatment 4 EA
00010-4 Ed 19-027
Terminal Connector 4 EA
6” Concrete Curb 54 LF
0029 Seeding and Mulching 14 AC
0030 Fertilizer
0030AA First 630 LBS 630 LBS
0030AB All Over 630 LBS 280 LBS
0031++ Lime Soil Amendment 14 TON
0032++ Sulfur Soil Amendment 7 TON
0033 Stoplogs 1 JOB
Stoplogs 12 EA
0034 Slide Gates and Hoists 1 JOB
Slide Gates and Hoists 4 EA
0035 Riprap 550 TON
0036 Riprap Bedding 90 TON
TOTAL BASE WORK: $
OPTIONAL WORK 1 (OW1)
0037 Separator Geotextile - OW1 2,700 SY
0038 Clearing and Grubbing - OW1 1 JOB
Medium Clearing and Grubbing 0.49 AC
Light Clearing and Grubbing 1.59 AC
Excavation, Drainage Canals -
OW1
Excavation, Drainage Canals –
OW1 3,100 BCY
Embankment, Compacted Fill -
OW1
2,100 CY
0041 Sand Fill - OW1 1,860 TON
0042 Surfacing - OW1 600 TON
72-Inch CMP Culvert Installation
– OW1
72-Inch CMP Culvert 525 LF
Bedding 405 TON
00010-5 Ed 19-027
0044 R-90 Riprap - OW1 420 TON
TOTAL OW1: $
OPTIONAL WORK 2 (OW2)
0045 Separator Geotextile – OW2 3,600 SY
Reinforcement Geotextile –
OW2
5,000 SY
0047 Clearing and Grubbing – OW2 1 JOB
Heavy Clearing and Grubbing 0.09 AC
Medium Clearing and Grubbing 8.09 AC
Light Clearing and Grubbing 10.48 AC
Excavation, Drainage Canals –
Interior Canal 22,700 BCY
Embankment, Compacted Fill –
34,000 CY
0050 Surfacing – OW2 1,200 TON
0051 Seeding and Mulching – OW2 5 AC
0052 Fertilizer
0052AA First 225 LBS 225 LBS
0052AB All Over 225 LBS 100 LBS
0053++ Lime Soil Amendment 5 TON
0054++ Sulfur Soil Amendment 2.5 TON
TOTAL OW2 $
TOTAL BASE WORK + OW1 + OW2 $
++Items not subject to the requirements of FAR 52.211-18 VARIATION IN ESTIMATED QUANTITY.
**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER
OMITS BOTH THE UNIT PRICE AND THE EXTENDED
| Am 0002 W912P823B0044_West Shore Lake Pontchartrain LA HSDRR Project WSLP 108 T-Wall and Drainage Structure St. John the Baptist Parish LA_Ed 19-027 (004).pdf |
| 34. PAYMENT FOR MATERIALS STORED OFFSITE |
| 3.3.1.1 Dynamic Pile Analysis |
File details come from the government source that posted it. Updated .