This solicitation package describes a requirements contract for stone repair and placement services along the banks of the Mississippi River in Southwest and South Passes in Louisiana. The solicitation will be issued as an invitation for bid resulting in an indefinite delivery/indefinite quantity, single award task order contract with a firm fixed price. The work includes placing various types of stone paving and repairs within the specified areas of the river. The contract value is estimated between $25 million and $50 million. The government will not provide paper copies of the solicitation and potential contractors must monitor the website for release and amendments. The Corps of Engineers Engineering District in New Orleans is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED 23-001
IFB NO. W912P8-23-B-0002
US Army Corps of Engineers New Orleans District
South & Southwest Pass, Mississippi River Indefinite Delivery-Indefinite Quantity Contract
2023 Stone Repair and Placement
Mississippi River Control Channels
Construction Solicitation and Specifications
9 May 2023
DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT
7400 LEAKE AVENUE
NEW ORLEANS, LA 70118-3651
ED 23-001
9 May 2023SOLICITATION: W912P823B0002
FOR: Flood Control, Mississippi River and Tributaries, Indefinite Delivery – Indefinite Quantity
Contract, 2023 Stone Placement, Mississippi River, South and Southwest Pass River Control
Channels TO OPEN: By Electronic Bid on June 8, 2023 at 09:00 AM Local Time
I. NOTE THE AFFIRMATIVE ACTION PROGRAM REQUIREMENT OF THE EQUAL OPPORTUNITY
CLAUSE WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS SOLICITATION.
II. NOTE THE CERTIFICATION OF NONSEGREGATED FACILITIES IN THIS SOLICITATION.
Bidders, offerors and applicants are cautioned to note the "Certification of Non-segregated Facilities" in the solicitation. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause.
III. Prospective contractors must register in the System for Award Management (SAM). See FAR Clause
52.204-7 for required information. The website for SAM is https://www.sam.gov. You will be required to provide your company’s Dun and Bradstreet (D&B) D-U-N-S number. If you do not already have a D&B
D-U-N-S number, one can be requested at http://fedgov.dnb.com/webform.
BIDDERS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS REQUIRED BY THIS
SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING FALSE STATEMENTS IN BIDS
IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of placing various types of stone paving and stone repairs along the banks of the Mississippi River SW Pass (between Miles 20.2 to 0.0 AHP) ans South Pass (between Miles 11.5 and 13.5).
CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time and for visitor background checks by MVN security when entering the installation at place of bid opening. Such delays DO NOT permit acceptance or consideration of late bids.
NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN ACCORDANCE WITH
THE PROVISIONS OF EM 385-1-1 "U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH
REQUIREMENTS MANUAL", DATED 30 NOVEMBER 2014.
https://www.sam.gov/ http://fedgov.dnb.com/webform
ALL INQUIRIES REGARDING THIS SOLICITATION
SHOULD BE MADE TO THE FOLLOWING:
JASON B. MEYERS
CONTRACT SPECIALIST
U.S. ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT
E‐MAIL: JASON.B.MEYERS@USACE.ARMY.MIL
Phone: (504) 862-1016
COLLECT CALLS NOT ACCEPTED
NOTE: ALL CONTRACTOR QUESTIONS IN WRITING THROUGH EMAIL
MUST BE RECEIVED BY 10:00 AM (CENTRAL), TUESDAY, 23 MAY 2023.
THE GOVERNMENT IS UNDER NO OBLIGATION TO PROVIDE A
RESPONSE TO LATE QUESTIONS.
FOR THE MOST PROMPT RESPONSE, PLEASE SEND ALL QUESTIONS VIA EMAIL.
ALL QUESTIONS MUST CONTAIN THE SOLICITATION NUMBER IN THE SUBJECT
LINE.
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE 8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
W912P823B0002
U.S. Army Corps of Engineer New Orleans District 7400 Leake Avenue NewOrleans, LA 70118-3651
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
South and Southwest Pass, Mississippi River, Indefinite Delivery – Indefinite Quantity Contract, 2023 Stone Placement, Mississippi River
This is an UNRESTRICTED procurement.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of placing various types of stone paving and stone repairs along the banks of the Mississippi River SW Pass (between Miles 20.2 to 0.0 AHP) and South Pass (between Miles 11.5 and 13.5).
The contract ceiling is $49,500,000.00 with a minimum guarantee of $10,000.00. Contract duration is 730 days from date of award.
** Performance and Payment Bonds and Notice to Proceed (NTP) w ill be received and issued on a task order basis. Each task order w ill have an individual period of performance which could, potentially, extend beyond the contract ordering period duration.
**ELECTONIC BID OPENING INSTRUCTIONS WILL BE ESTABLISHED BY AMENDMENT
U.S. Army Corps of Engineer, New Orleans
ATTN: CEMVN-CT-W
7400 Leake Avenue, Room 172 New Orleans, LA 70118
Jason Meyers
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
504-862-1016
6. PROJECT NUMBER
ED 23-001
05/9/2023 local time 06/7/2023
**6:00 pm x x
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Lafayette Area Office, U.S. Army Corps of Engineers 646 Cajundome Blvd, Suite 301 Lafayette, LA 70506
U.S. Army Corps of Engineers Finance Center 5722 Integrity Drive Millington, TN 38054-5005
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS
00010 Pricing Schedule 00100 Instructions to Bidders 00600 Representations and Certifications 00700 Contract Clauses 00800 Special Contract Requirements
DIVISION 01 - GENERAL REQUIREMENTS
01000 General Requirements 01100 General Provisions 01 33 00 Submittal Procedures 01 42 00 Sources for Reference Publications 01 45 00.15 10 Resident Management System Contractor Mode (RMS CM) 01 45 04.00 10 Contractor Quality Control 01 57 20.00 12 Environmental Protection 01 78 02.00 10 Closeout Submittals
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 31 19.01 12 Stone Placement
SECTION 00010 – PRICING SCHEDULE
Mississippi River, Baton Rouge to the Gulf of Mexico, Indefinite Delivery – Indefinite Quantity Contract, 2023 Southwest Pass and South Pass Stone Repairs Plaquemines Parish, Louisiana
DESCRIPTION Estimated Quantity Unit Unit
Price Estimated Amount
BASE WORK
0001 Mobilization and Demobilization 1 JOB
0002 Southwest Pass Foreshore Dike 2200 lb. Stone Repairs 80,000 TON
0003 Southwest Pass Jetty Stone A Repairs 6,000 TON
0004 South Pass Jetty Stone A Repairs 150,000 TON
TOTAL BASE WORK: $
OPTIONAL WORK (OW)
0005 Subsequent Mobilization and Demobilization - OW 1 JOB
0006 Southwest Pass Foreshore Dike 2200 lb. Stone Repairs - OW 100,000 TON
0007 Southwest Pass Jetty Stone A Repairs - OW 20,000 TON
0008 Southwest Pass Jetty Stone B Repairs - OW 10,000 TON
0009 South Pass Jetty Stone A Repairs -
OW 90,000 TON
0010 South Pass Jetty 2200 lb. Stone Repairs - OW 45,000 TON
0011 Flotation Channel Excavation - OW 40,000 CY
TOTAL OPTIONAL WORK: $
TOTAL BASE WORK + OPTIONAL WORK: $
NOTE 1: The award will be made as a whole to one offeror.
NOTE 2: Offerors shall furnish unit prices for each item listed in the Pricing Schedule requiring a unit price. If the offeror fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A OFFERORS OMIT BOTH THE UNIT PRICE AND THE EXTENDED TOTAL
OR ESTIMATED AMOUNT FOR ANY ITEM, ITS OFFER WILL BE DECLARED NON-
RESPONSIVE AND THEREFORE INELIGIBLE FOR AWARD.
NOTE 3: Any offer may be rejected if the Contracting Officer, in writing, determines that it is unreasonable as to price. Unreasonableness of price includes not only total price of the offer, but the price for individual line items as well. Any offer may be rejected if the prices for any line items or sub-line items are materially unbalanced.
NOTE 4: NOTICE OF AWARD/NOTICE TO PROCEED: The successful bidder is advised that performance and payment bonds will be submitted in accordance with the time frame in block 12B of SF 1442 after the Notice of Award. Performance and payment bonds will be required per individual task order. The Notice To Proceed will be issued immediately after verification of acceptable performance and payment bonds. A separate Notice To Proceed will be issued for each Task Order. Within 7 days after issuance of the Notice To Proceed, the Contractor will initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start on a first Task Order until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required have been submitted and approved and all preliminary meetings called for under the contract, have been conducted. Similarly, physical work cannot start on subsequent Task Orders until Task Order specific supplements to the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all Task Order specific preliminary meetings called for under the contract, have been conducted.
NOTE 5: OPTIONAL WORK ITEMS. The Government may require the delivery of the Optional Work items identified in the schedule in the quantities and prices stated in the schedule. If an Optional Work item quantity is exceeded, the overrun quantity will be paid for at the Optional Work item unit price stated in the schedule. The Contracting Officer may exercise the Optional Work by written notice to the Contractor within the two-year period of the contract. The Government will exercise the Optional Work in accordance with the Clause in Section 00700 CONTRACT CLAUSES entitled “OPTION FOR INCREASED QUANTITY-SEPERATELY PRICED LINE ITEM” (FAR 52.217-7, MAR 1989). Failure to bid on all items will result in a non-responsive bid.
NOTE 6: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
NOTE 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL WORK. In the event that the OPTIONAL WORK items are exercised under the terms of the contract, the time required for completion of the contract will not be adjusted but shall be performed concurrent with the original contract duration of 730 calendar days.
NOTE 8: Initial mobilization and demobilization costs will be paid for by the Government. Any subsequent mobilization and demobilization costs will be paid for by the Government provided that (a) the Contractor has completed all the work assigned in all the Task Orders issued and the Contractor has demobilized, or (b) the Government has suspended the Contractor and the Contractor has demobilized. Descriptions of the anticipated work is specified in Section 01100, paragraph entitled “LOCATIONS AND ANTICIPATED WORK”.
NOTE 9: Attention is directed to the Section 00700 CONTRACT CLAUSES entitled "ORDER LIMITATIONS" (FAR 52.216-19, Oct 1995) for Task Order limitations.
NOTE 10: Task Orders will be issued by electronic communications (e-mail or facsimile) by the Contracting Officer.
NOTE 11: All quantities are estimated and are to be used for evaluation purposes only.
Estimated quantities of individual contract line items may vary significantly either up or down depending on the work required during the two-year contract period as long as the earnings limitations of the contract are not exceeded. No adjustment will be made to the contract price under the VEQ clause (FAR 52.211-18) since this is an IDIQ contract. The VEQ clause is inserted only for the authority to adjust quantities in each Task Order through a modification.
NOTE 12: Any travel and lodging costs of Contractor personnel shall be considered in the Contractor’s pricing and shall be distributed among the individual Pricing Schedule line items.
NOTE 13: This Pricing Schedule is for evaluation purposes only to determine the lowest offeror.
NOTE 14: The unit “Job” as used in this Pricing Schedule is synonymous with the term “Lump Sum” used elsewhere within these plans and specifications.
NOTE 15: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;
http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx
BID BOND
(See instructions on reverse)
OMB Control Number: 9000-0045 Expiration Date: 8/31/2025
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
STATE OF INCORPORATION
SURETY(IES) (Name and business address)
PERCENT
OF BID
PRICE
PENAL SUM OF BOND
AMOUNT NOT TO EXCEED
MILLION(S) THOUSAND(S) HUNDRED(S) CENTS
BID IDENTIFICATION
BID DATE INVITATION NUMBER
PRINCIPAL
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1. 2.
2.
3.
3.
(Seal) (Seal) (Seal) Corporate Seal
INDIVIDUAL SURETY(IES)
SIGNATURE(S)
NAME(S)
(Typed)
1.
1.
2.
2.
(Seal) (Seal)
CORPORATE SURETY(IES)
SU
R
ET
Y
A
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is NOT usable
STANDARD FORM 24 (REV. 8/2016)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
FOR (Construction, Supplies or Services)
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
DATE BOND EXECUTED (Must not be later than bid opening date)
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.
JOINT VENTURE
OTHER (Specify)
PARTNERSHIPINDIVIDUAL
CORPORATION
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.
The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
SU
R
ET
Y
B
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
Corporate Seal
LIABILITY LIMIT ($)STATE OF INCORPORATION
2.
2.
1.
1.NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
C
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
D
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
E
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
F
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
G
STANDARD FORM 24 (REV. 8/2016) BACK
5/9/23, 11:38 AM SAM.gov https://sam.gov/wage-determination/LA20230005/3
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Mobilzation & Demobilization
FFP
FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 80,000 Net Ton
(2,000
LB).
Southwest Pass Foreshore Dike
FFP
2200 lb. Stone Repairs FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003 6,000 Net Ton
(2,000
LB).
Southwest Pass Jetty Stone A Repairs
FFP
FOB: Destination
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 150,000 Net Ton
(2,000
LB).
South Pass Jetty Stone A Repairs
FFP
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005 1 Job OPTION Mobilzation & Demobilization
FFP
Subsequent - OW FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0006 100,000 Net Ton
(2,000
LB).
OPTION Southwest Pass Foreshore Dike
FFP
2200 lb. Stone Repairs FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0007 20,000 Net Ton
(2,000
LB).
OPTION Southwest Pass Jetty Stone A Repairs -OW
FFP
FOB: Destination
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0008 10,000 Net Ton
(2,000
LB).
OPTION Southwest Pass Jetty Stone B Repairs -OW
FFP
FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0009 90,000 Net Ton
(2,000
LB).
OPTION South Pass Jetty Stone A Repairs
FFP
FOB: Destination
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0010 45,000 Net Ton
(2,000
LB).
OPTION South Pass Jetty 2200lb.Stone Repairs-OW
FFP
FOB: Destination
PSC CD: Y1PZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0011 40,000 Cubic
Yard OPTION Flotation Channel Excavation-OW
FFP
FOB: Destination
PSC CD: Y1PZ
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 12-JUN-2023 TO
11-JUN-2025
N/A USACE, CONTRACTING DIVISION
CHARLES R. ZAMMIT, JR.
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
504-862-1164 FOB: Destination
W912P8
0002 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
W912P8
0003 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0004 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0005 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0006 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0007 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0008 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0009 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0010 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
FOB: Destination
W912P8
0011 POP 12-JUN-2023 TO
11-JUN-2025
N/A (SAME AS PREVIOUS LOCATION)
W912P8 https://sam.gov/wage-determination/LA20230005/2 4/7
Section 00100 - Bidding Schedule/Instructions to Bidders
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-12 Preparation Of Bids APR 1984 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-29 Order Of Precedence--Sealed Bidding JAN 1986 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.222-5 Construction Wage Rate Requirements--Secondary Site of the
Work
MAY 2014
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
CLAUSES INCORPORATED BY FULL TEXT
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
(a) Definitions. As used in this provision--
Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
Federal contracts and grants with total value greater than $10,000,000 means--
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror ( ) has ( ) does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked “has” in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
4/21/23, 9:43 AM SAM.gov https://sam.gov/wage-determination/LA20230005/2 5/7
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in--
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).
(End of provision)
52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS--CERTIFICATION (NOV
2021)
(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial products and commercial services as defined in Federal Acquisition Regulation 2.101.
(b) Certification. [Offeror shall check either (1) or (2).]
____ (1) The Offeror certifies that--
(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; and
(ii) No entity owned or controlled by the Offeror has engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is https://sam.gov/wage-determination/LA20230005/2 6/7 available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; or
____ (2) The Offeror is providing separate information with its offer in accordance with paragraph (d)(2) of this provision.
(c) Procedures for reviewing the annual unclassified report (see paragraph (b)(1) of this provision). For clarity, references to the report in this section refer to the entirety of the annual unclassified report, including any separate reports that are incorporated by reference into the annual unclassified report.
(1) Check the table of contents of the annual unclassified report and the country section headings of the reports incorporated by reference to identify the foreign countries listed there. Determine whether the Offeror or any person owned or controlled by the Offeror may have engaged in any activity related to one or more of such foreign countries.
(2) If there may have been such activity, review all findings in the report associated with those foreign countries to determine whether or not each such foreign country was determined to be in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or to be not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. For clarity, in the annual report an explicit certification of non-compliance is equivalent to a determination of violation. However, the following statements in the annual report are not equivalent to a determination of violation:
(i) An inability to certify compliance.
(ii) An inability to conclude compliance.
(iii) A statement about compliance concerns.
(3) If so, determine whether the Offeror or any person owned or controlled by the Offeror has engaged in any activity that contributed to or is a significant factor in the determination in the report that one or more of these foreign countries is in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. Review the narrative for any such findings reflecting a determination of violation or non-adherence related to those foreign countries in the report, including the finding itself, and to the extent necessary, the conduct giving rise to the compliance or adherence concerns, the analysis of compliance or adherence concerns, and efforts to resolve compliance or adherence concerns.
(4) The Offeror may submit any questions with regard to this report by email to NDAA1290Cert@state.gov. To the extent feasible, the Department of State will respond to such email inquiries within 3 business days.
(d) Do not submit an offer unless--
(1) A certification is provided in paragraph (b)(1) of this provision and submitted with the offer; or
(2) In accordance with paragraph (b)(2) of this provision, the Offeror provides with its offer information that the President of the United States has--
(i) Waived application under U.S.C. 2593e(d) or (e); or
(ii) Determined under 22 U.S.C. 2593e(g)(2) that the entity has ceased all activities for which measures were imposed under 22 U.S.C.2593e(b).
(e) Remedies. The certification in paragraph (b)(1) of this provision is a material representation of fact upon which reliance was placed when making award. If it is later determined that the Offeror knowingly submitted a false https://sam.gov/wage-determination/LA20230005/2 7/7 certification, in addition to other remedies available to the Government, such as suspension or debarment, the Contracting Officer may terminate any contract resulting from the false certification.
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm-fixed price contract resulting from this solicitation.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
20-23% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
https://sam.gov/wage-determination/LA20230005/2 8/7
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Plaquemines Parish, LA.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be __twenty______ percent (20%) of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984)
The need for customary progress payments conforming to the regulations in Subpart 32.5 of the Federal Acquisition Regulation (FAR) will not be considered as a handicap or adverse factor in the award of the contract. The Progress Payments clause included in this solicitation will be included in any resulting contract, modified or altered if necessary in accordance with subsection 52.232-16 and its Alternate I of the FAR. Even though the clause is included in the contract, the clause shall be inoperative during any time the contractor's accounting system and controls are determined by the Government to be inadequate for segregation and accumulation of contract costs.
(End of clause)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall https://sam.gov/wage-determination/LA20230005/2 9/7 be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
US Army Corps of Engineers-New Orleans District Attn: Charles R. Zammit, Jr.
CEMVN-CT-W
7400 Leake Ave.
New Orleans, LA 70118-3651
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
a. Weather Conditions. Data on weather conditions may be obtained from the National Weather Service.
b. Conditions of Channel. Normally, ample width and depth of channel are available within the limits of the work to provide for normal navigation and to carry out the necessary construction operations.
c. Channel Traffic. Normal traffic of the river, consisting of self-propelled craft with or without tows, will pass the sites of the work.
d. Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army in accordance with the provisions of Section 7 of the River and Harbor Act of 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessels, to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles and other markers placed by him under the contract in the navigable waters or on shore.
e. Stage Hydrograph. Real time stage hydrograph data of the Mississippi River Basin may be obtained from the U.S Army Corps of Engineers, New Orleans District website at: http://rivergages.mvr.usace.army.mil/WaterControl/new/layout.cfm. The following staff gages shall be used for this contract. Historic hydrographic data provided does not constitute a prediction.
https://sam.gov/wage-determination/LA20230005/2 10/
Gage Name (ID) Location (Mile) MS River at Head of Passes (01545) -0.6 BHP (SP RDB) MS River SWP Mile 7.5 (01575) -7.5 BHP (SWP LDB) MS River SWP at East Jetty (01670) -17.9 BHP (SWP LDB) MS River SP at Port Eads (01850) -11.0 BHP (SP RDB)
f. Wharf Structures. Work will not be required beneath or landward of wharf structures that would interfere with ordinary construction methods or impede ordinary construction progress inherent in this type of work.
g. Existing Structures in Southwest Pass and South Pass. The attention of the Contractor is called to the existence of the Corps of Engineers’ dredging targets, oil pipelines and the U. S. Coast Guard’s navigation aids located in Southwest Pass and South Pass. The Contractor shall conduct his/her work in such a manner so as to not damage these structures.
NOTE: Hydrographic surveys of locations within the limits of work are available for inspection in the office of the Contracting Office.
(End of clause)
52.236-16 QUANTITY SURVEYS (APR 1984) - ALTERNATE I (APR 1984)
(a) Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.
(b) The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments are requested. All these surveys shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Government shall make such computations as are necessary to determine the quantities of work performed or finally in place. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested.
(c) Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The
Contractor shall retain copies of all such material furnished to the Contracting Officer.
(End of clause) https://sam.gov/wage-determination/LA20230005/2 11/
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
www.acquisition.gov
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFAR (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
Name: Mr. John Page Bradley Robinson Address: John.R.Page@usace.army.mil bradley.robinson@usace.army.mil Telephone: 337-291-3015 504-862-1194 https://sam.gov/wage-determination/LA20230005/2 12/
Section 00600 - Representations and Certifications
CLAUSES INCORPORATED BY REFERENCE
52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
252.203-7005 Representation Relating to Compensation of Former DoD Officials
SEP 2022
CLAUSES INCORPORATED BY FULL TEXT
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2022)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.
(2) The small business size standard is 45,000,000.00.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees if the acquisition--
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for…