This document is an amendment (AM0003) to a solicitation for the Port Fourchon Navigation Channel Maintenance Dredging #22-2 contract (W912P822B0031) in Lafourche Parish, Louisiana.
The key details are:
- The solicitation is being amended to provide government responses to a Request for Information (RFI). The bid opening date of May 8, 2024 remains unchanged.
- The amendment provides historical dredging limits and elevations for the navigation channel from 2008 to 2022.
- It clarifies that no survey data is available for the unconfined beach placement areas, and that the template for dredge fill placement is limited to elevation and shallow open water placement.
- It removes a confusing reference to the "top of bank of the shoreline" in the placement requirements.
- It notes that all work shall be performed in accordance with the new EM 385-1-1 "Safety and Occupational Health Requirements" dated March 15, 2024.
- The estimated value of the work is between $5,000,000 and $10,000,000. The procurement is unrestricted with a NAICS code of 237990.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED 22-010
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The subject Solicitation Port Fourchon Navigation Channel, Maintenance Dredging #22-2, Lafourche Parish, Louisiana (ED 22-010) is hereby amended to share Government responses to an RFI.
The bid opening, scheduled for 08 May 2024, remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822B0031
X 9B. DATED (SEE ITEM 11)
04-Aug-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
AM0003
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-May-2024
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P822B0031
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - SF 30 CONTINUATION
The following have been added by full text:
AM0003
Q1: Please provide all available history on the Port Fourchon Navigation Channel, Maintenance Dredging, as stated it may be requested in Section 35 20 23.00 12, Paragraph 3.1.6 CHARACTER OF MATERIALS “Dredging history of Port Fourchon is available on request.”
R1: See revised table below.
Limits Date Dredged Design Elevation Width Dimensions
C/L Sta. 200+00 to C/L Sta. 245+00
Oct 08 -27.0' MLG 300'
C/L Sta. 245+00 to C/L Sta. 290+00
Oct 08 -30.0' MLG 300'
C/L Sta. 200+00 to C/L Sta. 243+00
Mar 12 -27.0' MLG 300'
C/L Sta. 244+00 to C/L Sta. 272+00
Mar 12 -30.0' MLG 300'
C/L Sta. 60+00 to C/L Sta. 240+00
Aug 14 -27.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 265+00
Aug 14 -30.0' MLG 300'
C/L Sta. 60+00 to C/L Sta. 240+00 (non-continuous)
Sep 15 -27.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 250+00
Sep 15 -30.0' MLG 300'
C/L Sta. 233+50 to C/L Sta. 240+00
Jun 17 -27.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 270+81
Jun 17 -30.0' MLG 300'
C/L Sta. 155+00 to C/L Sta. 240+00
Mar 19 -27.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 313+00
Mar 19 -30.0' MLG 300'
C/L Sta. 200+00 to C/L Sta. 240+00
Feb 21 -26.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 275+00
Feb 21 -29.0' MLG 300'
W912P822B0031
C/L Sta. 60+00 to C/L Sta. 240+00 (non-continuous)
Oct 22 -27.0' MLG 300'
C/L Sta. 240+00 to C/L Sta. 260+00
Oct 22 -30.0' MLG 300'
Q2: Will USACE provide template and survey data for the unconfined beach placement for both east and west of the jetties?
R2: No survey data is available for the unconfined beach placement areas. Template for dredge fill placement is limited to elevation and shallow open water placement. No crown widths or side slopes are provided and these dimensions, if contractually required, would be resorted by the near shore environment. Slopes are Natural Angle of Repose (NAR).
Q3: Please define “shoreline” within Section 35 20 23.00 12, Paragraph 3.3.1.1 PLACEMENT OF DREDGED MATERIAL “The initial discharge shall begin approximately 300-feet east or west of the jetties and approximately 100-feet south of the top of bank of the shoreline.”
R3: Shoreline is the intercept of the beach to the Gulf. Location varies with tides. Fourth sentence of the paragraph with reference to top of bank for the shoreline is confusing and is removed with this amendment. Intent of the remaining paragraph and the notes in plan is to ensure near shore placement without direct placement on the beach (possible damage to vegetation).
In addition, there is a new EM 385-1-1 dated 15 March 2024. All work under these specifications shall be performed in accordance with the provisions of EM 385-1-1 "Safety and Occupational Health Requirements", dated 15 March 2024.