About this file

This abstract of offers summarizes bids received in response to Solicitation Number W912P822B0001 for flood control work. The U.S. Army Corps of Engineers Engineering District New Orleans is seeking bids for the Flood Control, Amite River and Tributaries, Comite River Basin, Comite River Diversion Project, Cypress Bayou Rock Chute. The 100% small business set aside opportunity involves mobilization, safety fencing, traffic control, excavation, fill, geotextiles, clearing, dewatering, access roads, turf establishment, bedding stone, riprap, and other flood control construction items. Eight contractors submitted bids by the December 30, 2021 deadline: Medvolt, LLC; Cycle Construction Company, LLC; Lakey, Inc.; Onshore Materials, LLC; Rigid Constructors, LLC; Tarpon Construction, LLC; Triumph Five S Group JV; and Young's General Contracting, Inc. The abstract lists estimated costs by line item for each bidder as well as overall totals ranging from $17.5 million to $26.7 million. The government estimate was $23.5 million. Award is pending.

View the file

Other files

File Type Posted
Revised Bid Abstract W912P822B0001_signed.pdf PDF
W912P822B0001 Amendment 0002.pdf PDF
W912P822B0001 Amendment 01.pdf PDF
W912P822B0001.pdf PDF
W912P822B0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

30-Dec-21 30-Dec-21

DATE SIGNED

30-Dec-21

7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED

NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JOB $ 838,000.00 $ 838,000.00 $ 1,000,000.00 $ 1,000,000.00 $ 1,194,197.50 $ 1,194,197.50 $ 650,000.00 $ 650,000.00 0002 Safety Fence 1 JOB $ 110,000.00 $ 110,000.00 $ 50,000.00 $ 50,000.00 $ 53,276.30 $ 53,276.30 $ 84,840.00 $ 84,840.00 0003 Video and Photographic Documentation 1 JOB $ 40,000.00 $ 40,000.00 $ 14,000.00 $ 14,000.00 $ 18,975.00 $ 18,975.00 $ 18,100.00 $ 18,100.00 0004 Traffic Control 1 JOB $ 149,000.00 $ 149,000.00 $ 26,500.00 $ 26,500.00 $ 15,870.00 $ 15,870.00 $ 36,200.00 $ 36,200.00 0005 Silt Fence 1 JOB $ 153,000.00 $ 153,000.00 $ 74,000.00 $ 74,000.00 $ 51,416.30 $ 51,416.30 $ 43,350.00 $ 43,350.00 0006 Truck Wash/Down Rack 1 JOB $ 192,000.00 $ 192,000.00 $ 75,000.00 $ 75,000.00 $ 24,200.00 $ 24,200.00 $ 39,600.00 $ 39,600.00 0007 Excavation - Cypress Bayou Rock 84,650 CY $ 6.70 $ 567,155.00 $ 9.25 $ 783,012.50 $ 5.43 $ 459,649.50 $ 7.95 $ 672,967.50 0008 Excavation - Comite Diversion Channel 414,780 CY $ 5.10 $ 2,115,378.00 $ 7.00 $ 2,903,460.00 $ 4.25 $ 1,762,815.00 $ 7.90 $ 3,276,762.00 0009 Compacted Fill 90,030 CY $ 5.80 $ 522,174.00 $ 4.00 $ 360,120.00 $ 5.99 $ 539,279.70 $ 10.40 $ 936,312.00 0010 Separator Geotextile 108,140 CY $ 4.90 $ 529,886.00 $ 6.00 $ 648,840.00 $ 5.78 $ 625,049.20 $ 5.10 $ 551,514.00 0011 Clearing and Grubbing 1 JOB $ 855,000.00 $ 855,000.00 $ 1,230,000.00 $ 1,230,000.00 $ 310,037.50 $ 310,037.50 $ 769,250.00 $ 769,250.00 0012 Construction Unwatering 1 JOB $ 534,000.00 $ 534,000.00 $ 500,000.00 $ 500,000.00 $ 734,660.00 $ 734,660.00 $ 150,000.00 $ 150,000.00 0013 Temporary Access Roads 1 JOB $ 3,822,000.00 $ 3,822,000.00 $ 706,000.00 $ 706,000.00 $ 875,213.75 $ 875,213.75 $ 1,131,300.00 $ 1,131,300.00 0014 Turf Establishment and Maintenance 51 AC $ 4,600.00 $ 234,600.00 $ 8,000.00 $ 408,000.00 $ 4,588.50 $ 234,013.50 $ 5,656.50 $ 288,481.50 0015 Bedding Stone No. 2 34,000 TON $ 60.00 $ 2,040,000.00 $ 66.00 $ 2,244,000.00 $ 56.34 $ 1,915,560.00 $ 64.48 $ 2,192,320.00 0016 Channel Riprap R90 36,060 TON $ 73.00 $ 2,632,380.00 $ 76.50 $ 2,758,590.00 $ 68.47 $ 2,469,028.20 $ 92.77 $ 3,345,286.20 0017 Channel Riprap R650 22240 TON $ 83.00 $ 1,845,920.00 $ 82.50 $ 1,834,800.00 $ 74.75 $ 1,662,440.00 $ 91.64 $ 2,038,073.60 0018 Channel Riprap R1000 8920 TON $ 86.00 $ 767,120.00 $ 85.50 $ 762,660.00 $ 74.75 $ 666,770.00 $ 94.75 $ 845,170.00 0019 Channel Riprap R3500 61750 TON $ 95.00 $ 5,866,250.00 $ 88.00 $ 5,434,000.00 $ 71.65 $ 4,424,387.50 $ 104.08 $ 6,426,940.00

$ 23,813,863.00 $ 21,812,982.50 $ 18,036,838.95 $ 23,496,466.80

NO. 3

C. OFFEROR: Medvolt, LLC

B. BID SECURITY (Type and amount)

Bid Bond $4,699,293.36

C. AMENDMENTS ACKNOWLEDGED: YES

NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)

6. NUMBER OF AMENDMENTS ISSUED

7400 Leake Avenue

New Orleans, LA 70118

A. HIRED LABOR A. OFFEROR: Cycle Construction Company, LLC B. OFFEROR: Lakey, Inc.

Dorothy Pitre Contract Specialist

Shermeka Showers Contracting Officer

Flood Control, Amite River and Tributaries, Comite River Basin, Comite River Diversion Project, Cypress Bayou Rock Chute, East Baton Rouge

Parish, Louisiana

C. AMENDMENTS ACKNOWLEDGED: YES C. AMENDMENTS ACKNOWLEDGED: YES

NO. 2

7B. DESCRIPTION OF OFFERED ITEM

C. REASONABLE CONTRACT

(Including Profit)

B. REASONABLE CONTRACT

(Without Profit)

NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA - FAR (48 CFR) 53.236-1

ABSTRACT OF OFFERS

1. SOLICITATION NUMBER

W912P822B0001

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

SIGNATURE

4. ISSUING OFFICE

US ARMY ENGINEER DISTRICT, NOD

5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

(Check A, B or C and complete D, E, and F) NO. 1

D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED

PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

$ 1,525,000.00 $ 1,525,000.00 $ 1,850,618.00 $ 1,850,618.00 $ 600,000.00 $ 600,000.00 $ 3,943,604.73 $ 3,943,604.73 $ 676,470.59 $ 676,470.59 $ 87,500.00 $ 87,500.00 $ 32,700.00 $ 32,700.00 $ 96,500.00 $ 96,500.00 $ 39,183.90 $ 39,183.90 $ 13,529.41 $ 13,529.41 $ 37,500.00 $ 37,500.00 $ 10,000.00 $ 10,000.00 $ 21,000.00 $ 21,000.00 $ 87,846.53 $ 87,846.53 $ 13,529.41 $ 13,529.41 $ 33,500.00 $ 33,500.00 $ 50,000.00 $ 50,000.00 $ 15,075.00 $ 15,075.00 $ 11,388.51 $ 11,388.51 $ 13,529.41 $ 13,529.41 $ 90,000.00 $ 90,000.00 $ 21,000.00 $ 21,000.00 $ 48,600.00 $ 48,600.00 $ 36,420.30 $ 36,420.30 $ 13,529.41 $ 13,529.41 $ 88,500.00 $ 88,500.00 $ 29,750.00 $ 29,750.00 $ 45,000.00 $ 45,000.00 $ 55,000.00 $ 55,000.00 $ 47,352.94 $ 47,352.94 $ 6.70 $ 567,155.00 $ 5.00 $ 423,250.00 $ 4.05 $ 342,832.50 $ 6.00 $ 507,900.00 $ 5.75 $ 486,737.50 $ 7.00 $ 2,903,460.00 $ 5.00 $ 2,073,900.00 $ 4.05 $ 1,679,859.00 $ 4.50 $ 1,866,510.00 $ 6.76 $ 2,803,912.80 $ 2.50 $ 225,075.00 $ 1.80 $ 162,054.00 $ 3.95 $ 355,618.50 $ 1.50 $ 135,045.00 $ 4.40 $ 396,132.00 $ 6.75 $ 729,945.00 $ 2.65 $ 286,571.00 $ 9.00 $ 973,260.00 $ 3.25 $ 351,455.00 $ 4.06 $ 439,048.40 $ 945,000.00 $ 945,000.00 $ 357,000.00 $ 357,000.00 $ 754,000.00 $ 754,000.00 $ 325,000.00 $ 325,000.00 $ 169,117.65 $ 169,117.65 $ 1,100,000.00 $ 1,100,000.00 $ 439,855.00 $ 439,855.00 $ 392,000.00 $ 392,000.00 $ 300,000.00 $ 300,000.00 $ 338,235.29 $ 338,235.29 $ 4,775,000.00 $ 4,775,000.00 $ 308,119.00 $ 308,119.00 $ 850,000.00 $ 850,000.00 $ 2,000,000.00 $ 2,000,000.00 $ 67,647.06 $ 67,647.06 $ 8,150.00 $ 415,650.00 $ 3,890.00 $ 198,390.00 $ 4,720.00 $ 240,720.00 $ 8,234.53 $ 419,961.03 $ 3,382.35 $ 172,499.85 $ 66.90 $ 2,274,600.00 $ 55.55 $ 1,888,700.00 $ 65.00 $ 2,210,000.00 $ 65.00 $ 2,210,000.00 $ 67.65 $ 2,300,100.00 $ 76.50 $ 2,758,590.00 $ 80.50 $ 2,902,830.00 $ 75.00 $ 2,704,500.00 $ 78.00 $ 2,812,680.00 $ 67.65 $ 2,439,459.00 $ 82.50 $ 1,834,800.00 $ 86.75 $ 1,929,320.00 $ 84.00 $ 1,868,160.00 $ 90.00 $ 2,001,600.00 $ 74.41 $ 1,654,878.40 $ 84.00 $ 749,280.00 $ 87.90 $ 784,068.00 $ 84.00 $ 749,280.00 $ 95.00 $ 847,400.00 $ 74.41 $ 663,737.20 $ 89.80 $ 5,545,150.00 $ 92.50 $ 5,711,875.00 $ 85.00 $ 5,248,750.00 $ 100.00 $ 6,175,000.00 $ 78.47 $ 4,845,522.50

$ 26,685,705.00 $ 19,460,000.00 $ 19,195,155.00 $ 24,125,995.00 $ 17,554,968.82

D. OFFEROR: Onshore Materials, LLC

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

C. AMENDMENTS ACKNOWLEDGED: YES

NO. 4

E. OFFEROR: Rigid Constructors, LLC

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

C. AMENDMENTS ACKNOWLEDGED: YES

NO. 6

F. OFFEROR: Tarpon Construction, LLC

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

C. AMENDMENTS ACKNOWLEDGED: YES

NO. 5

G. OFFEROR: Triumph Five S Group JV

B. BID SECURITY (Type and amount)

Bid Bond $3,000,000.00

C. AMENDMENTS ACKNOWLEDGED: YES

NO. 8

H. OFFEROR: Young's General Contracting, Inc.

B. BID SECURITY (Type and amount)

Bid Bond $0.00

C. AMENDMENTS ACKNOWLEDGED: YES

NO. 7

2022-01-03T09:35:15-0600
SHOWERS.SHERMEKA.LESHAWN.1120583111