A21 - W912P821B0033 AM0001 with attachments.pdf
PDF 2 MB Posted
- Attached to
- Mississippi River, New Orleans Harbor and Various Bar Channels Cutterhead Dredge No. 3-2021
- Solicitation number
- W912P821B0033
About this file
This solicitation is for a Mississippi River, New Orleans Harbor and Various Bar Channels Cutterhead Dredge project. Work will involve furnishing a fully crewed and equipped hydraulic pipeline cutterhead dredge to perform dredging in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, Bayou Lafourche, Baptiste Collette, Houma Navigation Canal, and Barataria Bar Channel. The estimated value of the work is between $5 million and $10 million. The solicitation will issue on April 19, 2021 as an invitation for bid resulting in a single firm fixed price contract awarded by the US Army Corps of Engineers, New Orleans District. The NAICS code is 237990 and responses are due based on a future amendment. Interested vendors should monitor the beta.SAM.gov website for solicitation documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B01 - W912P821B0033 Abstract (Signed).pdf | ||
| A21 - W912P821B0033 AM0001.pdf | ||
| W912P821B0033.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OM21032
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The subject Solicitation for Mississippi River, New Orleans Harbor and Various Bar Channels Cutterhead Dredge No. 3-2021, Orleans and Jefferson Parish, Louisiana (OM-21-032) has been modified to provide specif ic details on how contractors are to submit Bids, Bonds and the Conference Call details for the Virtual Bid Opening w hich is now scheduled for Thursday, June 24, 2021 at 11:30 AM CST. The Contracting Officer and Contract Specialist w ill begin dow nloading bids at 10:30 AM CST, w hich is the bid receipt cutoff time. All bids received after 10:30 AM CST on Thursday, 24 June 2021 w ill be considered late. See the attached pages.
For any questions, please contact the Contracting Officer, (Veronica F. Garner-Flint 504-862-1515), or the Contract Specialist, (Karen Hargrave, 504-862-1561).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P821B0033
X 9B. DATED (SEE ITEM 11)
19-Apr-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
AM0001
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jun-2021
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P821B0033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the days described in Section 00010-1.5 of the bidding schedule. The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
SECTION SF 30 - SF 30 CONTINUATION
The contractor period of performance begin date has increased by 10 days from 5 days to 15 days.
The required performance has changed from Mississippi River, New Orleans Harbor and Various Bar Channels, Cutterhead Dredge Contract No. 03-2021, Orleans and Jefferson Parish, Louisiana (OM-21-030)This is an UNRESTRICTED procurement.The work consists offurnishing one fully crewed and equipped hydraulic pipeline cutterhead dredge. Work will be performed in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, Bayou Lafourche, Baptiste Collette, Houma Navigation Canal, and Barataria Bar Channel.The estimated value of this work is between $5,000,000 and $10,000,000.Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.** TO BE ESTABLISHED BY AMENDMENT* See Paragraph 00010-1.5 to Mississippi River, New Orleans Harbor and Various Bar Channels, Cutterhead Dredge Contract No. 03-2021, Orleans and Jefferson Parish, Louisiana (OM-21-030)This is an UNRESTRICTED procurement.The work consists offurnishing one fully crewed and equipped hydraulic pipeline cutterhead dredge. Work will be performed in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, and Baptiste Collette.The estimated value of this work is between $5,000,000 and $10,000,000.Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.** TO BE ESTABLISHED BY AMENDMENT* See Paragraph 00010-1.5.
The following have been added by full text:
AM0001
1. Note: The dredge AND ATTENDANT PLANT must be able to operate in river stages above 12 feet at the New Orleans (Carrollton) gage, IF NECESSARY. Therefore, BY BIDDING ON THIS SOLICITATION, the Contractor IS CERTIFYING that its dredge meets this requirement.
2. Cover Sheet, Description and Magnitude of Work: Delete the second sentence of this paragraph and replace with the following sentence: “Work will be performed in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, and Baptiste Collette.”
3. Project Table of Contents: Delete the below sections:
35 20 23.23 15 Hydraulic Dredging – Bayou Lafourche Dredging Region 35 20 23.23 18 Hydraulic Dredging – Houma Navigation Canal Dredging Region 35 20 23.23 19 Hydraulic Dredging – Barataria Bay Waterway Bar Channel Dredging Region
4. Standard Form 1442, box 10, 3rd paragraph: Delete the second sentence of this paragraph and replace with the following sentence: “Work will be performed in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, and Baptiste Collette.”
5. Standard Form 1442, box 11: Delete “5 calendar days” and replace with “15 calendar days”.
6. Section 00010 “Bid Schedule”: Delete this section in its entirety and replace with the attached Section 00010
“Bid Schedule”.
7. Section 00700, FAR Clause 52.211-10 “Commencement, Prosecution, and Completion of Work (Apr 1984)”:
In the first sentence, delete “5 calendar days” and replace with “15 calendar days”.
8. Section 00800, paragraph 3.1 “Delivery of Plant”, subparagraph a: In the first sentence, delete “120 hours” and replace with “15 calendar days”.
9. Section 01 30 00, paragraph 1.12 “As-Built Drawings”: In the last paragraph, delete the first sentence which begins with “Upon approval of the “As-Built” drawings…”, and replace with the following sentences: “The Contractor shall submit the draft as-builts for review by email in PDF format to the New Orleans Area Office.
Upon approval/acceptance of the draft as-builts, the Contractor shall submit the final as-builts in both CADD and PDF format into RMS as a closeout submittal.”
10. Section 01 33 00, Submittal Register: Delete all references to “LAO” under the “Reviewer” column, and for
Item Nos. 12 & 13, delete all references to 35 20 23.23 15, 35 20 23.23 18, and 35 20 23.23 19.
11. Section 35 20 23.23, paragraph 1.1 “Scope”: In the first sentence, delete “27 inches” and replace with “24 inches”.
12. Section 35 20 23.23, paragraph 1.2.2 “Dredging and Option Dredging Items”: Delete the first sentence and replace with the following sentence: “Payment for a fully operated cutterhead dredge will be made at the contract unit price per hour for "NOH Dredging", "NOH Option Dredging", “Baptiste Collette Dredging”, and “Baptiste Collette Option Dredging”, at the pay times stipulated in the following subparagraphs.”
13. Section 35 20 23.23, paragraph 1.3.1 “Daily Report of Operations”: At the end of this paragraph, add the following sentence: “The MVN Form 4267 shall be used in lieu of the RMS Form 4267 and uploaded to RMS separately.”
14. Section 35 20 23.23, paragraph 1.3.4 “Distribution of Reports”: Delete the paragraph which references the
Lafayette Area Office. The New Orleans Area Office will be handling this contract.
15. Section 35 20 23.23, paragraph 1.4 “Dredge and Attendant Plant Data Sheet”: At the end of this paragraph, add the following sentence: “If the Contractor requests a substitution of plant or addition of plant during the contract, the plant data sheet of the substituted plant or the additional plant must be submitted at the time of the request.”
16. Section 35 20 23.23, paragraph 3.1.4 “Order of Work”, subparagraph a: Delete subparagraph a in its entirety and replace with the following:
a. Dredging will be performed in the following order:
(1) New Orleans Harbor Dredging Region
(2) Algiers, IHNC, and Harvey Lock Forebays Dredging Region
(3) Baptiste Collette Bar Channel Dredging Region
17. Section 35 20 23.23 07, paragraph 3.3 “Minimum Production Rate Requirements” and Section 35 20 23.23 08, paragraph 3.2 “Minimum Production Rate Requirements”:
In both of these paragraphs, delete the chart in subparagraph a and replace with the following chart:
Size of Dredge Pump Discharge (inches)
Submerged Pump
Minimum Output (cy/hr)
24 No 1013
24 Yes 1344
27 No 1283
30 No 1582
30 Yes 2100
18. Section 35 20 23.23 15 “Hydraulic Dredging – Bayou Lafourche Dredging Region”: Delete this section in its entirety.
19. Section 35 20 23.23 16 “Hydraulic Dredging – Baptiste Collette Bar Channel Dredging Region”: Delete this section in its entirety and replace with the attached Section 35 20 23.23 16 “Hydraulic Dredging – Baptiste Collette Bar Channel Dredging Region”.
20. Section 35 20 23.23 18 “Hydraulic Dredging – Houma Navigation Canal Dredging Region”: Delete this section in its entirety.
21. Section 35 20 23.23 19 “Hydraulic Dredging – Barataria Bay Waterway Bar Channel Dredging Region”: Delete this section in its entirety.
INSTRUCTION TO BIDDERS
INSTRUCTION TO BIDDERS
Due to the response for COVID-19, most federal employees have been mandated to telework, and currently only authorized personnel are allowed access to the District buildings throughout USACE. As a result, we have implemented the below procedures for all current and future bid openings, until such restrictions have been lifted and normal access has resumed at the MVN HQ Building.
Electronic Submission of Bids:
MVN will utilize the DoD Safe website for receipt of electronic bids under IFB Solicitations. In order to submit an electronic bid please follow these steps:
1. Send an email containing your name and email address to the Contracting Officer and Contract Specialist associated with the IFB:
Contracting Officer – Ms. Veronica Garner-Flint, email: veronica.garner-flint@usace.army.mil Contract Specialist – Ms. Karen Hargrave, email: karen.d.hargrave@usace.army.mil
2. The Contracting Officer or Contract Specialist will go to the DoD Safe site, input your name and email address, and then will request the file from you. You will then receive an automated email from the site with a unique link in the email.
3. Once the email with the link is received, please click on the link in the email, which will take you to the DoD Safe site.
4. This will be a unique webpage where you can upload your file. The default page will load with the box checked off next to, “Send me an email when each recipient picks up the files”.
Please leave this box checked in order to receive a notification when the file is received from the Contracting Officer or Contract Specialist. Please leave unchecked, “Encrypt every file”. The site itself contains a high level of security in which additional encryption is not required.
5. When you are ready to upload your bid file (please use pdf format for bid submission), you can either click the blue button which says, “Click to Add Files or Drag Them Here” to locate the file on your computer, or simply drag the file onto the screen.
6. In the Description box that appears after uploading your file, please type your Company Name.
7. Click the button that appears at the bottom of the page, “Drop-off Files”. A banner will pop-up asking for confirmation that your upload does not contain Classified Information. Click ok on the banner.
8. You will be taken to a confirmation page that should say, “Drop-Off Completed” at the top.
This is your confirmation that your file was successfully uploaded to the site.
9. The Contracting Officer or Contract Specialist will receive an automated email stating that the file has been submitted. They will then send an email back to the company, confirming that they received the notice from the DoD Safe site.
The Bid Opening is currently scheduled for Thursday, June 24, 2021 at 11:30 AM CST. The Contracting Officer and Contract Specialist will begin downloading bids at 10:30 AM CST, which is the bid receipt cutoff time. All bids received after 10:30 AM CST on Thursday, 24 June 2021 will be considered late.
Audio Teleconference Bid Opening Information:
Bid Opening will be held on Thursday, 24 June 2021 at 11:30 AM CST. Please use the following call-in information to attend the meeting:
Toll-Free: 844-291-5490 Access Code: 2882073
Following the conclusion of the bid opening, the Bid Abstract will be uploaded to SAM.gov website under this solicitation, within 24 hours.
Bid Bonds (Offer Guarantee) should be submitted electronically with the Bid Package as per the scheduled Bid Opening on Amendment. As per Class Deviation 2020-O0016, Electronic signatures and electronic, mechanically-applied, or printed dates may be used and shall be considered original signatures and dates. In addition, a Corporate Seal is not required, the SF 28 need not be sworn and notarized and a written authorization of the release signed by the surety is acceptable in lieu of the notarized authorization of release by the surety. Original Certified Bonds need not be submitted at time of bid. USACE MVN Contracting Division reserves the right to request the Original Certified Bonds, if deemed necessary to verify their authenticity.
The following deviation clauses now apply, in lieu of the corresponding FAR clauses:
52.228-11, Pledges of Assets (DEVIATION 2020-O0016), which removes the requirement for the Standard Form 28 to be sworn and notarized.
52.228-15, Performance and Payment Bonds—Construction (DEVIATION 2020- O0016), which removes the requirements for seals on Standard Forms.
52.228-16, Performance and Payment Bonds—Other than Construction (DEVIATION 2020-O0016), which removes requirements for seals on Standard Forms.
For any Questions please contact:
Contracting Officer – Ms. Veronica Garner-Flint, email: veronica.garner-flint@usace.army.mil ;
Phone: 504-862-1515 Contract Specialist – Ms. Karen Hargrave, email: karen.d.hargrave@usace.army.mil ;
Phone: 504-862-1561
(End of Summary of Changes)
Miss R, New Orleans Harbor and Various Bar Channels Cutterhead OM21032AMEND
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00010
BID SCHEDULE
PART 1 GENERAL
1.1 BIDDING SCHEDULES
1.2 BID FORM NOTES
1.3 BIDDING
1.4 EVALUATION OF BIDS
1.5 CONDITIONS OF CONTRACT AWARD
1.6 BIDDER QUALIFICATIONS
1.7 PRE-AWARD INSPECTION OF PLANT
1.8 OPTION ITEMS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 00010 Page 1
SECTION 00010
BID SCHEDULE
PART 1 GENERAL
1.1 BIDDING SCHEDULES
SECTION 00010 - BIDDING SCHEDULE
MISSISSIPPI RIVER, NEW ORLEANS HARBOR AND VARIOUS BAR CHANNELS
CUTTERHEAD DREDGE NO. 3-2021
ORLEANS, JEFFERSON, TERREBONNE, PLAQUEMINES, AND LAFOURCHE PARISHES, LA
SOLICITATION NO. W912P821B0033
LOT ONE, 24 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED PUMP
Bid Item DESCRIPTION Estimated Quantity
Unit Unit Price Total Price
0001 MOBILIZATION AND DEMOBILIZATION 1 JOB
0002 NOH DREDGING 747 HOUR
Option
NOH OPTION DREDGING 747 HOUR XXXXXXXX
0004 DREDGE TOWING SERVICE 100 MILE
Option
OPTION DREDGE TOWING SERVICE 100 MILE XXXXXXXX
0006 PREPARATORY WORK FOR BAPTISTE
COLLETTE DREDGING REGION
1 JOB
0007 BAPTISTE COLLETTE DREDGING 179 HOUR
Option
BAPTISTE COLLETTE OPTION
DREDGING
179 HOUR XXXXXXXX
Option
BIRD NESTING PREVENTION AND
AVOIDANCE MEASURES
18 DAY
TOTAL: LOT ONE BID
*SEE BID FORM NOTES FOLLOWING LAST BID LOT
SECTION 00010 Page 2
SECTION 00010 - BIDDING SCHEDULE
MISSISSIPPI RIVER, NEW ORLEANS HARBOR AND VARIOUS BAR CHANNELS
CUTTERHEAD DREDGE NO. 3-2021
ORLEANS, JEFFERSON, TERREBONNE, PLAQUEMINES, AND LAFOURCHE PARISHES, LA
SOLICITATION NO. W912P821B0033
LOT TWO, 24 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITH SUBMERGED PUMP
Bid Item DESCRIPTION Estimated Quantity
Unit Unit Price Total Price
0001 MOBILIZATION AND
DEMOBILIZATION
1 JOB
0002 NOH DREDGING 563 HOUR
Option
NOH OPTION DREDGING 563 HOUR XXXXXXXX
0004 DREDGE TOWING SERVICE 100 MILE
Option
OPTION DREDGE TOWING SERVICE 100 MILE XXXXXXXX
0006 PREPARATORY WORK FOR BAPTISTE
COLLETTE DREDGING REGION
1 JOB
0007 BAPTISTE COLLETTE DREDGING 149 HOUR
Option
BAPTISTE COLLETTE OPTION
DREDGING
149 HOUR XXXXXXXX
Option
BIRD NESTING PREVENTION AND
AVOIDANCE MEASURES
15 DAY
TOTAL: LOT TWO BID
SECTION 00010 Page 3
MISSISSIPPI RIVER, NEW ORLEANS HARBOR AND VARIOUS BAR CHANNELS
CUTTERHEAD DREDGE NO. 3-2021
ORLEANS, JEFFERSON, TERREBONNE, PLAQUEMINES, AND LAFOURCHE PARISHES, LA
SOLICITATION NO. W912P821B0033
LOT THREE, 27 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED PUMP
Bid Item DESCRIPTION Estimated Quantity
Unit Unit Price Total Price
0001 MOBILIZATION AND
DEMOBILIZATION
1 JOB
0002 NOH DREDGING 590 HOUR
Option
NOH OPTION DREDGING 590 HOUR XXXXXXXX
0004 DREDGE TOWING SERVICE 100 MILE
Option
OPTION DREDGE TOWING SERVICE 100 MILE XXXXXXXX
0006 PREPARATORY WORK FOR BAPTISTE
COLLETTE DREDGING REGION
1 JOB
0007 BAPTISTE COLLETTE DREDGING 125 HOUR
Option
BAPTISTE COLLETTE OPTION
DREDGING
125 HOUR XXXXXXXX
Option
BIRD NESTING PREVENTION AND
AVOIDANCE MEASURES
13 DAY
TOTAL: LOT THREE BID
SECTION 00010 Page 4
MISSISSIPPI RIVER, NEW ORLEANS HARBOR AND VARIOUS BAR CHANNELS
CUTTERHEAD DREDGE NO. 3-2021
ORLEANS, JEFFERSON, TERREBONNE, PLAQUEMINES, AND LAFOURCHE PARISHES, LA
SOLICITATION NO. W912P821B0033
LOT FOUR, 30 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED PUMP
Bid Item DESCRIPTION Estimated Quantity
Unit Unit Price
Total Price
0001 MOBILIZATION AND
DEMOBILIZATION
1 JOB
0002 NOH DREDGING 478 HOUR
Option
NOH OPTION DREDGING 478 HOUR XXXXXXXX
0004 DREDGE TOWING SERVICE 100 MILE
Option
OPTION DREDGE TOWING
SERVICE
100 MILE XXXXXXXX
0006 PREPARATORY WORK FOR
BAPTISTE COLLETTE DREDGING
REGION
1 JOB
0007 BAPTISTE COLLETTE DREDGING 95 HOUR
Option
BAPTISTE COLLETTE OPTION
DREDGING
95 HOUR XXXXXXXX
Option
BIRD NESTING PREVENTION
AND AVOIDANCE MEASURES
10 DAY
TOTAL: LOT FOUR BID
SECTION 00010 Page 5
MISSISSIPPI RIVER, NEW ORLEANS HARBOR AND VARIOUS BAR CHANNELS
CUTTERHEAD DREDGE NO. 3-2021
ORLEANS, JEFFERSON, TERREBONNE, PLAQUEMINES, AND LAFOURCHE PARISHES, LA
SOLICITATION NO. W912P821B0033
LOT FIVE, 30 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITH SUBMERGED PUMP
Bid Item DESCRIPTION Estimated Quantity
Unit Unit Price
Total Price
0001 MOBILIZATION AND
DEMOBILIZATION
1 JOB
0002 NOH DREDGING 360 HOUR
Option
NOH OPTION DREDGING 360 HOUR XXXXXXXX
0004 DREDGE TOWING SERVICE 100 MILE
Option
OPTION DREDGE TOWING
SERVICE
100 MILE XXXXXXXX
0006 PREPARATORY WORK FOR
BAPTISTE COLLETTE DREDGING
REGION
1 JOB
0007 BAPTISTE COLLETTE DREDGING 76 HOUR
Option
BAPTISTE COLLETTE OPTION
DREDGING
76 HOUR XXXXXXXX
Option
BIRD NESTING PREVENTION
AND AVOIDANCE MEASURES
8 DAY
TOTAL: LOT FIVE BID
SECTION 00010 Page 6
1.2 BID FORM NOTES
a. Bidders shall bid on all items including optional items (see " Evaluation of Options" FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.
b. Bidders shall use the Item No. 0002 unit price to compute Option Item No. 0003 total price, Item No. 0004 unit price to compute Option Item No. 0005 total price, and Item No. 0007 unit price to compute Option Item No. 0008 total price.
c. Any bid may be rejected if the Contracting Officer or his/her authorized representative determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only the total price of the bid, but the prices for individual line items as well. Any bid may be rejected if the prices for any line items or subline items are materially unbalanced (see " Rejection of Individual Bids" FAR 14.404-2).
d. THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued after verification of acceptable performance and payment bonds. Within 48 hours after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Administrative Contracting Officer or his/her authorized representative. Physical work cannot start until the Resident Management System is set-up, the Accident Prevention Program and other required submittals have been submitted and approved, and all preliminary meetings called for under the contract have been conducted.
e. RAPID VENDOR PAYMENT: See the following web based instructions for the submission of invoices:
www.mvn.usace.army.mil/Business-With-Us/Contracting/Rapid-Vendor-Payment.aspx
f. The unit "job" is a one-time payment for work performed. "Job" is synonymous with the previously used term "lump sum".
1.3 BIDDING
a. The bidder shall select only one bid lot, determined by the class of dredge intended to be used. Bids which are submitted on an inappropriate bid lot will be declared non-responsive.
b. Bidders shall furnish unit prices for all items listed on the schedule of bid items that require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required items but does furnish an extended total or an estimated amount for such items, the Government will deem the unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED
ESTIMATED AMOUNT FOR ANY REQUIRED ITEM, THE BID WILL BE DECLARED
NON-RESPONSIVE.
1.4 EVALUATION OF BIDS
a. To provide fair competition between dredges of dissimilar sizes and production rates, the hourly dredging quantities have been determined based on the estimated quantity of shoal material to be removed and the
SECTION 00010 Page 7 nominal production rate of the dredge in each bid lot. The production rates shown in the chart in the paragraph entitled "Minimum Production Rate Requirements" located in the Dredging Region Section(s) were used to make this determination.
b. The nominal dredge production rates listed in this solicitation were conservatively estimated based on an average "Standard" cross-sectional quantity of material for this solicitation's dredging regions, which have variable and dynamic shoaling conditions. It is the bidder's responsibility to make its own assessment of the actual dredging conditions in order to prepare a bid for this work.
c. Award will be made to that responsible bidder presenting the lowest priced responsive bid in response to this solicitation, regardless of the Bid Lot used.
d. The hourly quantities for the Dredging and Option Dredging Items shown on the bid lots are 100% pay time hours. The actual calendar duration of the contract may vary as a result of fractional pay time.
Refer to Section 35 20 23.23, paragraph entitled "Dredging and Option Dredging Items", for additional information.
1.5 CONDITIONS OF CONTRACT AWARD
a. Award will be made as a whole to one bidder. The dredge and attendant plant offered in the bidding schedule shall be complete with full operating personnel and in operating status for the contract period. EM 385-1-1, Section 19, "Floating Plant and Marine Activities" shall be complied with at all times. NOTE: All work under these specifications shall be performed in accordance with the provisions of EM 385-1-1 "Army Corps of Engineers Safety and Health Requirements Manual", latest edition.
b. The Government may award the contract at the total bid price, comprised of the base items and option item(s); however, the Government is not obligated to exercise any option item(s).
c. The number of hours stated in the bidding schedule is an estimated quantity. The dredge and attendant plant will be retained for an approximate number of days shown in the table below starting no later than 15 calendar days after issuance of the Notice to Proceed.
APPROXIMATE DREDGE
CONTRACT DURATION
Bid Lot
Discharge Line ID
(INCHES)
Submerged Pump
Approximate Number of Contract Days for
Item 0002
Approximate Number of Contract Days for
Option Item
Approximate Number of Contract Days for
Item 0007
Approximate Number of Contract Days for
Option Item
1 24 NO 43 43 16 16
2 24 YES 34 34 14 14
SECTION 00010 Page 8
Bid Lot
Discharge Line ID
(INCHES)
Submerged Pump
Approximate Number of Contract Days for
Item 0002
Approximate Number of Contract Days for
Option Item
Approximate Number of Contract Days for
Item 0007
Approximate Number of Contract Days for
Option Item
3 27 NO 36 36 13 13
4 30 NO 30 30 12 12
5 30 YES 25 25 11 11
The time required for completion of the contract shall be established as the sum of the calendar days listed in the columns entitled "Approximate Number of Contract Days for Item 0002" and "Approximate Number of Contract Days for Item 0007". In the event Option Item 0003 and Option Item 0008 are fully exercised under the terms of the contract, the time required for completion of the contract shall be extended by the sum of the calendar days listed in the columns entitled "Approximate Number of Contract Days for Option Item 0003" and "Approximate Number of Contract Days for Option Item 0008". In the event Option Item 0003 or 0008 is partially exercised, the contract completion date shall be extended using the following formula:
[(partial option hours exercised)/(option hours listed in bid schedule)] x (calendar days listed in column "Approximate Number of Contract Days for Option Item 0003" OR "Approximate Number of Contract Days for Option Item 0008")
d. The bidder shall be capable of providing for assignment of the dredge and all attendant plant, complete and in full operating condition in all respects, and to commence dredging no later than 15 calendar days after issuance of the Notice to Proceed.
1.6 BIDDER QUALIFICATIONS
a. Before the Government will award a contract based on this solicitation, the apparent low bidder shall establish that it is responsible and entitled to award of the contract, by certifying that its dredge meets the appropriate production rate for the dredging region, as listed in the chart in the paragraph entitled "Minimum Production Rate Requirements" located in the Dredging Region Section(s). The dredge must have performed at, or above, the listed production rate for at least 85 percent of the total contract duration, on any contracts that are used to prove plant capability, within three years prior to the bid opening date of this solicitation. Failure to establish the dredge's capability to meet the required production rate will result in a finding of non-responsibility.
b. A bidder may be rejected as non-responsible if it cannot show the necessary capital, experience, or equipment needed to perform the work described under this solicitation (see "Responsible Prospective Contractors" FAR 9.1). The bidder must also show that the dredge and attendant plant are not already obligated for the performance of other work which would delay commencement, performance, and completion of the solicited work, and must show that delivery of the dredge and attendant plant to the site of work can be made within the time allowed in the specifications.
SECTION 00010 Page 9
c. Bidders must register in the System for Award Management (SAM) database in accordance with FAR 52.204-7.
1.7 PRE-AWARD INSPECTION OF PLANT
a. The apparent low bidder shall make the dredge and attendant plant available for inspection, to determine compliance with these specifications, as soon as practicable after bids are opened, and prior to contract award. If deficiencies are found during the inspection, the bidder will be notified in writing, which may be transmitted by email or facsimile. Upon receipt of such notice, the bidder shall correct all deficiencies at least two calendar days in advance of the projected contract award date.
b. Two calendar days before the projected award date, or upon notification by the bidder that the deficiencies have been corrected, a Government representative will re-inspect the dredge and attendant plant. If at that time the dredge and attendant plant do not meet the requirements of these specifications, the bidder will be rejected as non-responsible.
c. The Government may choose to waive the pre-award inspection if the projected contract award date is less than five calendar days after the bid opening date. Waiver of the pre-award inspection does not relieve the bidder from the requirement to provide a dredge and attendant plant in full compliance with the specifications.
1.8 OPTION ITEMS
a. The Government may require the delivery of, in whole or part, any Option Items. The Government may exercise an Option Item by written notice to the Contractor. If the Government activates the Option Item, the activation will occur while the Contractor's equipment is in the work vicinity as described in the applicable Dredging Region Section(s). If Option Dredging Item work is exercised, it shall be performed as a continuance of Dredging Item work, which shall be activated first.
b. No additional mobilization/demobilization will be paid to the Contractor for Option Item work performed within the work region. The Contractor shall commence performance of optional work no more than three calendar days after the time the Contractor receives the Government's Notice to Proceed with the optional work.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 00010 Page 10
Mi ss R, New Or l eans Har bor and Var i ous Bar Channel s Cut t er head OM21032AMEND
SECTI ON TABLE OF CONTENTS
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
SECTI ON 35 20 23. 23 16
HYDRAULI C DREDGI NG - BAPTI STE COLLETTE BAR CHANNEL DREDGI NG REGI ON
PART 1 GENERAL
1. 1 SCOPE
1. 2 MEASUREMENT AND PAYMENT
1. 2. 1 Base I t em: Pr epar at or y Wor k For Bapt i s t e Col l et t e Dr edgi ng
Region
1. 2. 2 Opt i on I t em: Bi r d Nest i ng Pr event i on and Avoi dance Measur es
1. 2. 3 Non- St andar d Dr edgi ng Condi t i ons
1. 2. 4 Dr edgi ng and Opt i on Dr edgi ng I t ems
1. 2. 5 Ai r boat
1. 3 EXI STI NG STRUCTURES OR UTI LI TI ES
PART 2 PRODUCTS
2. 1 AI RBOAT
PART 3 EXECUTI ON
3. 1 DREDGI NG
3. 1. 1 Dr edgi ng Regi on
3. 1. 1. 1 Bapt i st e Col l et t e Bar Channel
3. 1. 2 Dr edge Di schar ge Pi pel i ne
3. 1. 3 Bef or e and Af t er Di sposal Sur veys
3. 1. 4 Bef or e and Af t er Dr edgi ng Cr oss- Sect i ons
3. 1. 5 Sur vey Dat a
3. 2 COLONI AL NESTI NG BI RDS
3. 2. 1 Gener al
3. 2. 2 I mpl ement at i on and Repor t i ng
3. 2. 3 No Wor k Di st ances
3. 2. 4 Bi r d Nest i ng Pr event i on and Avoi dance Measur es
3. 2. 5 Di scover y of Bi r d Nest s at t he Wor k Si t e
3. 3 PREVI OUS DREDGI NG CONTRACTS
3. 4 MI NI MUM PRODUCTI ON RATE REQUI REMENTS
3. 5 HORI ZONTAL AND VERTI CAL CONTROL POI NTS
ATTACHMENTS:
Bapt i st e Col l et t e Bar Channel Mai nt enance Dr edgi ng Pl at es
- - End of Sect i on Tabl e of Cont ent s - -
SECTI ON 35 20 23. 23 16 Page 1
SECTI ON 35 20 23. 23 16
HYDRAULI C DREDGI NG - BAPTI STE COLLETTE BAR CHANNEL DREDGI NG REGI ON
PART 1 GENERAL
1. 1 SCOPE
Thi s sect i on det ai l s speci f i c r equi r ement s, whi ch ar e i n addi t i on t o t he gener al r equi r ement s set f or t h i n t he speci f i cat i ons, f or t he Bapt i st e Col l et t e Bar Channel Dr edgi ng Regi on. The wor k cover ed by t hi s sect i on consi st s of f ur ni shi ng al l l abor , mat er i al s, and equi pment , and per f or mi ng al l wor k r equi r ed f or dr edgi ng i n t he speci f i ed dr edgi ng r egi on, except f or t hose measur es set f or t h i n ot her t echni cal por t i ons of t he speci f i cat i ons.
1. 2 MEASUREMENT AND PAYMENT
Payment f or t he wor k cover ed under t hi s sect i on shal l be i ncl uded i n t he cont r act uni t pr i ce per hour f or " Bapt i st e Col l et t e Dr edgi ng" and " Bapt i st e Col l et t e Opt i on Dr edgi ng" except f or " Pr epar at or y Wor k For Bapt i st e Col l et t e Dr edgi ng Regi on" and Opt i on I t em " Bi r d Nest i ng Pr event i on and Avoi dance Measur es" .
1. 2. 1 Base I t em: Pr epar at or y Wor k For Bapt i st e Col l et t e Dr edgi ng Regi on
Al l cost s associ at ed wi t h t he mobi l i zat i on of any dr edge pl ant r equi r ed f or t he Bapt i st e Col l et t e Bar Channel Dr edgi ng Regi on t hat i s i n excess of what was r equi r ed at t he Al gi er s, I HNC, and Har vey Lock For ebays Dr edgi ng Regi on shal l be i ncl uded i n t he cont r act j ob pr i ce f or " Pr epar at or y Wor k For Bapt i st e Col l et t e Dr edgi ng Regi on" . Once dr edgi ng oper at i ons ar e compl et e i n Bapt i st e Col l et t e, payment f or f i nal demobi l i zat i on of t he Cont r act or ' s pl ant and equi pment shal l be i ncl uded i n t he cont r act j ob pr i ce f or " Mobi l i zat i on and Demobi l i zat i on" .
1. 2. 2 Opt i on I t em: Bi r d Nest i ng Pr event i on and Avoi dance Measur es
Al l cost s associ at ed wi t h Bi r d Nest i ng Pr event i on and Avoi dance Measur es shal l be i ncl uded i n t he cont r act uni t pr i ce per day f or Opt i on I t em " Bi r d Nest i ng Pr event i on and Avoi dance Measur es" . Pay t i me f or t hi s opt i on i t em wi l l be measur ed by t he day. A day of per f or mi ng t he nest pr event i on measur es i s def i ned as dawn t o dusk. Nest pr event i on measur es shal l be per f or med as descr i bed i n t he par agr aph ent i t l ed " Bi r d Nest i ng Pr event i on and Avoi dance Measur es" . Por t i ons of a day when t he nest pr event i on measur es ar e r equi r ed wi l l be consi der ed as a f ul l day. Pr i ce and payment shal l const i t ut e f ul l compensat i on f or f ur ni shi ng al l equi pment , l abor , mat er i al s, suppl i es, super vi s i on, r emoval of nest pr event i on measur es, and al l oper at i ons i nci dent al t her et o.
1. 2. 3 Non- St andar d Dr edgi ng Condi t i ons
The f ol l owi ng condi t i ons wi l l be consi der ed non- st andar d:
a. Those condi t i ons descr i bed i n Sect i on 35 20 23. 23, par agr aph ent i t l ed " Dr edgi ng i n Non- St andar d Reaches and Condi t i ons" .
SECTI ON 35 20 23. 23 16 Page 2
b. Any l ocat i ons wi t hi n Bapt i st e Col l et t e Bar Channel wher e t he dr edgi ng t empl at e f r om st at i on 270+00 t o 330+00 yi el ds l ess t han a 150 f oot swi ng wi dt h, and wher e t he dr edgi ng t empl at e f r om st at i on 330+00 t o 590+00 yi el ds l ess t han a 250 f oot swi ng wi dt h wi l l be consi der ed non-standard.
1. 2. 4 Dr edgi ng and Opt i on Dr edgi ng I t ems
Ref er ence Sect i on 35 20 23. 23, par agr aph ent i t l ed " 70% Pay Ti me Hour s" .
Movement of t he dr edge and at t endant pl ant f r om t he Al gi er s, I HNC, and Har vey Lock For ebays Dr edgi ng Regi on t o t he Bapt i s t e Col l et t e Bar Channel Dr edgi ng Regi on wi l l be pai d at 70% of t he cont r act uni t pr i ce per hour f or " Bapt i st e Col l et t e Dr edgi ng" .
1. 2. 5 Ai r boat
Upon r equest by t he Cont r act i ng Of f i cer or hi s/ her aut hor i zed r epr esent at i ve, t he Cont r act or shal l suppl y an ai r boat t o t he Gover nment ' s i nspect or s and agent s. Payment f or t he ai r boat shal l be i ncl uded i n t he " Bapt i st e Col l et t e Dr edgi ng" and " Bapt i st e Col l et t e Opt i on Dr edgi ng" payment i t ems. When t he Cont r act i ng Of f i cer or hi s/ her aut hor i zed r epr esent at i ve r equest s an ai r boat f or a speci f i ed dat e and/ or t i me, t he Cont r act or shal l have t he ai r boat at t he dr edge r eady f or use. The Cont r act i ng Of f i cer or hi s/ her aut hor i zed r epr esent at i ve may r equest t he ai r boat f or ei t her consecut i ve or non- consecut i ve day per i ods.
1. 3 EXI STI NG STRUCTURES OR UTI LI TI ES
The st r uct ur es or ut i l i t i es l i s t ed bel ow ar e known t o be l ocat ed wi t hi n t he dr edgi ng r egi on.
Structure or Ut i l i t y
Owner I nf or mat i on Appr oxi mat e C/ L Station
Elevation ( f eet MLG)
16-inch Pipeline
Thi r d Coast Mi dst r eam
Mr . Robi n Asevado 2402 Bayou Road St Ber nar d, LA 70085 Of f i ce: 504- 800- 6686 Cel l : 504- 812- 7151 rasevado@3cmidstream.com
296+97 -22.0
( 2) 6- i nch Pipelines
( 2) 4- i nch Pipelines
Lobo Oper at i ng, I nc.
Mr . Br i an Dai gl e 1819 West Pi nhook Road, Sui t e Laf ayet t e, LA 70508 Cel l : 985- 249- 1771 ( cal l f i r st ) Of f i ce: 337- 314- 0700 brian.daigle@lobooil.com
300+57 -37.0
SECTI ON 35 20 23. 23 16 Page 3
Structure or Ut i l i t y
Owner I nf or mat i on Appr oxi mat e C/ L Station
Elevation ( f eet MLG)
26-inch Pipeline
Thi r d Coast Mi dst r eam ( see above)
355+76 -24.0
12-inch Pipeline
Thi r d Coast Mi dst r eam ( see above)
373+67 -24.0
2 3/ 8- i nch pipeline
Occi dent al Pet r ol eum ( pr evi ousl y Anadar ko Pet r ol eum) 1201 Lake Robbi ns Dr .
The Woodl ands, TX 77380 1-800-800-1101 par al l el t o channel on east bank unknown
20-inch Del t a Loop Oi l Pi pel i ne
Shel l Pi pel i ne Company
Mr . Kel l y Angel et t e 5317 Bayou Bl ack Dr .
Gi bson, LA 70356 Mai n: 985- 858- 2600 Of f i ce: 985- 858- 2570 Cel l : 985- 688- 7446 kelly.angelette@shell.com
543+53.57 -26.9
PART 2 PRODUCTS
Al t hough l i s t ed under PART 2 PRODUCTS, t he equi pment descr i bed her ei n r emai ns t he pr oper t y of t he Cont r act or at al l t i mes.
2. 1 AI RBOAT
The Cont r act or shal l pr ovi de an ai r boat , f ul l y oper at i onal , wi t h oper at or and f uel . The ai r boat shal l be capabl e of t r anspor t i ng t hr ee passenger s and shal l be equi pped wi t h noi se pr ot ect i on f or t he passenger s.
PART 3 EXECUTI ON
3. 1 DREDGI NG
3. 1. 1 Dr edgi ng Regi on
3. 1. 1. 1 Bapt i s t e Col l et t e Bar Channel
a. The aut hor i zed di mensi ons f or Bapt i st e Col l et t e Bar Channel ar e - 14 f eet Mean Low Gul f ( MLG) by 150 f eet bot t om wi dt h f r om St at i on 270+00 t o 320+00, wi t h a t r ansi t i on t o - 16 f eet MLG by 250 f eet f r om St at i on 320+00 t o 330+00, and - 16 f eet MLG by 250 f eet f r om St at i on 330+00 t o 590+00. The Cont r act i ng Of f i cer or hi s/ her aut hor i zed r epr esent at i ve may i ssue dr edgi ng assi gnment s f or al l or por t i ons of t hi s dr edgi ng r egi on. Each dr edgi ng assi gnment wi l l def i ne t he dr edgi ng t empl at e t o be dr edged by t he Cont r act or . The dr edgi ng t empl at e wi l l i nc l ude t he swi ng wi dt h, t he s i de s l ope, and t he speci f i ed el evat i on. The speci f i ed el evat i on i n t he dr edgi ng assi gnment wi l l not exceed 2 f eet bel ow t he aut hor i zed el evat i on and may be speci f i ed above t he aut hor i zed di mensi ons when det er mi ned t o be benef i c i al t o t he
SECTI ON 35 20 23. 23 16 Page 4
Government.
b. Di sposal of dr edged mat er i al wi l l be at t he Gover nment ' s di r ect i on. Appr oved di sposal s i t es ar e l i s t ed bel ow and shown on t he Bapt i st e Col l et t e Bar Channel Mai nt enance Dr edgi ng Pl at es.
(1) Wet l and Cr eat i on Si t es/ Di sposal Ar eas " A" and " B" : Mat er i al dr edged bet ween appr oxi mat e C/ L St at i ons 270+00 and 420+00 shal l be pl aced unconf i ned i n Di sposal Ar ea " A" and/ or Di sposal Ar ea " B" . Dr edged mat er i al shal l be pl aced bet ween t he j et t i es and exi st i ng mar sh and st acked t o a hei ght not t o exceed t he west j et t y ( +4. 5 f eet MLG) i n Di sposal Ar ea A or t he east j et t y ( +5. 5 f eet MLG) i n Di sposal Ar ea B. Thi s hei ght may be f i el d adj ust ed dependi ng on obser ved l ocal t i dal el evat i ons dur i ng di sposal oper at i ons. Access t o t hese di sposal ar eas shal l be acr oss t he exi st i ng j et t i es and/ or v i a Br et on Sound. The Cont r act or shal l t ake pr ecaut i ons when per f or mi ng di sposal oper at i ons, i n or der t o pr event damage t o t he exi st i ng r ock j et t i es and exi st i ng wet l ands. At no t i me shal l dr edge ef f l uent mat er i al be al l owed t o exceed one f oot i n hei ght over exi st i ng veget at ed wet l ands.
(2) Pl over I s l and, Shea I s l and, Gunn I s l and, and New Bi r d I s l and Si ngl e Poi nt Di schar ge ( SPD) : Mat er i al dr edged bet ween appr oxi mat e C/ L St at i ons 420+00 and 590+00 shal l be pl aced on Pl over I s l and, Shea I s l and, Gunn I s l and, and/ or t he New Bi r d I s l and SPD i n or der t o cr eat e a new bi r d i s l and, l ocat ed bet ween exi st i ng bi r d br eedi ng i s l ands Shea and Wi l l et . For Gunn I s l and and New Bi r d I s l and, t he dr edged mat er i al shal l i ni t i al l y be di schar ged at t he Si ngl e Poi nt Di schar ge ( SPD) l ocat i ons shown on t he pl at e, but f i el d adj ust ment s may be made as di r ect ed by t he Gover nment . For Gunn I s l and, dr edged mat er i al may be pl aced i n open wat er s adj acent t o t he i s l and, but no di r ect pl acement of mat er i al i s al l owed on t he i s l and. For Pl over and Shea I s l and, t he exact di schar ge l ocat i on( s) wi l l be di r ect ed by t he Gover nment , and dr edged mat er i al may be pl aced on exi st i ng veget at i on or i n open wat er s adj acent t o t he i s l ands. The el evat i on of t he dr edged mat er i al pl aced on t he bi r d i s l ands shal l not exceed +10. 0 f eet MLG. The Cont r act or shal l mai nt ai n at al l t i mes a mi ni mum di st ance of 2, 000 f eet at el evat i on 0. 0 f eet MLG bet ween Gunn I s l and and Shea/ New Bi r d I s l and, and bet ween Pl over I s l and and Shea/ New Bi r d I s l and.
3. 1. 2 Dr edge Di schar ge Pi pel i ne
The Cont r act or shal l pr ovi de 8, 000 f eet of ser vi ceabl e f l oat i ng, submer ged, or shor e pi pel i ne and al l associ at ed equi pment as di r ect ed by t he Gover nment . See Sect i on 35 20 23. 23, par agr aph ent i t l ed " Dr edge Di schar ge Pi pel i ne" , f or addi t i onal i nf or mat i on r egar di ng pi pel i ne r equi r ement s.
3. 1. 3 Bef or e and Af t er Di sposal Sur veys
a. Bef or e and af t er di sposal sur veys shal l be t aken at t he Gover nment ' s di r ect i on at each di sposal s i t e. Soundi ngs and/ or r od r eadi ngs shal l be r ecor ded t o t he near est t ent h of a f oot and t he di st ance bet ween soundi ngs and/ or r od r eadi ngs shal l not exceed 50 f eet . The sur veys shal l ext end t o adequat el y cover t he ar ea i mpact ed by dr edged mat er i al pl acement .
b. Di sposal Ar eas " A" , " B" , Pl over I s l and, Shea I s l and, Gunn I s l and, SECTI ON 35 20 23. 23 16 Page 5 and New Bi r d I s l and: The Cont r act or shal l t ake a mi ni mum of t hr ee di sposal cr oss sect i ons nor mal t o t he channel cent er l i ne and t hr ee di sposal cr oss sect i ons par al l el t o t he channel cent er l i ne. These cr oss sect i ons shal l be t aken pr i or t o and f ol l owi ng pl acement of dr edged mat er i al . I nt er val s and l ocat i ons wi l l be det er mi ned by t he Cont r act i ng Of f i cer ' s Repr esent at i ve.
c. Al l sur veys shal l be t i ed/ r ef er enced t o t he cent er l i ne of t he channel . Al l not es r esul t i ng f r om t hese sur veys shal l be pr esent ed t o t he Cont r act i ng Of f i cer ' s Repr esent at i ve. The Cont r act or shal l pr ovi de a t opogr aphi c pl ot of each di sposal s i t e. The pl ot shal l have cont our i nt er val s of not l ess t han 1 f oot and a scal e of 1 i nch = 100 f eet .
The bef or e and af t er di sposal sur veys shal l be f ur ni shed t o t he Gover nment i n a Mi cr ost at i on ver s i on 5. 07. 01. 22 ( or updat ed) desi gn f i l e cont ai ni ng sur vey el evat i ons wi t h cont our s i n one f oot i ncr ement s. A har d copy of t he bef or e and af t er di sposal sur veys wi t h cont our s shal l al so be f ur ni shed t o t he Gover nment . Al l sur vey dat a shal l be i n NAD 83. Dat a shal l al so be f ur ni shed t o t he Gover nment i n a comput er i zed I BM- compat i bl e st r uct ur ed ASCI I f or mat on magnet i c medi a. Each di sk submi t t ed shal l bear a pr e- pr i nt ed di sk l abel t hat pr ovi des f or di sk cont ent s, have a wr i t e pr ot ect seal mechani sm, and pr ovi de a space t o i ndi cat e di sk v i r us check. Al l di sks submi t t ed shal l be v i r us checked, c l ear ed of v i r uses i f necessar y, and al l di sk l abel ent r i es compl et ed. Al l di sposal sur veys shal l be submi t t ed and accept ed bef or e f i nal payment i s made t o t he Cont r act or . I n addi t i on, copi es of t he bef or e and af t er di sposal sur veys shal l be submi t t ed t o Mr . Jef f Cor bi no el ect r oni cal l y at Jef f r ey. M. Cor bi no@usace. ar my. mi l or by har d copy t o t he addr ess l i s t ed bel ow:
US Ar my Cor ps of Engi neer s New Or l eans Di st r i c t At t n: Mr . Jef f Cor bi no, CEMVN- ODT- E Room 291 7400 Leake Ave New Or l eans, LA 70118
3. 1. 4 Bef or e and Af t er Dr edgi ng Cr oss- Sect i ons
I n addi t i on t o t he r equi r ement s i n Sect i on 35 01 50. 73, par agr aph ent i t l ed " Bef or e and Af t er Dr edgi ng Cr oss Sect i ons" , t he bef or e and af t er dr edgi ng cr oss- sect i ons of t he channel shal l be t aken at appr oxi mat el y 200- f oot i nt er val s al ong t he channel , as wel l as at al l ut i l i t y cr ossi ngs and at al l P. C. ' s, P. T. ' s , P. I . ' s , and P. O. T' s. Dept h soundi ngs shal l be made wi t h t he hydr ogr aphi c sur veyi ng syst em and t he r ecor ded soundi ng densi t y shal l be one soundi ng f or ever y f i ve f eet . The gr aphi cal char t l ayout must r epr esent a scal ed pl an v i ew of t he sur vey ar ea wi t h t he r ecor ded f i ve- f oot i nt er val dept h soundi ngs ( 0. 1 f t . r esol ut i on) pl ot t ed at t hei r x, y posi t i ons. The act ual l ocat i on of each soundi ng t aken on each bef or e dr edgi ng cr oss sect i on r ange shal l be pr ovi ded i n t he f or m of a pr i nt out t abul at i on gi v i ng t he act ual di st ance of t he soundi ngs f r om t he cent er l i ne ( on an azi mut h nor mal t o t he cent er l i ne of t he cut ) .
3. 1. 5 Sur vey Dat a
I n addi t i on t o t he r equi r ement s i n Sect i on 35 01 50. 73, par agr aph ent i t l ed " Sur vey Dat a" , t he Cont r act or shal l pr ompt l y pl ot t he channel cr oss sect i ons on a scal e of 1 i nch = 200 f eet hor i zont al and 1 i nch = 5 f eet vertical.
SECTI ON 35 20 23. 23 16 Page 6
3. 2 COLONI AL NESTI NG BI RDS
3. 2. 1 Gener al
Col oni al nest i ng wadi ng bi r ds ( i ncl udi ng but not l i mi t ed t o, her ons, egr et s, and I bi s) and seabi r ds/ wat er - bi r ds ( i ncl udi ng, but not l i mi t ed t o t er ns, gul l s, Bl ack Ski mmer s, and Br own Pel i cans) ar e known t o nest i n t he pr oj ect ar ea. The nest i ng bi r ds and t hei r nest s must not be di st ur bed or dest r oyed. The nest i ng act i v i t y per i od ext ends f r om 15 Febr uar y t hr ough 15 Sept ember . Dr edgi ng act i v i t y dur i ng t hi s per i od may be subj ect t o addi t i onal r equi r ement s as st at ed bel ow.
3. 2. 2 I mpl ement at i on and Repor t i ng
a. I n addi t i on t o t he r equi r ement s i n Sect i on 01 57 20. 00 10, par agr aph ent i t l ed " I mpl ement at i on and Repor t i ng" , t he Cont r act or shal l al so submi t t he Bi r d Nest i ng Pr event i on Pl an. See t he par agr aph of t hi s sect i on ent i t l ed " Bi r d Nest i ng Pr event i on and Avoi dance Measur es" .
b. The pr esence of nest i ng wadi ng bi r ds and/ or seabi r ds/ wat er - bi r ds wi t hi n t he mi ni mum di st ances f r om t he wor k ar ea, as speci f i ed i n t he par agr aph ent i t l ed " No Wor k Di st ances" , shal l be i mmedi at el y r epor t ed t o Mr . Jef f Cor bi no of t he U. S. Ar my Cor ps of Engi neer s at ( 504) 862-1958.
3. 2. 3 No Wor k Di st ances
No- wor k di st ance r est r i c t i ons ar e as f ol l ows:
Ter ns, gul l s, and Bl ack Ski mmer s - 650 f eet Col oni al nest i ng wadi ng bi r ds - 1000 f eet Br own Pel i cans - 2000 f eet .
Coor di nat i on by t he New Or l eans Di st r i c t per sonnel wi t h t he U. S. Fi sh and Wi l dl i f e Ser vi ce may r esul t i n a r educt i on or r el axi ng of t hese no- wor k di st ances dependi ng on t he speci es of bi r ds f ound nest i ng at t he wor k s i t e and speci f i c s i t e condi t i ons.
3. 2. 4 Bi r d Nest i ng Pr event i on and Avoi dance…