A21 - W912P820B0012 AM0001.pdf

PDF 870 KB Posted

Attached to
Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Hopper Dredge
Solicitation number
W912P820B0012
Issued by

About this file

This solicitation seeks proposals for a hopper dredge rental contract to maintain shipping channels along the Mississippi River and Gulf of Mexico. The work includes furnishing a fully crewed self-propelled trailing suction hopper dredge from July 2021 through November 2021, with an option to extend, to dredge areas including the Mississippi River Southwest Pass. The estimated value of the contract is between $5-10 million. Offerors must register in SAM to be eligible for award. Proposals are due by September 2021 through the DoD Safe website, with the bid opening to be held via teleconference. The contract will be awarded on an unrestricted basis.

View the file

Other files

File Type Posted
B01 - W912P820B0012 Abstract.pdf PDF
W912P820B0012-0002.pdf PDF
W912P820B00012 Solicitation Package .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The subject Solicitation Mississippi River, Baton Rouge to Gulf of Mexico, Southw est Pass Hopper Dredge Contract No. 9-2020, Plaquemines Parish, Louisiana (OM-20-009) has been modified to provide specific details on how contractors are to submit Bids, Bonds and the Conference Call details for the Virtual Bid Opening w hich is now scheduled for Monday, September 21, 2020 at 11:30 AM CST. The Contracting Officer and Contract Specialist w ill begin dow nloading bids at 11:00 AM CST, w hich is the bid receipt cutoff time. All bids received after 11:00 AM CST on Monday, September 21, 2020w ill be considered late. See the attached pages.

For any questions, please contact the Contracting Officer, (Margaret C. Maine 504-862-2211), or the Contract Specialist, (Karen Hargrave, 504-862-1561).

1. CONTRACT ID CODE PAGE OF PAGES

1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P820B0012

X 9B. DATED (SEE ITEM 11)

14-Nov-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

AM0001

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Sep-2020

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P820B0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - SF 30 CONTINUATION

The following have been added by full text:

AM0001

SUBJECT: Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Hopper Dredge Contract No. 9- 2020, Plaquemines Parish, Louisiana (OM-20-009). Solicitation No. W912P820B0012.

1. General Comment: This solicitation will be used to dredge the channel for both maintenance and new construction. The new construction dimensions of the channel are -50.0 ft MLLW by 750 ft bottom width from Mile 6.0 AHP to Mile 17.5 BHP, then narrowing to 600 ft wide through the jetty channel and bar channel. The specified elevation in the dredging assignment will not exceed -56.0 ft MLLW. Previously, the specified elevation in dredging assignments did not exceed -54.5 ft MLLW.

2. General comment: Delete any reference within the specifications to Edward Creef and replace with the following point of contact: Jeff Corbino, phone: (504) 862-1958, email: Jeffrey.M.Corbino@usace.army.mil.

3. General comment: For all project titles, delete the word “rental”.

4. Page 2, Solicitation Letter: “Description and Magnitude of Work”: In the first sentence, delete “on a rental basis”.

5. Standard Form 1442, box 10: In the fourth paragraph, delete the first sentence and replace with “The

Contractor will furnish one fully-crewed and equipped self-propelled trailing suction type hopper dredge.”

6. Standard Form 1442, box 11: Delete “within 5 calendar days” and replace with “no earlier than 15 July 2021 and no later than 15 August 2021”.

7. Section 00010, paragraph 1.1 “Bidding Schedules”: Delete this paragraph in its entirety and replace with the attached paragraph 1.1 entitled “Bidding Schedules”.

8. Section 00010, paragraph 1.2 “Bid Form Notes”: Add the following subparagraph g to the end of the paragraph: “g. The Dredging Items (“Dredging” and “Option Dredging”) unit price shall be determined using a fuel price of $1.50 per gallon. A fuel price adjustment shall be made monthly for the Dredging Items, upward or downward, to reflect the percentage change in the fuel price as described in Section 01 30 00, paragraph entitled “Fuel Price Adjustment”.”

9. Section 00010, paragraph 1.2 “Bid Form Notes”: Add the following subparagraph h to the end of the paragraph: “h. The Item 0002 work must be completed by 30 November 2021. If the hours for the bid lot selected would extend past this required completion date additional hopper dredge(s) must be added to this contract, as described in Section 35 20 23.23 paragraph entitled “Addition of Plant”, to ensure the Item 0002 work is completed by 30 November 2021.”

10. Section 00010, paragraph 1.5 “Conditions of Contract Award”, subparagraph c: Delete this paragraph in its entirety and replace with the following:

“The number of hours for each bid lot of the bidding schedule are estimated quantities. The dredge and attendant plant will be retained until 30 November 2021, or the completion of Item 0002. In the event Option Item 0003 is fully exercised under the terms of the contract, the time required for completion of the contract shall be extended by the number of calendar days listed in column "Approximate Number of Days for Option Item 0003" for the applicable bid lot in the table below, entitled “Hopper Dredge Contract Duration”. In the event Option Item 0003 is partially exercised, the contract completion date shall be extended using the following formula:

[(partial option hours exercised)/(option hours listed in bid schedule for applicable bid lot)] x (calendar days listed in column "Approximate Number of Days for Option Item 0003" for the applicable bid lot).”

11. Section 00010, paragraph 1.5 “Conditions of Contract Award”, subparagraph c, table entitled “Approximate Hopper Dredge Contract Duration (Base Plus Option)”: Delete this table in its entirety and replace with the attached table entitled “Hopper Dredge Contract Duration”.

12. Section 00010, paragraph 1.5 “Conditions of Contract Award”, subparagraph d: Delete “within 120 hours after receipt of Notice to Proceed by the Contractor” and replace with “no earlier than 15 July 2021 and no later than 15 August 2021”.

13. Section 00700, FAR Clause 52.211-10 "Commencement, Prosecution, and Completion of Work (Apr 1984)":

Delete this clause in its entirety and replace with the following:

“52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract no earlier than 15 July 2021 and no later than 15 August 2021, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than as described in Section 00010-1.5 of the bidding schedule.”

14. Section 00800, paragraph 3.1 “Delivery of Plant”, subparagraph a: Delete the first sentence and replace with the following: “Delivery of the dredge and attendant plant and commencement of dredging shall be completed no earlier than 15 July 2021 and no later than 15 August 2021.”

15. Section 00800, paragraph 3.2 “Prosecution, Option and Completion”, subparagraph a: In the last sentence, delete “time runs” and replace with “available hours run”.

16. Section 00800, paragraph 3.2 “Prosecution, Option and Completion”, subparagraph b: Delete this paragraph in its entirety and replace with the following: “This contract shall be completed by 30 November 2021.

Additional time may be added to the contract if any or all of the “Option Dredging” hours are exercised. If all necessary work is completed prior to the completion date, the Government will release the dredge and declare the contract complete.”

17. Section 00800, paragraph 3.2 “Prosecution, Option and Completion”, subparagraph d: In the first sentence, delete “option rental hours” and replace with “option hours”.

18. Section 00800, paragraph 3.4 “Equipment Ownership and Operating Expense Schedule”: Delete this paragraph in its entirety and replace with attached paragraph 3.4 entitled “Construction and Architect-Engineer (A-E) Contracts (UAI 5131.105)”.

19. Section 01 30 00, Part 1 “General”: Insert the attached paragraph 1.16 “Fuel Price Adjustment” after existing paragraph 1.15 “E-Verify Program”.

20. Section 01 57 20.00 10, paragraph 3.13 “Partial List of NMFS-Approved Protected Species Observers”: For Coastwise Consulting, add “Cell: 760-540-6655” and add POC “Gib Frye at 865-771-0081”.

21. Section 35 20 23.23, paragraph 1.2.2.1 “Unit of Measure”, subparagraph a: In the last sentence, delete “rental”.

22. Section 35 20 23.23, Part 2 “Products”: In the first sentence, delete “due to the fact that the services of the equipment are leased by the Government,”.

23. Section 35 20 23.23, paragraph 2.2 “Gages”: Delete subparagraph d in its entirety and replace with the attached paragraph d.

24. Section 35 20 23.23, paragraph 2.2 “Gages”, subparagraph g: Delete the third sentence in the first paragraph.

25. Section 35 20 23.23, paragraph 3.1 “Location and Description of Work”, subparagraph a: Delete the first sentence and replace with the following, “The dredge will be used for maintenance dredging and new construction operations in the location described in the paragraph entitled “Primary Dredging Region”.”

26. Section 35 20 23.23, paragraph 3.3.1 “Mississippi River and Southwest Pass, Louisiana”: Delete the first two sentences of the paragraph and replace with: “The authorized dimensions of the channel are -50 feet Mean Lower Low Water (MLLW) datum by 750 feet bottom width from New Orleans to Mile 17.5 Below Head of Passes, then narrowing to 600 feet wide through the jetty channel and bar channel.”

27. Section 35 20 23.23, paragraph 3.4 “Secondary Dredging Regions”: In the first paragraph, delete the second sentence. In the third sentence, delete “applicable contract unit price” and replace it with “contract unit price per hour”.

28. Section 35 20 23.23, paragraph 3.8 “Work For Others”: Insert the following as subparagraph c, and rename existing subparagraph c as subparagraph d: “c. If the dredge returns to an assignment in another dredging region and the dredge in tow never enters the route that would have been taken had the dredge not been released, when dredged material starts flowing into the hopper; or”.

29. Section 35 20 23.23, paragraph 3.10.1 “Mississippi River & Southwest Pass”: For the 8” Hilcorp/Harvest

Pipeline at approx. Station 534+13, change the email address for Mark Bordelon to “mbordelon@harvestmidstream.com”.

Section 00010, Paragraph 1.1 “Bidding Schedules”:

1.1 BIDDING SCHEDULES

SECTION 00010 – BIDDING SCHEDULE

MISSISSIPPI RIVER, BATON ROUGE TO GULF OF MEXICO, SOUTHWEST PASS

HOPPER DREDGE RENTAL CONTRACT NO. 9-2020

PLAQUEMINES PARISH, LOUISIANA

SOLICITATION NO. W912P820B0012

LOT ONE (Ellis Island), 34 inch Inside Diameter (ID) Pump Suction, 14,788 cubic yard Nominal Hopper Capacity, Two Dragarms and all attendant plant

Bid Item

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

2070 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

690 Hour XXXXXXXX XXXXXXXX

Total: LOT ONE BID

*SEE BID FORM NOTES

*A FUEL PRICE OF $1.50 PER GALLON SHALL BE USED TO DETERMINE THE DREDGING

ITEMS UNIT PRICE. SEE BID FORM NOTE “G” AND SECTION 01 30 00, PARAGRAPH

ENTITLED “FUEL PRICE ADJUSTMENT”, FOR MORE INFORMATION.

LOT TWO (Glenn Edwards), 38 inch Inside Diameter (ID) Pump Suction, 12,430 cubic yard Nominal Hopper Capacity, Two Dragarms and all

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

2160 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

720 Hour XXXXXXXX XXXXXXXX

Total: LOT TWO BID

LOT THREE (Stuyvesant), 33.5 inch Inside Diameter (ID) Pump Suction, 9,400 cubic yard Nominal Hopper Capacity, Two Dragarms and all

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

2849 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

950 Hour XXXXXXXX XXXXXXXX

Total: LOT THREE BID

LOT FOUR (Terrapin Island), 33.5 inch Inside Diameter (ID) Pump Suction, 6,300 cubic yard Nominal Hopper Capacity, Two Dragarms and all

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

3481 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1160 Hour XXXXXXXX XXXXXXXX

Total: LOT FOUR BID

LOT FIVE (Magdalen), 39.37 inch Inside Diameter (ID) Pump Suction, 8,300 cubic yard Nominal Hopper Capacity, One Dragarm and all attendant plant

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

3736 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1245 Hour XXXXXXXX XXXXXXXX

Total: LOT FIVE BID

HOPPER DREDGE RENTAL CONTRACT NO. 7-2020

SOLICITATION NO. W912P820B0010

LOT SIX (Liberty Island), 31.5 inch Inside Diameter (ID) Pump Suction, 6,540 cubic yard Nominal Hopper Capacity, Two Dragarms and all

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

3901 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1300 Hour XXXXXXXX XXXXXXXX

Total: LOT SIX BID

LOT SEVEN (Bayport), 30 inch Inside Diameter (ID) Pump Suction, 4,815 cubic yard Nominal Hopper Capacity, Two Dragarms and all attendant

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

4004 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1335 Hour XXXXXXXX XXXXXXXX

Total: LOT SEVEN BID

LOT EIGHT (BE Lindholm), 28 inch Inside Diameter (ID) Pump Suction, 4,000 cubic yard Nominal Hopper Capacity, Two Dragarms and all

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

4301 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1434 Hour XXXXXXXX XXXXXXXX

Total: LOT EIGHT BID

LOT NINE (Dodge Island, Padre Island), 27 inch Inside Diameter (ID) Pump Suction, 3,600 cubic yard Nominal Hopper Capacity, Two Dragarms and all attendant plant

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

4852 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1617 Hour XXXXXXXX XXXXXXXX

Total: LOT NINE BID

LOT TEN (Newport), 26 inch Inside Diameter (ID) Pump Suction, 4,000

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

5340 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1780 Hour XXXXXXXX XXXXXXXX

Total: LOT TEN BID

LOT ELEVEN (RN Weeks), 27 inch Inside Diameter (ID) Pump Suction, 3,700

Description Estimated Quantity

Unit Fuel Price

(per gallon) Unit Price

Total Price

Mobilization & Demobilization of hopper dredge and all attendant plant.

1 Job -

Dredging - Rental of a trailing type hopper dredge.

5590 Hour $1.50

Option

Option Dredging - Same plant listed in Item No. 0002 of this bid lot.

1863 Hour XXXXXXXX XXXXXXXX

Total: LOT ELEVEN BID

Section 00010, paragraph 1.5.c, table entitled “Hopper Dredge Contract Duration”

HOPPER DREDGE CONTRACT DURATION

Bid Lot Pump Inside

Dia.

(inches)

Hopper Size (Cubic Yards)

Number of Dragarms

Completion Date for Item 0002

Approximate Number of Days for

Option Item

1 34 14788 2 30 November 2021 42

2 38 12430 2 30 November 2021 43

3 33.5 9400 2 30 November 2021 54

4 33.5 6300 2 30 November 2021 63

5 39.37 8300 1 30 November 2021 67

6 31.5 6540 2 30 November 2021 70

7 30 4815 2 30 November 2021 71

8 28 4000 2 30 November 2021 76

9 27 3600 2 30 November 2021 84

10 26 4000 2 30 November 2021 92

11 27 3700 2 30 November 2021 96

Section 00800, paragraph 3.4 “Equipment Ownership and Operating Expense Schedule”:

3.4 CONSTRUCTION AND ARCHITECT-ENGINEER (A-E) CONTRACTS (UAI 5131.105)

(d)(2)(i)(B) For the predetermined schedule of construction equipment use rates, use Engineer Pamphlet (EP) 1110- 1-8, Construction Equipment Ownership and Operating Expense Schedule.

(End of special contract requirement)

Note 1: Reference "Construction and Architect-Engineer Contracts" (FAR 31.105). Costs for repairs or overhauling are not allowed.

Note 2: A copy of the "EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE" (Region III) can be obtained from the following website:

https://www.publications.usace.army.mil/Portals/76/Users/182/86/2486/EP%201110-1- 8%20Vo3%20.pdf?ver=2019-12-02-104221-527

Section 01 30 00, Part 1 “General”, paragraph 1.16 “Fuel Price Adjustment”:

1.16 FUEL PRICE ADJUSTMENT

a. The fuel price adjustment shall be made monthly for the item identified below, upward or downward, to reflect the percentage change in the fuel price index of the Bureau of Labor Statistics (BLS) Producer Price Indexes for #2 diesel fuel, WPU 057303 (Not Seasonally Adjusted). For the purpose of this clause, the term "fuel cost per contract unit" means that part of the contract unit price of the dredging operation that is attributable solely to the cost of fuel.

The fuel cost per contract unit is established below:

Dredging Items........................13.7% of contract unit price

b. The Preliminary BLS Producer Price Index for No. 2 diesel fuel, WPU 05703, available on the BLS website for the August 2020 price shall be recorded in contract documents and shall serve as the basis of any price adjustments throughout the contract, to include any option periods, if exercised. The monthly fuel price adjustment shall be calculated by multiplying the fuel cost per contract unit as determined above, by the percentage change in the Preliminary BLS Indices, by the quantity of work performed under the item.

Fuel Price Adjustment for Dredging Items = [(Dollar Amount of Dredging Items)*(0.137)*(Latest Preliminary BLS Index - Preliminary BLS Index for August 2020)] / [Preliminary BLS Index for August 2020]

A price adjustment, upward or downward, shall be made on each monthly payment. Option periods, if exercised, shall be calculated in the same manner, always comparing to the Preliminary BLS Index for August 2020. If any preliminary index is later revised by the BLS, this contract will not be adjusted based upon the revision.

The Dredging Item’s unit price will be adjusted using the formula provided above, as shown in the example below.

Example fuel adjustment calculation:

If a contract is awarded with a Dredging Item unit price of $3000 / hour the Dredging Item unit price will be adjusted as shown below. The Preliminary BLS Index for August 2020 and an example Preliminary BLS Index value for August 2021 are listed below for the purposes of the example calculation:

Preliminary BLS Index for August 2020 = 192.1 (actual) Preliminary BLS Index for August 2021 = 200.0 (example – for calculations)

Fuel Price Adjustment for Dredging Items = [(Dollar Amount of Dredging Items)*(0.137)*(Latest Preliminary BLS Index - Preliminary BLS Index for August 2020)] / [Preliminary BLS Index for August 2020]

August 2021 Fuel Price Adjustment = [($3000)*(0.137)*(200.0-192.1)] / [192.1] = $16.90/hour

Section 35 20 23.23, paragraph 2.2 “Gages”, subparagraph d:

d. The following staff gages shall be used for the Southwest Pass dredging region.

GAGE NAME (ID) LOCATION (MILE) GAGE CORRECTION

TO MLLW

Venice (01480) 10.5 AHP (RDB) (-) 0.53 Pilottown (01525) 2.0 AHP (LDB) (-) 0.70

WH-7 (01545) -0.5 BHP (LDB) (-) 0.47

Mile 7.5 (01575) -7.2 BHP (RDB) (-) 0.27

Light #14 (01625) -12.0 BHP (LDB) (-) 0.02 East Jetty (01670) -17.9 BHP (LDB) 0.31

Note: The gage corrections shall be added to the gage readings to adjust them to MLLW.

UPDATED WAGE DETERMINATION

"General Decision Number: LA20200007 01/03/2020

Superseded General Decision Number: LA20190007

State: Louisiana

Construction Type: Heavy Dredging

Counties: Louisiana Statewide.

DREDGING PROJECTS ALONG THE GULF COAST AREA INCLUDING THE

MISSISSIPPI RIVER AND ITS TRIBUTARIES TO THE OHIO RIVER

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020

* SULA1994-001 04/01/1994

Rates Fringes

Derrick Operator.................$ 7.25

Dozer Operator...................$ 7.25

Dredge 16"" and Over Deckhand....................$ 7.25 Dredge tender operator......$ 7.25 Fireman.....................$ 7.25 First assistant engineer....$ 7.25 Leverman....................$ 7.25 Oiler.......................$ 7.25 Second assistant engineer...$ 7.25 Shoreman....................$ 7.25 Third assistant engineer....$ 7.25 Truck driver................$ 7.25 Welder......................$ 7.25

Dredge Under 16"" Deckhand....................$ 7.25 Dredge tender operator......$ 7.25 Leverman....................$ 7.25 Oiler.......................$ 7.25 Welder......................$ 7.25

Hydraulic Dredging First cook..................$ 7.25 Handyman....................$ 7.25 Janitor, cabin person.......$ 7.25 Second cook.................$ 7.25

Marsh Buggy Dragline, Oiler......$ 7.25

Marsh Buggy Dragline, Operator...$ 7.25

Self-Propelled Hopper Dredge, Drag Tender......................$ 9.70 3.45+a

FOOTNOTE: Fourteen paid vacation days and eight paid holidays: New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving

Day & Christmas Day provided the employee has one year of service.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

VBO INSTRUCTIONS

INSTRUCTION TO BIDDERS

Due to the response for COVID-19, most federal employees have been mandated to telework, and currently only authorized personnel are allowed access to the District buildings throughout USACE. As a result, we have implemented the below procedures for all current and future bid openings, until such restrictions have been lifted and normal access has resumed at the MVN HQ Building.

Electronic Submission of Bids:

MVN will utilize the DoD Safe website for receipt of electronic bids under IFB Solicitations. In order to submit an electronic bid please follow these steps:

1. Send an email containing your name and email address to the Contracting Officer and Contract Specialist associated with the IFB:

Contracting Officer – Ms. Margaret C. Maine, email: Margaret.C.Maine@usace.army.mil Contract Specialist – Ms. Karen Hargrave, email: karen.d.hargrave@usace.army.mil

2. The Contracting Officer or Contract Specialist will go to the DoD Safe site, input your name and email address, and then will request the file from you. You will then receive an automated email from the site with a unique link in the email.

3. Once the email with the link is received, please click on the link in the email, which will take you to the DoD Safe site.

4. This will be a unique webpage where you can upload your file. The default page will load with the box checked off next to, “Send me an email when each recipient picks up the files”.

Please leave this box checked in order to receive a notification when the file is received from the Contracting Officer or Contract Specialist. Please leave unchecked, “Encrypt every file”. The site itself contains a high level of security in which additional encryption is not required.

5. When you are ready to upload your bid file (please use pdf format for bid submission), you can either click the blue button which says, “Click to Add Files or Drag Them Here” to locate the file on your computer, or simply drag the file onto the screen.

6. In the Description box that appears after uploading your file, please type your Company Name.

7. Click the button that appears at the bottom of the page, “Drop-off Files”. A banner will pop-up asking for confirmation that your upload does not contain Classified Information. Click ok on the banner.

8. You will be taken to a confirmation page that should say, “Drop-Off Completed” at the top.

This is your confirmation that your file was successfully uploaded to the site.

9. The Contracting Officer or Contract Specialist will receive an automated email stating that the file has been submitted. They will then send an email back to the company, confirming that they received the notice from the DoD Safe site.

The Bid Opening is currently scheduled for Monday, September 21, 2020 at 11:30 AM CST.

The Contracting Officer and Contract Specialist will begin downloading bids at 11:00 AM CST, which is the bid receipt cutoff time. All bids received after 11:00 AM CST on Monday, September 21, 2020 will be considered late.

Audio Teleconference Bid Opening Information:

Bid Opening will be held on Monday, September 21, 2020 at 11:30 AM CST. Please use the following call-in information to attend the meeting:

Toll-Free: 844-291-6362 Access Code: 207837

Following the conclusion of the bid opening, the Bid Abstract will be uploaded to Beta.SAM website under this solicitation, within 24 hours.

Bid Bonds (Offer Guarantee) should be submitted electronically with the Bid Package as per the scheduled Bid Opening on Amendment. As per Class Deviation 2020-O0016, Electronic signatures and electronic, mechanically-applied, or printed dates may be used and shall be considered original signatures and dates. In addition, a Corporate Seal is not required, the SF 28 need not be sworn and notarized and a written authorization of the release signed by the surety is acceptable in lieu of the notarized authorization of release by the surety. Original Certified Bonds need not be submitted at time of bid. USACE MVN Contracting Division reserves the right to request the Original Certified Bonds, if deemed necessary to verify their authenticity.

The following deviation clauses now apply, in lieu of the corresponding FAR clauses:

52.228-11, Pledges of Assets (DEVIATION 2020-O0016), which removes the requirement for the Standard Form 28 to be sworn and notarized.

52.228-15, Performance and Payment Bonds—Construction (DEVIATION 2020- O0016), which removes the requirements for seals on Standard Forms.

52.228-16, Performance and Payment Bonds—Other than Construction (DEVIATION 2020-O0016), which removes requirements for seals on Standard Forms.

For any Questions please contact:

Contracting Officer – Ms. Margaret C. Maine, email: Margaret.C.Maine@usace.army.mil Phone: 504-862-2211

Contract Specialist – Ms. Karen Hargrave, email: karen.d.hargrave@usace.army.mil ;

Phone: 504-862-1561

(End of Summary of Changes)