A22_-_Solicitation_W912P818B0054.pdf
PDF 2 MB Posted
- Attached to
- Mississippi River & Tributaries, Old River Lock, New Miter Gates, Pointe Coupee Parish, LA
- Solicitation number
- W912P818B0054
About this file
Solicitation and Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| A22_-_Amendment_0003.pdf | ||
| A22_-_Amendment_0002.pdf | ||
| A22_-_Amendment_0001.pdf | ||
| Drawings,_8-10-18.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED 18-069
IFB NO. W912P818B0054
US Army Corps of Engineers New Orleans District
Mississippi River and Tributaries Old River Lock
New Miter Gates
Pointe Coupee Parish, Louisiana
Solicitation and Specifications
29 July 2018
ED 18-069
SOLICITATION: W912P818B0054
FOR: MISSISSIPPI RIVER AND TRIBUTARIES, OLD RIVER LOCK, NEW MITER GATES, POINTE
COUPEE PARISH, LOUISIANA
TO OPEN: 2:00PM CST, 14 SEPTEMBER 2018 AT PLACE OF BID OPENING
I. NOTE THE AFFIRMATIVE ACTION PROGRAM REQUIREMENT OF THE EQUAL
OPPORTUNITY CLAUSE WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS
SOLICITATION.
II. NOTE THE CERTIFICATION OF NONSEGREGATED FACILITIES IN THIS SOLICITATION.
Bidders, offerors and applicants are cautioned to note the "Certification of Non-segregated Facilities" in the solicitation. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause.
BIDS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS REQUIRED BY
THIS SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING FALSE
STATEMENTS IN BIDS IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)
III BIDDER REGISTRATION REQUIREMENTS: Prospective contractors must register in the System for Award Management (SAM). See FAR Clause 52.204-7 for required information. The website for SAM is https://www.sam.gov. You will be required to provide your company’s Dun and Bradstreet number. If you do not already have a D&B number, one can be requested from Dun and Bradstreet at (800) 333-0505 or http://fedgov.dnb.com/webform. Contractors must complete, and submit with their bid, the provisions located in section 00600. A bidder may also submit, in lieu of the completed section 00600, a complete hard copy of their Online Representations and Certifications which is located within the System for Award Management (SAM). Prospective contractors with expired or inactive Representations and Certifications in SAM at time of award will be deemed unresponsive.”
DESCRIPTION AND MAGNITUDE OF WORK: THE WORK CONSISTS OF FABRICATING ONE NEW
MITER GATE (TWO LEAVES) AND DELIVERING THE MITER GATE TO THE PORT ALLEN LOCK
STORAGE FACILITY. ALSO INCLUDED IS THE FABRICATION AND MACHINING OF
MISCELLANEOUS SPARE PARTS AND DELIVERING THEM TO THE OLD RIVER LOCK FACILITY.
CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time. Such delays DO NOT permit acceptance or consideration of late bids.
NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN ACCORDANCE
WITH THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS SAFETY AND HEALTH
REQUIREMENTS MANUAL", DATED NOVEMBER 2014.
SOLICITATION NUMBER: W912P818B0054
ALL QUESTIONS MUST CONTAIN THE SOLICITATION NUMBER IN
THE SUBJECT LINE.
IN ACCORDANCE WITH FEDERAL ACQUISITION REGULATIONS; ALL
QUESTIONS MUST BE SUBMITTED IN WRITING. ANY QUESTIONS
RECEIVED IN ANY OTHER FORMAT WILL NOT WARRANT A
RESPONSE.
QUESTIONS MUST BE SENT VIA EMAIL AND RECEIVED BY
2:00 P.M. CST, AUGUST 29, 2018. THE GOVERNMENT IS
UNDER NO OBLIGATION TO PROVIDE A RESPONSE TO LATE
QUESTIONS.
ALL INQUIRIES REGARDING THIS SOLICITATION
SHOULD BE MADE TO THE FOLLOWING:
CHRIS NUCCIO, CONTRACT SPECIALIST U.S. ARMY
CORPS OF ENGINEERS, NEW ORLEANS DISTRICT
E-MAIL:
CHRISTOPHER.M.NUCCIO@USACE.ARMY.MIL
PHONE: (504) 862-2704
COLLECT CALLS NOT ACCEPTED
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) W912P818B0054 IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
504-862-2704
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
U.S. Army Corps of Engineers, Contracting Division Attn: CEMVN-CT-E, Room 172 7400 Leake Avenue New Orleans, LA 70118-3651
Mississippi River and Tributaries, Old River Lock, New Miter Gates, Pointe Coupee Parish, Louisiana (ED 18-069)
This requirement is a 100% Small Business Set-Aside.
The work consists of fabricating one new miter gate (two leaves) and delivering the miter gate to the Port Allen Lock Storage facility. Also included is the fabrication and machining of miscellaneous spare parts and delivering them to the Old River Lock facility.
The magnitude of cost is between $5,000,000 and $10,000,000.
See Item 7
Chris Nuccio
ED 18-069
08/15/2018 local time 09/14/2018
2:00PM
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after he date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d )
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14 )
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document ) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) he solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office ) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
MTC-i ED 18-069
MAIN TABLE OF CONTENTS
Section B – SUPPLIES OR SERVICES AND PRICES/COSTS
Section C – TECHNICAL SPECIFICATIONS
C1 Miter Gates C1-1 thru 22
C2 Fabrication of Hydraulic Steel Structures C2-1 thru 19
C3 Metalwork Fabrication, Machine Work, and Miscellaneous Provisions C3-1 thru 8
C4 Painting C4-1 thru 23
C5 Submittal Procedures C5-1 thru 5
C6 Closeout Submittals C6-1 thru 3
C7 Network Analysis Schedules (NAS) C7-1 thru 6
C8 Resident Management System Contractor Mode (RMS CM) C8-1 thru 4
Section E – INSPECTION AND ACCEPTANCE
Section F – DELIVERIES OR PERFORMANCE
Section H – SPECIAL CONTRACT REQUIREMENTS
Section I – CONTRACT CLAUSES
Section J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
Mississippi River and Tributaries Old River Lock
New Miter Gates Pointe Coupee Parish, Louisiana
ITEM DESCRIPTION QUANTITY U/M U/P AMOUNT
0001 Miter Gate Leaves 02 EA
0002 Roller Bracket Shims (MK 12-152-6) 02 EA
0003 Roller Bracket Shims (MK 12-152-7) 04 EA
0004 Roller Bracket Shims (MK 12-152-8) 08 EA
0005 Guide Bracket Shims (MK 12-152-10) 02 EA
0006 Guide Bracket Shims (MK 12-152-11) 04 EA
0007 Guide Bracket Shims (MK 12-152-12) 08 EA
0008 Adjusting Washers (MK 12-152-13) 02 EA
0009 Adjusting Washers (MK 12-152-14) 02 EA
0010 Adjusting Washers (MK 12-152-15) 04 EA
0011 Collar (MK 13-154-7) 04 EA
0012 Adjusting Ring (MK 13-154-8) 16 EA
0013 Strut Pin (MK 13-154-1) 02 EA
0014 Pintle Bushing (MK 14-155-4) 02 EA
0015 Pintle Shoe (MK 14-155-5) 02 EA
0016 Pintle (MK 14-155-3) 02 EA
0017 Gudgeon Bushing (MK 20-145-5) 02 EA
0018 Gudgeon Pin (MK 20-145-4) 02 EA
0019 Strut Pin (MK 20-165-6) 02 EA
0020 Pin (MK 20-167-4) 04 EA
0021 Strut Pin (MK 20-165-2) 06 EA
0022 Sector Gear Arm Bushing (MK 20-165-3) 02 EA
0023 Nut (MK 20-165-4) 02 EA
0024 Pin (MK 20-168-4) 10 EA
0025 Dowel (MK 20-145-E) 08 EA
0026 Pin (MK 20-167-9) 04 EA
0027 Thrust Bushing, Greaseless
(MK 13-154-6A) 02 EA
0028 Thrust Bushing, Greaseless
(MK 13-154-6B) 02 EA
0029 Thrust Washer, Greaseless
(MK 13-154-8A) 04 EA
0030 Thrust Washer, Greaseless
(MK 13-154-8B) 04 EA
0031 Strut Gate Connection, Greaseless
(MK 13-154-14) 04 EA
0032 Set Screw (MK 14-155-6) 20 EA
0033 Machine Screw (For Key)
(MK 14-155-8) 02 EA
0034 Key (MK 14-155-10) 02 EA
0035 Bolt (MK 14-155-7) 20 EA
0036 Gasket (MK 21-163-1) 02 EA
0037 Gasket (MK 21-163-2) 02 EA
0038 Gasket (MK 21-163-3) 02 EA
0039 Retainer (MK 21-163-5) 02 EA
0040 Keeper Plate (MK 21-165-5) 02 EA
0041 Sector Gate Pin (MK 21-164-4) 02 EA
0042 Retainer (MK 21-163-4) 02 EA
0043 Drive Strut (MK 21-181-23) 04 EA
0044 Grease Seal (MK 21-163-11) 02 EA
0045 Self-Aligning Spherical Roller
(MK 21-163-12) 02 EA
0046 Self-Aligning Spherical Roller
(MK 21-163-13) 02 EA
0047 Lock Washer (MK 21-163-15) 02 EA
0048 Lock Nut (MK 21-163-16) 02 EA
0049 Eye Bolt (MK 13-154-5) 02 EA
0050 Timber Shim (MK 17-1) 50 EA
TOTAL:
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each items listed in the Schedule of bid items which require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such items), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE
EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE
DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR AWARD.
NOTE 2: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.
NOTE 3. U/M = UNIT MEASUREMENT; U/P = UNIT PRICE
Section Table of Contents
SECTION C1 - MITER GATES
1. SCOPE.
2. QUALIFICATIONS AND EXPERIENCE.
3. REFERENCES.
4. QUALITY CONTROL.
5. SUBMITTALS.
6. DELIVERY, STORAGE, AND HANDLING.
7. MATERIALS.
8. FABRICATION.
9. ASSEMBLY.
10. GATE SPARE PARTS.
C1-1 ED 18-069
SECTION C1 - MITER GATES
1. SCOPE. The work covered by this Section consists of furnishing all plant, equipment, labor and materials, and performing all operations in connection with the fabrication, assembly, delivery, and unloading of the miter gate and appurtenant items as specified herein and shown on the drawings. Delivery of the gates shall be made at the Port Allen Lock Storage Facility, and Contractor shall provide all equipment, material, and personnel required for unloading and placing the gates onto the Government-furnished carriages. The equipment shall include the crane to offload the gates at the Port Allen Lock Storage Facility. Delivery of the spare parts shall be made at the Old River Navigation Lock.
2. QUALIFICATIONS AND EXPERIENCE. The fabrication plant that constructs the miter gates shall have be qualified as stated in Section C2, “FABRICATION OF
HYDRAULIC STEEL STRUCTURES”.
3. REFERENCES. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
Aerospace Industries Association of America, Inc. (AIA/NAS)
NASM17828 (2013) Nut, Self-Locking, Hexagon Regular Height, (Non-Metallic Insert) 250 °F OR 450 °F, Nickel-Copper
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
B46.1 (2009) Surface Texture (Surface Roughness, Waviness and Lay)
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
A 36/A 36M (2014) Standard Specification for Carbon Structural Steel
A 53/A 53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
A 108 (2013) Standard Specification for Steel Bar, Carbon and Alloy, Cold-Finished
A 123/A 123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
A 148/A 148M (2015a) Standard Specification for Steel Castings, High-Strength, for Structural Purposes
A 193/A 193M (2017) Standard Specification for Alloy-Steel and Stainless Steel
C1-2 ED 18-069
Bolting for High-Temperature or High Pressure Service and Other Special Purpose Applications
A 194/A 194M (2017a) Standard Specification for Carbon Steel, Alloy Steel, and Stainless Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both
A 240/A 240M (2017) Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications
A 276/ A 276M (2017) Standard Specification for Stainless Steel Bars and Shapes
A 354 (2017e1) Standard Specification for Quenched and Tempered Alloy Steel Bolts, Studs and Other Externally Threaded Fasteners
A 370 (2017a) Standard Test Methods and Definitions for Mechanical
Testing of Steel Products
A 563 (2015) Standard Specification for Carbon and Alloy Steel Nuts
A 564/A 564M (2013e1) Standard Specification for Hot-Rolled and Cold-Finished Age-Hardening Stainless Steel Bars and Shapes
A568/A 568M (2017a) Standard Specification for Steel, Sheet, Carbon, Structural, and High-Strength, Low Alloy, Hot-Rolled and Cold-Rolled, General Requirements for
A 668/A 668M (2017) Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial Use
A 705/A 705M (2017) Standard Specification for Age-Hardening Stainless Steel Forgings
A 709/A 709M (2017e1) Standard Specification for Structural Steel for Bridges
B 271/b 271M (2015) Standard Specification for Copper-Base Alloy Centrifugal Castings
B 505/B 505M (2018) Standard Specification for Copper-Based Alloy Continuous Castings
B 584 (2014) Standard Specification for Copper Alloy Sand Castings for General Applications
D 395 (2016e1) Standard Test Methods for Rubber Property -Compression
C1-3 ED 18-069
Set
D 256 (2010e1) Standard Test Methods for Determining the Izod Pendulum Impact Resistance of Plastics
D 412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
D 471 (2016a) Standard Test Method for Rubber Property - Effect of Liquids
D 543 (2014) Standard Practices for Evaluating the Resistance of Plastics to Chemical Reagents
D 570 (1998(2010)e1) Standard Test Method for Water Absorption of Plastics
D 572 (2004(2015)) Standard Test Method for Rubber - Deterioration by Heat and Oxygen
D 638 (2014) Standard Test Method for Tensile Properties of Plastics
D 695 (2015) Standard Test Method for Compressive Properties of Rigid Plastics
D 746 (2014) Standard Test Method for Brittleness Temperature of Plastics and Elastomers by Impact
D 792 (2013) Standard Test Methods for Density and Specific Gravity (Relative Density) of Plastics by Displacement
D 1761 (2012) Standard Test Methods for Mechanical Fasteners in Wood
D 1894 (2014) Standard Test Method for Static and Kinetic Coefficients of Friction of Plastic Film and Sheeting
D 2240 (2015e1) Standard Test Method for Rubber Property - Durometer Hardness
D 3951 (2015) Standard Practice for Commercial Packaging
D 4060 (2014) Standard Test Method for Abrasion Resistance of Organic Coatings by the Taber Abraser
D 4329 (2013) Standard Practice for Fluorescent Ultraviolet (UV) Lamp Apparatus Exposure of Plastics
C1-4 ED 18-069
D 6117 - (2018) Standard Test Methods for Mechanical Fasteners in Plastic Lumber and Shapes
E 1547 (2009(2017)) Standard Terminology Relating to Industrial and Specialty Chemicals
F 436/F 436M (2016) Standard Specification for Hardened Steel Washers Inch and Metric Dimensions
F 468 (2016) Standard Specification for Nonferrous Bolts, Hex Cap Screws, and Studs for General Use
F 489 (1996) Standard Test Method for Using a James Machine
F 593 (2017) Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs
F 594 (2009(2015)) Standard Specification for Stainless Steel Nuts
F3125/F3125M (2015a) Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi (830 MPa) and 150 ksi (1040 MPa) Minimum Tensile Strength, Inch and Metric Dimensions
FEDERAL SPECIFICATIONS
FF-S-92B(1) (31 Jul 1975) Screw, Machine: Slotted, Cross Recessed or Hexagon
Head
FF-S-200A(3) (15 Apr 1994) Setscrews: Hexagon Socket and Spline Socket, Headless
FF-W-84A (27 May 1992) Washers, Lock (Spring)
FF-W-92B (9 May 1974) Washers, Flat (Plain)
4. QUALITY CONTROL.
4.1. General. The Contractor shall establish and maintain a quality control system in accordance with Section E, "INSPECTION AND ACCEPTANCE" for fabrication, assembly, delivery and unloading procedures to assure compliance with contract requirements and maintain records of his quality control for all operations including but not limited to the following:
1) Equipment. Type, size, and suitability for fabrication of the prescribed work.
2) Fabrication. Verify shop drawings.
C1-5 ED 18-069
3) Assembly. Verify assembly drawings and connections.
4) Welding. Verify welding is performed by certified welders and welds are completed appropriately.
5) Tolerances. Verify dimensional tolerances are within those specified and shown on the drawings.
6) Delivery. Verify miter gate leaves are secured and transported in accordance with delivery drawings.
4.2. Tests of Materials. The Contractor shall, at his expense, perform analyses and tests to demonstrate that all materials are in conformity with the specifications including fender material sampling as specified in paragraph 4.3 below. Should the Contractor desire to use stock materials not manufactured specifically for the work covered by these specifications, he shall submit evidence, satisfactory to the Contracting Officer, that such material conforms to the requirements of the specifications. Detailed tests of these materials will then not be required, if so approved by the Contracting Officer.
Tests, except where modified, shall be made as indicated in the respective detailed specifications or on the drawings and, unless otherwise authorized, in the presence of the Contracting Officer. The Contractor shall furnish specimens and samples for additional independent tests and analyses upon request by the Contracting Officer.
Specimens and samples shall be properly labeled and prepared for shipment.
4.3. Fender Material Visual Testing. Prior to use in the work, two (2) samples of each size from each lot of plastic fender delivered to the jobsite, or a quantity of three thousand five hundred (3,500) cubic feet, or fraction thereof, of said plastic fender, whichever is smaller, will be selected by the Contracting Officer’s Representative for visual tests.
4.3.1. Exterior. The samples will be examined by the Contracting Officer’s Representative for exterior voids first. The dense outer skin of the plastic composite marine timber shall be generally smooth but may contain occasional blisters and pockmarks.
4.3.2. Interior. After passing the requirements above, the samples are to be cut into twelve (12) inch long segments by the Contractor and visually examined by the Contracting Officer’s Representative. The cut sections of each segment shall conform to the following requirements:
1) The foamed inner core should be homogenous and reflect a consistent cell structure when viewed across the grain.
2) It shall be uniform in color.
C1-6 ED 18-069
3) The product shall contain no singular void in excess of 3% of the total foamed cross sectional area and greater than 3-inches in length.
If a cut section examined for interior voids fails to conform to any requirement above, a retest shall be performed on an additional two (2) samples selected by the Contracting Officer’s Representative. If a cut section in the retest fails to conform to either requirement, the entire lot of plastic fender represented by the samples will be rejected.
4.3.3. Reports. Test results will be reported in writing to the Contractor within fifteen
(15) working days after receipt of the samples by the Contracting Officer’s Representative. In the event the Contracting Officer’s Representative fails to provide the test results within the time allowed, and if, in the opinion of the Contracting Officer, completion of the work is delayed or interfered with by reason of the Contracting Officer’s Representative delay in providing the results, the Contractor will be compensated for any resulting loss, and an extension of time will be granted, in the same manner in accordance with the Contract Clause in Section F entitled, “CHANGES
(FAR 52.243-4)”.
4.4. Workmanship. Workmanship shall be of the highest grade and in accordance with the best modern practices to conform with the specifications for the item of work being furnished. All metalwork fabrication and machine work shall comply with this Section and the applicable provisions of Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES”, and Section C3, "METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS PROVISIONS". All parts shall be properly fabricated, assembled and delivered to conform to the shapes, sizes and dimensions indicated on the Contract Drawings and approved shop drawings.
4.5. Reporting. The original and two (2) copies of these records of inspections and tests, as well as the records of corrective action taken, shall be furnished to the Government daily. Format of the report shall be as prescribed in Section E, "INSPECTION AND ACCEPTANCE".
5. SUBMITTALS. The following shall be submitted in accordance with the Section C5, "SUBMITTAL PROCEDURES”, Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES” and Section C3, "METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS PROVISIONS".
5.1. Shop Drawings. The Contractor shall prepare and submit for approval, complete shop drawings and descriptive literature showing details of all items required as indicated herein or on the contract drawings. Shop drawings shall indicate computed weights/quantities of each material and approval of shop drawings will constitute acceptance of the computed weights shown on these drawings. Shop drawings shall include catalog cuts, templates, and type, grade and class of materials as appropriate.
Elements of fabricated items inadvertently omitted on Contract Drawings shall be detailed by the fabricator and indicated on the shop drawings. The shop drawings shall have a weld symbol listing the approved AWS (American Welding Society) Joint number
C1-7 ED 18-069
the contractor plans on using for each joint in the structure, nondestructive testing to be performed, the Welding Procedure Specification (WPS) number that will be used for each weld and the splice locations. All welded joints shall be detailed in accordance with an approved AWS joint design.
5.1.1. Fabrication Drawings. Fabrication drawings shall show complete details of materials, tolerances, connections, and proposed welding sequences.
5.1.2. Assembly Drawings. Assembly drawings shall provide details indicating the sequence of fabrication and assembly and provide details for connecting the adjoining fabricated components in the shop. Assembly details shall identify the required order of assembly and details of witness points as described in these specifications.
5.1.3. Delivery Drawings. Delivery drawings shall provide descriptions of methods of delivering components to the site, including details for supporting fabricated components during shipping to prevent distortion or other damages.
5.1.4. Control Dimensions Drawings. Control dimensions drawings shall indicate the measurement of the critical dimensions that are shown on Contract Drawings 3 and 4.
In addition to the dimensions shown, control points shall be established at locations near the four corners of each gate leaf to determine if the gate is square. The location of these points shall be determined by the Contractor and approved by the Contracting Officer.
5.2. Lists of Materials. The Contractor shall furnish the Contracting Officer three (3) copies of all purchase and mill orders, shop orders for materials and work orders, including all new orders placed by Contractors and old orders extended by each supplier. The Contractor, at the time of submittal of shop drawings, shall furnish a list designating the material to be used for each item. Where mill tests are required, purchase orders shall contain the test site address and the name of the testing agency.
5.3. Certificates.
5.3.1. Mill Test Reports. Certified copies of mill test reports for structural steel, stainless steel, structural bolts, nuts, washers and other related structural steel items shall be submitted. Charpy V-Notch testing shall also be submitted as specified herein.
5.3.2. Materials Test Reports. Certified copies of materials test reports shall be submitted for all required material tests, noting the specific standards followed in the performance of tests. Test reports shall be submitted for each material shipment, and be identified with specific lots prior to use of materials in the work. Charpy V-Notch testing shall also be submitted as specified herein.
5.3.3. Manufacturer's Certification. The galvanizing compound shall be certified for compliance with all specification requirements.
C1-8 ED 18-069
5.3.4. Certified Test Reports for Spare Parts. The Contractor shall submit within sixty
(60) days of delivery to the Old River Navigation Lock certified test reports for material tests for all “Spare Parts” materials delivered to the site.
5.4. Disposition Records. Disposition records shall provide a system of identification, which shows the disposition of specific lots of approved tested materials in the work.
These records shall be submitted before completion of the contract.
5.5. Plastic Fender Samples. Samples of the plastic fenders shall be submitted for visual testing as specified in paragraph 4.3 above.
6. DELIVERY, STORAGE, AND HANDLING.
6.1. Government Furnished Items. The Government will supply trolley including the winches and cables required to operate the trolley in order to place new gates in storage. No other materials, equipment, or tools, including tools fabricated specifically for this work, will be supplied by the Government. Government personnel will only assist the Contractor in placing the gates onto the trolleys. After gates are on the trolley, Government Personnel will relocate the gates and place them onto the storage pedestals.
6.2. Contractor Furnished Items. Materials and shop-fabricated components shall be shipped, handled, and stored in a manner to prevent permanent deflection, distortion, or other damage. Provisions for delivery shall be as shown on approved delivery drawings. Items that can be damaged by water, rust, and dirt shall be suitably packaged for delivery and storage at the Port Allen Lock Storage Facility except for all items listed as “SPARE PARTS” which shall be delivered to the Old River Navigation Lock. The Contractor shall provide all equipment (cranes, cable, slings, etc), material and personnel necessary for unloading the gates and appurtenances at the Port Allen Lock Storage Facility and place them onto the trolley system. The crane shall be a barge mounted crane. The Contractor shall notify the Contracting Officer twenty-eight
(28) days before gates are to arrive at the Port Allen Lock Storage Facility or the Spare Parts at the Old River Navigation Lock. Gates or spare parts shall only be delivered Monday through Thursday, no earlier than 7:00AM and unloading shall be completed by 5:00PM the same day unless prior approval has been obtained by the Contracting Officer. The Contractor shall expect the unloading of the gates to take two days since the trolley can move only one gate at a time.
6.3. Packaging. The spare parts shall not be prepared for shipment until they have been inspected and accepted for shipment at origin by the Contracting Officer or his authorized representative, unless inspection has been waived in writing. Each spare part shall be crated separately with part Mark Numbers painted on the top and at least 2 of the sides. Each complete set of gate leaf seals shall be shipped as a unit. Adjusting washers, guide bracket shims, roller bracket shims, and adjusting rings shall have each thickness packaged together. The spare parts shall be provided with adequate protective pads, supports, and blocking and shall be securely restrained to prevent
C1-9 ED 18-069
distortion or damage to the machined surfaces in transit. Standard commercial packaging in accordance with ASTM D 3951 will be acceptable except where a different method or standard of packaging is specifically called for herein. The items shall be packed in a manner to insure carrier acceptance and safe delivery at the Old River Navigation Lock. Containers shall be in accordance with consolidated Freight Classification Rules or other carrier regulations as applicable to the mode of transportation. Any loss or damage during shipment, including damage to the machined surfaces, will be considered the responsibility of the Contractor, and shall be replaced or repaired without cost to the Government. All accessories and spare parts shall be packed separately in containers plainly marked "ACCESSORIES ONLY”, or "SPARE PARTS ONLY”. A packing list, listing the contents of each container, shall be placed in a moisture-proof envelope and securely fastened to the outside of the container.
6.4. Shipping, Preservation, and Storage. Packing, crating, cradles, etc., to ensure safe shipment, are the responsibility of the Contractor. Machined surfaces shall be adequately protected from corrosion and physical damage.
7. MATERIALS.
7.1. Carbon (Structural) Steel.
7.1.1. Shapes and Plates. Structural steel shapes and plates shall meet the requirements of ASTM A 709/A 709M, Grade 50, Zone 2 Impact Testing Temperature.
All structural steel shape and plate material shall be considered Fracture Critical as specified in ASTM A 709/A709M. Plates four (4) inches or greater in thickness shall meet the requirements of ASTM A 36/A 36M.
7.1.2. Pipes. Steel pipes shall meet the requirements of ASTM A 53/A 53M, Grade B.
7.1.3. Sheets. Steel sheets shall meet the requirements of ASTM A 568/A 568M, any grade.
7.1.4. Alloy Steel. Miter Guide Roller (MK 12-152-2) shall be fabricated from AISI 4140 Alloy hot rolled bar, either annealed or quenched and tempered.
7.2. Corrosion Resistant (Stainless) Steel.
7.2.1. Shapes and Plates. Stainless steel shapes and plates shall meet the requirements of ASTM A 276, Type 316L. Stainless steel bars may be sheared from sheets conforming to ASTM A 240/A 240M, Type 316L.
7.3. Castings.
7.3.1. General. Castings shall meet the requirements of Section C3, "METALWORK
FABRICATION, MACHINE WORK, AND MISCELLANEOUS PROVISIONS".
C1-10 ED 18-069
7.3.2. Steel Castings. Strut connection bearings thimbles (MK 13-154-2 and MK 13- 154-3), guide brackets (MK 12-152-9), pintle shoe (MK 14-155-5), and pintle sockets (MK 14-155-1) shall meet the requirements of ASTM A 148/A 148M, Grade 80-50.
Sector gear base retainer (MK 21-163-4) shall meet the requirements of ASTM A 27/A 27M, Grade 60-30. Any casting which requires welding shall be stress relieved after welding is performed.
7.3.3. Bushings. Pintle bushing (MK 14-155-4) shall be leaded bronze casting meeting the requirements of ASTM B 271, B 505 or B 584, Alloy C93700. Diagonal bushings (MK 15-1 and MK 15-2) shall be aluminum bronze casting meeting the requirements of ASTM B 271, B 505 or B 584, Alloy C95400.
7.3.4. Greaseless Bushings. Strut bushing (MK 13-154-6(A&B)), thrust washer bushing (MK 13-154-8(A&B)), strut/gate connection bushing (MK 13-154-14), gudgeon bushing (MK 20-145-5), and sector gear arm bushing (MK 20-165-3) shall be self-lubricating.
The self-lubricating system shall have been tested and approved under the test procedure "Performance Evaluation of Self Lubricating Bushings" by Powertech Labs Inc., 12388-88th Ave., Surrey, B.C., Canada V3W 7R7. Example of self-lubricating bearing systems that meet the above requirements are Columbia Industrial Products CIP Hydro, KAMATICS Corp Karon V, Oiles America Corp 500 series and Glacier Garlock Bearings HPM. Self lubricated bushings shall not be of the graphite impregnated kind. Bearing material thickness, running clearances and surface finishes shall be as specified by the bearing supplier, with a minimum thickness of two-hundredths of an inch (0.020") of bearing wear provided before metal to metal contact.
If used, bushing substrate shall be aluminum bronze castings meeting the requirements of Alloy C95400.
7.4. Forgings.
7.4.1. Steel Forgings. Miter Gate Guide Roller Pin (MK12-152-3) shall meet the requirements of ASTM A 668/A 668M, Class G. Strut pin (MK 13-154-1), pintle (MK 14- 155-3), strut pin (MK 20-165-6), strut pin (MK 20-165-2) and gudgeon pin (MK 20-145-
4) shall meet the requirements of ASTM A 705/A 705M, Type 630, minimum hardness 40 Rc as shown on the drawings. Nut (MK 20-165-4) shall meet the requirements of ASTM A 668/A 668M, Class F forgings as shown on the drawings. Collar (MK 13-154- 7), adjusting ring (MK 13-154-8), pin (MK 20-168-4) and pin (MK 20-167-4) shall meet the requirements of ASTM A 564/A 564M, Type 630, minimum hardness 38 Rc as shown on the drawings. Sector gear pin (MK 21-164-4) shall meet the requirements of ASTM A 668/A 668M, Class L. Drive strut (MK 21-181-23) fitting shall meet the requirements of ASTM A 668/A 668M, Class H. Diagonal 8” pin (MK 15-3) shall meet the requirements of ASTM A 668/A 668M, Class E.
7.4.2. Eye Bolts. Eye bolts shall be made from quenched and tempered forged steel and shall meet or exceed the requirements of ASME B30.26.
7.5. Structural Bolts, Nuts, Washers, Pins and Screws.
C1-11 ED 18-069
7.5.1. High Strength Carbon Steel.
7.5.1.1. Carbon Steel Fasteners shall conform to the requirements specified in Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES”.
7.5.1.2. Pins. Pins (MK 21-167-9) shall meet the requirements of ASTM A 108, Grade 1045. Pins shall not be galvanized.
7.5.2. Corrosion Resistant Steel.
7.5.2.1. Stainless Steel Bolts and Cap Screws. All bolts and cap screws designated as corrosion resistant steel (CRS) or stainless steel on the drawings shall meet the requirements of ASTM F 593, Group 2, Alloy 316, Condition CW.
7.5.2.2. Stainless Steel Nuts. Nuts for stainless steel bolts shall bronze nylon insert nuts meeting the requirements of NASM17828.
7.5.2.3. Stainless Steel Washers. Stainless steel washers shall meet the requirements of Fed. Spec. FF-W-92B, Type A, Grade I (Sizes: Light and Heavy), Class B (Alloy 316).
7.5.2.4. Stainless Steel Lock Washers. Stainless steel lock washers shall meet the requirements of Fed. Spec. FF-W-84A, Class C, Style 2, Type 316 stainless steel.
7.5.2.5. Stainless Steel Machine Screws. Stainless steel machine screws shall meet the requirements of Fed. Spec. FF-S-92B, 18-8 chromium nickel alloy steel. Nuts and washers for machine screws shall be stainless steel as specified above.
7.5.2.6. Setscrews. Setscrews shall be in accordance with Fed. Spec. FF-S-200A(3), Type 1, Style 4, corrosion-resisting steel.
7.5.2.7. Bronze Bolts. Bronze bolts shall be silicon bronze bolts meeting the requirements of ASTM F 468. Alloy shall be C65100, C65500 or C66100.
7.5.3. Turned Bolts and Custom Fabricated Fasteners.
7.5.3.1. Bolt Steel. Bolt steel turned bolts or other custom fabricated fasteners shall be made from steel meeting the requirements of ASTM A 572/A 572M, Grade 50. Nuts and washers shall be as specified in paragraph 7.5.1 above.
7.5.3.2. Corrosion Resistant Steel. Corrosion resistant steel turned bolts or other custom fabricated fasteners shall be made from corrosion resistant steel meeting the requirements of ASTM A 276, Type 304, Condition B. Nuts for turned bolts shall meet the requirements of ASTM A 194/A 194M, Grade 8MN, Type 316. Washers for turned bolts shall be stainless steel as specified above.
C1-12 ED 18-069
7.6. Rubber Seals. Rubber seals shall be of the mold type only and shall be compounded of natural rubber, synthetic polyisoprene, or a blend of both, and shall contain reinforcing carbon black, zinc oxide, accelerators, antioxidants, vulcanizing agents, and plasticizers. Physical characteristics of the seals shall meet the following requirements:
Test Method Test Method Physical Test Test Value Specification
Tensile Strength 2500 psi (min) ASTM D 412
Elongation at Break 450% (min) ASTM D 412
300% Modulus 900 psi (min) ASTM D 412
Durometer Hardness 60 to 70 ASTM D 2240 (Shore Type A)
*Water Absorption 5% by weight (max) ASTM D 471
Compression Set 30% (max) ASTM D 395
Tensile Strength 80% (min) of ASTM D 572 (after aging 48 hrs) tensile strength
*The "Water Absorption" test shall be performed with distilled water. The washed specimen shall be blotted dry with filter paper or other absorbent material and suspended by means of small glass rods in the oven at a temperature of 70 degrees +/- 2 degrees Celsius for 22 +/-1/4 hour. The specimen shall be removed, allowed to cool to room temperature in air, and weighed. The weight shall be recorded to the nearest 1 mg as W1 (W1 is defined in ASTM D 471). The immersion temperature shall be 70 degrees +/- 1 degree Celsius and the duration of immersion shall be one hundred sixty-six (166) hours.
7.6.1. Fabrication. Strip seals shall be factory-molded in lengths suitable for obtaining the finish lengths shown on the drawings and with sufficient excess length to provide test specimens.
7.6.2. Testing. Failure of any specimen to meet the requirements of the test used will be cause for rejection of the piece from which the test specimen was taken.
7.7. Fenders. The plastic marine fenders shall be in accordance with the requirements of this Section and shall be the manufacturer’s standard commercial
C1-13 ED 18-069
product. Materials used shall be free from defects which would adversely affect the performance or maintainability of individual components or of the overall assembly.
Materials not specified herein shall be of the same quality used for the intended purpose in commercial practice. Manufacturer shall provide documentation that it has manufactured the product for a minimum of 4 years.
7.7.1. Materials. The plastic shall be a mixture of one or more of the following recycled post consumer or post industrial thermoplastics: High density polyethylene, medium density polyethylene, low density polyethylene or polypropylene. This plastic shall be mixed with the appropriate colorants, UV inhibitors and antioxidants, so that the resulting plastic portion of the product shall conform to the characteristics as listed in Table I at the end of this Section. If the fender is cast, the density shall be thirty-four (34) to fifty (50) pounds per cubic foot per ASTM D 792. Fenders shall be in full lengths. No splicing of fenders is permitted.
7.7.2. Construction. The fenders shall be manufactured in a continuous process that will result in the fender having no joints. The extruded fenders shall have an outer skin of dense plastic and an inner core of foamed plastic. Outer skin of the fender shall be yellow in color. It shall contain hindered amine light stabilizers to provide sufficient resistance to ultra violet light degradation as to meet the requirements in Table I. The outer skin of the plastic composite marine timber shall be continuous and homogenous throughout the entire length and perimeter of the timber. Inner part(s) of the fender shall be black in color. The inner core shall be produced so that it is a continuous foamed structure throughout the entire length of the fender. The annulus of the timber shall be a continuous foamed structure throughout the entire length of the timber. It shall conform to those applicable Sections of Table I. The annulus shall be melt fused to the inner core in such a manner that the joint between the inner core and the annulus develops the full strength of the plastic. The plastic marine fender shall have a square cross section with radiused corners. Cast fenders shall meet the requirements of Table 1 and shall be yellow in color. Both ends shall be cut square and then chamfered if required. It shall be seamless with a smooth outer skin.
7.7.3. Performance Characteristics. The plastic composite marine timber shall be designed to provide the following structural characteristics when using the material properties shown in Table I.
Flexural Modulus of Elasticity 154,000 psi Stiffness (EI) >6.89 x 107 lb.in2 Yield Stress in Bending >2,600 psi Weight 31-38 lbs/ft.
TABLE 1
7.7.4. Reparability. The outer skin must be repairable if chipped or spalled by using a commercially available compound in accordance with the plastic fender manufacturer’s recommendation or other similar procedure recommended by the manufacturer.
C1-14 ED 18-069
7.7.5. Owners Field Guide. With the shipment of the plastic marine fenders, the manufacturer shall provide one copy of its owner’s field guide. This guide shall include information and diagrams describing and illustrating the recommended means for handling, placing, installing, and finishing the plastic fenders.
7.7.6. Cracking. Each plastic fender shall be inspected for cracks prior to installation.
Cracking of plastic fenders will be cause for rejection. The plastic fenders shall be inspected for cracks again prior to final acceptance of the work. The Contractor shall be responsible for all costs incurred to replace the rejected plastic fenders.
7.8. Gaskets. Gaskets MK21-163-1, MK21-163-2, and MK 21-163-3 shall be Garlock 681 vegetable fiber gasketing or equal.
7.9. Prestressing Diagonals. The miter gates diagonals shall be fabricated from steel plate as specified in paragraph 7.1.1 above. The tensioning rods shall be made from material conforming to ASTM A 354, Grade BC. Threads for the rods shall be fabricated by a rolling process, 4.5 threads per inch UNC. Rods shall be furnished with two (2) matching bolts per rod.
7.10. UHMW Plates and Timber Shims. UHMW plastic for the plates and shims shall be manufactured from UHMW PE 1000 Grade material. Material shall be yellow in color.
8. FABRICATION.
8.1 General. The fabrication requirements shall conform with the requirements shown and specified herein, Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES”, and in Section C3, "METALWORK FABRICATION, MACHINE WORK, MISCELLANEOUS PROVISIONS". Brackets, eye bar sections, and other components requiring straightening shall be straightened by methods which will not damage the material. Bushings shall be press-fitted with supporting components. Bolt connections, lugs, clips, or other pick-up assembly devices shall be provided for components as shown and required for proper assembly and installation.
8.2. Welding. Welding shall conform to the requirements specified in Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES”.
8.3. Bolted Connections. Bolted connections shall conform to the requirements specified herein, Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES”, and Section C3, "METALWORK FABRICATION, MACHINE WORK, AND
MISCELLANEOUS PROVISIONS".
8.4. Machine Work. Machine work shall conform to the requirements specified in Section C3, "METALWORK FABRICATION, MACHINE WORK, AND
MISCELLANEOUS PROVISIONS".
C1-15 ED 18-069
8.5. Miscellaneous Provisions. Miscellaneous provisions for fabrication shall conform to the requirements specified herein and in Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES” and Section C3, "METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS PROVISIONS". Provisions shall be made for the installation of appurtenances as required.
8.6. Tolerances. The overall height of the gate leaf shall not vary from the nominal dimension or differ from the mating gate leaf by more than 1/4 inch. Overall width of the gate leaf shall be within 1/4 inch of the dimension shown on the drawings. The surfaces of framing elements to which skin plates are to be welded shall not vary from a true plane by more than 1/8 in. The outside surfaces of skin plates welded to framing members shall not vary from a true plane by more than 1/8 inch.
8.7. Painting. All parts of the miter gate, diagonals (except threaded portion) and appurtenances, except machined surfaces, fenders, and seals and other specified surfaces shall be painted at the shop as specified in Section C4, "PAINTING". Only repair of damaged surfaces shall be performed at the Port Allen Lock Storage Facility.
9. ASSEMBLY.
9.1. General. Assembly requirements for miter gate leaves and appurtenant items shall be as shown on the drawings and specified herein and in Section C2, “FABRICATION OF HYDRAULIC STEEL STRUCTURES” and Section C3, "METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS
PROVISIONS". Miter gate leaves and appurtenant items shall be assembled completely in the shop to assure satisfactory field installation and to determine the correctness of the fabrication and matching of the component parts. The tolerances shall not exceed those shown on the drawings or as specified herein, and each unit assembled shall be closely checked to ensure that all necessary clearances have been provided and that binding does not occur in any moving part. Assembled components shall be shop-welded in their final locations as much as delivery will permit. Rubber seals shall be fitted and drilled to match the seal retainers and installed. Necessary precautions shall be taken during welding to prevent any distortion of the miter gate leaves. Assembly shall be performed in the presence of the Contracting Officer unless otherwise approved by the Contracting Officer. The presence of the Contracting Officer will not relieve the Contractor of any responsibility under this contract. Errors or defects disclosed shall be immediately remedied by the Contractor without cost to the Government. Mating surfaces and machined surfaces shall be covered with a rust preventive until assembly. Brackets and other components requiring straightening shall be straightened by methods which will not damage the material. Bushings shall be press-fitted with supporting components.
9.2. Miter Gate Leaf. Gate leaf shall be of welded structural steel fabrication consisting of horizontal girders, vertical beams, intercostals, diaphragms, quoin block, gudgeon pin hood, operating strut connections, skin plate, and adjustable diagonals.
C1-16 ED 18-069
Gate leaf shall be completely shop-fabricated. Contractor shall not shop-fabricate gate leaf in separate segments for assembly at the Port Allen Storage Facility. Components shall be fabricated of the materials specified. Dimensional tolerances shall be as specified and shown on the drawings. Splices in skin plates shall be located only where shown or approved. Gate leaf shall be provided complete with quoin and miter contact blocks, miter guide assembly, pintle assembly, gudgeon anchorage, seal assembly, and other appurtenant components as required for complete installation, specified herein and shown. The diagonals shall be tightened to a snug fit prior to transport.
9.3. Pintle. Pintle assembly shall consist of pintle socket and pintle bushing as shown. Pintle socket shall be press-fitted with bushing with bearing surfaces finished truly hemispherical.
This is the start of the file's text. The full file is on GovTribe.