A21_W912P818B0017_Am_0001.pdf

PDF 4 MB Posted

Attached to
Atchafalaya Basin Flood Protection, West Bayou Sale, North Bend Phase B, St. Mary Parish, Louisiana
Solicitation number
W912P818B0017
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
W912P818B0017_Abstract(v2).pdf PDF
W912P818B0017_Signed_Abstract(v1).pdf PDF
A21_W912P818B0017_Am_0005.pdf PDF
A21_W912P818B0017_Am_0004.pdf PDF
A21_W912P818B0017_Am_0003.pdf PDF
A21_W912P818B0017_Am_0002.pdf PDF
18-B-0017_Drawing_Package.pdf PDF
W912P818B0017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above numbered solicitation for Atchafalaya Basin Flood Protection, West Bayou Sale, North Bend Phase B, St. Mary Parish, Louisiana (ED 15-061) is hereby amended as follow s:

1. DEADLINE FOR QUESTIONS: Contractor questions shall be submitted via email to edith.m.brandon@usace.army.mil by Friday, 12 January 2018, 12:00 noon CST.

2. Answ er questions received.

3. Update specifications in accordance w ith the attached.

BID OPENING DATE REMAINS UNCHANGED

1. CONTRACT ID CODE PAGE OF PAGES

1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jan-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-18-B-0017

X 9B. DATED (SEE ITEM 11)

18-Dec-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jan-2018

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P8-18-B-0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

The following items are applicable to this modification:

AMENDMENT 0001

Questions and Answers - W912P818B001 7 - Atchafalaya Basin Flood Protection, West Bayou Sale, North Bend Phase B, St. Mary Parish, Louisiana (ED 15-061)_Amendment 0001

Question 1

Sheets GI101 and CG103 call out a borrow area 3.5 miles Southwest of Cabot on Hwy 317. Sheet GC102 shows the borrow area being near Hwy 90 and the Wax Lake Outlet which is Northeast of Cabot and approximately 11 miles by road. Is there a borrow area 3.5 miles Southwest of Cabot? If so, please provide location information regarding that borrow area.

Answer 1 The borrow area is near Hwy 90 and the Wax Lake Outlet.

Question 2 Surfacing Thickness – The typical sections on plan sheets CS301-CS303 call for 6” thick granular surfacing.

The cross sections on plan sheets CS305-CS317 call for 10” thick granular surfacing. Please advise which thickness is required.

Answer 2 It is 10 inch granular surfacing.

Question 3 Item 0015 Granular Surfacing has an estimated quantity of 44,000 CY on the Bidding Schedule. Our takeoff resulted in a significantly lower quantity of granular surfacing. Please confirm whether the 44,000 CY quantity is correct.

Answer 3 The quantity is correct.

Question 4 Please provide the Government’s estimated quantities of the lump sum/1 JOB bid items:

a. 0002 - Clearing, Grubbing and Stripping

b. 0005 - Borrow Pit Development

c. 0006 - Construction Dewatering

d. 0011 - Truck Wash Down Racks

e. 0013 - Storm Drainage System

f. 0014 - Culvert

g. 0023 - Reinforced Concrete Floodwall

h. 0024 - Demolition

i. 0025 - Maintenance and Diversion of Storm Water

j. 0026 - Optional Work Area

k. Estimated quantity of Safety Fence required

Answer 4 The estimable quantities:

a. 48 LF of culvert

b. embankment quantity is 46,000 CY

c. Other quantities are dependent on the contractor’s operational procedures and other mitigating factors (such as weather).

Question 5 Plan sheet S-102 Note 6 states that an existing pipe rack and piping will be removed and reinstalled after installation of the piling. Is the contractor responsible for this work or is this work being performed by others?

Answer 5 It will be done by others.

SPECIFICATIONS:

SECTION 00100

52.236-27 SITE VISIT (CONSTRUCTION) (b). Delete the point of contact at the end of subparagraph b in its entirety and substitute the revised as follows:

”Name: Timothy White, Lafayette Area Office Address: 646 Cajundome Blvd, Suite 301, Lafayette, LA 70506-4280 Telephone: (337) 291-3049”

SECTION 01100

Page 11, paragraph 9. UTILITIES AND IMPROVEMENTS. Delete paragraph 9 in its entirety and substitute the revised paragraph 9 as follows:

“9. UTILITIES AND IMPROVEMENTS

(a) All known utilities within the limits of the work, such as pipes, communication lines, power lines, etc., that would interfere with construction work will be removed, modified or relocated by local interests or utility companies at no cost to the Contractor unless otherwise noted in the plans and/or specifications. The Contractor, however, shall cooperate with the authorities or company representatives and shall conduct his/her operations in such manner as to result in a minimum of inconveniences to the owners of said utilities. The Contractor shall notify each utility owner by certified mail 45 days, 15 days, and again 72 hours prior to the date utilities must be moved and provide a copy of these notifications to the Contracting Officer.

(b) Any unidentified pipes or structures which may be found within the limits of the work during the course of construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer.

(c) Important Notice Regarding Pipelines: Notification of Pipeline Company/Facility Owner immediately after Notice to Proceed. The Contractor shall not track heavy equipment or truck loads of embankment or other material across any pipeline without prior coordination and agreement with the facility owner.

(d) Contractor shall contact Louisiana One Call prior to mobilization at 1-800-273-3020.

(e) Utility Points of Contact:

Tennessee Gas (Kinder-Morgan)

Wesley Little Operations Supervisor White Castle/Shadyside Wesley_Little@kindermorgan.com Office: 225-545-2569(ext. 2023) Cell: 504-481-0557

Crosstex (EnLink) Keith Charpentier Operations Foreman keith.charpentier@crosstexenergy.com Cell: 985-856-9372

Crimson Gulf Pipeline April Harvey 3760 Kilroy Airport Way, Suite 300 Long Beach, CA 90806 Office: 562-285-4112 Cell: 562-714-3201 AHarvey@crimsonpl.com

AT&T

Curtis Davis 5565 Hwy LA-311 Houma, LA 70360 Office: 985-580-7168 Cell: 337-967-9254 cd1986@att.com

CLECO Electrical Distribution

Brandon Moffett 2030 Donahue Ferry Rd.

Pineville, LA 71360 Office: 318-484-4178 Cell: 318-880-4615 brandon.moffett@cleco.com

CLECO Power

Chris Ireson 2030 Donahue Ferry Rd.

Pineville, LA 71360 Office: 318-484-7577 Cell: 318-528-0517 Chris.Ireson@cleco.com

Cabot Corporation

Chris German

Highway 317 P.O. Box 598 Franklin, LA 70538 Office: 337-836-2258 Cell: 337-578-8488 Chris.German@cabotcorp.com

St. Mary Parish Water & Sewer Commission No. 3

Jamie Miller P.O Box 119 Centerville LA 70522 Office: 337-836-5831 checkvalve@cox.com

St. Mary Parish Government

Henry LaGrange 500 Main Street Courthouse, Fifth Floor Franklin, LA 70538 Office: 337-828-4100 ext. 511 hlagrange@stmaryparishla.gov

(f) Crimson Gulf – Crimson’s pipeline is located within a No Work Area. The Contracting Officer will issue a modification for levee construction in the vicinity of Crimson’s pipeline upon resolution and construction of an up-and-over pipeline relocation.

(g) ) AT&T – AT&T’s underground utilities in the levee footprint are to be relocated outside of the Project Area prior to contract award.

(h) CLECO Electrical Distribution – CLECO owns and operates overhead powerlines on the east side of the Project Area paralleling the north-south section of the levee ROW. These facilities are located within the levee footprint in a No Work Area. Upon resolution of CLECO’s relocation plan, facilities will be relocated eastward outside of the levee ROW. The overhead powerline will cross the levee with 18’ overhead clearance from final levee crown grade at approx. C/L Sta. 1026+00.

(i) CLECO Power – Temporary intake and discharge pipelines for CLECO’s proposed power generation station traverse the proposed levee at approx. C/L Sta. 1040+00. These temporary lines are located within an Optional Work Area as defined in Section 01100, paragraphs OPTIONAL WORK AREA and ORDER OF WORK, and were installed as temporary bypasses with knowledge of upcoming levee construction. This alignment allows construction of a full levee section at the location of the lines’ permanent alignment, just down station of the Optional Work Area. Upon completion of a full levee section by USACE Contractor, an up-and-over pipeline crossing will be installed by CLECO’s own labor, temporary pipelines will be removed, and the Optional Work Area shall be exercised by the Contracting Officer.

(j) Cabot Facilities

1. Near Project Base Station 1030+015: Cabot has a 4” Natural Gas Pipeline that feeds the entire plant.

This line operates at 300 to 400 PSI, and is noted on the COE drawings as “Do Not Disturb.” Cabot will mark and locate this line for the Contractor when he is working in this area.

2. Near Project Base Station 1055+088: In previous COE levee enlargement plans (1992), Cabot relocated its utilities in this area AND INSTALLED A REMOVABLE PIPE RACK to allow headroom for the Contractor to install steel sheet piles as indicated on project design drawings. When required, Cabot will remove and re-install the pipe rack and associated utilities to allow the Contractor to install the sheet piling in this immediate area. Coordination is very critical here – this provides off-loading of feedstock oil from the barges to the plant. The maximum time allowable from start of removal to re-installation completion is only SEVEN (7) DAYS. All costs associated with mitigating the impact of Contractor’s sole failure to complete their portion of the work within the seven-day schedule limitation will be borne by Contractor. The Contractor can expect to have unimpeded access for a 72-hour period during the seven-day schedule.

3. Near Project Base Station 1084+001: Cabot operates a 12” Raw Water Supply Pipeline that feeds the entire plant along with the electrical power to these dedicated pumps. You will notice that the pipeline has a “crook” in its design at this particular location. In previous COE levee enlargement plans (1992), it was proposed to have the COE Contractor to complete part of the levee enlargement from the North up to this site location. The Contractor would schedule work elsewhere on the levee project while Cabot would relocate its facilities over the newly enlarged levee, after which the Contractor would then continue levee enlargement proceeding further Southward. Work on this relocation at Station 1084+001 and Station 1055+088 CANNOT OCCUR SIMULTANEOUSLY.

4. Near Project Base Station 1066+033: Cabot owns a 3” Electrical Conduit that provides power to a Raw Water Pump supplying the plant. The relocation of this utility MUST OCCUR at the same time as the relocation of the 12” Raw Water Supply Pipeline (1084+001) above.

(k) St. Mary Parish Water & Sewer Commission No. 3 – St. Mary Parish’s existing water line servicing Cabot passes through the project Area and shall not be disturbed. Item P2 is an abandoned water line located in a No Work Area and will be removed from Project right-of-way.”

SECTION 01 32 17.00 20

Page 3, paragraph 1.5. Delete paragraph “1.5 SOFTWARE” in its entirety and substitute the revised paragraph 1.5 as follows:

“1.5 SOFTWARE

Project schedules, including the three-week look-ahead schedule, must be prepared and maintained using Primavera P6, Version 15.1 (or later).”

DRAWINGS:

SHEET IDENTIFICATION No. CS101. Delete this drawing in its entirety and substitute the attached revised drawing SHEET IDENTIFICATION No. CS101.

A21_W912P818B0017-0001
Drawing_CS101