RFIs_Richmond_10242024.pdf

PDF 210 KB Posted

Attached to
RICHMOND INNER HARBOR FY24 MAINTENANCE DREDGING PROJECT
Solicitation number
W912P725B0001
Issued by

About this file

This document contains questions and responses regarding an upcoming federal contract opportunity for the RICHMOND INNER HARBOR FY24 MAINTENANCE DREDGING PROJECT, solicitation number W912P725B0001.

The key details are:

  • This is an Invitation for Bid (IFB) for a Firm Fixed Price contract to perform maintenance dredging of the Richmond Inner Harbor to a depth of -37.5 ft MLLW plus 1 ft of overdepth. Material from reaches 1-10 is to be placed at a contractor-furnished upland beneficial reuse site, while material from reaches 11-13 can be placed at the government-furnished SF-DODS site or a contractor-furnished upland beneficial reuse site.
  • The estimated cost range is between $10-25 million. All bids are due by November 12, 2024 at 1:00 PM PST.
  • The contract completion period is 120 calendar days after the Notice to Proceed. Authorization will be provided to dispose of material at the SF-DODS site after November 30, per the 2015 Biological Opinion.
  • The solicitation and amendments will be posted on SAM.gov, and prospective bidders should frequently check the website for updates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI # SPEC SECTION/DRAWING RFI QUESTION RESPONSES

1 Topic: Commencement, Prosecution, and Completion of Work Drawing: N/A Section: 00 72 00 Subpart: 52.211-10 Specification Language:

FAR 52.211-10 COMMENCEMENT, PROSECUTION,

AND COMPLETION OF WORK (APR 1984), states the following” The Contractor shall be required to (a) commence work under this contract within one (1) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.” Please clarify the duration is 120 calendar days or working days.

120 calendar days

2 Topic: Disposal Site Drawing: N/A Section: 35 20 24 Subpart: 3.6.2.10.1 Specification Language: "...all ocean disposal operations, including transport to and discharge at SF-DODS, must cease by midnight of November 30 in any year. The Contractor is prohibited from disposing dredged material at the SF-DODS after November 30 without authorization from the Contracting Officer or delegated representative"

The contract specification designated that material from reaches 11-13 are suitable for disposal at SF-DODS, yet the contract also specifies that dredged material is prohibited from disposal at SF-DODS after November 30 without authorization from the Contracting Officer. What date does the USACE expect the NTP to be issued? Will authorization to take material to SF-DODS be given on this project. If so, to what date will the contractor be authorized to take material to SF-DODS.

Estimated NTP date is around 09 December 2024.

Yes, Contractor is authorized to take material to SF-DODS after November 30 accordance with the 2015 Biological Opinion. The following paragraph is included on page 537 of the specification:

"Projects may plan work for the period outside the work window (December 1 through May 31) provided the project mitigates for its impacts by placing dredged material at a beneficial re-use site, such as tidal wetlands restoration site. If a project is unable to place all material dredged outside the work window at a beneficial re-use site, the LTMS Program measures allow for an equivalent volume of dredged material to be placed at a beneficial re-use site from a project conducted within the work windows during the following season."

The contractor shall complete the dredging work including reaches 11 through 13 within the performance period specified for the project.

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided.

RICHMOND INNER HARBOR FY 24 MAINTENANCE DREDGING PROJECT

AS OF: October 24, 2024

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P725B0001