W912P724B0005 Amendment 2_ 15 May.pdf

PDF 2 MB Posted

Attached to
Sacramento Deep Water Ship Channel (DWSC) FY24 Maintenance Dredging Project
Solicitation number
W912P724B0005
Issued by

About this file

This document is an amendment to a solicitation for the W912P724B0005 contract for the Sacramento Deep Water Ship Channel (DWSC) FY24 Maintenance Dredging Project. The key details are:

The amendment extends the bid submission deadline from May 24, 2024 to May 28, 2024, and moves the public bid opening from May 24, 2024 to May 28, 2024. It also corrects errors in the bid schedule quantities. The work includes annual maintenance dredging of the Sacramento River DWSC to -30-ft MLLW plus 1-ft of paid over-depth, and transporting the dredged material to various upland disposal sites. The contract will be awarded as a single firm-fixed price contract through full and open competition. The estimated cost range is between $1,000,000 - $5,000,000.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT ID CODE PAGE OF PAGES

J 1 91

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P724B0005

X 9B. DATED (SEE ITEM 11)

24-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY CODE

USACE, SAN FRANCISCO DISTRICT

450 GOLDEN GATE

SAN FRANCISCO CA 94102

W912P7 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL: melissa.a.denigris@usace.army.mil(916) 557-5137

DeNigris, Melissa x

1. Plans: None.

2. Specifications: See the track changes in the Sections below.

*Bid Schedule, Page 6 – 8 of 816

The errors on the Reach Order and Bid quantities were corrected and updated.

3. Change Response Due Date FROM: May 24, 2024 at 12pm PST -TO: May 28, 2024 at 12pm PST.

(PDF Pages 2-89)

4. (1.7 SPECIAL INSTRUCTIONS FOR SUBMITTING YOUR BID:)

Changed From: All submissions must be no earlier than 6 days before and no later than the Bid Opening. This allows a submission window from May 18, 2024 at 12pm PST until 11:59am PST on Monday May 24, 2024.

Changed To: All submissions must be no earlier than 6 days before and no later than the Bid Opening. This allows a submission window from May 22, 2024 at 12pm PST until 11:59am PST on Monday May 28, 2024.

Changed From: The public bid opening will be held via WebEx at 1230 pm PST on May 24 , 2024, which will allow participants to hear a live reading of the bids.

Changed To: The public bid opening will be held via WebEx at 1230 pm PST on May 28 , 2024, which will allow participants to hear a live reading of the bids.

3. EFFECTIVE DATE

15 - MAY-2024

Contract Line Item No.(CLIN)

Description of Supplies and Services *Quantity Unit Unit

Price($) Amount($)

Mobilization, Demobilization and Disposal Site Prep at Decker Island, Rio Vista, Grand Island, and S-31 1 Job

0002 Dredging Reach 1 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

2,500 CY

0003 Dredging Reach 2 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

5,000 CY

0004 Dredging Reach 3 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

3,000 CY

0005 Dredging Reach 4 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

3,300 CY

0006 Dredging Reach 6 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

1,000 CY

SECTION 00 10 00

PRICING SCHEDULE

SACRAMENTO DWSC FY24 MAINTENANCE DREDGING

4,000

4,100

2,600

2,700

1,100

SO

LIC

ITATIO

N

0007 Dredging Reach 7 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

6,000 CY

0008 Dredging Reach 8 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

400 CY

0009 Dredging Reach 9 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

500 CY

0010 Dredging Reach 10 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

25,000 CY

0011 Dredging Reach 11 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

14,000 CY

0012 Dredging Reach 11 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site

200 CY

Total (Item 0001 and 0012)

Notes:

60,900 CY + 1 Job

* - ALL QUANTITIES ARE ESTIMATES. SEE FAR 52.211-18, SECTION 00 72 00 (GENERAL CONDITION)

OF THE CONTRACT.

5,000

59,500

1 .

2 .

3 .

4 .

5 .

6 .

7 .

8 .

End of Document

To be considered responsive, prices must be submitted on all individual items within Pricing Schedule. Failure to do so may be cause for rejection of bids.

Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms Page 1 and Page 2 as part of their solicitation package for bid evaluation. Failure to do so may cause the bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.

CLIN 0001's reference to site prep refers only to sites the bidder anticipates using for disposal.

BASIS of AWARD: The contract will be awarded in accordance with FAR 52.214-19 Contract Award – Sealed Bidding – Construction.

The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site in accordance with the Change Clause FAR 52.243-4.

The Contractor shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.

Dredge material placement shall meet the requirements in specification Section

01 11 00 SUMMARY OF WORK.

The term "Job", which appears on the Pricing Schedule (Section 00 01 00) under “Unit” for Bid Item No. 0001 shall be considered as a Lump Sum. The Variation in Estimated Quantities contract clause, FAR 52.211-18, shall not apply to Bid Item No. 0001.

FY24 Sacramento DWSC O&M W912P724B0005

SECTION 01 11 00

SUMMARY OF WORK

08/11

PART 1 GENERAL

1.1 PROJECT DESCRIPTION

The work includes annual maintenance dredging of the federal navigation channel in the Sacramento River Deep Water Ship Channel (DWSC), which cannot begin before 1 August in any year and must be completed by 31 October. The period of performance will not be extended to the following calendar year..

1.1.1 Requirements

a. Dredge the specified dredge reaches in the Sacramento DWSC to -30-ft MLLW plus 1-ft of allowable paid overdepth in Sacramento River DWSC.

All dredge material is suitable for the Government furnished upland sites at Decker Island, Rio Vista, Grand Island, and S-31 shown on plan sheets. Dredge material may be suitable for beneficial reuses at Contractor furnished sites in accordance with the permit requirements of the specific reuse site. The most recent sediment sampling report is attached at the end of the specification package.

b. Dredging operations in the Sacramento River DWSC shall begin at the downstream end of the channel (dredge reach 1) and continue in ascending order towards the upstream of the channel.

c. If a second dredge plant is used, dredging operations shall follow the order of the aforementioned requirement (item b). Multiple dredge plants shall not work in the same dredging reach.

d. The Contractor is responsible for for hiring a 3rd party Contractor to fullfill the requirements of fish monitoring and water quality monitoring tasks. Upon request by the Government, the Contractor shall coordinate with Government personnel to allow oversight of the monitoring efforts, such as fish monitoring and water quality monitoring tasks. Fish entrainment monitoring shall be performed on at least 30% of the dredged material.

e. Contractor shall conduct water quality monitoring and sampling as required in the Memorandum of Understanding (MOU) Resolution R5-2019-0041 with the Central Valley Regional Water Quality Control Board (CVRWQCB) for hydraulic dredging, or in accordance with Attachment B of CRWQCB Waste Discharge Requirements for Maintenance Dredging Operations Order R5-2022-0052 (WDR) for clamshell dredging.

The Contractor shall note that the specific monitoring and sampling requirements of the MOU are different from the WDR. Conduct dredging, material placement and discharge in a manner that meets water quality criteria in the MOU or WDR. Additional BMPs like discharge management and turbidity curtains may be required at some sites to meet the criteria.

f. If Government furnished upland dredged material placement sites are used, the Contractor shall notify the Government 72 hours prior to

SECTION 01 11 00 Page 1 May 06, 2024 starting site work at Government-furnished placement sites, so that Government can perform Environmental inspections of dredge material placement sites prior to ground disturbance.

g. This project can be dredged ither with a clamshell dredger or a hydraulic cutterhead dredger. If a hydraulic cutterhead dredge plant(s) is used, the plant(s) shall have a minimum of 16-in diameter pipeline and 1,800 horsepower for the main pump engine.

h. The Contractor is responsible for the Government furnished dredge material placement site preparation and dredge material management.

See Section TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19 for additional requirements.

1.1.2 Constraints

a. The environmental work window for the Sacramento DWSC is from 1 August to 31 October. Dredging is prohibited prior to 1 August. Pipeline assembly and disposal site preparation is allowed prior to 1 August.

b. All diesel-powered equipment must meet California Air Board emissions requirements.

c. Contractor is allowed a total accidental take of not more than 5 delta smelt (a listed endangered species) as stipulated in the USFWS biological opinions from the Sacramento River DWS Channel for the entire contract. Conduct dredging and material placement in a manner that minimizes adverse impacts to listed species and adheres to the conservation measures in the BO's as outlined in Section TEMPORARY

ENVIRONMENTAL CONTROLS 01 57 19.

d. Contractor must be in compliance with the Memorandum of Understanding Resolution R5-2019-0041 (MOU) (for hydraulic pipeline dredging) or WDR Order R5-2022-0052 (WDR) (for clamshell dredging) with the Central Valley Regional Water Quality Control Board (CVRWQCB). See Section

TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19.

1.2 MEETINGS

1.2.1 Preconstruction Conference

The preconstruction conference will be held at such time and location as determined by the Contracting Officer or delegated representative for purposes of discussing and developing mutual understanding between the Contracting Officer or delegated representative and the Contractor's Representatives regarding the terms, conditions, and requirements of the contract. Members of the conference from the Government will include the quality assurance staff, the Contracting Officer or delegated representative, and construction staff. Members from the Contractor shall include the dredge master, chief hydrographic surveyor, and the quality control staff. The discussion will include, but will not be limited to, the following:

- Contractor supervisory and quality control project staff

- Correspondence procedures

- Accident Prevention Plan

- Operations and Water Quality Monitoring Plan

- Lines of communication and communication protocols

SECTION 01 11 00 Page 2 May 06, 2024

- Pollution control program

- Quality Control and Hydrographic Surveying

- Project scheduling and payment procedures

- Resident Management System (RMS-QC)

- Other subjects that may be of interest to the contracting parties

- Schedule of Weekly Meeting

1.3 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. The USACE uses the web-based Construction Contractor Performance Assessment Reporting System (CPARS) to document contractor's performance and prepare performance reports. After an evaluation (interim or final) is written up by the USACE, the Contractor may access, review and comment on the evaluation for a period of 30 days.

Accessing and using CPARS requires Public Key Infrastructure (PKI) certification. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. This certification is purchased from an External Certificate Authorities (ECA) vendor. Contractor access to CPARS is required for Contractor participate in the performance evaluation process. PKI certification is required for Contractor access to CPARS. PKI certification is the sole responsibility of the Contractor. Current information about the PKI certification process and known PKI vendors can be found on the web site: http://www.cpars.gov/.

1.4 PERMITS

The Contractor shall obtain and comply with all licenses and permits required by Federal, State, and local laws, codes, and regulations unless otherwise specified in these contract documents.The Government has provided the requirements of (1)The Memorandum of Understanding (MOU) of the California Regional Water Quality Control Board,(2) The Central Valley Regional Water Quality Control Board Waste Discharge Requirements for Maintenance Dredging Operations Order R5-2022-0052 (WDR),(3)The Fisheries Service (NMFS) Stockton Deep Water Ship Channel Biological Opinion (2016-2025),(4)The United States Fish and Wildlife Service (USFWS) Stockton Deep Water Ship Channel Biological Opinion (2023-2028). The Contractor shall comply with these requirements and provisions in these contract specifications included in Sections TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19 and DREDGING 35 20 23.

1.5 PUBLIC SAFETY

The Contractor shall provide guard personnel as required to provide protection in the interest of public safety. Whenever the Contractor's operations create a condition hazardous to the public, he shall furnish at his own expense and without cost to the Government, such guards as are necessary to give adequate warning to the public of any dangerous conditions to be encountered, and he shall furnish, erect, or maintain such lights, signs and other devices as are necessary to prevent accidents and to avoid damage or injury to the public. Flagmen and guards, while on duty and assigned to give warning to the public that the dredging is being

SECTION 01 11 00 Page 3 May 06, 2024 extent feasible.

(7) If significant damage to wetlands or associated vegetation occurs, the Contractor shall restore the area to pre-existing conditions.

(8) The contractor is responsible for providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations to ensure compliance with water quality standards. The Contractor is responsible for the placement of temporary and permanent erosion and sediment control best management practices. These may include, but are not limited to, vegetation cover, stream bank stabilization, slope stabilization, silt fences, construction of terraces, interceptor channels, sediment traps, inlet and outfall protection, diversion channels, and sedimentation basins. Silt fences and other non-natural temporary measures shall be removed after the area has been stabilized.

1.4.2 Additional Conservation Measures for the Protection of Aquatic Resources for Cutterhead Dredgers

(1) If using a cutterhead dredger, the cutterhead will not be operated more than three feet above the channel bottom.

(2) Suction will not be employed while the dredge head is deployed and retrieved through the water column.

(3) The dredger will maintain the suction head at a constant elevation near the channel bed when dredging, to reduce the field of influence where fish may be entrained into the dredge pipe.

(4) Draghead deflectors will be installed on the leading edge of hopper dredge dragheads to minimize the risk of incidental take of benthic species such as green sturgeon. The deflector is designed to have a plowing effect of at least 6 inches.

1.4.3 Additional Conservation Measures for the Protection of Aquatic Resources for Clamshell Dredgers

(1) Multiple horizontal dredge cuts will be taken where a thick horizontal volume needs to be dredged to avoid overfilling the bucket and causing spillage.

(2) Once the clamshell bucket reaches the target depth, it will be fully closed before the dredge operator begins to raise it to the surface of the water column. This method, coupled with the use of a mechanical cable arm environmental clamshell bucket, minimizes the potential for generating turbidity in the water column.

(3) Once out of the water, the clamshell bucket will place dredged sediment directly into the scow. Sediment will not be released from the bucket until it is fully inside the scow. Within the scow, dredged sediment will pass through a 12-inch-by-12-inch grid to prevent any solid debris or artificial objects from entering the scow. Solid debris and artificial objects trapped on the grid will be removed and brought to an approved waste disposal site. Large woody debris with environmental value will be returned to the channel where not a hazard to navigation. The bucket will be held open over the grid within the scow until all the sediment and water has drained from within it to minimize the potential for resuspension of the sediment in the water

SECTION 01 57 19 Page 8 May 06, 2024 column.

(4) The load line on disposal barges used for mechanical dredging will be predetermined based on channel conditions, and the barge will not be filled above this predetermined level. Under no circumstance will scows be loaded to more than 90% capacity.

(5) Untreated water shall not be overflowed, decanted, discharged, or otherwise released from the vessel.

(6) Before each disposal barge is transported to a placement site, the dredging contractor and a site inspector must certify that it is filled correctly. Scows will be inspected to ensure no loss of sediment during loading and transport.

(a) If turbidity levels reach a value that represents 75% of the relevant allowable limit as identified in the MOU or WDR for any reason, the Corps' contractor will immediately slow the dredge rate by 50% to prevent turbidity levels from increasing further (i.e., if the cycle time for the bucket to descend, collect material, and drop that material in the scow is 30 seconds when the violation occurs, the revised cycle time should be 45 seconds until levels return to below 75% relevant allowable limits).

(b) If turbidity levels reach a value that represents 90% of the relevant allowable limit as identified in the MOU or WDR for any reason, the Corps' contractor will deploy a type II turbidity curtain, bubble curtain, or other similar measure to prevent the plume from migrating away from the dredge site. The curtain shall remain in place until levels have returned to below 75% relevant allowable limits.

1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS

The Contractor shall conduct dredging, material placement, and any discharge of decant water from dredged material placement sites in accordance with (1)The Memorandum of Understanding (MOU) of the California Regional Water Quality Control Board,(2) The Central Valley Regional Water Quality Control Board Waste Discharge Requirements for Maintenance Dredging Operations Order R5-2022-0052 (WDR),(3)The Fisheries Service (NMFS) Stockton Deep Water Ship Channel Biological Opinion (2016-2025),(4)The United States Fish and Wildlife Service (USFWS) Stockton Deep Water Ship Channel Biological Opinion (2023-2028).

Biological Opinions (BOs) and associated Addendums of U.S. Fish and Wildlife Service (USFWS) and National Oceanic and Atmospheric Administration (NOAA). The contractor is responsible for maintaining regular communication to its fish and water quality monitoring staff regarding when and where dredging and material placement will be occurring, when discharge from dredged material placement sites will begin and end, if there are any unexpected discharges, etc. The contractor shall give the monitoring staff as much notice of these items as possible.

1.6 QUALITY ASSURANCE

1.6.1 Preconstruction (pre-dredge) Survey and Protection of Features

This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to

SECTION 01 57 19 Page 9 May 06, 2024 start of any onsite construction activities, perform a Pre-Dredge Survey of the project site with the Contracting Officer or delegated representative, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.

Include in the report a plan describing the features requiring protection under the provisions of the Contract Clauses, which are not specifically identified on the drawings as environmental features requiring protection along with the condition of trees, shrubs and grassed areas immediately adjacent to the site of work and adjacent to the Contractor's assigned storage area and access route(s), as applicable. The Contractor and the Contracting Officer or delegated representative will sign this survey report upon mutual agreement regarding its accuracy and completeness.

Protect those environmental features included in the survey report and any indicated on the drawings, regardless of interference that their preservation may cause to the work under the Contract.

1.6.2 Environmental Brief

Attend an environmental brief to be included in the pre-dredge / preconstruction conference. Provide the following information: types, quantities, and use of hazardous materials that will be brought onto the installation; and types and quantities of wastes/wastewater that may be generated during the Contract. Discuss the results of the pre-dredge Survey at this time.

Prior to initiating any work on site, meet with the Contracting Officer or delegated representative and USACE Environmental Team to discuss the proposed Environmental Protection Plan (EPP). The Contractor shall use this brief to develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as turbidity monitoring and mitigation measures), and other measures to be taken.

1.6.3 Employee Training Records

Prepare and maintain Employee Training Records throughout the term of the contract meeting applicable 40 CFR requirements. Provide Employee Training Records in the Environmental Records Binder.

Train personnel to meet state requirements. Conduct environmental protection/pollution control meetings for personnel prior to commencing construction activities. Conduct additional meetings for new personnel and when site conditions change. Include in the training and meeting agenda: methods of detecting and avoiding pollution; familiarization with statutory and contractual pollution standards; installation and care of devices, vegetative covers, and instruments required for monitoring purposes to ensure adequate and continuous environmental protection/pollution control; anticipated hazardous or toxic chemicals or wastes, and other regulated contaminants; recognition and protection of archaeological sites, artifacts, waters of the United States, and endangered species and their habitat that are known to be in the area.

1.6.4 Non-Compliance Notifications

The Contracting Officer or delegated representative will notify the Contractor in writing of any observed noncompliance with federal, state or local environmental laws or regulations, permits, and other elements of the Contractor's EPP. After receipt of such notice, inform the

SECTION 01 57 19 Page 10 May 06, 2024

Contracting Officer or delegated representative of the proposed corrective action and take such action when approved by the Contracting Officer or delegated representative. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer or delegated representative may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.

1.6.4.1 Mis-Dumping of Dredge Material Notification Procedure

Contractor shall immediately notify the Government COR, Government Representative, and the Government Environmental Representative in the event of a draft loss occurs of 2 feet or greater. In the event that a draft loss has occurred scow shall be removed from rotation and inspected.

Inspection report shall be provided to the Government. If required by resource agencies, testing of contaminants shall be performed at no cost to the Government."

(a) E-Mail Alerts: The third-party system must also generate and distribute "e-mail alerts" regarding any degree of apparent dumping outside the project placement site ("mis-dumping"), and regarding any apparent substantial leakage/spillage or other loss of material en route to the project placement site.? Substantial leakage/spillage or other loss shall be defined as an apparent loss of draft of one foot or more between the time that the disposal vessel begins the trip to the project placement site and the time of actual disposal.? E-mail alerts for any disposal trip must be sent within 24 hours of the end of that trip to project placement site.

(b) 24-Hour Notification Requirement for Potential Leaks or Mis-Dumps: The permittee shall report any anticipated, potential, or actual variances from compliance with these project placement sites, and any additional project-specific Special Conditions, to the Government COR within 24 hours of discovering such a situation.? In addition, the permittee shall prepare and submit a detailed report of any such compliance problems on a weekly basis by noon Monday, to the to the Government COR.? These reports shall describe the cause(s) of the problems, any steps taken to rectify the problems, and whether the problems occurred on subsequent disposal trips.

1.7 ENVIRONMENTAL PROTECTION PLAN

The purpose of the EPP is to present an overview of known or potential environmental issues that must be considered and addressed during dredging. Include in the EPP measures for protecting natural and cultural resources, required reports, and other measures to meet the turbidity limits and other requirements in the MOU and/or WDR with the Central Valley Regional Water Quality Control Board (CVRWQCB). See 1.6.2 for requirements for pre-meeting with the Government prior to preparing the EPP for initial submission. Contingency plans should be discussed in the EPP that explain what actions will be taken if minimum freeboard isn't being maintained, if turbidity requirements are not being met, or if an adverse incident occurs. Submit the EPP within 15 days after Contract award and not less than 10 days before the preconstruction meeting.

Revise the EPP throughout the project to include any reporting requirements, changes in site conditions, or contract modifications that change the project scope of work in a way that could have an environmental

SECTION 01 57 19 Page 11 May 06, 2024 impact. No requirement in this section will relieve the Contractor of any applicable federal, state, and local environmental protection laws and regulations. During dredging, identify, implement, and submit for approval any additional requirements to be included in the EPP. Maintain the current version onsite.

The EPP includes, but is not limited to, the following elements:

1.7.1 General Overview and Purpose

1.7.1.1 Descriptions

A brief description of each specific plan required by environmental permit or elsewhere in this Contract such as spill control plan, solid waste management plan, wastewater management plan, air pollution control plan, contaminant prevention plan, biological resources and wetlands plan, Non-Hazardous Solid Waste Disposal Plan.

1.7.1.2 Duties

The duties and level of authority assigned to the person(s) on the job site who oversee environmental compliance, such as who is responsible for adherence to the EPP, who is responsible for spill cleanup and training personnel on spill response procedures, who is responsible for manifesting hazardous waste to be removed from the site (if applicable), and who is responsible for training the Contractor's environmental protection personnel.

1.7.1.3 Procedures

A copy of any standard or project-specific operating procedures that will be used to effectively manage and protect the environment on the project site.

1.7.1.4 Communications

Communication and training procedures that will be used to convey environmental management requirements to Contractor employees and subcontractors.

1.7.1.5 Contact Information

Emergency contact information (office phone number, cell phone number, and e-mail address).

1.7.2 General Site Information

1.7.2.1 Drawings

Drawings showing locations of proposed temporary excavations or embankments for haul roads, stream crossings, jurisdictional wetlands, material storage areas, structures, sanitary facilities, storm drains and conveyances, and stockpiles of excess soil.

1.7.2.2 Work Area

Work area plan showing the proposed activity in each portion of the area and identify the areas of limited use or nonuse. Include measures for marking the limits of use areas, including methods for protection of

SECTION 01 57 19 Page 12 May 06, 2024 features to be preserved within authorized work areas and methods to control runoff and to contain materials on site, and a traffic control plan.

1.7.2.3 Documentation

A letter signed by an officer of the firm appointing the CQC System Manager and stating that person is responsible for managing and implementing the Environmental Program as described in this contract.

Include in this letter the CQC System Manager's authority to direct the removal and replacement of non-conforming work.

1.7.3 Management of Natural Resources

a. Fish and wildlife resources

b. Wetland areas

1.7.4 Protection of Historical and Archaeological Resources

a. Objectives

b. Methods

1.7.5 Protection of the Environment from Waste Derived from Contractor Operations

Control and disposal of solid and sanitary waste. Control and disposal of hazardous waste.

This item consists of the management procedures for hazardous waste to be generated. As a minimum, include the following:

a. List of the types of hazardous wastes expected to be generated

b. Procedures to ensure a written waste determination is made for appropriate wastes that are to be generated

c. Sampling/analysis plan, including laboratory method(s) that will be used for waste determinations and copies of relevant laboratory certifications

d. Methods and proposed locations for hazardous waste accumulation/storage (that is, in tanks or containers)

e. Management procedures for storage, labeling, transportation, and disposal of waste (treatment of waste is not allowed unless specifically noted)

f. Management procedures and regulatory documentation ensuring disposal of hazardous waste complies with Land Disposal Restrictions(40 CFR 268)

g. Management procedures for recyclable hazardous materials such as lead-acid batteries, used oil, and similar

h. Used oil management procedures in accordance with 40 CFR 279;

Hazardous waste minimization procedures

i. Plans for the disposal of hazardous waste by permitted facilities; and

SECTION 01 57 19 Page 13 May 06, 2024

Procedures to be employed to ensure required employee training records are maintained.

1.7.6 Operation and Prevention of Releases to the Environment

a. Name and location of Dredge Material Placement (DMP) sites to be used;

b. Operation plan for DMP sites, with discharge points if applicable;

c. Approximate available capacity (cubic meters volume) of the DMP sites;

d. Expectation of discharge of effluent to receiving waters;

e. Calculations for minimum holding times required for dredge slurry before effluent discharge to receiving waters, if applicable;

f. Description of dredge material handling equipment;

g. Method of transporting dredged materials to placement sites;

h. Expected dredging rate in cubic yards per day;

i. Schedule with hours of operation and estimated days to complete project

j. Best management practices to be implemented during dredging operations to prevent impacts to water quality;

k. Measures to meet the turbidity limits and other requirements in the

Memorandum of Understanding and/or General Order with the Central Valley Regional Water Quality Control Board (CVRWQCB). Contingency plans should be discussed in that explain what actions will be taken if minimum freeboard isn't being maintained, if turbidity requirements are not being met, or if an adverse incident occurs.

l. Plans for Notifications in the event of an unplanned release to the environment

1.7.7 Clean Air Act Compliance

1.7.7.1 Pollution Generating Equipment

Identify air pollution generating equipment or processes that may require federal, state, or local permits under the Clean Air Act. Determine requirements based on any current installation permits and the impacts of the project. Provide a list of all fixed or mobile equipment, machinery or operations that could generate air emissions during the project to the USACE Environmental Team.

In accordance with 40 CFR § 51.853(c)(2)(ix), the USACE has determined that the proposed agency action is exempt from the requirement to prepare a conformity determination with the State Implementation Plan under the Clean Air Act because the project consists of maintenance dredging, no new depths are required, and disposal would be at approved disposal sites.

The Contractor shall be responsible for compliance with all Bay Area Air Quality Management District (BAAQMD) regulations and standards including obtaining a permit if necessary, for operation of a stationary source of air pollutants. Mechanical failures resulting in violations of particulate matter or sulfur compounds (Regulation #2) would be handled through application for a variance from the BAAQMD.

Unless "optimized" or diesel powered equipment with the "Best Available Control Technology" (BACT) emission devices are used, injection timing on diesel powered dredges and equipment shall be retarded two degrees from manufacturer's recommended setting to reduce air pollutant emissions.

Reformulated diesel fuel shall be used for all diesel powered dredges and equipment to reduce air pollutant emissions. Reformulated diesel fuel shall be a low sulfur, reduced aromatics diesel fuel meeting the following

SECTION 01 57 19 Page 14 May 06, 2024 specifications, unless otherwise approved by the Contracting Officer or delegated representative: (1) Sulfur content less than 0.05 percent by weight and (2) Aromatics content less than 20 percent by volume Prior to dredging or construction operations, the Contractor shall submit certification from the fuel supplier or manufacturer stating that the fuel contents meet the above requirements and proof of reformulated diesel fuel purchase of the above specified fuel shall be submitted to the Contracting Officer or delegated representative.

Dredges and equipment shall not be allowed to idle when not required in performing the work.

1.7.7.2 Stationary Internal Combustion Engines

Identify portable and stationary internal combustion engines that will be supplied, used or serviced. Comply with 40 CFR 60 Subpart IIII, 40 CFR 60 Subpart JJJJ, 40 CFR 63 Subpart ZZZZ, and local regulations as applicable. At minimum, include the make, model, serial number, manufacture date, size (engine brake horsepower), and EPA emission certification status of each engine. Maintain applicable records and log hours of operation and fuel use. Logs must include reasons for operation and delineate between emergency and non-emergency operation.

1.7.7.3 Refrigerants

Identify management practices to ensure that heating, ventilation, and air conditioning (HVAC) work involving refrigerants complies with 40 CFR 82 requirements. Technicians must be certified, maintain copies of certification on site, use certified equipment and log work that requires the addition or removal of refrigerant. Any refrigerant reclaimed is the property of the Government, coordinate with the USACE Environmental Team to determine the appropriate turn in location.

1.7.7.4 Air Pollution-engineering Processes

Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions). Log hours of operations and track quantities of materials used.

1.7.7.5 Compliant Materials

Provide the Government a list of and SDSs for all hazardous materials proposed for use on site. Materials must be compliant with all Clean Air Act regulations for emissions including solvent and volatile organic compound contents, and applicable National Emission Standards for Hazardous Air Pollutants requirements. The Government may alter or limit use of specific materials as needed to meet installation permit requirements for emissions.

1.8 LICENSES AND PERMITS

Obtain licenses and permits required for the dredging of the project and in accordance with FAR 52.236-7 Permits and Responsibilities. Notify the Government of all general use permitted equipment the Contractor plans to use on site.

SECTION 01 57 19 Page 15 May 06, 2024

a. The following certifications and approvals were obtained by the Government and are attached:

(1)the Memorandum of Understanding (MOU) Resolution R5-2019-0041 with the Central Valley Regional Water Quality Control Board

(2)the Central Valley Regional Water Quality Control Board Waste Discharge Requirements for Maintenance Dredging Operations Order

R5-2022-0052 (WDR)

(3)the Fisheries Service (NMFS) Sacramento Deep Water Ship Channel Biological Opinion (2016-2025)

(4)the United States Fish and Wildlife Service (USFWS) Sacramento Deep Water Ship Channel Biological Opinion (2023-2028)

1.9 ENVIRONMENTAL RECORDS BINDER

Maintain on-site a separate electronic Environmental Records Binder and submit at the completion of the project. Make separate parts within the binder that correspond to each submittal listed under paragraph CLOSEOUT SUBMITTALS in this section.

1.10 SOLID WASTE MANAGEMENT PERMIT

Provide the Contracting Officer or delegated representative with written notification of the quantity of anticipated solid waste or debris that is anticipated or estimated to be generated by construction. Include in the report the locations where various types of waste will be disposed or recycled. Include letters of acceptance from the receiving location or as applicable; submit one copy of the receiving location state and local Solid Waste Management Permit or license showing such agency's approval of the disposal plan before transporting wastes off Government property.

1.10.1 Solid Waste Management Report

Monthly, submit a solid waste disposal report to the Contracting Officer or delegated representative. For each waste, the report will state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste.

1.11 FACILITY HAZARDOUS WASTE GENERATOR STATUS

Not Used.

1.12 OPERATIONS AND WATER QUALITY MONITORING WORK PLAN

Within 15 days after NTP, the contractor must submit an Operations and Water Quality Monitoring Work Plan to the government. The plan shall cover the following:

(a) Name and location of Dredge Material Placement Sites (DMPSs) to be used.

(b) Operation plan for DMPSs, with discharge points if applicable.

(c) Approximate volume of material in cubic meters to be placed at the

DMPSs.

(d) Expectation of discharge of effluent to receiving waters.

(e) Calculations for minimum holding times required for dredge slurry before effluent discharge to receiving waters, if applicable.

SECTION 01 57 19 Page 16 May 06, 2024

(f) Description of dredge material handling equipment.

(g) Method of transporting dredged materials to placement sites.

(h) Expected dredging rate in cubic yards per day.

(i) Schedule with hours of operation and estimated days to complete project.

(j) Best management practices to be implemented during dredging operations to prevent impacts to water quality.

(k) Brief description of the equipment to be used for water quality parameter monitoring (such as brand, model number, etc.) and calibration procedures.

(l) Water Quality Field Forms that will be used.

(m) Measures to meet the turbidity limits and other requirements in the

Memorandum of Understanding Resolution R5-2019-0041 (MOU) for hydraulic pipeline dredging) or WDR Order R5-2022-0052 (WDR, for clamshell dredging) with the Central Valley Regional Water Quality Control Board (CVRWQCB). Contingency plans should be discussed that explain what actions will be taken if minimum freeboard isn't being maintained, if turbidity requirements are not being met, or if an adverse incident, such as accidental discharge of dredged materials to the river, occurs.

1.13 FISH ENTRAINMENT AND BIOLOGICAL RESOURCES MONITORING

WORK PLAN

The Contractor shall prepare and submit a fish entrainment and biological resources monitoring work plan 30 days after contract award following the guidelines set forth by the Fish Monitoring and Water Quality Plan for the Stockton Deep Water Ship Channel and Sacramento Deep Water Ship Channel Maintenance Dredging and Dredged Material Placement Projects prepared by Mari-Gold Environmental Consulting Inc. for the U.S. Army Corps of Engineers, March 2011, Sacramento, California. The Contractor will submit a draft work plan to the Corps for review and comment, including a description of attaining 30% monitoring goal or higher if operating in an extension period, and a final work plan for Corps approval prior to initiating fish entrainment monitoring activities.

The work plan must also cover how pre-ground disturbance DMPS surveys will be conducted. The main goal of these surveys is to prevent adverse effects to terrestrial species in accordance with the BO's. The work plan should specify how the contractor will transit to each DMPS in advance of ground disturbance, as some DMPS are only accessible via boat or ferry.

The work plan must also identify how the Contractor will appropriately clean all previously used monitoring equipment prior to bringing it onto the project site. The Contractor must ensure that the equipment is free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. Consult with the USDA jurisdictional office for additional cleaning requirements. The Contractor's plan shall identify the fish entrainment monitoring biologist(s) who will be conducting the monitoring.

The fish entrainment monitor(s) monitoring the screen shall be trained and permitted to handle applicable ESA and CESA listed fish. Copies of the permits must be appended to the workplan prior to acceptance. The biologist(s) shall be experienced with Delta fish identification, use careful and limited handling, and take efforts to return all encountered fish back to sampled waters unharmed.

In addition, the work plan must identify how the Contractor shall maintain permanent and temporary pollution control facilities and devices for the

SECTION 01 57 19 Page 17 May 06, 2024 duration of the contract or for that length of time construction activities create the particular pollutant.

The work plan must also identify how the Contractor will clean up all areas used for monitoring. At a minimum, unless otherwise instructed in writing by the Contracting Officer or delegated representative, obliterate all signs of temporary monitoring facilities such as haul roads, work area, structures, foundations of temporary structures, stockpiles of excess or waste materials, and other vestiges of construction prior to final acceptance of the work. The disturbed area used for monitoring task must be restored and the entire area seeded unless otherwise indicated.

1.14 Environmental Compliance Work Plan Review Meeting

After submittal of Operations and Water Quality Monitoring Work Plan but prior to workplan acceptance, the contractor shall schedule a meeting with the government to cover the following:

(a) Review and discuss the workplan to ensure understanding by all parties.

(b) Resolve any outstanding comments on the workplan.

(c) Review with contracted personnel the requirements of governing documents including but not limited to the CVRWQCB MOU or WDR and Biological Opinions.

(d) Review lines of communication with the government and expectations of coordination and communication.

(e) Discuss any other concerns pertinent to environmental compliance.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 PROTECTION OF NATURAL RESOURCES

Minimize interference with, disturbance to, and damage to fish, wildlife, and plants, including their habitats. Prior to the commencement of activities, consult with the Government, regarding rare species or sensitive habitats that need to be protected. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility. The following special status species are known to occur and could be affected within the construction area: green sturgeon, Chinook salmon, steelhead, valley elderberry longhorn beetle, and delta smelt, and giant garter snake.

Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work that is consistent with the requirements of the USACE Environmental Team or as otherwise specified. Confine construction activities to within the limits of the work indicated or specified.

SECTION 01 57 19 Page 18 May 06, 2024

3.1.1 Flow Ways

Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as specified and permitted.

3.1.2 Vegetation

Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer or delegated representative's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer or delegated representative. Where such use of attached ropes, cables, or guys is authorized, the Contractor is responsible for any resultant damage.

Protect existing trees that are to remain to ensure they are not injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas. Coordinate with the Contracting Officer or delegated representative and USACE Environmental Team to determine appropriate action for trees and other landscape features scarred or damaged by equipment operations.

3.1.3 Streams

Stream crossings must allow movement of materials or equipment without violating water pollution control standards of the federal, state, and local governments. Construction of stream crossing structures must be in compliance with any required permits including, but not limited to, Clean Water Act Section 404, and Section 401 Water Quality.

The Contracting Officer or delegated representative's approval and appropriate permits are required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges.

This is the start of the file's text. The full file is on GovTribe.