W912P724B0005 AMENDMENT 0004.pdf
PDF 827 KB Posted
- Solicitation number
- W912P724B0005
About this file
This document is an Amendment to Solicitation/Modification of Contract for the Sacramento Deep Water Ship Channel (DWSC) FY24 Maintenance Dredging Project, Solicitation Number W912P724B0005. The key details are:
The amendment corrects errors in the Reach Order and Bid quantities in the Bid Schedule, and extends the Response Due Date from June 11, 2024 to June 18, 2024. It also updates the public bid opening date from June 11, 2024 to June 18, 2024. The amendment reinstalls the original language regarding clamshell dredging that was previously removed. The total quantity of dredging across the 11 reaches is 60,900 cubic yards plus 1 Job for Mobilization, Demobilization and Disposal Site Prep. The contract will be awarded as a Firm Fixed Price contract in accordance with FAR 52.214-19. The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
1. CONTRACT ID CODE PAGE OF PAGES
J 1 90
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P724B0005
X 9B. DATED (SEE ITEM 11)
24-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matterwhere feasible.
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
U0004
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
CODE
USACE, SAN FRANCISCO DISTRICT
450 GOLDEN GATE
SAN FRANCISCO CA 94102
W912P7 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
7-JUN-2024
1. Plans: None.
2. Specifications: See Summary of Changes (Pages 2 - 45) *Bid Schedule, Page 6 – 8 of 816 (Page 3&4 of this Document) The errors on the Reach Order and Bid quantities were corrected and updated.
3. Change Response Due Date FROM: June 11, 2024 12:00 pm PDT-TO: June 18, 2024 at 12pm PST.
4. (1.7 SPECIAL INSTRUCTIONS FOR SUBMITTING YOUR BID:)
Changed From: All submissions must be no earlier than 6 days before and no later than the Bid Opening. This allows a submission window from June 5 2024 at 12pm PST until 11:59am PST on Tuesday June 11 2024.
Changed To: All submissions must be no earlier than 6 days before and no later than the Bid Opening. This allows a submission window from June 12 2024 at 12pm PST until 11:59am PST on Tuesday June 18, 2024.
Changed From: The public bid opening will be held via WebEx at 1230 pm PST on June 11, 2024, which will allow participants to hear a live reading of the bids.
Changed To: The public bid opening will be held via WebEx at 1230 pm PST on June 18 , 2024, which will allow participants to hear a live reading of the bids.
4. Update Davis-Bacon Act WD # CA20240007 -dated 05/24/2024 x
W912P724B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. Plans: None.
2. Specifications: The original language with clamshell dredging has been reinstalled. See the highlighted changes on the following pages.
*Bid Schedule, Page 6 – 8 of 816 The errors on the Reach Order and Bid quantities were corrected and updated.
*01 11 00, SUMMARY OF WORK, Page 166 of 816 Reinstall the language of clamshell dredging.
Para. 1.1.1 (e), (g)
1.1.2 (d) 1.4
*01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, Page 256 of 816 Para. 1.4.3
1.5
1.8 (a) (2)
1.12 (m) 3.1.4 3.1.5 3.1.5.1 3.1.5.2
* 35 20 23, DREDGING, Page 280 of 816 Para. 1.3.1.1
*Reinstalled Attachment for clamshell dredging, Page of 464 - 529 of 816
Contract Line Item No.(CLIN)
Description of Supplies and Services *Quantity Unit Unit
Price($) Amount($)
Mobilization, Demobilization and Disposal Site Prep at Decker Island, Rio Vista, Grand Island, and S-31 1 Job
0002 Dredging Reach 1 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
2,500 CY
0003 Dredging Reach 2 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
5,000 CY
0004 Dredging Reach 3 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
3,000 CY
0005 Dredging Reach 4 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
3,300 CY
0006 Dredging Reach 6 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
1,000 CY
SECTION 00 10 00
PRICING SCHEDULE
SACRAMENTO DWSC FY24 MAINTENANCE DREDGING
4,000
4,100
2,600
2,700
1,100
0007 Dredging Reach 7 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
6,000 CY
0008 Dredging Reach 8 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
400 CY
0009 Dredging Reach 9 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
500 CY
0010 Dredging Reach 10 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
25,000 CY
0011 Dredging Reach 11 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
14,000 CY
0012 Dredging Reach 11 to -30-ft MLLW plus 1 foot of paid Over-depth with disposal at Government-furnished upland site or Contractor-furnished upland beneficial reuse site
200 CY
Total (Item 0001 and 0012)
Notes:
60,900 CY + 1 Job
* - ALL QUANTITIES ARE ESTIMATES. SEE FAR 52.211-18, SECTION 00 72 00 (GENERAL CONDITION)
OF THE CONTRACT.
5,000
59,500
1 .
2 .
3 .
4 .
5 .
6 .
7 .
8 .
End of Document
To be considered responsive, prices must be submitted on all individual items within Pricing Schedule. Failure to do so may be cause for rejection of bids.
Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms Page 1 and Page 2 as part of their solicitation package for bid evaluation. Failure to do so may cause the bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.
CLIN 0001's reference to site prep refers only to sites the bidder anticipates using for disposal.
BASIS of AWARD: The contract will be awarded in accordance with FAR 52.214-19 Contract Award – Sealed Bidding – Construction.
The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site in accordance with the Change Clause FAR 52.243-4.
The Contractor shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.
Dredge material placement shall meet the requirements in specification Section
01 11 00 SUMMARY OF WORK.
The term "Job", which appears on the Pricing Schedule (Section 00 01 00) under “Unit” for Bid Item No. 0001 shall be considered as a Lump Sum. The Variation in Estimated Quantities contract clause, FAR 52.211-18, shall not apply to Bid Item No. 0001.
FY24 Sacramento DWSC O&M W912P724B0005
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/11 SUMMARY OF WORK
01 32 01.00 10 PROJECT SCHEDULE
01 32 23 SURVEY
01 33 00 08/18 SUBMITTAL PROCEDURES
01 35 26 11/20 GOVERNMENT SAFETY REQUIREMENTS
(DREDGING)
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 02/10 QUALITY CONTROL
01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 50 00 08/09 TEMPORARY FACILITIES AND CONTROLS
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 04/06 DREDGING
35 20 23.13 02/22 NATIONAL DREDGING QUALITY MANAGEMENT
PROGRAM - SCOW MONITORING AND ULLAGE
PROFILE
35 20 23.33 02/22 NATIONAL DREDGING QUALITY MANAGEMENT
PROGRAM - PIPELINE HYDRAULIC DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 57 19 Page 1 June 04, 2024
PART 1 GENERAL
1.1 REFERENCES
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
11/15
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.120 Hazardous Waste Operations and Emergency Response
40 CFR 112 Oil Pollution Prevention
40 CFR 241 Solid Wastes Used as Fuels or Ingredients in Combustion Units
40 CFR 243 Guidelines for the Storage and Collection of Residential, Commercial, and Institutional Solid Waste
40 CFR 258 Criteria for Municipal Solid Waste Landfills
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 261.7 Residues of Hazardous Waste in Empty Containers
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities
SECTION 01 57 19 Page 2 June 04, 2024
40 CFR 268 Land Disposal Restrictions
40 CFR 273 Standards For Universal Waste Management
40 CFR 279 Standards for the Management of Used Oil
40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan
40 CFR 300.125 National Oil and Hazardous Substances Pollution Contingency Plan - Notification and Communications
40 CFR 355 Emergency Planning and Notification
40 CFR 60 Standards of Performance for New Stationary Sources
40 CFR 63 National Emission Standards for Hazardous Air Pollutants for Source Categories
40 CFR 64 Compliance Assurance Monitoring
40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 173 Shippers - General Requirements for Shipments and Packagings
49 CFR 178 Specifications for Packagings
1.2 DEFINITIONS
1.2.1 Class I and II Ozone Depleting Substance (ODS)
Class I ODS is defined in Section 602(a) of The Clean Air Act. A list of Class I ODS can be found on the EPA website at the following weblink.
http://www.epa.gov/ozone/science/ods/classone.html.
Class II ODS is defined in Section 602(s) of The Clean Air Act. A list of Class II ODS can be found on the EPA website at the following weblink.
http://www.epa.gov/ozone/science/ods/classtwo.html.
1.2.2 Contractor Generated Hazardous Waste
Contractor generated hazardous waste is materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint
SECTION 01 57 19 Page 3 June 04, 2024 thinners (i.e. methyl ethyl ketone, toluene), waste thinners, excess paints, excess solvents, waste solvents, and marine biofouling agents.
1.2.3 Electronics Waste
Electronics waste is discarded electronic devices intended for salvage, recycling, or disposal.
1.2.4 Environmental Pollution and Damage
Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally or historically.
1.2.5 Environmental Protection
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction.
The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
1.2.6 Hazardous Debris
As defined in paragraph SOLID WASTE, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) in accordance with 40 CFR 261. Hazardous debris also includes debris that exhibits a characteristic of hazardous waste in accordance with 40 CFR 261.
1.2.7 Hazardous Materials
Hazardous materials as defined in 49 CFR 171 and listed in 49 CFR 172.
Hazardous material is any material that: Is regulated as a hazardous material in accordance with 49 CFR 173; or requires a Safety Data Sheet (SDS) in accordance with 29 CFR 1910.120; or during end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, C, or D.
Designation of a material by this definition, when separately regulated or controlled by other sections or directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this section for "control" purposes. Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).
1.2.8 Hazardous Waste
Hazardous Waste is any material that meets the definition of a solid waste and exhibit a hazardous characteristic (ignitability, corrosivity, reactivity, or toxicity) as specified in 40 CFR 261, Subpart C, or
SECTION 01 57 19 Page 4 June 04, 2024 contains a listed hazardous waste as identified in 40 CFR 261, Subpart D.
1.2.9 Land Application
Land Application means spreading or spraying discharge water at a rate that allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur.
Comply with federal, state, and local laws and regulations.
1.2.10 National Pollutant Discharge Elimination System (NPDES)
The NPDES permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.
1.2.11 Oily Waste
Oily waste are those materials that are, or were, mixed with Petroleum, Oils, and Lubricants (POLs) and have become separated from that POLs.
Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, POLs and may be appropriately tested and discarded in a manner which is in compliance with other state and local requirements.
This definition includes materials such as oily rags, "kitty litter" sorbent clay and organic sorbent material. These materials may be land filled provided that: It is not prohibited in other state regulations or local ordinances; the amount generated is "de minimus" (a small amount);
it is the result of minor leaks or spills resulting from normal process operations; and free-flowing oil has been removed to the practicable extent possible. Large quantities of this material, generated as a result of a major spill or in lieu of proper maintenance of the processing equipment, are a solid waste. As a solid waste, perform a hazardous waste determination prior to disposal. As this can be an expensive process, it is recommended that this type of waste be minimized through good housekeeping practices and employee education.
1.2.12 Regulated Waste
Regulated waste are solid wastes that have specific additional federal, state, or local controls for handling, storage, or disposal.
1.2.13 Sediment
Sediment is soil and other debris that have eroded and have been transported by runoff water or wind.
1.2.14 Solid Waste
Solid waste is a solid, liquid, semi-solid or contained gaseous waste. A solid waste can be a hazardous waste, non-hazardous waste, or non-Resource Conservation and Recovery Act (RCRA) regulated waste. Types of solid waste typically generated at project sites may include:
1.2.14.1 Debris
Debris is non-hazardous solid material generated during the dredging activities that exceeds 2.5-inch particle size that is: a manufactured
SECTION 01 57 19 Page 5 June 04, 2024 object; plant or animal matter; or natural geologic material (for example, cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials may be reinforced with or contain ferrous wire, rods, accessories and weldments. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.
1.2.14.2 Material not regulated as solid waste
Material not regulated as solid waste is nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended; suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges;
regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.
1.2.14.3 Non-Hazardous Waste
Non-hazardous waste is waste that is excluded from, or does not meet, hazardous waste criteria in accordance with 40 CFR 263.
1.2.14.4 Recyclables
Recyclables are materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable, wiring, insulated/non-insulated copper wire cable, wire rope, and structural components. It also includes commercial-grade refrigeration equipment with Freon removed, household appliances where the basic material content is metal, clean polyethylene terephthalate bottles, cooking oil, used fuel oil, textiles, high-grade paper products and corrugated cardboard, stackable pallets in good condition, clean crating material, and clean rubber/vehicle tires. Metal meeting the definition of lead contaminated or lead based paint contaminated may not be included as recyclable if sold to a scrap metal company. Paint cans that meet the definition of empty containers in accordance with 40 CFR 261.7 may be included as recyclable if sold to a scrap metal company.
1.2.14.5 Scrap Metal
This includes scrap and excess ferrous and non-ferrous metals such as reinforcing steel, structural shapes, pipe, and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.
1.2.14.6 Wood
Wood is dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included. Treated wood includes, but is not limited to, lumber, utility poles, crossties, and other wood products with chemical treatment.
1.2.15 Surface Discharge
Surface discharge means discharge of water into drainage ditches, storm sewers, creeks or "waters of the United States". Surface discharges are discrete, identifiable sources and require a permit from the governing
SECTION 01 57 19 Page 6 June 04, 2024 agency. Comply with federal, state, and local laws and regulations.
1.2.16 Waters of the United States
Waters of the United States means federally jurisdictional waters, including wetlands, that are subject to regulation under Section 404 of the Clean Water Act or navigable waters, as defined under the Rivers and Harbors Act.
1.2.17 Wetlands
Wetlands are those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.
1.2.18 Universal Waste
The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (for example, thermostats), and lamps (for example, fluorescent bulbs). The rule is designed to reduce hazardous waste in the municipal solid waste (MSW) stream by making it easier for universal waste handlers to collect these items and send them for recycling or proper disposal. These regulations can be found at
40 CFR 273.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Pre-Dredge Submittals
Preconstruction Survey
Solid Waste Management Permit;
Environmental Protection Plan; G
Operations and Water Quality Monitoring Plan; G
Fish Entrainment and Biological Resources Monitoring Work Plan; G
Scientific Collecting Permit(s)
SD-07 Certificates
Employee Training Records; G
Worker Environmental Awareness Training; G
SD-11 Closeout Submittals
Solid Waste Management Report; G
SECTION 01 57 19 Page 7 June 04, 2024
Water Quality Monitoring Report; G
Fish Entrainment And Biological Resources Monitoring Report; G
1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during construction practice.
Plan for and provide environmental protective measures required to correct conditions that develop during dredging. Protect the environmental resources within the project boundaries and those affected outside the limits of work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by law, the laboratories must be certified.
1.4.1 Conservation Measures for the Protection of Aquatic Resources
The following measures are non-discretionary actions required to protect species listed as threatened or endangered under the endangered species act (ESA). These measures are also listed under the Avoidance and Minimization Measures for Dredging Activities in the biological opinions issued by the USFWS and NMFS.
(1) Dredging at depths of less than 20 feet will be avoided to the maximum extent achievable.
(2) Maintenance dredging will only be conducted in the authorized channel to the authorized depths.
(3) The contractor will notify the Government of the project dredging schedule and plans as soon as they are known, and will keep the Government informed of any schedule changes. The Government will notify USFWS, NMFS, and CDFW.
(4) The maintenance dredging work window extends from August 1 through October 31 in the Sacramento DWSC.
(a) Within the Sacramento DWSC, to avoid peak migration of juvenile salmonids and adult presence in the project area, dredging will proceed from downstream to upstream during the environmental work window from August 1 until October 31.
(5) If two dredgers are used in a single channel, they shall not operate in the same reach. Alternatively, if two dredgers are used in the same reach, a turbidity curtain must be used downstream of each dredger to reduce the length of channel that fish are exposed to elevated turbidity.
(6) All slurry pipe placement and bank stabilization activities shall specifically avoid known locations containing special status species and/or designated critical and other sensitive habitats to the maximum
SECTION 01 57 19 Page 8 June 04, 2024 extent feasible.
(7) If significant damage to wetlands or associated vegetation occurs, the Contractor shall restore the area to pre-existing conditions.
(8) The contractor is responsible for providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations to ensure compliance with water quality standards. The Contractor is responsible for the placement of temporary and permanent erosion and sediment control best management practices. These may include, but are not limited to, vegetation cover, stream bank stabilization, slope stabilization, silt fences, construction of terraces, interceptor channels, sediment traps, inlet and outfall protection, diversion channels, and sedimentation basins. Silt fences and other non-natural temporary measures shall be removed after the area has been stabilized.
1.4.2 Additional Conservation Measures for the Protection of Aquatic Resources for Cutterhead Dredgers
(1) If using a cutterhead dredger, the cutterhead will not be operated more than three feet above the channel bottom.
(2) Suction will not be employed while the dredge head is deployed and retrieved through the water column.
(3) The dredger will maintain the suction head at a constant elevation near the channel bed when dredging, to reduce the field of influence where fish may be entrained into the dredge pipe.
(4) Draghead deflectors will be installed on the leading edge of hopper dredge dragheads to minimize the risk of incidental take of benthic species such as green sturgeon. The deflector is designed to have a plowing effect of at least 6 inches.
1.4.3 Additional Conservation Measures for the Protection of Aquatic Resources for Clamshell Dredgers
(1) Multiple horizontal dredge cuts will be taken where a thick horizontal volume needs to be dredged to avoid overfilling the bucket and causing spillage.
(2) Once the clamshell bucket reaches the target depth, it will be fully closed before the dredge operator begins to raise it to the surface of the water column. This method, coupled with the use of a mechanical cable arm environmental clamshell bucket, minimizes the potential for generating turbidity in the water column.
(3) Once out of the water, the clamshell bucket will place dredged sediment directly into the scow. Sediment will not be released from the bucket until it is fully inside the scow. Within the scow, dredged sediment will pass through a 12-inch-by-12-inch grid to prevent any solid debris or artificial objects from entering the scow. Solid debris and artificial objects trapped on the grid will be removed and brought to an approved waste disposal site. Large woody debris with environmental value will be returned to the channel where not a hazard to navigation. The bucket will be held open over the grid within the scow until all the sediment and water has drained from within it to minimize the potential for resuspension of the sediment in the water
SECTION 01 57 19 Page 9 June 04, 2024 column.
(4) The load line on disposal barges used for mechanical dredging will be predetermined based on channel conditions, and the barge will not be filled above this predetermined level. Under no circumstance will scows be loaded to more than 90% capacity.
(5) Untreated water shall not be overflowed, decanted, discharged, or otherwise released from the vessel.
(6) Before each disposal barge is transported to a placement site, the dredging contractor and a site inspector must certify that it is filled correctly. Scows will be inspected to ensure no loss of sediment during loading and transport.
(a) If turbidity levels reach a value that represents 75% of the relevant allowable limit as identified in the MOU or WDR for any reason, the Corps' contractor will immediately slow the dredge rate by 50% to prevent turbidity levels from increasing further (i.e., if the cycle time for the bucket to descend, collect material, and drop that material in the scow is 30 seconds when the violation occurs, the revised cycle time should be 45 seconds until levels return to below 75% relevant allowable limits).
(b) If turbidity levels reach a value that represents 90% of the relevant allowable limit as identified in the MOU or WDR for any reason, the Corps' contractor will deploy a type II turbidity curtain, bubble curtain, or other similar measure to prevent the plume from migrating away from the dredge site. The curtain shall remain in place until levels have returned to below 75% relevant allowable limits.
1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS
The Contractor shall conduct dredging, material placement, and any discharge of decant water from dredged material placement sites in accordance with (1)The Memorandum of Understanding (MOU) of the California Regional Water Quality Control Board,(2) The Central Valley Regional Water Quality Control Board Waste Discharge Requirements for Maintenance Dredging Operations Order R5-2022-0052 (WDR),(3)The Fisheries Service (NMFS) Sacramento and Stockton Deep Water Ship Channel Biological Opinion(2016-2025),(4)The United States Fish and Wildlife Service (USFWS) Sacramento Deep Water Ship Channel Biological Opinion (2023-2028).
Biological Opinions (BOs) and associated Addendums of U.S. Fish and Wildlife Service (USFWS) and National Oceanic and Atmospheric Administration (NOAA). The contractor is responsible for maintaining regular communication to its fish and water quality monitoring staff regarding when and where dredging and material placement will be occurring, when discharge from dredged material placement sites will begin and end, if there are any unexpected discharges, etc. The contractor shall give the monitoring staff as much notice of these items as possible.
1.6 QUALITY ASSURANCE
1.6.1 Preconstruction (pre-dredge) Survey and Protection of Features
This paragraph supplements the Contract Clause PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS. Prior to
SECTION 01 57 19 Page 10 June 04, 2024 start of any onsite construction activities, perform a Pre-Dredge Survey of the project site with the Contracting Officer or delegated representative, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.
Include in the report a plan describing the features requiring protection under the provisions of the Contract Clauses, which are not specifically identified on the drawings as environmental features requiring protection along with the condition of trees, shrubs and grassed areas immediately adjacent to the site of work and adjacent to the Contractor's assigned storage area and access route(s), as applicable. The Contractor and the Contracting Officer or delegated representative will sign this survey report upon mutual agreement regarding its accuracy and completeness.
Protect those environmental features included in the survey report and any indicated on the drawings, regardless of interference that their preservation may cause to the work under the Contract.
1.6.2 Environmental Brief
Attend an environmental brief to be included in the pre-dredge / preconstruction conference. Provide the following information: types, quantities, and use of hazardous materials that will be brought onto the installation; and types and quantities of wastes/wastewater that may be generated during the Contract. Discuss the results of the pre-dredge Survey at this time.
Prior to initiating any work on site, meet with the Contracting Officer or delegated representative and USACE Environmental Team to discuss the proposed Environmental Protection Plan (EPP). The Contractor shall use this brief to develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as turbidity monitoring and mitigation measures), and other measures to be taken.
1.6.3 Employee Training Records
Prepare and maintain Employee Training Records throughout the term of the contract meeting applicable 40 CFR requirements. Provide Employee Training Records in the Environmental Records Binder.
Train personnel to meet state requirements. Conduct environmental protection/pollution control meetings for personnel prior to commencing construction activities. Conduct additional meetings for new personnel and when site conditions change. Include in the training and meeting agenda: methods of detecting and avoiding pollution; familiarization with statutory and contractual pollution standards; installation and care of devices, vegetative covers, and instruments required for monitoring purposes to ensure adequate and continuous environmental protection/pollution control; anticipated hazardous or toxic chemicals or wastes, and other regulated contaminants; recognition and protection of archaeological sites, artifacts, waters of the United States, and endangered species and their habitat that are known to be in the area.
1.6.4 Non-Compliance Notifications
The Contracting Officer or delegated representative will notify the Contractor in writing of any observed noncompliance with federal, state or local environmental laws or regulations, permits, and other elements of the Contractor's EPP. After receipt of such notice, inform the
SECTION 01 57 19 Page 11 June 04, 2024
Contracting Officer or delegated representative of the proposed corrective action and take such action when approved by the Contracting Officer or delegated representative. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer or delegated representative may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.
1.6.4.1 Mis-Dumping of Dredge Material Notification Procedure
Contractor shall immediately notify the Government COR, Government Representative, and the Government Environmental Representative in the event of a draft loss occurs of 2 feet or greater. In the event that a draft loss has occurred scow shall be removed from rotation and inspected.
Inspection report shall be provided to the Government. If required by resource agencies, testing of contaminants shall be performed at no cost to the Government."
(a) E-Mail Alerts: The third-party system must also generate and distribute "e-mail alerts" regarding any degree of apparent dumping outside the project placement site ("mis-dumping"), and regarding any apparent substantial leakage/spillage or other loss of material en route to the project placement site.? Substantial leakage/spillage or other loss shall be defined as an apparent loss of draft of one foot or more between the time that the disposal vessel begins the trip to the project placement site and the time of actual disposal.? E-mail alerts for any disposal trip must be sent within 24 hours of the end of that trip to project placement site.
(b) 24-Hour Notification Requirement for Potential Leaks or Mis-Dumps: The permittee shall report any anticipated, potential, or actual variances from compliance with these project placement sites, and any additional project-specific Special Conditions, to the Government COR within 24 hours of discovering such a situation.? In addition, the permittee shall prepare and submit a detailed report of any such compliance problems on a weekly basis by noon Monday, to the to the Government COR.? These reports shall describe the cause(s) of the problems, any steps taken to rectify the problems, and whether the problems occurred on subsequent disposal trips.
1.7 ENVIRONMENTAL PROTECTION PLAN
The purpose of the EPP is to present an overview of known or potential environmental issues that must be considered and addressed during dredging. Include in the EPP measures for protecting natural and cultural resources, required reports, and other measures to meet the turbidity limits and other requirements in the MOU and/or WDR with the Central Valley Regional Water Quality Control Board (CVRWQCB). See 1.6.2 for requirements for pre-meeting with the Government prior to preparing the EPP for initial submission. Contingency plans should be discussed in the EPP that explain what actions will be taken if minimum freeboard isn't being maintained, if turbidity requirements are not being met, or if an adverse incident occurs. Submit the EPP within 15 days after Contract award and not less than 10 days before the preconstruction meeting.
Revise the EPP throughout the project to include any reporting requirements, changes in site conditions, or contract modifications that change the project scope of work in a way that could have an environmental
SECTION 01 57 19 Page 12 June 04, 2024 impact. No requirement in this section will relieve the Contractor of any applicable federal, state, and local environmental protection laws and regulations. During dredging, identify, implement, and submit for approval any additional requirements to be included in the EPP. Maintain the current version onsite.
The EPP includes, but is not limited to, the following elements:
1.7.1 General Overview and Purpose
1.7.1.1 Descriptions
A brief description of each specific plan required by environmental permit or elsewhere in this Contract such as spill control plan, solid waste management plan, wastewater management plan, air pollution control plan, contaminant prevention plan, biological resources and wetlands plan, Non-Hazardous Solid Waste Disposal Plan.
1.7.1.2 Duties
The duties and level of authority assigned to the person(s) on the job site who oversee environmental compliance, such as who is responsible for adherence to the EPP, who is responsible for spill cleanup and training personnel on spill response procedures, who is responsible for manifesting hazardous waste to be removed from the site (if applicable), and who is responsible for training the Contractor's environmental protection personnel.
1.7.1.3 Procedures
A copy of any standard or project-specific operating procedures that will be used to effectively manage and protect the environment on the project site.
1.7.1.4 Communications
Communication and training procedures that will be used to convey environmental management requirements to Contractor employees and subcontractors.
1.7.1.5 Contact Information
Emergency contact information (office phone number, cell phone number, and e-mail address).
1.7.2 General Site Information
1.7.2.1 Drawings
Drawings showing locations of proposed temporary excavations or embankments for haul roads, stream crossings, jurisdictional wetlands, material storage areas, structures, sanitary facilities, storm drains and conveyances, and stockpiles of excess soil.
1.7.2.2 Work Area
Work area plan showing the proposed activity in each portion of the area and identify the areas of limited use or nonuse. Include measures for marking the limits of use areas, including methods for protection of
SECTION 01 57 19 Page 13 June 04, 2024 features to be preserved within authorized work areas and methods to control runoff and to contain materials on site, and a traffic control plan.
1.7.2.3 Documentation
A letter signed by an officer of the firm appointing the CQC System Manager and stating that person is responsible for managing and implementing the Environmental Program as described in this contract.
Include in this letter the CQC System Manager's authority to direct the removal and replacement of non-conforming work.
1.7.3 Management of Natural Resources
a. Fish and wildlife resources
b. Wetland areas
1.7.4 Protection of Historical and Archaeological Resources
a. Objectives
b. Methods
1.7.5 Protection of the Environment from Waste Derived from Contractor Operations
Control and disposal of solid and sanitary waste. Control and disposal of hazardous waste.
This item consists of the management procedures for hazardous waste to be generated. As a minimum, include the following:
a. List of the types of hazardous wastes expected to be generated
b. Procedures to ensure a written waste determination is made for appropriate wastes that are to be generated
c. Sampling/analysis plan, including laboratory method(s) that will be used for waste determinations and copies of relevant laboratory certifications
d. Methods and proposed locations for hazardous waste accumulation/storage (that is, in tanks or containers)
e. Management procedures for storage, labeling, transportation, and disposal of waste (treatment of waste is not allowed unless specifically noted)
f. Management procedures and regulatory documentation ensuring disposal of hazardous waste complies with Land Disposal Restrictions(40 CFR 268)
g. Management procedures for recyclable hazardous materials such as lead-acid batteries, used oil, and similar
h. Used oil management procedures in accordance with 40 CFR 279;
Hazardous waste minimization procedures
i. Plans for the disposal of hazardous waste by permitted facilities; and
SECTION 01 57 19 Page 14 June 04, 2024
Procedures to be employed to ensure required employee training records are maintained.
1.7.6 Operation and Prevention of Releases to the Environment
a. Name and location of Dredge Material Placement (DMP) sites to be used;
b. Operation plan for DMP sites, with discharge points if applicable;
c. Approximate available capacity (cubic meters volume) of the DMP sites;
d. Expectation of discharge of effluent to receiving waters;
e. Calculations for minimum holding times required for dredge slurry before effluent discharge to receiving waters, if applicable;
f. Description of dredge material handling equipment;
g. Method of transporting dredged materials to placement sites;
h. Expected dredging rate in cubic yards per day;
i. Schedule with hours of operation and estimated days to complete project
j. Best management practices to be implemented during dredging operations to prevent impacts to water quality;
k. Measures to meet the turbidity limits and other requirements in the
Memorandum of Understanding and/or General Order with the Central Valley Regional Water Quality Control Board (CVRWQCB). Contingency plans should be discussed in that explain what actions will be taken if minimum freeboard isn't being maintained, if turbidity requirements are not being met, or if an adverse incident occurs.
l. Plans for Notifications in the event of an unplanned release to the environment
1.7.7 Clean Air Act Compliance
1.7.7.1 Pollution Generating Equipment
Identify air pollution generating equipment or processes that may require federal, state, or local permits under the Clean Air Act. Determine requirements based on any current installation permits and the impacts of the project. Provide a list of all fixed or mobile equipment, machinery or operations that could generate air emissions during the project to the USACE Environmental Team.
In accordance with 40 CFR § 51.853(c)(2)(ix), the USACE has determined that the proposed agency action is exempt from the requirement to prepare a conformity determination with the State Implementation Plan under the Clean Air Act because the project consists of maintenance dredging, no new depths are required, and disposal would be at approved disposal sites.
The Contractor shall be responsible for compliance with all Bay Area Air Quality Management District (BAAQMD) regulations and standards including obtaining a permit if necessary, for operation of a stationary source of air pollutants. Mechanical failures resulting in violations of particulate matter or sulfur compounds (Regulation #2) would be handled through application for a variance from the BAAQMD.
Unless "optimized" or diesel powered equipment with the "Best Available Control Technology" (BACT) emission devices are used, injection timing on diesel powered dredges and equipment shall be retarded two degrees from manufacturer's recommended setting to reduce air pollutant emissions.
Reformulated diesel fuel shall be used for all diesel powered dredges and equipment to reduce air pollutant emissions. Reformulated diesel fuel shall be a low sulfur, reduced aromatics diesel fuel meeting the following
SECTION 01 57 19 Page 15 June 04, 2024 specifications, unless otherwise approved by the Contracting Officer or delegated representative: (1) Sulfur content less than 0.05 percent by weight and (2) Aromatics content less than 20 percent by volume Prior to dredging or construction operations, the Contractor shall submit certification from the fuel supplier or manufacturer stating that the fuel contents meet the above requirements and proof of reformulated diesel fuel purchase of the above specified fuel shall be submitted to the Contracting Officer or delegated representative.
Dredges and equipment shall not be allowed to idle when not required in performing the work.
1.7.7.2 Stationary Internal Combustion Engines
Identify portable and stationary internal combustion engines that will be supplied, used or serviced. Comply with 40 CFR 60 Subpart IIII, 40 CFR 60 Subpart JJJJ, 40 CFR 63 Subpart ZZZZ, and local regulations as applicable. At minimum, include the make, model, serial number, manufacture date, size (engine brake horsepower), and EPA emission certification status of each engine. Maintain applicable records and log hours of operation and fuel use. Logs must include reasons for operation and delineate between emergency and non-emergency operation.
1.7.7.3 Refrigerants
Identify management practices to ensure that heating, ventilation, and air conditioning (HVAC) work involving refrigerants complies with 40 CFR 82 requirements. Technicians must be certified, maintain copies of certification on site, use certified equipment and log work that requires the addition or removal of refrigerant. Any refrigerant reclaimed is the property of the Government, coordinate with the USACE Environmental Team to determine the appropriate turn in location.
1.7.7.4 Air Pollution-engineering Processes
Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions). Log hours of operations and track quantities of materials used.
1.7.7.5 Compliant Materials
Provide the Government a list of and SDSs for all hazardous materials proposed for use on site. Materials must be compliant with all Clean Air Act regulations for emissions including solvent and volatile organic compound contents, and applicable National Emission Standards for Hazardous Air Pollutants requirements. The Government may alter or limit use of specific materials as needed to meet installation permit requirements for emissions.
1.8 LICENSES AND PERMITS
Obtain licenses and permits required for the dredging of the project and in accordance with FAR 52.236-7 Permits and Responsibilities. Notify the Government of all general use permitted equipment the Contractor plans to use on site.
SECTION 01 57 19 Page 16 June 04, 2024
a. The following certifications and approvals were obtained by the Government and are attached:
(1) the Memorandum of Understanding (MOU) Resolution R5-2019-0041 with the Central Valley Regional Water Quality Control Board
(2) the Central Valley Regional Water Quality Control Board Waste Discharge Requirements for Maintenance Dredging Operations Order
R5-2022-0052 (WDR)
(3) the Fisheries Service (NMFS) Sacramento and Stockton Deep Water Ship Channel Biological Opinion (2016-2025)
(3)
(4) the United States Fish and Wildlife Service (USFWS) Sacramento Deep
Water Ship Channel Biological Opinion (2023-2028)
1.9 ENVIRONMENTAL RECORDS BINDER
Maintain on-site a separate electronic Environmental Records Binder and submit at the completion of the project. Make separate parts within the binder that correspond to each submittal listed under paragraph CLOSEOUT SUBMITTALS in this section.
1.10 SOLID WASTE MANAGEMENT…