Pajaro PL 84-99 Site 3 Repair
Solicitation number
W912P723B0011
Issued by

About this file

This document is an amendment to a solicitation for the Pajaro PL 84-99 Site 3 Repair project. The amendment revises specification sections to provide additional requirements for biological surveys, fish relocation, and the timing of in-water construction work. Specifically, it adds language on incorporating raptor perch deterrents on project fencing and notifying the contracting officer of biological surveys 72 hours in advance. It also modifies the allowed timing for in-water work to be between June 1 and September 30, provides more details on dewatering and fish removal requirements, and specifies a two-tiered approach using fish herding and capture/relocation to be overseen by a qualified fisheries biologist.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P723B0011

X 9B. DATED (SEE ITEM 11)

26-Jun-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to revise Section 01 57 19 Paragraph 3.1.6 and Section 00 21 00 Paragraph 1.1.

See Page 2 for details of the amendment.

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Jul-2023

CODE

USACE, SAN FRANCISCO DISTRICT

450 GOLDEN GATE

SAN FRANCISCO CA 94102

W912P7 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P723B0011-AM0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

This amendment makes changes to the solicitation; these changes represent one of three types, either adding new information, deleting information, or revising existing information. Changes made by this amendment replace the previously issued sections of the advertisement, as referenced in the below summary of changes:

SPECIFICIATIONS:

(1) Revise Specification Section 01 57 19, Paragraph 3.1.6. Please see revised attached.

(2) Revise Specification Section 00 21 00, Paragraph 1.1 to delete the following sentence:

“The existing headwall will be removed and replaced with cast-inplace concrete and backfilled with suitable compacted import fill”.

(End of Summary of Changes)

Pajaro River PL 84-99 Site #3 PAJPL8499SITE3 Amendment 0004

j. The Contractor shall incorporate raptor perch deterrents on all fencing in the project area to minimize raptor predation on listed species.

k. The Contractor is responsible for notifying the Contracting Officer 72 hours in advance of performing biological surveys to allow sufficient time for Government Environmental Planner to also attend the survey.

3.1.5 Contact Information

The Contractor shall report all sightings of ESA-listed species to the Contracting Officer.

3.1.6 Aquatic Species

For construction of the project features that extend into the water where South-Central Coast California Steelhead or Tidewater Goby may be present, the Contractor shall perform construction activities only between June 1 and September 30 unless otherwise approved by the Contracting Officer.

Within this window, work below the water line shall be performed under dewatered conditions. Refer to the project specific Dewatering Plan for detailed requirements for in-water work. Allowed in water work includes installation or removal of a sheet pile wall, knockdown dredging, and dewatering the area behind the sheet pile wall. Dewatering cannot begin before fish are removed from the area to be dewatered.

3.1.6.1 Fish Relocation

A two-tiered approach must be used to minimize the adverse effects on fish from the in-water construction work. The two approaches are the following:

1) fish relocation through herding and 2) fish capture and relocation.

Ideally, only the first approach should be used as it is the easiest to implement and is expected to have the lowest impact to fish. It is possible that a combination of the methods may be necessary during the in-water work. The two methods are discussed in detail below.

3.1.6.1.1 Fish Relocation Through Herding

If fish relocation needs to be performed, a qualified fisheries biologist must oversee the work at all times. The qualified fisheries biologist must first be approved by the Contracting Officer via resume submittal which shows experience with surveying fish to genus and species and relocating fish using seining and transport via buckets.

1. A qualified fisheries biologist must first survey the area to be dewatered to determine if fish are present. If fish are present and the water depths and substrate allow for seining, an appropriately sized seine that covers the width of the area must be used and the seine pull must begin as close to the shore on one side as is feasible and pulled to the opposite side to ensure the majority of the fish are captured in the seine net. A minimum of three seine pulls must be performed.

a. Seining With an Opening in the Sheet Pile Wall:

The seine may be pulled through an opening of the sheet pile wall which should be of sufficient width so as to not injure fish as they are pulled through the opening, and then the seine net should be held in place blocking the sheet pile opening to ensure no fish reenter the area to be dewatered behind the sheet pile wall, and must be held in place blocking the entire sheet pile opening until a temporary block net can be installed.

SECTION 01 57 19 Page 23

W912P723B0011-AM0004