This document contains an invitation for bids for annual maintenance dredging of the Oakland Inner and Outer harbor channels in California. The solicitation seeks bids for dredging material to a depth of -50 feet MLLW plus 1 foot of overdepth allowance and transporting all dredged materials to contractor-provided upland reuse sites. The estimated cost range for the contract is between $10 million and $25 million. Bids are due on June 2, 2023 by 1:00 PM PDT and will be publicly opened via WebEx at 1:30 PM PDT. The work must be completed within 192 calendar days of notice to proceed. Questions regarding this solicitation must be submitted by email to the specified contracting officer by 14 calendar days before the bid opening date. The solicitation and any amendments will be posted to SAM.gov. Interested vendors must register in SAM.gov to access the full documents.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P723B0003-1419-GOOD FORM.pdf | ||
| USACE San Francisco Bay Programmatic SFBRWQB WDR and WQC_2020_to_2024-POST.pdf | ||
| USACE San Francisco Bay Programmatic BCDC LOA and CN_2020-2024-POST.pdf | ||
| USACE San Francisco Bay Programmatic LTMS Bioloigcal Opinion_2015-POST.pdf | ||
| LTMS EFH full signed agreement FINAL 6-9-2011 (2) (1)-POST.pdf | ||
| RFI-OAKLAND 5_24_23.pdf | ||
| W912P723B0003-U0001.pdf | ||
| W912P723B0003 - Oakland InnerOuter FY23 Specs.pdf | ||
| W912P723B0003 - Oakland InnerOuter FY23 Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A0002 W912P7
W912P723B0003- A0002 The purpose of this amendment is to revise SF 1442 Block 11 to check the performance is mandatory. As a result, page 3 of the solicitation is replaced in its entirety with the attached. In addition, to confirm FAR Clause 252.236-7004 that the payment will be 60% upon competition of mobilization and 40% upon competition of demobilization. As a result, page 61 of the solicitation is replaced in its entirety with the attached. All other terms and conditions remain unchanged.
CONTRACTING DIVISION
450 GOLDEN GATE AVE, 4TH FL
SAN FRANCISCO CA 94102
See Item 6
W912P723B0003
1 3
05/24/2023
05/02/2023
SOLICITATION, OFFER, 1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DA 1E ISSUED PAGE OF PAGES
AND AWARD � SEALEDBID (IFB) 02-May-2023 (Construction, Alteration, or Repair)
Vl/912P723B0003 □ NEGOTIA TBJ
(RFP)
IMPORTANT-The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITlON/RJROiASE REQUEST NO. 6. PROJECT NO.
7. ISSUEDBY CODE IVl/912P7 8. ADDRESS OFFffi TO (If Other Than Item 7) CODE I
USACE, SAN FRANCISCO DISTRICT
450 GOLDEN GATE
See Item 7
SAN FRANCISCO CA 94102
lEL: ( 415) 503-6995 FAX: lEL: FAX:
9. FOR INFORtM TION A. NAIVE B. TB.EPHONE NO. (Include area code) (NO COLLECT CALLS)
C'ALL: KAREN S SMITH 415-503-6989
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNIVENT REQURES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
DESCRIPTION OF WORK:
The w ork includes annual maintenance dredging of the Oakland Inner and Outer harbor channel to -50-ft (MLLW) plus 1-ft of paid over-depth and transporting of the dredged material per the requirerrents in specification Section 00 10 00 PRCING SOiEDULE and 01 11 00 SUIVMARY OF WORK. All material is suitable for disposal at Contractor-furnished upland beneficial reuse sites.
The North Arrerican Industry aassification System (NAICS)C ode applicable to this acquisition is 237990.
ESTIMATED COSTRANGE IS BETWEEN $10,000,000 AND $25,000,000
See FAR Oause 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
BIDDffi QUESTlONS Questions releating to this solicitation and technical inquiries will be subrritted via email to the assigned contract specialist. Inquiries must be received no later than 14 calendar days prior to the date set for bid opening
11. The Contractor shall begin performance within 1 calendar days and complete it within
D award, � notice to proceed. This performance period is D mandatory, D negotiable.
192 calendar days after receiving
(See 52.211-10 .)
12 A. THECONTRACTOR MUST FURNISH ANY REQUREDPERFORMANCEANDPAYIVENTBONDS? 12B. C'AL8'1DARDAYS (If "YES," indicate within how many calendar days after award in Item 128.)
�YES □ NO
13. AOOTIONAL SOLICITA TlON REQUIRBl,ENTS:
A. Sealed offers in original and 1 copies to perform the w ork required are due at the place specified in Item 8 by 01 :00 Al/I (hour) local tirre 02 Jun 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that tirre. Sealed envelopes containing offers shall be marked to show the offerer's narre and address, the solicitation nurrber, and the date and tirre offers are due.
B. An offer guarantee � is, D is not required.
C. All offers are subject to the (1) work requirerrents, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60
NSN 7540-01-155-3212
calendar days for Governrrent acceptance after the date offers are due will not be considered and will be rejected.
1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
X
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Drawings .Attachment. See Separate
(End of clause)
252.236-7002 OBSTRUCTION OF NAVIGABLE WATERWAYS. (DEC 1991)
(a) The Contractor shall --
(1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;
(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and
(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.
(b) The Contracting Officer may --
(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and
(2) Deduct the cost of removal from any monies due or to become due to the Contractor; or
(3) Recover the cost of removal under the Contractor's bond.
(c) The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et. seq.).
252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991)
(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.
(1) Sixty (60) percent of the lump sum price upon completion of the contractor's mobilization at the work site.
(2) The remaining forty (40) percent upon completion of demobilization.
(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a) (1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.
(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of --
(i) Actual mobilization costs at completion of mobilization;
(ii) Actual demobilization costs at completion of demobilization; and
(iii) The remainder of this item in the final payment under this contract.