San Rafael Amendment 0001.pdf
PDF 1019 KB Posted
- Attached to
- SAN RAFAEL CREEK MAINTENANCE DREDGING PROJECT Federal contract opportunity
- Solicitation number
- W912P722B0001
About this file
This document contains an amendment to a solicitation and related federal contract opportunity. The amendment makes changes to the solicitation for the SAN RAFAEL CREEK MAINTENANCE DREDGING PROJECT, including revising bid quantities, updating reach boundaries and angle point coordinates on drawings. Bidders must acknowledge and sign the amendment.
The federal contract opportunity is for maintenance dredging of San Rafael Creek and Channel. The estimated cost range is between $5-10 million. The work includes dredging reaches of the Creek and Channel to depths of -6 to -8 feet MLLW plus 1 foot of overdepth, and transporting dredged materials to disposal sites. The requirement is a small business set-aside to be awarded as a firm fixed price contract through an invitation for bids. Bids are due on June 21, 2022. The solicitation and amendments will be posted on Sam.Gov. It is the contractor's responsibility to check Sam.Gov for any changes to the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| San Rafael Bid Abstract- W912P722B0001.pdf | ||
| Amendment 0002.pdf | ||
| WDR_WQC_2020_to_2024_Final signed.pdf | ||
| 2015 LTMS BIOP with Addendum.pdf | ||
| BCDC_Consistency Notification.pdf | ||
| Request for Information.pdf | ||
| San Rafael Creek Plans _ Amendment 1.pdf | ||
| W9129722B001_SanRafaelFY22Dredging_Plans.pdf | ||
| W912P722B0001.pdf | ||
| W912P722B0001 San Rafael Creek FY22 Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Please see summary of changes on page 2 of this amendment for all changes to the solicitation documents.
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P722B0001
X 9B. DATED (SEE ITEM 11)
20-May-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0001
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
CODE
CONTRACTING DIVISION
450 GOLDEN GATE AVE, 4TH FL
SAN FRANCISCO CA 94102
W912P7 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X 1
02-JUN-2022
This amendment makes changes to the solicitation; these changes represent one of three types, either adding new information, deleting information, or revising existing information. Changes made by this amendment replace the previously issued sections of the advertisement, as referenced in the below summary of changes:
ADVERTISEMENT FRONT-END (DIVISION 00):
1. Revised Section 00 10, Price Schedule- CLINs 0002, 0003 and 0004 – Bid quantities were updated.
DRAWINGS:
1. Sheets G-02, C-01, C-02 and C-03 – Reach boundaries were updated.
2. Sheet G-03 – Angle Point Coordinates I-3, I-6 and I-21 were updated.
All offerors are required to acknowledge this amendment and provide a signed copy of this amendment (SF30) with their bid submission. If this amendment is not acknowledged or signed, the bid will be considered non- responsive.
W912P7-22-B-0001
Contract Line Item No.(CLIN)
Description of Supplies and Services
*Estimated Quantity
Unit Unit Price
Amount
0001 Mobilization and Demobilization 1 Job
0002 Dredging Reaches 1 and 2 to -8-ft MLLW including 1 foot of paid Over-depth with disposal at SF-10
196,700
192,500 CY $ $
0003 Dredging Reach 3 to -6-ft MLLW including 1 foot of paid Over-depth with disposal at SF-10
37,800
30,800 CY $ $
Total Base Bid Price (Item 0001 through 0003)
234,500
223,300 CY $
0004 Dredging Reach 4 to -6-ft MLLW including 1 foot of paid Over-depth with disposal at SF-DODS
21,500
27,200 CY $ $
Total Optional Bid Price (Item 0004) 21,500
27,200 CY $
Total Evaluated Bid Price $
Notes:
1 .
2 .
OPTIONAL BID ITEMS
SECTION 00 10 00
PRICING SCHEDULE
SAN RAFAEL CREEK AND ATF CHANNEL MAINTENANCE DREDGING PROJECT
BASE BID ITEMS
* - ALL QUANTITIES ARE ESTIMATES. SEE FAR 52.211-18, SECTION 00 72 00 (GENERAL
CONDITION) OF THE CONTRACT.
To be considered responsive, prices must be submitted on all individual items within Pricing Schedule. Failure to do so may be cause for rejection of bids.
Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms Page 1 and Page 2 as part of their solicitation package for bid evaluation. Failure to do so may cause the bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.
SECTION 00 10 00 Page 1 of 2
W912P7-22-B-0001
3 .
4 .
5 .
6 .
End of Document
The Contractor shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.
The term "Job", which appears on the Pricing Schedule (Section 00 10 00) under “Unit” for Bid Item No. 0001 shall be considered as a Lump Sum. The Variation in Estimated Quantities contract clause, FAR 52.211-18, shall not apply to Bid Item No. 0001.
BASIS of AWARD: The contract will be awarded in accordance with FAR 52.214-19 Contract Award – Sealed Bidding – Construction. Award will include BASE plus OPTION. OPTIONS will be evaluated based on FAR 52.217-4 Evaluation of Options exercised at the time of contract award.
The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site in accordance with the Change Clause FAR 52.243-4.
SECTION 00 10 00 Page 2 of 2
File details come from the government source that posted it. Updated .