AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment: Changes the pricing schedule, updates construction plans, provides answers to RFI's.
PAGE OF PAGES1. CONTRACT ID
CODE
1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X
X 9B. DATED (SEE ITEM 11)
11-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
W912P719B0005
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SACRAMENTO AND STOCKTON DEEP WATER SHIP CHANNEL (DWSC) DREDGING PROJECT, SACRAMENT, SAN JOAQUIN, SOLANO, YOLO COUNTIES, CALIFORNIA
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION
NO. 0002
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20 May 2019
CODE
US ARMY ENGINEER DISTRICT, SAN FRANCISCO
CONTRACTING DIVISION
450 GOLDEN GATE AVE, 4TH FLOOR, SUITE 0134
SAN FRANCISCO CA 94102-3406
W912P7 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
Continuation page of SF 30 Amendment of Solicitation/Modification of Contract Changes - Added and Deleted Requirements
SF Form 1442
• Attached SF 1442
Section 00 10 00 Pricing Schedule
• Page 2
- Deleted Bid Item 0005 Incremental Mobilization
- Changed Bid Items 0006, 0006AA and 0006AB to 0005, 0005AA and 0005AB, respectively.
- Changed disposal location from Rio Vista to Decker Island.
- Added Bid Item 0006 Incremental Mobilization to Rio Vista.
• Page 3
- Corrected Bid Items under Total Price Sacramento DWSC
• Page 5
- Changed Bid Items 00018, 0019, 0020 and 0021 Station Designation for Twitchell North to
STA 1050+00. Correction based on Contractor’s Request for Information (RFI) and questions.
• Page 7
- Changed Bid Item 0029 to start at STA 1710+00.
- Bid Items on this page were changed to match the plans.
• Page 8
- Corrected Bid Item 0032AA to reflect the correct depth. Correction based on RFI.
- Corrected Bid Items under Total Price Sacramento DWSC
Construction Plans
• Sheet C-17 – Changed end station to match the pricing schedule
SACRAMENTO AND STOCKTON DEEP WATER SHIP CHANNELS (DWSC) DREDGING PROJECT, YOLO, SOLANO, SACRAMENTO, SAN JOAQUIN
COUTIES, CALIFORNIA
PROJECT DESRIPTION: The work includes annual maintenance dredging of the Sacramento and Stockton Deep Water Ship Channels (DWSC). The Sacramento DWSC project has an estimated 24,910 cubic yards of material to be dredged for a depth of -30-feet plus 1-foot of allow able paid over-depth to be transported and disposed at the various Government-furnished upland disposal sites adjacent to the river. The Stockton DWSC project has an estimated 282,470 cubic yards of material to be dredged for a depth of -35-feet plus 1-foot of allow able paid over-depth, and one area that contains a sediment trap to be dredged to -40-feet with no allow able over-depth. All dredged material shall be transported and disposed at the various Government-furnished disposal sites adjacent to the river. Disposal includes all disposal site preparation and dredged material management at the sites.
This requirement is for an Unrestricted Competition. It w ill be issued as an Invitation for Bids (IFB) which w ill result in the award of a single Firm Fixed Price (FFP) contract.
The North American Industry Classif ication System (NAICS) Code applicable to this acquisition is: 237990
ESTIMATED COST RANGE IS BETWEEN $10,000,000 - $25,000,000
X
JAMES E GARROR
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
11-Apr-2019
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
415-503-6988
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______5 calendar days and complete it w ithin ________165 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time 10 June 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY ENGINEER DISTRICT, SAN FRANCISCO
CONTRACTING DIVISION
450 GOLDEN GATE AVE, 4TH FLOOR, SUITE 0134
SAN FRANCISCO CA 94102-3406
W912P7
PAGE OF PAGES
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912P719B0005 1 OF 194
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9127P19B0005
Section 00 10 00 - Page 1
SECTION 00 10 00
PRICING SCHEDULES
THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC.,
NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND
CONDITIONS SET FORTH IN THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO.
SACRAMENTO AND STOCKTON DEEP WATER SHIP CHANNELS (DWSC) – DREDGING WITH DISPOSAL AT
VARIOUS UPLAND DISPOSAL SITES
Item Description Estimated Unit Quantity Unit Price Amount
SACRAMENTO DWSC BID ITEMS
0001 Mobilization and Demobilization 1 JOB $_______ $_________
0002 Dredging, Sacramento DWSC Dredge Area 1 STA 240+00 to STA 325+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at Decker Island STA 368+00.
0002AA Required Dredging to -30-ft MLLW In Sacramento DWSC 2,000 CY $________ $________
0002AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 26,000 CY $________ $________
0003 Dredging, Sacramento DWSC Dredge Area 2 STA 329+00 to STA 360+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at Decker Island STA 368+00.
0003AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 4,000 CY $________ $_______
0003AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 13,000 CY $________ $________
0004 Dredging, Sacramento DWSC Dredge Area 3STA 370+00 to STA 390+00
SO
LI
CI
TA
TI
ON
FI
NA
L
2019-04-09 Page 8 of 382
Section 00 10 00 - Page 2
2019-04-09 Page 9 of 382 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at Decker Island STA 368+00.
0004AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 1,000 CY $
0004AB Overdepth Dredging to -31-ft
MLLW in Sacramento DWSC 3,000 CY $_ _ $_ _
0005 Site Prep – S-16 Rio Vista & Incremental Mobilization 1 JOB $ $
0006 0005 Dredging, Sacramento DWSC Dredge Area 4 STA 400+00 to STA 435+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at S-16 Rio Vista STA 586+00 Decker Island STA 368+00.
0006AA 0005AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 2,000 CY $ _ $_
0006AB 00005AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 8,000 CY $ $
0006 Site Prep – S-16 Rio Vista & Incremental Mobilization 1 JOB $ $
0007 Dredging, Sacramento DWSC Dredge Area 5 STA 453+00 to STA 500+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at S-16 Rio Vista STA 586+00.
0007AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 4,000 CY $ $
0007AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 17,000 CY $ $
0008 Dredging, Sacramento DWSC Dredge Area 6STA 639+00 to STA 670+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at S-16 Rio Vista STA 586+00.
0008AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 1,000 CY $ $
SO
LI
CI
TA
Section 00 10 00 - Page 3
0008AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 3,000 CY $________ $________
0009 Dredging, Sacramento DWSC Dredge Area 7 STA 672+00 to STA 703+00 to -30-ft (MLLW)including 1-foot of paid overdepth with disposal at S-16 Rio Vista STA 586+00.
0009AA Required Dredging to -30-ft MLLW In Sacramento DWSC. 1,000 CY $________ $_______
0009AB Overdepth Dredging to -31-ft MLLW in Sacramento DWSC 5,000 CY $________ $________
TOTAL PRICE SACRAMENTO DWSC (Line Items 0001, 0002AA, 0002AB, 0003AA, 0003AB, 0004AA, 0004AB
0005, 0005AA, 0005AB, 0006, 0006AA, 0006AB,
0007AA, 0007AB, 0008AA, 0008AB, 0009AA,
0009AB)
STOCKTON DWSC BID ITEMS
0010 Site Prep – Antioch Dunes & Incremental Mobilization 1 JOB $________ $________
0011 Dredging, Stockton DWSC Dredge Area 1 STA 288+00 to STA 324+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Antioch Dunes STA 314+00.
0011AA Required Dredging to -35-ft MLLW In Stockton DWSC 3,000 CY $_______ $________
0011AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 9,000 CY $________ $________
0012 Site Prep – McCormick Pit & Incremental Mobilization 1 JOB $________ $________
2019-04-09 Page 10 of 382
SO
LI
CI
TA
Section 00 10 00 - Page 4
0013 Dredging, Stockton DWSC Dredge Area 4 STA 570+00 to STA 640+00 to -35-ft (MLLW) including 1-foot of paid overdepth with disposal at McCormack Pit STA 564+00.
0013AA Required Dredging to -35-ft MLLW In Stockton DWSC 4,000 CY $________ $_______
0013AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 8,000 CY $________ $_______
0014 Site Prep – Bradford Island & Incremental Mobilization 1 JOB $________ $________
0015 Dredging, Stockton DWSC Dredge Area 5 STA 702+00 to STA 740+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Bradford Island STA 740+00.
0015AA Required Dredging to -35-ft MLLW In Stockton DWSC. 1,000 CY $________ $_______
0015AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 2,000 CY $________ $_______
0016 Dredging, Stockton DWSC Dredge Area 6 STA 800+00 to STA 856+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Bradford Island STA 740+00.
0016AA Required Dredging to -35-ft MLLW In Stockton DWSC 8,000 CY $________ $_______
0016AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 11,000 CY $________ $_______
0017 Site Prep – Twitchell North & Incremental Mobilization 1 JOB $________ $________
SO
LI
CI
TA
2019-04-09 Page 11 of 382
Section 00 10 00 - Page 5
0018 Dredging, Stockton DWSC Dredge Area 7 STA 882+00 to STA 922+00 to -35-ft (MLLW) including 1-foot of paid overdepth with disposal at Twitchell North STA 960+00 STA 1050+00.
0018AA Required Dredging to -35-ft MLLW In Stockton DWSC. 16,000 CY $________ $_______
0018AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 11,000 CY $________ $_______
0019 Dredging, Stockton DWSC Dredge Area 8 STA 982+00 to STA 1020+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Twitchell North STA 960+00 STA 1050+00.
0019AA Required Dredging to -35-ft MLLW In Stockton DWSC. 6,000 CY $________ $_______
0019AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 8,000 CY $________ $_______
0020 Dredging, Stockton DWSC Dredge Area 9 STA 1045+00 to STA 1058+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Twitchell North STA 960+00 STA 1050+00.
0020AA Required Dredging to -35-ft MLLW In Stockton DWSC. 3,000 CY $________ $_______
0020AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 3,000 CY $________ $_______
0021 Dredging, Stockton DWSC Dredge Area 10 STA 1099+00 to STA 1128+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Twitchell North STA 960+00 STA 1050+00.
0021AA Required Dredging to -35-ft MLLW In Stockton DWSC. 3,000 CY $________ $_______
2019-04-09 Page 12 of 382
SO
LI
CI
TA
Section 00 10 00 - Page 6
0021AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 5,000 CY $________ $_______
0022 Site Prep – Mandeville & Incremental Mobilization 1 JOB $________ $________
0023 Dredging, Stockton DWSC Dredge Area 11 STA 1302+00 to STA 1345+00 to -35-ft (MLLW) including 1-foot of paid overdepth with disposal at Mandeville STA 1296+00.
0023AA Required Dredging to -35-ft MLLW In Stockton DWSC. 2,000 CY $________ $_______
0023AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 4,000 CY $________ $_______
0024 Dredging, Stockton DWSC Dredge Area 12 STA 1375+00 to STA 1395+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Mandeville STA 1296+00.
0024AA Required Dredging to -35-ft MLLW In Stockton DWSC. 1,000 CY $________ $_______
0024AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 1,000 CY $________ $_______
0025 Dredging, Stockton DWSC Dredge Area 13 STA 1462+00 to STA 1481+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Mandeville STA 1296+00.
0025AA Required Dredging to -35-ft MLLW In Stockton DWSC. 2,000 CY $________ $_______
0025AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 3,000 CY $________ $_______
0026 Site Prep – Tule Island & Incremental Mobilization 1 JOB $________ $________
SO
LI
CI
TA
2019-04-09 Page 13 of 382
Section 00 10 00 - Page 7
0027 Dredging, Stockton DWSC Dredge Area 14 STA 1558+00 to STA 1658+00 to -35-ft (MLLW)including 1-foot of paid overdepth with disposal at Tule Island STA 1590+00.
0027AA Required Dredging to -35-ft MLLW In Stockton DWSC. 9,000 CY $________ $_______
0027AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 16,000 CY $________ $_______
0028 Site Prep – Roberts II & Incremental Mobilization 1 JOB $________ $________
0029 Dredging, Stockton DWSC Dredge Area 15 STA 1740+00 STA 1710+00 to STA 1771+00 to -35-ft (MLLW) including 1-foot of paid overdepth with disposal at Roberts II STA 1840 +00.
0029AA Required Dredging to -35-ft MLLW In Stockton DWSC. 1,000 CY $________ $_______
0029AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 5,000 CY $________ $_______
0030 Site Prep – Roberts I & Incremental Mobilization 1 JOB $________ $________
0031 Dredging, Stockton DWSC Dredge Area 16 STA 1976+00 to STA 2089+00 to -35-ft (MLLW) including 1-foot of paid overdepth with disposal at Roberts I STA 1975+00.
0031AA Required Dredging to -35-ft MLLW In Stockton DWSC. 22,000 CY $________ $_______
0031AB Overdepth Dredging to -36-ft MLLW in Stockton DWSC 25,000 CY $________ $_______
2019-04-09 Page 14 of 382
SO
LI
CI
TA
Section 00 10 00 - Page 8
0032 Dredging, Stockton DWSC Dredge Area 17 STA 2089+00 to STA 2113+00 to -40-ft (MLLW)with no paid overdepth with disposal at Roberts
I STA 1975+00.
0032AA Required Dredging to -35-ft -40-ft MLLW In Stockton DWSC. 11,000 CY $________ $_______
TOTAL PRICE STOCKTON DWSC (Line Items 0010, 0011AA, 0011AB, 0012, 0013AA, 0013AB, 0014, 0015AA, 0015AB, 0016AA, 0016AB, 0017, 0018AA, 0019AA, 0019AB, 0020AA, 0020AB, 0021AA, 0021AB, 0022, 0023AA, 0023AB, 0024AA, 0024AB, 0025AA, 0025AB, 0026AA, 0026AB, 0027AA, 0027AB, 0028, 0029AA, 0029AB, 0030, 0031AA, 0031AB, 0032AA) $________________
TOTAL BID PRICE (Line Items 0001, 0002AA, 0002AB, 0003AA, 0003AB, 0004AA, 0004AB, 0005, 0005AA, 0005AB, 0006, 0006AA, 0006AB, 0007AA, 0007AB, 0008AA, 0008AB, 0009AA, 0009AB, 0010, 0011AA, 0011AB, 0012, 0013AA, 0013AB, 0014, 0015AA, 0015AB, 0016AA, 0016AB, 0017, 0018AA, 0019AA, 0019AB, 0020AA, 0020AB, 0021AA, 0021AB, 0022, 0023AA, 0023AB, 0024AA, 0024AB, 0025AA, 0025AB, 0026, 0027AA, 0027AB, 0028, 0029AA, 0029AB, 0030, 0031AA, 0031AB, 0032AA) $________________
2019-04-09 Page 15 of 382
SO
LI
CI
TA
Section 00 10 00 - Page 9
Notes:
*QUANTITY IS AN ESTIMATED AMOUNT, SEE SECTION 00 72 00, FAR 52.211-18.
1. Prices must be submitted on all individual items within Pricing Schedule. Failure to do so may be cause for rejection of bids.
2. Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms P.1 and P.2 as part of their solicitation package for bid evaluation. Failure to do so may cause the bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.
3. The term "Job", which appears on the Pricing Schedule (Section 00 10 00) under “Unit” for Bid Item Nos. 0001, 0005, 0010, 0012, 0014, 0017, 0022, 0026, 0028, and 0030 shall be considered as a Lump Sum. The Variation in Estimated Quantities contract clause, FAR 52.211-18, shall not apply to Bid Item No. 0001, 0005, 0010, 0012, 0014, 0017, 0022, 0026, 0028, and 0030.
4. BASIS of AWARD: The contract will be awarded in accordance with FAR 52.214-19 Contract Award – Sealed Bidding – Construction.
- End of Document –
SO
LI
CI
TA
2019-04-09 Page 16 of 382
D R
E D
G
IN
G R
E A
C H
S T
K
N
E
C-17
S T
O C
K T
O
W S
C
D
R E
D G
I N
G
P
L A
N
S T
A
T
O
M A
R K
SHEET ID
G
2 3 4 5 6 7 8 9 10
F
E
D
C
B
A
US Army Corps of Engineers
U S
A
R M
Y
C
O R
P S
F
E
N G
I N
E E
R S
S A
N
F
R A
N C
I S
C
I S
T R
I C
T
G
O L
D E
N
G
A T
E
T H
F
S
U I T
E
S A
N
F
R A
N C
I S
C O
C
A
S A
N
J O
A Q
U
U
N T
Y
C
A L I F
O R
N I A
S A
C R
A M
E N
O
C K
T O
N
D
E E
P
W
A T
R
P
A
N N
E L S
M A
I N
T E
N A
N C
E
D
R E
D G
I N
G
P
R O
J E
C T
C:\Users\l3etevjv\Documents\Sac to Stock Dredging\CAD\ Sac-Stockton DWSC O&M FY19 C-Sheets.dwg 15 May 2019 - 3:49pm
D E
S I G
N E
D
B
Y
D R
A W
N
B
Y
C H
E C
K E
D
B
Y
S U
B M
I T
T E
D
B
Y
S I Z
E
V
V
I G
I L
V V
I G
I L
D
D
O A
K
S
H
A
A N
S I
D
I S
S U
E
D
A T
E
S O
L I C
I T
A T
I O
N
N
O
C O
N T
R A
A P
R I L
W P
B
W P
C
X
X X
X
D E
S C
R I P
T I O
N D
A T
E
D R
A W
I N
G
N
O
STATUS 100%
VICINITY MAP
LEGEND
-35.0 FEET
-33.0 TO -32.0
-32.0 TO -31.0
RED BEACON
RED BUOY
GREEN BUOY
-35.0 TO -34.0
-34.0 TO -33.0
STOCKTON DEEP WATER SHIP CHANNEL
PLAN
AutoCAD SHX Text
SJ-313
AutoCAD SHX Text
SJ-314
AutoCAD SHX Text
LIGHT 42
AutoCAD SHX Text
LIGHT 45
AutoCAD SHX Text
LIGHT 44
AutoCAD SHX Text
LIGHT 43
AutoCAD SHX Text
S P PIPELINE P/L
AutoCAD SHX Text
PERMIT NO. 2909
AutoCAD SHX Text
ELEV. UNKNOWN
AutoCAD SHX Text
GRAPHICS SCALE 1" = 200' 200' 0 100' 200' 400' 800'